CN106703416A - 狭小空间中钢结构屋架拔杆吊装方法 - Google Patents
狭小空间中钢结构屋架拔杆吊装方法 Download PDFInfo
- Publication number
- CN106703416A CN106703416A CN201510250450.0A CN201510250450A CN106703416A CN 106703416 A CN106703416 A CN 106703416A CN 201510250450 A CN201510250450 A CN 201510250450A CN 106703416 A CN106703416 A CN 106703416A
- Authority
- CN
- China
- Prior art keywords
- steel
- truss
- whole
- structure beam
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种狭小空间中钢结构屋架拔杆吊装方法,钢结构屋架总重量400t,设5榀钢桁架,每榀钢桁架梁长34米,高2米;两侧塔楼阻挡,不允许吊车进入现场直接吊装;其特征在于包括以下步骤:a钢结构屋架的每榀钢桁架梁分段吊运到整榀钢桁架梁组装位置,b分段钢桁架梁拼装焊接成整榀桁架梁,c整榀桁架梁通过拔杆起吊就位于混凝土柱子上完成钢结构屋架安装。本发明的具有采用分段拼装、拔杆吊装的施工方法,吊装空间需求不大,方法简单,施工方便,使大跨度钢梁得以安全、有效的进行施工;能够极大降低狭小空间吊装的安全隐患,降低钢结构桁架梁吊装工程施工成本,满足吊装施工的经济效益的优点。
Description
技术领域
本发明涉及一种钢结构屋架吊装方法,具体地说,是一种狭小空间中钢结构屋架拔杆吊装方法。
背景技术
国内钢结构的吊装方式多种多样,随着科学技术的不断发展,钢结构的造型及结构形式也越来越复杂,这给钢结构的吊装施工带来了新的挑战。传统的钢结构屋面吊装采用吊车站位,凭借吊车臂长直接将构件调至安装位置,因此吊车起吊时,吊车的站位、幅度、臂长均要有足够的空间来完成。然而在吊车的站位、幅度、臂长均受限制的空间中,使得吊车不能直接完成吊装任务。
因此已知的钢结构屋架吊车吊装方法存在着上述种种不便和问题。
发明内容
本发明的目的,在于提出一种安全可靠的狭小空间中钢结构屋架拔杆吊装方法。
为实现上述目的,本发明的技术解决方案是:
一种狭小空间中钢结构屋架拔杆吊装方法,钢结构屋架总重量400t,设5榀钢桁架,每榀钢桁架梁长34米,高2米;两侧塔楼阻挡,不允许吊车进入现场直接吊装;其特征在于包括以下步骤:
a、钢结构屋架的每榀钢桁架梁分段吊运到整榀桁架梁组装位置
依据工程特点及设计意图,将钢结构屋架的每榀钢桁架梁分成三段工厂加工完成,转运现场后每一段钢桁架梁应按照顺序进行吊装,放置在移动铁滑床上,用卷扬机吊至标高14.25m整榀钢桁架梁组装位置;
b、分段钢桁架梁拼装焊接成整榀钢桁架梁
在整榀钢桁架梁组装位置将三个分段钢桁架梁拼装焊接成整榀钢桁架梁;
c、整榀钢桁架梁通过拔杆起吊就位于混凝土柱子上,包括以下步骤:
(1)安装拔杆
根据整榀钢桁架梁的长度,设置二根拔杆,二根拔杆用钢丝绳连接整榀钢桁架梁上的两个吊点;拔杆底部的支撑面或者支座应垫实,根据现场情况采用在土建剪力墙上设刚性垫块,拔杆杆头应垂直于整榀钢桁架梁上方,钢丝绳收紧提升时将整榀钢桁架梁水平就位,拔杆四周缆风绳应绑扎牢固,确保其吊装的稳定性;吊装过程中,整榀钢桁架梁两端的绳子应控制好整榀桁架梁的摆动方向,以便于整榀钢桁架梁可靠地在混凝土柱子上就位,整榀钢桁架梁就位标高为20.50m;
(2)试吊
在正式吊装整榀钢桁架梁前应认真做好工艺性试吊工作,确保拔杆的稳定性、吊具的牢固性、空间的可操作性、钢丝绳的张力、起吊的速度、构件标高和垂直度工艺参数符合设计要求;
(3)吊装
