CN106436720B - The construction method of jacking construction small size deep foundation pit supporting structure - Google Patents

The construction method of jacking construction small size deep foundation pit supporting structure Download PDF

Info

Publication number
CN106436720B
CN106436720B CN201611004018.4A CN201611004018A CN106436720B CN 106436720 B CN106436720 B CN 106436720B CN 201611004018 A CN201611004018 A CN 201611004018A CN 106436720 B CN106436720 B CN 106436720B
Authority
CN
China
Prior art keywords
construction
pile
cast
foundation
situ bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611004018.4A
Other languages
Chinese (zh)
Other versions
CN106436720A (en
Inventor
朱太山
贾少燕
姚高岭
李玉娥
杨华军
王志军
陈满圈
李红涛
姜辉
曹捷
魏珂
黄杏成
王春磊
杨保军
翁宛
李洋
范梦宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Water and Power Engineering Consulting Co Ltd
Original Assignee
Henan Water and Power Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Water and Power Engineering Consulting Co Ltd filed Critical Henan Water and Power Engineering Consulting Co Ltd
Priority to CN201611004018.4A priority Critical patent/CN106436720B/en
Publication of CN106436720A publication Critical patent/CN106436720A/en
Application granted granted Critical
Publication of CN106436720B publication Critical patent/CN106436720B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A kind of construction method the invention discloses jacking construction with small size deep foundation pit supporting structure:First it is determined that foundation ditch around construction drill perfusion row of piles, construction high-pressure rotary-spray row of piles, from ground excavation slope, and pours annular Guan Liang at the top of drill-pouring row of piles at the gap of adjacent two cast-in-situ bored pile, asphalt felt is spread between Guan Liang and pile body, then builds brick wall by laying bricks or stones at the top of Guan Liang;Guan Liang reaches excavation pit after intensity, and after foundation plane reaches construction requirement, foundation pit side-wall and bottom plate liner are poured into a mould with reinforced concrete(Reserved push pipe wears position), broken pile enabling processing at push pipe is finally carried out, and build the second stage of reinforced concrete floor by laying bricks or stones in dismounting face, meet the requirement of later stage jacking construction, integer support structure construction is completed.The present invention breaches the method for protecting support of conventional cantilever stake, and the supporting mechanism set in the foundation ditch of the confined space meets the supporting of around environment, in combination with the construction characteristic of pipe-jacking project, is provided the foundation guaranteed conditions for the normal safe construction of pipe-jacking project.

Description

The construction method of jacking construction small size deep foundation pit supporting structure
Technical field
The present invention relates to piping laying construction technology, more particularly, to a kind of jacking construction small size deep foundation pit support knot The construction method of structure.
Background technology
Jacking construction is exactly no-dig technique(Or few excavation)Pipeline(Including Urban Underground water supply and sewerage pipeline, day hot gas petroleum pipeline Road, communication cable pipeline etc.)Burial and construction technology.The technology is thoroughly solved in piping laying work progress to City Building Destruction and the problem such as influence to road traffic, to steady soil and environmental protection in terms of advantage become apparent.Normal condition Under, for the various pipe traverse projects that caliber is 1m ~ 3m, particularly in urban environment and in order to protect earth's surface important The facility such as ecological, greenery patches and river course, building exempts from destruction, it will usually selects the jacking construction of non-excavation type.
To meet long-distance pipe jacking engine request, need at engineering both ends and along journey to set various working pit or received well bases Hole, 8m foundation ditch is less than for depth, it is general that supporting is carried out using conventional single-cantilever stake.But some push pipe foundation ditches are in order to pass through Ji, investment reduction, interior diameter are generally smaller(It is only capable of meeting jacking construction requirement), therefore conventional cantilever soldier pile retaining structure scheme by To limitation, and subsurface geology complicated condition, the foundation ditch in urban environment, if peripheral facility(Various pipelines, optical cable and building Thing)It is numerous, it is also not suitable for being constructed using the supporting scheme that conventional anchor cable and inner support are combined, therefore, for this small Diameter(3 ~ 8 meters)And depth is more than 8m(8 ~ 13 meters)Deep basal pit just need to design a kind of new supporting scheme, to meet safety The requirement of construction.
The content of the invention
It is an object of the invention to provide one kind can meet pipe-jacking project construction safety, protect surrounding enviroment to pacify again Entirely, and economic and good social benefit jacking construction small size deep foundation pit supporting structure construction method.
To achieve the above object, the present invention can take following technical proposals:
The construction method of jacking construction of the present invention small size deep foundation pit supporting structure, its construction procedure are:
The first step, around the multiple cast-in-situ bored piles of foundation ditch interval construction around the foundation ditch position that ground determines, form ring The drill-pouring row of piles of shape;The diameter of cast-in-situ bored pile, depth can be according to hydrogeologic condition, peripheral facility load, foundation ditch branch Protect the conditions such as the foundation depth of safe class and supporting and calculate determination;
Second step, according to the underground water elevation actually measured, high pressure of being constructed at the gap of adjacent two cast-in-situ bored pile rotation Stake is sprayed, high-pressure rotary jet grouting pile and cast-in-situ bored pile is formed the pile body diameter of the water-stop curtain of closing, wherein high-pressure rotary jet grouting pile together Less than the pile body diameter of cast-in-situ bored pile;
3rd step, from ground according to not suddenly in 1:1 side slope is excavated, and cutting depth is not more than three meters, is reduced and is put as far as possible Influence of the slope to surrounding enviroment, then pours annular Guan Liang at the top of drill-pouring row of piles, annular Guan Liang and cast-in-situ bored pile Asphalt felt is laid on faying face, ensures that stake top forms freely-supported force structure;Then build height by laying bricks or stones in circular crown back portion and be less than two The brick wall of rice;
4th step, after annular Guan Liang reaches intensity requirement, by projected depth excavation pit;
5th step, after excavation of foundation pit finishes and foundation plane reaches construction requirement, carry out the cast of foundation ditch liner:Use reinforced concrete Casting lining side wall and interior underboarding, push pipe is worn position and reserved during casting lining side wall;
6th step, detection cast-in-situ bored pile, high-pressure rotary jet grouting pile and liner side wall, the intensity of interior underboarding reach acceptance condition Afterwards, broken pile enabling processing at push pipe is carried out:According to design requirement, by the cast-in-situ bored pile and high-pressure rotary-spray at reserved position of pushing tube The pile body of stake is removed, and builds reinforced concrete floor by laying bricks or stones in dismounting face, to meet the space requirement of later stage jacking construction, integer support Structure construction is completed.
The advantage of the invention is that the method for protecting support of conventional cantilever stake is breached, and unlike conventional cantilever stake, top Guan Liang is set for detailing requiments, but forms support system, the prop together as overall force structure with campshed System can meet the supporting of around environment in the foundation ditch of the confined space, in combination with the construction characteristic of pipe-jacking project, Provided the foundation guaranteed conditions for the normal safe construction of pipe-jacking project.
Brief description of the drawings
Fig. 1 is the supporting construction top view that present invention construction finishes.
Fig. 2 is Figure 1A-A to sectional view.
Fig. 3 is the sectional schematic diagram at Fig. 1 polings.
Embodiment
Jacking construction of the present invention with small size deep foundation pit supporting structure as shown in Figure 1-2, according to walking in detail below Suddenly constructed:
The first step, around the multiple cast-in-situ bored piles 1 of foundation ditch interval construction around the foundation ditch position that ground determines, form ring The drill-pouring row of piles of shape;During Specific construction, the diameter of cast-in-situ bored pile and the depth of interval and supporting according to foundation depth, Present situation geological conditions, all side loads and Groundwater feature etc. carry out calculating comprehensive determination.Under normal circumstances, cast-in-situ bored pile Diameter typically just be intended to be 0.80m~2m;
Second step, according to the underground water elevation actually measured, high pressure of being constructed at the gap of adjacent two cast-in-situ bored pile 1 rotation Spray stake 2, wherein the pile body diameter of high-pressure rotary jet grouting pile 2 be less than cast-in-situ bored pile 1 pile body diameter, it is contemplated that base pit engineering feature and Economy, the pile body diameter of high-pressure rotary jet grouting pile 2 are generally 40 ~ 80cm, high-pressure rotary jet grouting pile 2 and the collective effect of cast-in-situ bored pile 1 The water stop curtain structure of closing is formed, meets anhydrous job requirements inside construction period foundation ditch;
3rd step, from ground 1:After 1 slope excavates three meters, poured at the top of drill-pouring row of piles longitudinal section for rectangle or Asphalt felt 4 is laid on the faying face of the annular Guan Liang 3 of square, annular Guan Liang 3 and cast-in-situ bored pile 1, ensures that stake top forms letter Branch force structure;Then the brick wall 5 that height is less than two meters is built by laying bricks or stones at the annular top of Guan Liang 3, brick wall thickness can according to earth-retaining height For 24cm or 37cm, later stage temporary project is facilitated to remove and surface management work;
4th step, after annular Guan Liang 3 reaches intensity requirement, by projected depth excavation pit 6, the diameter of foundation ditch 6 is general No more than eight meters;
5th step, foundation ditch 6, which excavates, to be finished and after foundation plane reaches construction requirement, carries out the cast of foundation ditch liner:Use reinforcing bar Concrete casting lining side wall 7 and interior underboarding 8, the position that wears of push pipe 9 is reserved during casting lining side wall 7;Pour thickness Power is integrally pushed up according to construction technology and push pipe and calculates requirement, generally 20 ~ 40cm;
6th step, detection cast-in-situ bored pile 1, high-pressure rotary jet grouting pile 2 and liner side wall 7, the intensity of interior underboarding 8 reach examination After condition, broken pile enabling processing at push pipe is carried out:According to design requirement, by the cast-in-situ bored pile and high pressure at reserved position of pushing tube The pile body of rotary churning pile is removed, and builds the second stage of reinforced concrete floor 10 by laying bricks or stones in dismounting face(Borehole structure, according to pipe diameter and combine Pipe pushing technology requirement, is computed determining, generally 30 ~ 50cm), by the Bar Anchorage at pile body broken pile in reinforced concrete floor In, to meet the space requirement of later stage jacking construction, so far, integer support structure construction is completed.
7th step, after integer support structure reaches intensity requirement, jacking and two end pipes of push pipe 9 are carried out according to a conventional method The connection in road, the section structure of the push pipe 9 passed from the second stage of reinforced concrete floor 10 are as shown in Figure 3;It can also carry out permanent It is combined with temporary project, pipeline valve pit and pipe laying valve member is poured in the foundation ditch opening position, or on demand at pipeline Corner arranges anchor block 11, meets the pressure requirements of pipeline.
8th step, after the completion of valve pit in push pipe 9 and well or anchor block 11 are constructed, foundation ditch 6 is backfilled, backfill is organic Matter content must not exceed 5%, and compactness cannot be less than 0.96, and need compaction in layers to handle.
Review correlation computations are carried out to supporting construction of the present invention according to structural mechanics method:1. by the top pile body after dismounting Deadweight is overhang at Guan Liang as Vertical Load, and Guan Liang is checked according to simply supported beam at this, and support distance is that both sides are complete Pile body opening position.2. by top pile body whole Gravitative Loads at the hole top of the second stage of lining concrete, the second stage of lining cutting circular hole according to " O " type framework carries out structure review.3. for the top pile body after broken pile according to both ends freely-supported, bearing is respectively Guan Liang and inner liner location Place, pile body are primarily subjected to horizontal earth pressure and checked.4. liner plane is checked to the reaction force of liner using top pile body Framework.
According to member structure system, calculated according to structural mechanics method, computation model is as follows:Stake top Guan Liang is according to list Support structure designs, Guan Liang cross section are rectangle, reinforced concrete structure:1. horizontal direction:At the top of supporting construction Guan Liang according to Structural mechanics method calculates, and top Guan Liang is born horizontal loading and calculated according to hinged-support transmission counter-force, according to reinforced concrete Native flexure member correlation formula is determined Guan Liang section.2. vertical direction:Consider pile body pair when push pipe opens the door Guan Liang vertical load is influenceed to be checked, and internal force meter is carried out according to armored concrete flexure member correlation formula Calculate.
Conclusion:After checking calculation being carried out according to the above method to supporting construction of the present invention, it was demonstrated that:On small size deep basal pit top In plumber's journey, by regarding Guan Liang as a structure stress system part, and the common coordinative role of campshed, as a kind of pipe-jacking project Foundation pit supporting construction can fully meet jacking construction safety requirements.

Claims (1)

  1. A kind of 1. jacking construction construction method of small size deep foundation pit supporting structure, it is characterised in that:Comprise the steps:
    The first step, around the multiple cast-in-situ bored piles of foundation ditch interval construction around the foundation ditch position that ground determines, form annular Drill-pouring row of piles;
    Second step, according to the underground water elevation actually measured, high-pressure rotary jet grouting pile of being constructed at the gap of adjacent two cast-in-situ bored pile, High-pressure rotary jet grouting pile (2) and cast-in-situ bored pile (1) is set to form the pile body diameter of the water-stop curtain, wherein high-pressure rotary jet grouting pile closed Less than the pile body diameter of cast-in-situ bored pile;
    3rd step, from ground according to not suddenly in 1:1 side slope is excavated, and cutting depth is not more than three meters, then in drill-pouring Pour annular Guan Liang at the top of row of piles, lay asphalt felt on the faying face of annular Guan Liang and cast-in-situ bored pile, ensure that stake top forms letter Branch force structure;Then the brick wall that height is less than two meters is built by laying bricks or stones in circular crown back portion;
    4th step, after annular Guan Liang reaches intensity requirement, by projected depth excavation pit;
    5th step, after excavation of foundation pit finishes and foundation plane reaches construction requirement, carry out the cast of foundation ditch liner:Poured into a mould with reinforced concrete Liner side wall and interior underboarding, push pipe is worn position and reserved during casting lining side wall;
    6th step, after detection cast-in-situ bored pile, high-pressure rotary jet grouting pile and liner side wall, the intensity of interior underboarding reach acceptance condition, Carry out broken pile enabling processing at push pipe:According to design requirement, by the cast-in-situ bored pile and high-pressure rotary jet grouting pile at reserved position of pushing tube Pile body remove, and reinforced concrete floor is built by laying bricks or stones in dismounting face, to meet the space requirement of later stage jacking construction, integer support knot Structure construction is completed.
CN201611004018.4A 2016-11-15 2016-11-15 The construction method of jacking construction small size deep foundation pit supporting structure Active CN106436720B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611004018.4A CN106436720B (en) 2016-11-15 2016-11-15 The construction method of jacking construction small size deep foundation pit supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611004018.4A CN106436720B (en) 2016-11-15 2016-11-15 The construction method of jacking construction small size deep foundation pit supporting structure

Publications (2)

Publication Number Publication Date
CN106436720A CN106436720A (en) 2017-02-22
CN106436720B true CN106436720B (en) 2018-04-10

Family

ID=58207805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611004018.4A Active CN106436720B (en) 2016-11-15 2016-11-15 The construction method of jacking construction small size deep foundation pit supporting structure

Country Status (1)

Country Link
CN (1) CN106436720B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107142948A (en) * 2017-05-18 2017-09-08 河北省高速公路廊坊北三县管理处 A kind of highway wears high ferro viaduct system and construction method without pre- leave
CN107326911B (en) * 2017-08-28 2022-11-29 西南交通大学 Foundation pit fender pile
CN107988894B (en) * 2017-08-31 2023-07-18 中铁二院工程集团有限责任公司 Concrete buttress structure for preventing high-steep slope pier from shifting
CN108062453B (en) * 2018-01-12 2021-06-29 河南省水利勘测设计研究有限公司 Flood high-efficiency simulation and high-fidelity visual dynamic display method for water conservancy information system
CN109025970A (en) * 2018-08-21 2018-12-18 中国十七冶集团有限公司 A kind of contraction type engineering pile enters rock controller and control method
CN109208608A (en) * 2018-10-17 2019-01-15 上海市城市建设设计研究总院(集团)有限公司 Facet foundation pit is inverse to make rapid construction devices and methods therefor
CN109797778A (en) * 2019-03-27 2019-05-24 中铁四局集团有限公司 One kind being suitable for the anhydrous layer of sand area upper pipe working well in desert and construction method
CN110629763B (en) * 2019-08-19 2022-05-10 中国一冶集团有限公司 Drag pipe well chamber foundation pit supporting structure and construction method thereof
CN110670586B (en) * 2019-09-29 2021-06-04 上海隆基建设股份有限公司 Construction method for light reconstruction of airport runway surface
CN110792085A (en) * 2019-09-30 2020-02-14 成都市市政工程设计研究院 Pipe-jacking working pit supporting method
CN111778992A (en) * 2020-07-01 2020-10-16 中电建十一局工程有限公司 Construction method for crossing U-shaped channel section of old city building group area
CN111851597B (en) * 2020-07-31 2021-09-07 安徽省交通建设股份有限公司 Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3507730A1 (en) * 1985-03-05 1986-09-11 Dyckerhoff & Widmann AG, 8000 München Trench sheeting designed for driving through by means of a driving shield during the driving of an earth tube between a starting shaft and a target shaft
JPH03169914A (en) * 1989-11-27 1991-07-23 Aisawa Kogyo Kk Laying of underground structure and open shield machine therefor
CN202430723U (en) * 2011-12-29 2012-09-12 南京金宸建筑设计有限公司 Horizontal jacking pipe and rigid pile composite supporting structure
CN202440823U (en) * 2012-03-02 2012-09-19 天津市赛英工程建设咨询管理有限公司 Supporting structure of pipe jacking pit
CN104846829A (en) * 2014-02-18 2015-08-19 宏润建设集团股份有限公司 Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN105986578A (en) * 2015-02-13 2016-10-05 杭州南联地基基础工程有限公司 Ejecting pipe construction method of roadside tubular underground garage

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3507730A1 (en) * 1985-03-05 1986-09-11 Dyckerhoff & Widmann AG, 8000 München Trench sheeting designed for driving through by means of a driving shield during the driving of an earth tube between a starting shaft and a target shaft
JPH03169914A (en) * 1989-11-27 1991-07-23 Aisawa Kogyo Kk Laying of underground structure and open shield machine therefor
CN202430723U (en) * 2011-12-29 2012-09-12 南京金宸建筑设计有限公司 Horizontal jacking pipe and rigid pile composite supporting structure
CN202440823U (en) * 2012-03-02 2012-09-19 天津市赛英工程建设咨询管理有限公司 Supporting structure of pipe jacking pit
CN104846829A (en) * 2014-02-18 2015-08-19 宏润建设集团股份有限公司 Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN105986578A (en) * 2015-02-13 2016-10-05 杭州南联地基基础工程有限公司 Ejecting pipe construction method of roadside tubular underground garage

Also Published As

Publication number Publication date
CN106436720A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106436720B (en) The construction method of jacking construction small size deep foundation pit supporting structure
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
Liu et al. Structural responses and treatments of shield tunnel due to leakage: A case study
Yang et al. Research of surface settlement for a single arch long-span subway station using the Pipe-roof Pre-construction Method
Meng et al. Observed behaviors of a long and deep excavation and collinear underlying tunnels in Shenzhen granite residual soil
CN106150506B (en) A kind of entrance open excavation section inverted side-wall construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN104612696B (en) Overpass column hole method construction method is passed through in big cross section tunneling subway station in fine sand layer
CN205876348U (en) Multi -level advance support structure of transverse passage -way vault under complex geological condition
CN102635113A (en) Construction method for hydraulic vibrating sinking pipe cast-in-place piles
CN108843333A (en) Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
Zhang et al. A case study on performances of overlying pipelines due to shallow tunnels excavation in water-rich gravel ground
CN110306989A (en) A kind of non-open cut assembled pipe canal digging support reinforcement method
CN107165640B (en) Tunnels and underground engineering surely builds method certainly
CN109113092A (en) Construction method is protected in underground large-diameter pipeline original position water flowing
CN108978709B (en) Urban comprehensive pipe gallery branch construction method in space-limited environment
CN207878451U (en) A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN202560234U (en) Astylar long-span underground space structure
CN113202106B (en) Deep foundation pit excavation method
CN206173974U (en) Push pipe construction is with dark underground structure of small -size
Yang et al. Monitoring and controlling on surface settlement in sand and gravel strata caused by subway station construction applying pipe-roof pre-construction method (PPM)
Tan et al. Challenges in design and construction of deep excavation for KVMRT in Kuala Lumpur limestone formation
CN106968271B (en) Underground pipe gallery excavates and the construction method of support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhu Taishan

Inventor after: Cao Jie

Inventor after: Wei Ke

Inventor after: Huang Xingcheng

Inventor after: Wang Chunlei

Inventor after: Yang Baojun

Inventor after: Weng Wan

Inventor after: Li Yang

Inventor after: Fan Mengyu

Inventor after: Jia Shaoyan

Inventor after: Yao Gaoling

Inventor after: Li Yue

Inventor after: Yang Huajun

Inventor after: Wang Zhijun

Inventor after: Chen Manquan

Inventor after: Li Hongtao

Inventor after: Jiang Hui

Inventor before: Zhu Taishan

Inventor before: Cao Jie

Inventor before: Wei Ke

Inventor before: Huang Xingcheng

Inventor before: Wang Chunlei

Inventor before: Yang Baojun

Inventor before: Weng Wan

Inventor before: Li Yang

Inventor before: Fan Mengyu

Inventor before: Jia Shaoyan

Inventor before: Yao Gaoling

Inventor before: Li Yue

Inventor before: Yang Huajun

Inventor before: Wang Zhijun

Inventor before: Chen Manquan

Inventor before: Li Hongtao

Inventor before: Jiang Hui