CN106351428B - A kind of floor tile paving suite of tools and its paving technique - Google Patents
A kind of floor tile paving suite of tools and its paving technique Download PDFInfo
- Publication number
- CN106351428B CN106351428B CN201610748531.8A CN201610748531A CN106351428B CN 106351428 B CN106351428 B CN 106351428B CN 201610748531 A CN201610748531 A CN 201610748531A CN 106351428 B CN106351428 B CN 106351428B
- Authority
- CN
- China
- Prior art keywords
- behaviour
- paving
- floor tile
- mortar
- flatrack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
- E04F21/20—Implements for finishing work on buildings for laying flooring
- E04F21/22—Implements for finishing work on buildings for laying flooring of single elements, e.g. flooring cramps ; flexible webs
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Floor Finish (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a kind of floor tile paving suite of tools and its paving techniques, wherein floor tile paving suite of tools, including:Behaviour's pricker rake tries bed board and scrapes crutch, and behaviour's pricker rake includes:Handle, end body and Duo Gen spike-tooths, the end body are vertically installed in one end of handle, and the more spike-tooths are uniformly arranged on the side of end body, and the length of the end body is set as 350 ~ 550mm;The examination bed board includes:Plate body and handle, the handle are set in the middle part of any one large end face of plate body, and the thickness of the plate body is set as 5 ~ 10mm;The crutch of scraping includes:Flatrack and bearing support are grasped, behaviour's flatrack is set to above bearing support, and the bottom setting of behaviour's flatrack is there are four casing, and four branch leg outer sides of the bearing support are provided with four journal stirrups, and middle sleeve and journal stirrup match.By the above-mentioned means, the present invention can reduce labor intensity, paving quality and efficiency are improved.
Description
Technical field
The present invention relates to building fields, more particularly to a kind of floor tile paving suite of tools and its paving technique.
Background technology
Existing floor tile paving technological process is:Brick → tile work → maintenance → jointing is selected in preparation of construction → base treatment →.Its
Middle tile work specific operation process is:Operating personnel mixing is qualified, as bed course 1:4 stiff mortars are shoveled with spade in paving
On ground, then squats down and flattened stiff mortar with trowel;Stand up again will the floor tile of paving remove to paving position and squat down progress
Examination paving;It digs floor tile and checks that whether uniform the bedding mortar after examination paving is, closely knit consistent;It stands again and brick is removed to operation console,
The sticking mortar (to prevent floor tile hollowing, sticking mortar from also requiring that uniformly) of thickness about 10-12mm is smeared at its back side with trowel, then will
Brick is removed to paving, is squatted down and is carried out paving.
In terms of from tile work this operating process, either flattening bedding mortar or applied sticking mortar, operating personnel makes
Trowel.And the device without controllable mortar flatness, the uniformity on trowel, mortar quality is entirely because of the horizontal height of operating personnel
And there are deviations;In addition, one piece of brick of paving, it can be seen that operator needs to squat down repeatedly,.Floor tile also will be moved repeatedly, work
Make that step is more, labor intensity is big, work efficiency is low.
Invention content
The invention mainly solves the technical problem of providing a kind of floor tile paving suite of tools and its paving techniques, can drop
Low labor intensity improves paving quality and efficiency.
In order to solve the above technical problems, one aspect of the present invention is:A kind of floor tile paving tool cover is provided
Part, including:Behaviour's pricker rake tries bed board and scrapes crutch, and behaviour's pricker rake includes:Handle, end body and Duo Gen spike-tooths, the end body
It is vertically installed in one end of handle, the more spike-tooths are uniformly arranged on the side of end body, and the length of the end body is set as 350
~550mm;The examination bed board includes:Plate body and handle, the handle are set in the middle part of any one large end face of plate body, the plate
The thickness of body is set as 5~10mm;The crutch of scraping includes:Behaviour's flatrack and bearing support, behaviour's flatrack are set on bearing support
Side, there are four casing, four branch leg outer sides of the bearing support are provided with four journal stirrups for the bottom setting of behaviour's flatrack, wherein
Casing and journal stirrup match, and the planar dimension of behaviour's flatrack is set as 900mm*900mm, and the planar dimension of the bearing support is set
It is set to 300mm*300mm, the height of bearing support is set as 650~850mm, and the outline border height of behaviour's flatrack is higher than bearing support 22
~24mm.