吊装过程的控制:整榀钢桁架梁起吊后,不得在高空停留过久,如需要较长时间停留时,需在整榀桁架梁下面搭设支架或枕木垛支承;所有钢丝绳绑扎在混凝土柱上临时固定时,均需要在其4个角点用直径114mm圆管切半保护好绑扎点,以防钢丝绳受力摩擦断裂;整榀钢桁架梁的临时固定:第一榀钢桁架梁安装就位后,经测量达到要求后,利用原先预埋钢板做临时支撑点,固定住第一榀桁架梁,两边还应用缆风绳拉牢第一榀钢桁架梁的两侧临时固定;继续吊装操作,直至完成5榀钢桁架梁吊装;
(4)校正
整体钢结构屋架就位后应及时进行校正,根据布设的观测点、中心线,通过经纬仪已建立的三维坐标系统形成空间模型,对整体钢结构屋架的水平度、垂直度、标高和挠度进行矫正控制;如偏差超出规定数值,转动支撑上的螺栓纠正,校正无误后,做最后固定。
本发明的狭小空间中钢结构屋架拔杆吊装方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述每榀钢桁架梁的重量为39t。
采用上述技术方案后,本发明的狭小空间中钢结构屋架拔杆吊装方法具有以下优点:
1、采用分段拼装、拔杆吊装的施工方法,吊装空间需求不大,方法简单,施工方便;
2、使大跨度钢梁得以安全、有效的进行施工,特别是受周边环境影响较大、吊车不能直接吊装的工程,能够极大降低狭小空间吊装的安全隐患;
3、降低钢结构桁架梁吊装工程施工成本,满足吊装施工的经济效益。
附图说明
图1为本发明实施例的钢桁架梁分段起吊示意图;
图2为本发明实施例的钢桁架梁分段在组装位置拼装焊接成整榀钢桁架梁示意图;
图3为本发明实施例的用拔杆吊装整榀钢桁架梁示意图。
图中:1第1段钢桁架梁,2第2段钢桁架梁,3第3段钢桁架梁,4混凝土柱钢桁架梁固定座,5钢桁架梁临时支撑点的预设预埋钢板,6整榀钢桁架梁,7拔杆,8钢桁架梁第1吊点,9钢桁架梁第2吊点,10拔杆底部的支撑面。
具体实施方式
以下结合实施例及其附图对本发明作更进一步说明。
实施例1
福州市轨道交通指挥中心工程,位于福州市台江区广达路与达道路交叉口东北角地块。本工程中塔裙楼5层屋面采用钢结构屋架形式,钢结构设计使用年限为100年,结构安全等级为一级,钢屋架长宽为34m*30.3m,标高为20.5m,总重量约400t。屋架上下弦采用焊接箱型管,最大规格为300*350*50*50,最小规格为200*300*14*14,中间连杆有焊接工字钢、H型钢、焊接箱型管。
该工程钢结构屋架由5榀GHJ1焊接箱型管、25榀GHJ2焊接箱型管及GL1、GL2、GC1钢结构连接件组成。中塔钢结构屋架在四层混凝土柱施工完,混凝土强度达到要求后进行钢结构吊装施工。
该工程钢结构屋架采用本发明的狭小空间中钢结构屋架拔杆吊装方法,钢结构屋架设5榀钢桁架,该工程两侧塔楼阻挡,不允许吊车进入现场直接吊装。本发明的狭小空间中钢结构屋架拔杆吊装方法包括以下步骤:
a、钢结构屋架的每榀钢桁架梁分段吊运到整榀桁架梁组装位置
依据工程特点及设计意图,将钢结构屋架的每榀钢桁架梁分成三段工厂加工完成,转运现场后每一段钢桁架梁1,2,3应按照顺序进行吊装,放置在移动铁滑床上,用卷扬机吊至标高14.25m整榀钢桁架梁组装位置。图1为本发明实施例的钢桁架梁分段起吊示意图。
b、分段钢桁架梁拼装焊接成整榀钢桁架梁6
图2为本发明实施例的钢桁架梁分段在组装位置拼装焊接成整榀钢桁架梁示意图。在整榀钢桁架梁组装位置将三个分段钢桁架梁拼装焊接成整榀钢桁架梁,所述每榀钢桁架梁的重量为39t。
c、整榀钢桁架梁通过拔杆起吊就位于混凝土柱钢桁架梁固定座4上,包括以下步骤:
图3为本发明实施例的用拔杆吊装整榀钢桁架梁示意图。
(1)安装拔杆
根据整榀钢桁架梁的长度,设置二根拔杆7,二根拔杆用钢丝绳连接整榀钢桁架梁上的两个吊点8,9;拔杆底部的支撑面10应垫实,根据现场情况采用在土建剪力墙上设刚性垫块,拔杆杆头应垂直于整榀钢桁架梁上方,钢丝绳收紧提升时将整榀钢桁架梁水平就位,拔杆四周缆风绳应绑扎牢固,确保其吊装的稳定性;吊装过程中,整榀钢桁架梁两端的绳子应控制好整榀桁架梁的摆动方向,以便于整榀钢桁架梁可靠地在混凝土柱子上就位,整榀钢桁架梁就位标高为20.50m。
(2)试吊
在正式吊装整榀钢桁架梁前应认真做好工艺性试吊工作,确保拔杆的稳定性、吊具的牢固性、空间的可操作性、钢丝绳的张力、起吊的速度、构件标高和垂直度工艺参数符合设计要求。
(3)吊装
吊装过程的控制:整榀钢桁架梁起吊后,不得在高空停留过久,如需要较长时间停留时,需在整榀桁架梁下面搭设支架或枕木垛支承;所有钢丝绳绑扎在混凝土柱上临时固定时,均需要在其4个角点用直径114mm圆管切半保护好绑扎点,以防钢丝绳受力摩擦断裂;整榀钢桁架梁的临时固定:第一榀钢桁架梁安装就位后,经测量达到要求后,利用原先钢桁架梁临时支撑点的预设预埋钢板5做临时支撑点,固定住第一榀桁架梁,两边还应用缆风绳拉牢第一榀钢桁架梁的两侧临时固定;继续吊装操作,直至完成5榀钢桁架梁吊装。
(4)校正
整体钢结构屋架就位后应及时进行校正,根据布设的观测点、中心线,通过经纬仪已建立的三维坐标系统形成空间模型,对整体钢结构屋架的水平度、垂直度、标高和挠度进行矫正控制;如偏差超出规定数值,转动支撑上的螺栓纠正,校正无误后,做最后固定。
本工程钢结构屋架制作始于2015年3月20日,由于屋架GHJ1长度较大为34m,因此在制造厂对每榀桁架梁进行了分段加工,达到要求后运至现场进行拼装,最后通过拔杆进行吊装作业。
该工程于2015年4月15日进行了钢结构屋架的吊装作业,至2015年5月10日吊装完成,整个吊装过程控制到位,钢桁架梁准确固定,吊装过程无任何安全事故,钢结构屋面稳定性满足要求。
本发明具有实质性特点和显著的技术进步,本发明的狭小空间中钢结构屋架拔杆吊装方法,在周边有建筑物、吊装位置为四层楼面的狭小空间进行吊装施工,吊装过程控制其起吊速度、旋转方向、水平度、垂直度等因素,最终圆满完成了吊装作业。在吊装过程中,有监理及业主代表进行了旁站、观察验收等。
通过检查验收显示,该工程钢结构屋面吊装如期完成钢结构安装任务,质量符合设计及规范要求,并无任何安全事故,整个过程满足现场施工管理及福建省标化工地要求,得到各参建方的好评。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。
Claims (2)
1.一种狭小空间中钢结构屋架拔杆吊装方法,钢结构屋架总重量400t,设5榀钢桁架,每榀钢桁架梁长34米,高2米;两侧塔楼阻挡,不允许吊车进入现场直接吊装;其特征在于包括以下步骤:
a、钢结构屋架的每榀钢桁架梁分段吊运到整榀钢桁架梁组装位置
依据工程特点及设计意图,将钢结构屋架的每榀钢桁架梁分成三段工厂加工完成,转运现场后每一段钢桁架梁应按照顺序进行吊装,放置在移动铁滑床上,用卷扬机吊至标高14.25m整榀钢桁架梁组装位置;
b、分段钢桁架梁拼装焊接成整榀桁架梁
在整榀桁架梁组装位置将三个分段钢桁架梁拼装焊接成整榀桁架梁;
c、整榀桁架梁通过拔杆起吊就位于混凝土柱子上,包括以下步骤:
(1)安装拔杆
根据整榀桁架梁的长度,设置二根拔杆,二根拔杆用钢丝绳连接整榀桁架梁上的两个吊点;拔杆底部的支撑面或者支座应垫实,根据现场情况采用在土建剪力墙上设刚性垫块,拔杆杆头应垂直于整榀桁架梁上方,钢丝绳收紧提升时将整榀桁架梁水平就位,拔杆四周缆风绳应绑扎牢固,确保其吊装的稳定性;吊装过程中,整榀桁架梁两端的绳子应控制好整榀桁架梁的摆动方向,以便于整榀桁架梁可靠地在混凝土柱子上就位,整榀桁架梁就位标高为20.50m;
(2)试吊
在正式吊装整榀桁架梁前应认真做好工艺性试吊工作,确保拔杆的稳定性、吊具的牢固性、空间的可操作性、钢丝绳的张力、起吊的速度、构件标高和垂直度工艺参数符合设计要求;
(3)吊装
吊装过程的控制:整榀桁架梁起吊后,不得在高空停留过久,如需要较长时间停留时,需在整榀桁架梁下面搭设支架或枕木垛支承;所有钢丝绳绑扎在砼柱上临时固定时,均需要在其4个角点用直径114mm圆管切半保护好绑扎点,以防钢丝绳受力摩擦断裂;整榀桁架梁的临时固定:第一榀桁架梁安装就位后,经测量达到要求后,利用原先预埋钢板做临时支撑点,固定住第一榀桁架梁,两边还应用缆风绳拉牢第一榀桁架梁的两侧临时固定;继续吊装操作,直至完成5榀钢桁架吊装;
(4)校正
整体钢结构屋架就位后应及时进行校正,根据布设的观测点、中心线,通过经纬仪已建立的三维坐标系统形成空间模型,对整体钢结构屋架的水平度、垂直度、标高和挠度进行矫正控制;如偏差超出规定数值,转动支撑上的螺栓纠正,校正无误后,做最后固定。
2.如权利要求1所述的狭小空间中钢结构屋架拔杆吊装方法,其特征在于,所述每榀钢桁架梁的重量为39t。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510250450.0A CN106703416B (zh) | 2015-07-30 | 2015-07-30 | 狭小空间中钢结构屋架拔杆吊装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510250450.0A CN106703416B (zh) | 2015-07-30 | 2015-07-30 | 狭小空间中钢结构屋架拔杆吊装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106703416A true CN106703416A (zh) | 2017-05-24 |
CN106703416B CN106703416B (zh) | 2018-12-14 |
Family
ID=58898043
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510250450.0A Active CN106703416B (zh) | 2015-07-30 | 2015-07-30 | 狭小空间中钢结构屋架拔杆吊装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106703416B (zh) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107558743A (zh) * | 2017-08-28 | 2018-01-09 | 南通振华重型装备制造有限公司 | 一种升压站分段划分及合拢工艺 |
CN107740588A (zh) * | 2017-10-21 | 2018-02-27 | 北京房修建筑工程有限公司 | 一种城市内狭小地段建筑施工材料的吊装运输方法 |
CN108265987A (zh) * | 2018-01-29 | 2018-07-10 | 江苏江中集团有限公司 | 一种大跨度空间桁架的安装方法 |
CN109083268A (zh) * | 2018-10-29 | 2018-12-25 | 中国冶集团有限公司 | 狭小多障碍区域双层不同倾斜角度通廊一次吊装就位方法 |
CN109972845A (zh) * | 2019-04-11 | 2019-07-05 | 中国十九冶集团有限公司 | 钢屋架的安装方法 |
CN110409840A (zh) * | 2019-07-29 | 2019-11-05 | 中国人民解放军63926部队 | 屋架吊装方法 |
CN110984611A (zh) * | 2019-11-29 | 2020-04-10 | 中国二十二冶集团有限公司 | 狭窄空间钢柱安装方法 |
CN111379425A (zh) * | 2020-03-26 | 2020-07-07 | 山西四建集团有限公司 | 一种狭小空间大跨度多曲面异型组合钢桁架安装施工方法 |
CN111719860A (zh) * | 2020-07-05 | 2020-09-29 | 青岛新华友建工集团股份有限公司 | 一种大跨度复杂拱架屋盖施工工艺 |
CN111877761A (zh) * | 2020-06-19 | 2020-11-03 | 上海建工集团股份有限公司 | 一种可装配式预制混凝土柱自动化安装工装系统及方法 |
CN114439249A (zh) * | 2022-04-07 | 2022-05-06 | 中铁建工集团有限公司 | 一种大跨三角桁架空中转体提升施工方法 |
CN114687565A (zh) * | 2022-04-26 | 2022-07-01 | 中国建筑第七工程局有限公司 | 高空拼接滑移提升大跨度钢梁施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101255768A (zh) * | 2008-03-21 | 2008-09-03 | 宁波建工集团有限公司 | 一种大跨度钢桁架高空安装方法 |
CN103132702A (zh) * | 2011-12-01 | 2013-06-05 | 安徽跨宇钢结构网架工程有限公司 | 一种大跨度管桁架拔杆提升、空中施转就位施工方法 |
CN103669885A (zh) * | 2013-12-12 | 2014-03-26 | 上海通用金属结构工程有限公司 | 超大跨度钢桁架分段吊装工艺 |
-
2015
- 2015-07-30 CN CN201510250450.0A patent/CN106703416B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101255768A (zh) * | 2008-03-21 | 2008-09-03 | 宁波建工集团有限公司 | 一种大跨度钢桁架高空安装方法 |
CN103132702A (zh) * | 2011-12-01 | 2013-06-05 | 安徽跨宇钢结构网架工程有限公司 | 一种大跨度管桁架拔杆提升、空中施转就位施工方法 |
CN103669885A (zh) * | 2013-12-12 | 2014-03-26 | 上海通用金属结构工程有限公司 | 超大跨度钢桁架分段吊装工艺 |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107558743A (zh) * | 2017-08-28 | 2018-01-09 | 南通振华重型装备制造有限公司 | 一种升压站分段划分及合拢工艺 |
CN107740588A (zh) * | 2017-10-21 | 2018-02-27 | 北京房修建筑工程有限公司 | 一种城市内狭小地段建筑施工材料的吊装运输方法 |
CN107740588B (zh) * | 2017-10-21 | 2019-09-06 | 北京房修一建筑工程有限公司 | 一种城市内狭小地段建筑施工材料的吊装运输方法 |
CN108265987A (zh) * | 2018-01-29 | 2018-07-10 | 江苏江中集团有限公司 | 一种大跨度空间桁架的安装方法 |
CN109083268A (zh) * | 2018-10-29 | 2018-12-25 | 中国冶集团有限公司 | 狭小多障碍区域双层不同倾斜角度通廊一次吊装就位方法 |
CN109972845A (zh) * | 2019-04-11 | 2019-07-05 | 中国十九冶集团有限公司 | 钢屋架的安装方法 |
CN110409840A (zh) * | 2019-07-29 | 2019-11-05 | 中国人民解放军63926部队 | 屋架吊装方法 |
CN110984611A (zh) * | 2019-11-29 | 2020-04-10 | 中国二十二冶集团有限公司 | 狭窄空间钢柱安装方法 |
CN111379425A (zh) * | 2020-03-26 | 2020-07-07 | 山西四建集团有限公司 | 一种狭小空间大跨度多曲面异型组合钢桁架安装施工方法 |
CN111877761A (zh) * | 2020-06-19 | 2020-11-03 | 上海建工集团股份有限公司 | 一种可装配式预制混凝土柱自动化安装工装系统及方法 |
CN111719860A (zh) * | 2020-07-05 | 2020-09-29 | 青岛新华友建工集团股份有限公司 | 一种大跨度复杂拱架屋盖施工工艺 |
CN114439249A (zh) * | 2022-04-07 | 2022-05-06 | 中铁建工集团有限公司 | 一种大跨三角桁架空中转体提升施工方法 |
CN114687565A (zh) * | 2022-04-26 | 2022-07-01 | 中国建筑第七工程局有限公司 | 高空拼接滑移提升大跨度钢梁施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106703416B (zh) | 2018-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106703416B (zh) | 狭小空间中钢结构屋架拔杆吊装方法 | |
CN103291076B (zh) | 弧形框架内多层次钢桁架分片逆向吊装施工方法 | |
CN103410322B (zh) | 大跨度平行桁架钢连廊施工方法 | |
CN201321675Y (zh) | 大跨度双层球面网壳穹顶结构 | |
CN102296858B (zh) | 水泥生产线熟料储存库屋面钢结构及其施工方法 | |
CN107013038B (zh) | 一种大型建筑物屋顶采光中庭的钢结构滑移换柱施工方法 | |
CN205558304U (zh) | 一种大型钢连廊桁架的吊装系统 | |
CN203296361U (zh) | 大跨度钢结构跨外组对吊装平台 | |
CN114439249B (zh) | 一种大跨三角桁架空中转体提升施工方法 | |
CN103184722B (zh) | 大跨度双层贝雷桁架结构及其施工方法 | |
CN104674665B (zh) | 大空间钢结构连廊桥安装方法 | |
CN114232805B (zh) | 一种超高度大跨度钢混凝土梁吊挂结构的施工方法 | |
CN108277882A (zh) | 恶劣条件下特大型钢结构雨棚施工工艺 | |
CN106223623B (zh) | 钢结构箱型拱形屋架安装方法 | |
CN103290784A (zh) | 拱梁结合桥吊装施工方法 | |
CN102337782B (zh) | 一种高大空间顶部施工桁架平台提升系统 | |
CN109607399B (zh) | 一种安装屋顶网架的吊装工艺 | |
CN112324131B (zh) | 一架两用大跨度劲性梁施工结构及其施工工法 | |
CN107245953A (zh) | 一种多层桥梁结构的排架装置及交叉施工方法 | |
CN114775882B (zh) | 一种膜-不锈钢-铝合金-拉索组合结构 | |
CN109457814B (zh) | 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法 | |
CN202689016U (zh) | 深水桥墩双壁钢围堰施工用围堰拼装及提升平台 | |
CN107419907A (zh) | 一种炼钢塔楼钢结构平台的交错安装焊接方法 | |
CN108792963A (zh) | 一种用于高层屋面构架的空间钢桁架式塔吊附墙支座方法 | |
CN207499525U (zh) | 一种用于剧院主舞台钢梁的安装支撑结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |