CN106368438A - 一种钢结构厂房屋面施工方法 - Google Patents
一种钢结构厂房屋面施工方法 Download PDFInfo
- Publication number
- CN106368438A CN106368438A CN201611018458.5A CN201611018458A CN106368438A CN 106368438 A CN106368438 A CN 106368438A CN 201611018458 A CN201611018458 A CN 201611018458A CN 106368438 A CN106368438 A CN 106368438A
- Authority
- CN
- China
- Prior art keywords
- roof
- construction method
- roofing
- purlin
- truss beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
Abstract
本发明公开了一种钢结构厂房屋面施工方法,包括:在安装好的各钢柱之间,采用双机抬吊的方式安装屋架梁;安装屋面檩条和屋面水平支撑;用升降平台进行屋面反吊板的安装;安装屋面板;安装屋面板同时安装天沟与屋脊盖板部分。本发明能有效减少变形,保证垂直度和正直度。
Description
技术领域
本发明涉及厂房屋面施工方法。
背景技术
钢结构厂房因其建造方便、成本比较、牢固结实等优点,被普遍应用于各个行业。钢结构厂房的屋面因有防水、防风等功能要求,施工时需要特别有无变形、是否垂直、是否正直等,并采取相应的施工手段,保证这些要求能够满足。
发明内容
本发明的目的在于提供一种钢结构厂房屋面施工方法,能有效减少变形,保证垂直度和正直度。
实现上述目的的技术方案是:
一种钢结构厂房屋面施工方法,包括:
在安装好的各钢柱之间,采用双机抬吊的方式安装屋架梁:吊装时,在屋架梁的两端向内10m处分别设置两个吊点,起吊高度按吊索与构件轴线方向呈60°来确定起吊高度;屋架梁安装时,慢慢吊起屋架梁,指引到正确位置,使梁及柱的翼缘孔对准后用临时螺栓或冲钉固定,待屋架梁的垂直度和正直度经过检验满足要求后,用高强螺栓将其固定,用经纬仪校正各段梁是否位于同一立面;
安装屋面檩条和屋面水平支撑;
用升降平台进行屋面反吊板的安装;
安装屋面板:用吊机把屋面板吊置屋面上,按图纸编号,预先铺置在屋面上,然后将连接板、接口卡用密封胶沾上,再用螺丝紧固好;按图纸编号,先把边部连接件固定在檩条上,再铺设保温棉,然后再把预先连接好的屋面板移置在保温棉上面,再安装冷桥檩条和连接夹。
安装屋面板同时安装天沟与屋脊盖板部分。
在上述的钢结构厂房屋面施工方法中,安装的第一件屋面板需要保证垂直,板缝连接接口采用直立缝360度卷边进行缝合。
在上述的钢结构厂房屋面施工方法中,保温棉的下料长度是从檐口檩条到相应的屋脊檩条间距离。
本发明的有益效果是:本发明通过对吊点选定、采用临时固定、垂直度和正直度检验等措施,使得施工时有效减少变形,确保垂直度和正直度,从而确保实现高质量的屋面施工。
附图说明
图1是本发明的钢结构厂房屋面施工方法的流程图。
具体实施方式
下面将结合附图对本发明作进一步说明。
请参阅图1,本发明的钢结构厂房屋面施工方法,包括下列步骤:
步骤S1,在安装好的各钢柱之间,采用双机抬吊的方式安装屋架梁。
具体地,为减少屋架梁形变,需要选择吊点。吊点的选择原则:a)吊点应选择起重机幅度较小的位置。b)要保证起吊后的构件在自重作用下两端的轴向相对变形等于或接近零,这样吊装到设计位置时,不会由于变形而无法安装。c)吊钩的位置应在构件重心线上,这样可以保证构件吊装时的稳定性,有效防止或减少变形。d)吊点间距不能过近,否则会导致构件两端变形过大而影响安装就位。
所以吊装时,在屋架梁的两端向内10m处分别设置两个吊点,起吊高度按吊索与构件轴线方向呈60°来确定起吊高度;先在地面上进行试吊,如发现大梁侧向弯曲超出规范允许范围,应在大梁腹板位置加设加强杆。吊装时,为使屋架在吊起后不致发生摇摆,以免与其它构件发生碰撞,在起吊时前,将屋架梁两端绑扎好溜绳,随吊随放松,以保证其位置和姿势的正确。屋架梁安装时,慢慢吊起屋架梁,指引到正确位置,使梁及柱的翼缘孔对准后用临时螺栓或冲钉临时固定。待屋架梁的垂直度(用锤球栓检测)和正直度(用接紧的测绳检验)满足要求后,用高强螺栓将其最后固定。屋面梁安装时,用经纬仪检验校正各段梁是否位于同一立面,以保证屋面梁垂直度、侧向弯曲满足要求。
步骤S2,安装屋面檩条和屋面水平支撑。
步骤S3,在屋面檩条、拉条安装完毕、校正、检查没有错误,所有连接螺栓全部紧固情况下用专用升降平台进行屋面反吊板的安装。
步骤S4,安装屋面板:用吊机把屋面板吊置屋面上,按图纸编号,预先铺置在屋面上,然后将连接板、接口卡用密封胶沾上,再用螺丝紧固好。按图纸编号,先把边部连接件固定在檩条上,再铺设保温棉,然后再把预先连接好的屋面板移置在保温棉上面,再安装冷桥檩条和连接夹。安装的第一件屋面板需要保证垂直,用经纬仪给予校直,合格后,方可进行第二件屋面板的安装。板缝连接接口采用直立缝360度卷边进行缝合。这样以次类推安装下面的屋面板。
保温棉铺设与屋面板安装应紧随,保温棉的下料长度主要是屋面单坡长,从檐口檩条到相应的屋脊檩条间距离。如果一卷保温棉不够长以覆盖屋面一个单坡长时,则需要搭接,搭接时在檩条上用双面胶带。
步骤S5,在安装屋面板同时可分小组人安装天沟与屋脊盖板部分。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。
Claims (3)
1.一种钢结构厂房屋面施工方法,其特征在于,包括:
在安装好的各钢柱之间,采用双机抬吊的方式安装屋架梁:吊装时,在屋架梁的两端向内10m处分别设置两个吊点,起吊高度按吊索与构件轴线方向呈60°来确定起吊高度;屋架梁安装时,慢慢吊起屋架梁,指引到正确位置,使梁及柱的翼缘孔对准后用临时螺栓或冲钉固定,待屋架梁的垂直度和正直度经过检验满足要求后,用高强螺栓将其固定,用经纬仪校正各段梁是否位于同一立面;
安装屋面檩条和屋面水平支撑;
用升降平台进行屋面反吊板的安装;
安装屋面板:用吊机把屋面板吊置屋面上,按图纸编号,预先铺置在屋面上,然后将连接板、接口卡用密封胶沾上,再用螺丝紧固好;按图纸编号,先把边部连接件固定在檩条上,再铺设保温棉,然后再把预先连接好的屋面板移置在保温棉上面,再安装冷桥檩条和连接夹。
安装屋面板同时安装天沟与屋脊盖板部分。
2.根据权利要求1所述的钢结构厂房屋面施工方法,其特征在于,安装的第一件屋面板需要保证垂直,板缝连接接口采用直立缝360度卷边进行缝合。
3.根据权利要求1所述的钢结构厂房屋面施工方法,其特征在于,保温棉的下料长度是从檐口檩条到相应的屋脊檩条间距离。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611018458.5A CN106368438A (zh) | 2016-11-16 | 2016-11-16 | 一种钢结构厂房屋面施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611018458.5A CN106368438A (zh) | 2016-11-16 | 2016-11-16 | 一种钢结构厂房屋面施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106368438A true CN106368438A (zh) | 2017-02-01 |
Family
ID=57891442
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611018458.5A Pending CN106368438A (zh) | 2016-11-16 | 2016-11-16 | 一种钢结构厂房屋面施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106368438A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107700736A (zh) * | 2017-10-15 | 2018-02-16 | 张海江 | 一种钢结构屋顶及其安装方法 |
CN108035553A (zh) * | 2017-11-09 | 2018-05-15 | 中国化学工程第六建设有限公司 | 大跨度钢结构厂房压型板现场预制安装施工工艺 |
CN112049270A (zh) * | 2020-08-31 | 2020-12-08 | 常州第一建筑集团有限公司 | 钢结构厂房彩板与铝箔层叠屏蔽系统施工方法 |
CN112609911A (zh) * | 2020-12-04 | 2021-04-06 | 刘礼艾 | 一种钢结构建筑屋顶面彩钢板铺设安装方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0654571B1 (en) * | 1993-05-14 | 1999-04-14 | Mitsubishi Jukogyo Kabushiki Kaisha | Zone module construction method of steel structure construction |
CN1752366A (zh) * | 2004-09-23 | 2006-03-29 | 万平华 | 一种用组装的方式建造建筑物的方法 |
CN103711258A (zh) * | 2013-12-27 | 2014-04-09 | 常州第一建筑集团有限公司 | 扣件插接式曲面金属屋面及其施工方法 |
-
2016
- 2016-11-16 CN CN201611018458.5A patent/CN106368438A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0654571B1 (en) * | 1993-05-14 | 1999-04-14 | Mitsubishi Jukogyo Kabushiki Kaisha | Zone module construction method of steel structure construction |
CN1752366A (zh) * | 2004-09-23 | 2006-03-29 | 万平华 | 一种用组装的方式建造建筑物的方法 |
CN103711258A (zh) * | 2013-12-27 | 2014-04-09 | 常州第一建筑集团有限公司 | 扣件插接式曲面金属屋面及其施工方法 |
Non-Patent Citations (2)
Title |
---|
孙天东: "重钢厂房钢结构安装方法", 《建筑结构与设计》 * |
林文虎,姚刚: "《混凝土结构工程施工手册》", 31 December 1999 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107700736A (zh) * | 2017-10-15 | 2018-02-16 | 张海江 | 一种钢结构屋顶及其安装方法 |
CN107700736B (zh) * | 2017-10-15 | 2019-09-20 | 江西佳慧钢结构工程有限公司 | 一种钢结构屋顶及其安装方法 |
CN108035553A (zh) * | 2017-11-09 | 2018-05-15 | 中国化学工程第六建设有限公司 | 大跨度钢结构厂房压型板现场预制安装施工工艺 |
CN112049270A (zh) * | 2020-08-31 | 2020-12-08 | 常州第一建筑集团有限公司 | 钢结构厂房彩板与铝箔层叠屏蔽系统施工方法 |
CN112609911A (zh) * | 2020-12-04 | 2021-04-06 | 刘礼艾 | 一种钢结构建筑屋顶面彩钢板铺设安装方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106368438A (zh) | 一种钢结构厂房屋面施工方法 | |
CN103291076B (zh) | 弧形框架内多层次钢桁架分片逆向吊装施工方法 | |
CN104141383B (zh) | 一种贝雷梁悬吊模板支撑体系及其施工工法 | |
CN104929373B (zh) | 大跨度方钢管桁架及其累积滑移施工方法 | |
CN103711323B (zh) | 利用移动式管桁架平台安装屋面反吊顶板施工方法 | |
CN103195256B (zh) | 吊柱式钢结构胎架法施工工法 | |
CN103982045B (zh) | 一种屋面网壳结构无支架悬挑安装施工方法 | |
CN102979313B (zh) | 转换层超重钢桁架高空吊装施工方法 | |
CN101255768A (zh) | 一种大跨度钢桁架高空安装方法 | |
CN104818772B (zh) | 一种大跨度长悬臂连体结构及施工工艺 | |
CN102733615B (zh) | 非对称整体提升施工方法 | |
CN104480862A (zh) | 一种斜拉桥边跨钢桁梁的架设方法 | |
CN201043354Y (zh) | 整体式建筑模板及模板托架 | |
CN106703416A (zh) | 狭小空间中钢结构屋架拔杆吊装方法 | |
CN103883129B (zh) | 一种钢结构屋面梁安装方法 | |
CN105970819A (zh) | 一种钢锚梁的安装施工方法 | |
CN107642225A (zh) | 一种悬空脚手架及其拼装和拆除方法 | |
CN104153586B (zh) | 一种用悬索吊来安装檩条的施工方法 | |
CN103061508A (zh) | 一种三角形滑模装置及施工方法 | |
CN107419907B (zh) | 一种炼钢塔楼钢结构平台的交错安装焊接方法 | |
CN103821375A (zh) | 吊船辅助吊顶幕墙安装工法 | |
CN202865996U (zh) | 一种核电厂房间模块结构 | |
CN203441069U (zh) | 外墙悬空可翻转工作平台 | |
CN102733644B (zh) | 超高空屋顶超长天线提升施工方法及系统 | |
CN105040592B (zh) | 一种平拉索桥及其架设方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District Applicant after: Shanghai General Construction Engineering Co., Ltd. Address before: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District Applicant before: Shanghai General Metal Structure Engineering Co.,Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170201 |