Preferably, the upper surface of behaviour's flatrack is provided with a rotating handle, one end of the rotating handle is solid by shaft
Due to one end of behaviour's flatrack.
Preferably, it is symmetrically arranged with a pair of of reinforcing plate between the handle and end body of behaviour's pricker rake.
In order to solve the above technical problems, another technical solution used in the present invention is:A kind of floor tile paving technique is provided,
It is characterized in that, including mainly the following steps:
One, early-stage preparations:In-site measurement unwrapping wire, and tile work typesetting is carried out according to actual size, draw CAD construction drawings;
Two, base treatment:Flooring cleaning, wet water;
Three, live tile work
One), mortar mixing:Mixing is laid on dry cement mortar of the flooring as bed course and gluing for the floor tile back side
Paste mortar;
Two) control line, is drawn:According to typesetting figure, vertical, horizontal paving finished surface control line is drawn in shown position;
Three), matting layer mortar:Place mat dry cement mortar bedding cushion on flooring will disposably need the same of paving
The bedding mortar of row's floor tile is transported to paving position, and mortar thickness need to be slightly above longitudinal and transverse horizontal absolute altitude control line;
Four), bedding mortar behaviour is smooth even:Operating personnel are longitudinal and transverse to screed with behaviour's pricker rake in slightly stooped over position of standing
Both direction is harrowed one time one by one, and it is even that phaeodium therein is broken up rake, and is bulldozed mortar face, keeps it substantially concordant with control line;
Five), examination spreads and adjusts:Paving point is played according to typesetting figure, carrying out examination paving when examination is spread with examination bed board uses rubber hammer
Tapped around among examination bed board, the flatness and density of board bottom bedding mortar checked after examination paving, to local out-of-flatness or
Uncompacted position is suitably adjusted with behaviour's pricker rake, is allowed to meet the requirements;
Six), slurry is scraped at the floor tile back side:The floor tile back side is positioned over upward in the behaviour's flatrack for scraping crutch, is taken with trowel appropriate viscous
It is placed on it to paste mortar, and tentatively behaviour is flat;Rotating handle in rotation behaviour's flatrack, keeps sticking mortar face smooth, closely knit, to local injustice
Whole, closely knit place, carry out benefit slurry, grasp again it is flat;
Seven), floor tile paving:Floor tile alignment paving position is gently put down, face is touched with rubber hammer to fully horizontal, and is made
It is concordant with longitudinal and transverse control line, keeps horizontal with adjacent floor tile, it is ensured that gap size is consistent, and horizon rule is used in combination to check whole water
Pingdu;
Four, removing surface:After the completion of paving, the dust and mortar of tile surface are cleared up immediately, to prevent mortar on ground
Brick surface is bonded;
Five, jointing and finished product protection:After paving is completed 24 hours, the dust impurity in floor tile brickwork joint is cleared up in time, is carried out
Jointing and finished product protection.
The beneficial effects of the invention are as follows:1, with behaviour's pricker rake operation bedding mortar, harrowing studded one side with behaviour's pricker will
Phaeodium rake in bedding mortar dissipates, and using the consistency of its tooth pitch, makes dry mortar density evenly;Also pricker will can be grasped
Upward, using its, end body is counter pushes away mortar, makes its surface more smooth for the tooth mouth of rake, is harrowed using behaviour's pricker, operating personnel can stand
Operation, it is both lighter than trowel operation, and operating surface is big every time, work efficiency is high;2, floor tile examination paving is replaced with examination bed board, floor tile is avoided to remove
It removes, reduces operation sequence and labor intensity;Again because examination bed board carries handle, examination paving is convenient, fast, is not easy disturbance lower part
Bedding mortar and surrounding floor tile, improve construction quality and work efficiency;3, sand is pasted batch to scrape the floor tile back side using scraping crutch
Slurry had not only alleviated usually floor tile and has been put in ground or operates the problem easily tired out every bending in lower positions such as buckets temporarily, but also improved
The density and flatness of sticking mortar reduce the quality problems of floor tile paving hollowing.
Description of the drawings
Fig. 1 is that a kind of floor tile paving suite of tools of the present invention and its paving technique one are preferably implemented
The dimensional structure diagram of behaviour's pricker rake in example;
Fig. 2 is the dimensional structure diagram of shown examination bed board;
Fig. 3 is the vertical view for scraping crutch;
Fig. 4 is the Section A-A schematic diagram of shown Fig. 3;
Fig. 5 is the section B-B schematic diagram of shown Fig. 3;
Fig. 6 is the front view of the bearing support;
Fig. 7 is the front view of behaviour's flatrack;
The label of each component is as follows in attached drawing:1, behaviour's pricker rake, 11, handle, 12, end body, 13, spike-tooth, 14, reinforcing plate,
2, bed board is tried, 21, plate body, 22, handle, 3, scrape crutch, 31, behaviour's flatrack, 32, bearing support, 33, rotating handle, 34, shaft, 35, branch
Ear, 36, casing, 4, floor tile.
Specific implementation mode
The preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings, so that advantages and features of the invention energy
It is easier to be readily appreciated by one skilled in the art, so as to make a clearer definition of the protection scope of the present invention.
It please refers to Fig.1 to Fig. 7, the embodiment of the present invention 1 includes:
A kind of floor tile paving suite of tools, including:Behaviour's pricker rake 1 tries bed board 2 and scrapes crutch 3,1 packet of behaviour's pricker rake
It includes:Handle 11, end body 12 and Duo Gen spike-tooths 13, the end body 12 are vertically installed in one end of handle 11, the more spike-tooths 13
It is uniformly arranged on the side of end body 12, the length of the end body 12 is set as 550mm;The examination bed board 2 includes:Plate body 21 and handle
Hand 22, the handle 22 are set in the middle part of any one large end face of plate body 21, and the thickness of the plate body 21 is set as 8mm;It is described
Scraping crutch 3 includes:Flatrack 31 and bearing support 32 are grasped, behaviour's flatrack 31 is set to 32 top of bearing support, behaviour's flatrack 31
There are four casing 36, four branch leg outer sides of the bearing support 32 are provided with four journal stirrups 35,36 He of middle sleeve for bottom setting
Journal stirrup 35 matches, and the planar dimension of behaviour's flatrack 31 is set as 900mm*900mm, and the planar dimension of the bearing support 32 is set
It is set to 300mm*300mm, the height of bearing support 32 is set as 700mm, and the outline border height of behaviour's flatrack 31 is higher than bearing support
22mm。
Further, the upper surface of behaviour's flatrack 31 is provided with a rotating handle 33, one end of the rotating handle 33 is logical
One end that shaft 34 is fixed on behaviour's flatrack 31 is crossed, a pair is symmetrically arranged between the handle 11 and end body 12 of behaviour's pricker rake 1
Reinforcing plate 14.
The invention also discloses a kind of floor tile paving techniques, include mainly the following steps:
One, early-stage preparations:In-site measurement unwrapping wire, and tile work typesetting is carried out according to actual size, draw CAD construction drawings;
Two, base treatment:Flooring cleaning, wet water;
Three, live tile work
One), mortar mixing:Mixing is laid on dry cement mortar of the flooring as bed course and gluing for the floor tile back side
Paste mortar;
Two) control line, is drawn:According to typesetting figure, vertical, horizontal paving finished surface control line is drawn in shown position;
Three), matting layer mortar:Place mat dry cement mortar bedding cushion on flooring will disposably need the same of paving
The bedding mortar of row's floor tile is transported to paving position, and mortar thickness need to be slightly above longitudinal and transverse horizontal absolute altitude control line;
Four), bedding mortar behaviour is smooth even:Operating personnel are longitudinal and transverse to screed with behaviour's pricker rake in slightly stooped over position of standing
Both direction is harrowed one time one by one, and it is even that phaeodium therein is broken up rake, and is bulldozed mortar face, keeps it substantially concordant with control line;
Five), examination spreads and adjusts:Paving point is played according to typesetting figure, carrying out examination paving when examination is spread with examination bed board uses rubber hammer
Tapped around among examination bed board, the flatness and density of board bottom bedding mortar checked after examination paving, to local out-of-flatness or
Uncompacted position is suitably adjusted with behaviour's pricker rake, is allowed to meet the requirements;
Six), slurry is scraped at the floor tile back side:The floor tile back side is positioned over upward in the behaviour's flatrack for scraping crutch, is taken with trowel appropriate viscous
It is placed on it to paste mortar, and tentatively behaviour is flat;Rotating handle in rotation behaviour's flatrack, keeps sticking mortar face smooth, closely knit, to local injustice
Whole, closely knit place, carry out benefit slurry, grasp again it is flat;
Seven), floor tile paving:Floor tile alignment paving position is gently put down, face is touched with rubber hammer to fully horizontal, and is made
It is concordant with longitudinal and transverse control line, keeps horizontal with adjacent floor tile, it is ensured that gap size is consistent, and horizon rule is used in combination to check whole water
Pingdu;
Four, removing surface:After the completion of paving, the dust and mortar of tile surface are cleared up immediately, to prevent mortar on ground
Brick surface is bonded;
Five, jointing and finished product protection:After paving is completed 24 hours, the dust impurity in floor tile brickwork joint is cleared up in time, is carried out
Jointing and finished product protection.
In embodiment 1, the length of the handle is set as 1200mm, and 12 length of end body of behaviour's pricker rake 1 is set as
550mm is relatively suitble to big region floor tile paving.
Embodiment 2, a kind of floor tile paving suite of tools, including:Behaviour's pricker rake 1 tries bed board 2 and scrapes crutch 3, behaviour's sand
Rake 1 includes:Handle 11, end body 12 and Duo Gen spike-tooths 13, the end body 12 are vertically installed in one end of handle 11, described more
Spike-tooth 13 is uniformly arranged on the side of end body 12, and the length of the end body 12 is set as 350mm;The examination bed board 2 includes:Plate body
21 and handle 22, the handle 22 is set in the middle part of any one large end face of plate body 21, and the thickness of the plate body 21 is set as
10mm;The crutch 3 of scraping includes:Flatrack 31 and bearing support 32 are grasped, behaviour's flatrack 31 is set to 32 top of bearing support, the behaviour
There are four casing 36, four branch leg outer sides of the bearing support 32 are provided with four journal stirrups 35 for the bottom setting of flatrack 31, wherein
Casing 36 and journal stirrup 35 match, and the planar dimension of behaviour's flatrack 31 is set as 900mm*900mm, and the bearing support 32 is put down
Face is sized to 300mm*300mm, and the height of bearing support 32 is set as 800mm, and the outline border height of behaviour's flatrack 31 is higher than
Bearing support 24mm.
Its tile work mode is same as Example 1, unlike, the length of the handle 11 is set as 300mm, the end body
12 length are set as 350mm, compare the floor tile paving of suitable cell domain.
Conventional to use trowel tool, can only squat down bed course grasp and put down below in floor tile, can not stand, rapidly entire row
It grasps in advance smooth even, especially for large area, large space floor tile paving, and behaviour pricker of the present invention is used to harrow 1, behaviour puts down
The advantage of bed course becomes apparent from, surface more smooth, and using behaviour's pricker rake 1, operating personnel can both be operated than trowel with standing operation
Easily, and every time operating surface is big, and work efficiency is high.
Example the above is only the implementation of the present invention is not intended to limit the scope of the invention, every to utilize this hair
Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills
Art field, is included within the scope of the present invention.
Claims (4)
1. a kind of floor tile paving suite of tools, which is characterized in that including:Behaviour's pricker rake tries bed board and scrapes crutch, behaviour's pricker
Rake includes:Handle, end body and Duo Gen spike-tooths, the end body are vertically installed in one end of handle, and the more spike-tooths are uniformly arranged
In the side of end body, the length of the end body is set as 350~550mm;The examination bed board includes:Plate body and handle, described
Hand is set in the middle part of any one large end face of plate body, and the thickness of the plate body is set as 5~10mm;The crutch of scraping includes:Behaviour
Flatrack and bearing support, behaviour's flatrack are set to above bearing support, and there are four casing, the branch for the bottom setting of behaviour's flatrack
Four branch leg outer sides of bolster are provided with four journal stirrups, and middle sleeve and journal stirrup match, and the planar dimension of behaviour's flatrack is set
It is set to 900mm*900mm, the planar dimension of the bearing support is set as 300mm*300mm, and the height of bearing support is set as 650~
The outline border height of 850mm, behaviour's flatrack are higher than 22~24mm of bearing support.
2. a kind of floor tile paving suite of tools according to claim 1, which is characterized in that in the upper surface of behaviour's flatrack
It is provided with a rotating handle, one end of the rotating handle is fixed on one end of behaviour's flatrack by shaft.
3. a kind of floor tile paving suite of tools according to claim 1, which is characterized in that it is described behaviour pricker rake handle with
It is symmetrically arranged with a pair of of reinforcing plate between the body of end.
4. a kind of existed using a kind of paving technique of floor tile paving suite of tools, feature as described in claim any one of 1-3
In mainly including the following steps:
One, early-stage preparations:In-site measurement unwrapping wire, and tile work typesetting is carried out according to actual size, draw CAD construction drawings;
Two, base treatment:Flooring cleaning, wet water;
Three, live tile work
One), mortar mixing:Mixing is laid on dry cement mortar of the flooring as bed course and the stickup sand for the floor tile back side
Slurry;
Two) control line, is drawn:According to typesetting figure, vertical, horizontal paving finished surface control line is drawn in shown position;
Three), matting layer mortar:Place mat dry cement mortar bedding cushion on flooring, with will disposably needing the same row of paving
The bedding mortar of brick is transported to paving position, and mortar thickness need to be slightly above longitudinal and transverse horizontal absolute altitude control line;
Four), bedding mortar behaviour is smooth even:Operating personnel harrow two longitudinal and transverse to screed in slightly stooped over position of standing, with behaviour's pricker
Direction is harrowed one time one by one, and it is even that phaeodium therein is broken up rake, and is bulldozed mortar face, keeps it substantially concordant with control line;
Five), examination spreads and adjusts:Paving point is played according to typesetting figure, examination paving is carried out with examination bed board, when examination is spread, uses rubber hammer from examination
It is tapped around among bed board, the flatness and density of board bottom bedding mortar is checked after examination paving, to local out-of-flatness or not close
Real position is suitably adjusted with behaviour's pricker rake, is allowed to meet the requirements;
Six), slurry is scraped at the floor tile back side:The floor tile back side is positioned over upward in the behaviour's flatrack for scraping crutch, appropriate stickup sand is taken with trowel
Starch placed on it, and tentatively behaviour is flat;Rotation behaviour flatrack on rotating handle, keep sticking mortar face smooth, closely knit, to local out-of-flatness,
Closely knit place, carry out benefit slurry, grasp again it is flat;
Seven), floor tile paving:Floor tile alignment paving position is gently put down, face is touched with rubber hammer to fully horizontal, and make its with
Longitudinal and transverse control line is concordant, keeps horizontal with adjacent floor tile, it is ensured that gap size is consistent, and horizon rule is used in combination to check integral level degree;
Four, removing surface:After the completion of paving, the dust and mortar of tile surface are cleared up immediately, to prevent mortar in floor tile table
Face is bonded;
Five, jointing and finished product protection:After paving is completed 24 hours, the dust impurity in floor tile brickwork joint is cleared up in time, carries out jointing
And finished product protection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610748531.8A CN106351428B (en) | 2016-08-30 | 2016-08-30 | A kind of floor tile paving suite of tools and its paving technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610748531.8A CN106351428B (en) | 2016-08-30 | 2016-08-30 | A kind of floor tile paving suite of tools and its paving technique |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106351428A CN106351428A (en) | 2017-01-25 |
CN106351428B true CN106351428B (en) | 2018-10-09 |
Family
ID=57855477
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610748531.8A Active CN106351428B (en) | 2016-08-30 | 2016-08-30 | A kind of floor tile paving suite of tools and its paving technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106351428B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111794061B (en) * | 2020-07-17 | 2021-09-28 | 济南园林开发建设集团有限公司 | Trial paving device for stone paving and stone paving method |
CN113379917B (en) * | 2021-06-30 | 2023-04-07 | 杭州群核信息技术有限公司 | Space joint method and device for 3D cloud design, electronic equipment and medium |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US988457A (en) * | 1909-07-06 | 1911-04-04 | Winfield Scott Glasscock | Sidewalk-tool. |
CA1223750A (en) * | 1986-03-05 | 1987-07-07 | Roger Rouillard | Concrete levelling screed |
US4702641A (en) * | 1986-05-01 | 1987-10-27 | Atlanta Concrete Accessories Inc. | Multi-purpose concrete working tool |
US5605415A (en) * | 1995-05-25 | 1997-02-25 | Michael A. Marshall | Screed bar attachment |
CN102900224A (en) * | 2012-04-28 | 2013-01-30 | 郭卫康 | Device and method for fixing floor tiles quickly and accurately |
CN202787910U (en) * | 2012-08-31 | 2013-03-13 | 包德彬 | Plate-type plaster hawk |
CN203320915U (en) * | 2013-06-06 | 2013-12-04 | 王海浪 | Tool for paving floor tiles |
CN103726642A (en) * | 2013-11-25 | 2014-04-16 | 成都市翻鑫家科技有限公司 | Plastering trowel |
-
2016
- 2016-08-30 CN CN201610748531.8A patent/CN106351428B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN106351428A (en) | 2017-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106351428B (en) | A kind of floor tile paving suite of tools and its paving technique | |
CN105587102B (en) | A kind of wet construction method to the wet type high abrasion terrace that paves | |
CN107152145A (en) | A kind of stone material flooring construction method | |
CN104372916B (en) | The sand-lime tiling device of floor tile | |
CN109098464A (en) | A kind of renovation technology of old tile floor | |
CN103174274A (en) | Stone material seamless polishing construction method | |
CN110397291A (en) | A kind of fast placing box-shaped spatula tool | |
CN207829495U (en) | Control the combination tool of building wall level, vertical mortar joint plumpness and thickness | |
CN206503342U (en) | One kind laying floor tile leveling unit | |
CN204326481U (en) | The sand-lime tiling device of paving brick | |
CN111197357A (en) | Anti-cracking construction method for floor insulation board surface layer | |
CN210798338U (en) | Mortar laying and seam scraping integrated construction device for wall masonry | |
CN206360380U (en) | A kind of horizontal mortar joint and vertical mortar joint control device | |
CN105155388A (en) | Road surface laying method for exposed aggregate finish | |
CN212535125U (en) | High-precision low-power-consumption simple masonry tool | |
CN108547431A (en) | Paste the processing unit and method of floor infiltration after floor tile in a kind of toilet | |
CN204754149U (en) | A husky ware of electronic harrow for laying ceramic tile | |
CN208105802U (en) | A kind of floor tile joint filling device for interior decoration | |
CN207526073U (en) | A kind of ceramic tile positioning and gap control device | |
CN216340680U (en) | Ceramic tile plastering device | |
CN206448501U (en) | A kind of floor covering layers locating rack | |
CN207079887U (en) | A kind of exterior wall leatheroid brick gummer | |
CN110469131A (en) | The building wall grey raking integrative construction device of paving and method | |
CN206308955U (en) | Stone material terrace makes somebody a mere figurehead pre- assembling structure | |
CN214834491U (en) | Special tool for jointing paving stone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |