CN106284011A - Roadbed construction method - Google Patents
Roadbed construction method Download PDFInfo
- Publication number
- CN106284011A CN106284011A CN201610674178.3A CN201610674178A CN106284011A CN 106284011 A CN106284011 A CN 106284011A CN 201610674178 A CN201610674178 A CN 201610674178A CN 106284011 A CN106284011 A CN 106284011A
- Authority
- CN
- China
- Prior art keywords
- layer
- making
- construction method
- roadbed
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/04—Foundations produced by soil stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The open a kind of roadbed construction method of the present invention, comprises the following steps: S1, excavates rhone outside the roadbed of original place, and S2, the unwrapping wire of pile for prestressed pipe positions, press-fits, determines stake;S3, original place road excavation to target depth forms basic unit, element soil and the Calx levelling grinding compacting of doping;S4, point two-layer making blotter, every layer thickness is 90 100mm;S5, making geogrids layer: point two-layer making, first making steel plastic geogrid, repave stone powder levelling;S6, making reinforced concrete floor: form tiling grid shape bar-mat reinforcement, casting concrete on bar-mat reinforcement and pile for prestressed pipe in pile for prestressed pipe assembling reinforcement weld around;S7, making anti-filter geotechnique's layer of cloth;Anti-filter geotechnique's layer of cloth includes anti-filter geotextiles and covers the geomembrane at anti-filter Geotextile;S8, pours bitumen layer;Divide three layers to pour, every layer of 5cm.The present invention has the advantage that steadiness is good, settling amount is low.
Description
Technical field
The present invention relates to road construction territory, it is more particularly related to a kind of roadbed construction method.
Background technology
There is considerable muddy soft soil coastal area, and muddy soft soil layer is thicker, and some areas are even more than 15
Rice.For the deepest Soft Roadbed, its embankment stability extreme difference, use change fill out, draining board consolidation, powder-spray pile, water
Soft base construction quality after the conventional construction method process such as mud mixing pile is difficult to reach ideal effect, its treatment of soft foundation road
Settlement after construction and the jumping car phenomenon of section are extremely serious.
Summary of the invention
For weak point present in above-mentioned technology, the present invention provides the roadbed that a kind of steadiness is good, reduce settling amount
Construction method.
In order to realize according to object of the present invention and further advantage, the present invention is achieved through the following technical solutions:
Roadbed construction method of the present invention,
S1, removes original place surface irregularities, excavates rhone outside the roadbed of original place,
S2, the unwrapping wire of pile for prestressed pipe positions, press-fits, determines stake;
S3, original place road excavation forms basic unit to target depth, rolls levelling with the element soil doping of described basic unit for Calx
Closely knit;
S4, making blotter, point two-layer making, every layer thickness is 90-100mm, and the rubble of lower level floor embeds element soil
In;
S5, making geogrids layer: point two-layer making, first making steel plastic geogrid, repave stone powder levelling;
S6, making reinforced concrete floor: in described geogrids layer, in pile for prestressed pipe assembling reinforcement weld around shape
Becoming tiling grid shape bar-mat reinforcement, casting concrete on described bar-mat reinforcement and described pile for prestressed pipe, described concrete is by weight
Mark is poured formed in stone 10%-15%, cement 22%-35%, sand 30%-40%, the ratio of water 20%-30%;
S7, making anti-filter geotechnique's layer of cloth;Described anti-filter geotechnique's layer of cloth includes anti-filter geotextiles and covers anti-filter geotechnique
The geomembrane on cloth surface;
S8, pours bitumen layer;Divide three layers to pour, every layer of 5cm.
Preferably, described rhone is less than original place roadbed 1.6m;Described excavation target depth is 50mm.
Preferably, the weight fraction ratio of described Calx and described element soil is 0.18:1, and the compactness of described basic unit is
90%.
Preferably, described blotter by cobble or particle size range 30~40mm crushed stone roll laying and form.
Preferably, in described stone powder, stone, stone powder, white lime granule, the weight fraction ratio of miscellaneous soil are 42:37:
11:10。
The present invention at least includes following beneficial effect:
Roadbed construction method of the present invention, after excavating rhone outside roadbed, placing pile for prestressed pipe, opens
After digging basic unit, making blotter, geogrids layer, reinforced concrete floor, anti-filter geotechnique's layer of cloth and bitumen layer successively, effectively
Consolidate basic unit, improve antiseepage, thus reduce settling amount.
Part is embodied by the further advantage of the present invention, target and feature by description below, and part also will be by this
Invention research and practice and be understood by the person skilled in the art.
Accompanying drawing explanation
Fig. 1 is the flow chart of roadbed construction method of the present invention.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art with reference to description literary composition
Word can be implemented according to this.
Should be appreciated that used herein such as " have ", " comprising " and " including " term do not allot one or many
Other element individual or the existence of a combination thereof or interpolation.
As it is shown in figure 1, the present invention provides a kind of roadbed construction method, comprise the following steps:
S1, removes original place surface irregularities, excavates rhone outside the roadbed of original place,
S2, the unwrapping wire of pile for prestressed pipe positions, press-fits, determines stake;
S3, original place road excavation forms basic unit to target depth, rolls levelling with the element soil doping of described basic unit for Calx
Closely knit;
S4, making blotter, point two-layer making, every layer thickness is 90-100mm, and the rubble of lower level floor embeds element soil
In;
S5, making geogrids layer: point two-layer making, first making steel plastic geogrid, repave stone powder levelling;
S6, making reinforced concrete floor: in described geogrids layer, in pile for prestressed pipe assembling reinforcement weld around shape
Becoming tiling grid shape bar-mat reinforcement, casting concrete on described bar-mat reinforcement and described pile for prestressed pipe, described concrete is by weight
Mark is poured formed in stone 10%-15%, cement 22%-35%, sand 30%-40%, the ratio of water 20%-30%;
S7, making anti-filter geotechnique's layer of cloth;Described anti-filter geotechnique's layer of cloth includes anti-filter geotextiles and covers anti-filter geotechnique
The geomembrane on cloth surface;
S8, pours bitumen layer;Divide three layers to pour, every layer of 5cm.
Wherein, rhone is less than original place roadbed 1.6m;Excavation target depth is 50mm.Calx and the weight fraction ratio of element soil
Example is 0.18:1, and the compactness of basic unit is 90%.The element soil doping levelling grinding compacting of Calx of basic unit, significantly reduces element soil
Water content.Place pile for prestressed pipe, improve the bearing capacity of roadbed.Blotter by cobble or particle size range 30~40mm broken
Stone rolls laying and forms, making blotter, further increases the bearing capacity of roadbed.Stone in stone powder, stone powder, white
Ash particle, the weight fraction ratio of miscellaneous soil are 42:37:11:10, repave stone powder levelling after making steel plastic geogrid, aging resistance,
Oxidation susceptibility, can the corrosion of the adverse circumstances such as acid and alkali resistance, salt, there is stronger bearing capacity.Good the breathing freely of anti-filter geotextiles
Property and water penetration, make current pass through, and the soil particle that effectively dams, fine sand, little building stones etc., to keep the steadiness of roadbed.
Comparative example
The roadbed construction method of the present invention is compared with comparative example 1 and comparative example 2 construction method, such as table 1 institute
Show:
Table 1 construction technology and parameter compare
From above-mentioned table 1, in the roadbed construction method of present invention offer and work progress, parameters ratio sets
Putting, subgrade moisture content is relatively low, compacting counting is higher;There is the advantage that steadiness is good, settling amount is low.
Although embodiment of the present invention are disclosed as above, but it is not restricted in description and embodiment listed
Use.It can be applied to various applicable the field of the invention completely.Can be easily for those skilled in the art
Realize other amendment.Therefore, under the general concept limited without departing substantially from claim and equivalency range, the present invention does not limit
In specific details with shown here as the legend with description.
Claims (5)
1. a roadbed construction method, it is characterised in that construction method comprises the following steps:
S1, removes original place surface irregularities, excavates rhone outside the roadbed of original place,
S2, the unwrapping wire of pile for prestressed pipe positions, press-fits, determines stake;
S3, original place road excavation forms basic unit to target depth, and adulterate levelling grinding compacting by the element soil of Calx with described basic unit;
S4, making blotter, point two-layer making, every layer thickness is 90-100mm, and the rubble of lower level floor embeds in element soil;
S5, making geogrids layer: point two-layer making, first making steel plastic geogrid, repave stone powder levelling;
S6, making reinforced concrete floor: in described geogrids layer, formed flat in pile for prestressed pipe assembling reinforcement weld around
Lapping trellis bar-mat reinforcement, casting concrete on described bar-mat reinforcement and described pile for prestressed pipe, described concrete is by weight fraction
Poured formed in stone 10%-15%, cement 22%-35%, sand 30%-40%, the ratio of water 20%-30%;
S7, making anti-filter geotechnique's layer of cloth;Described anti-filter geotechnique's layer of cloth includes anti-filter geotextiles and covers at anti-filter geotextiles table
The geomembrane in face;
S8, pours bitumen layer;Divide three layers to pour, every layer of 5cm.
2. roadbed construction method as claimed in claim 1, it is characterised in that described rhone is less than original place roadbed 1.6m;Institute
Stating excavation target depth is 50mm.
3. roadbed construction method as claimed in claim 1, it is characterised in that described Calx and the weight fraction ratio of described element soil
Example is 0.18:1, and the compactness of described basic unit is 90%.
4. roadbed construction method as claimed in claim 1, it is characterised in that
Described blotter by cobble or particle size range 30~40mm crushed stone roll laying and form.
5. roadbed construction method as claimed in claim 1, it is characterised in that
In described stone powder, stone, stone powder, white lime granule, the weight fraction ratio of miscellaneous soil are 42:37:11:10.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610674178.3A CN106284011B (en) | 2016-08-16 | 2016-08-16 | Roadbed construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610674178.3A CN106284011B (en) | 2016-08-16 | 2016-08-16 | Roadbed construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106284011A true CN106284011A (en) | 2017-01-04 |
CN106284011B CN106284011B (en) | 2018-08-28 |
Family
ID=57678074
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610674178.3A Active CN106284011B (en) | 2016-08-16 | 2016-08-16 | Roadbed construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106284011B (en) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419630A (en) * | 2017-06-13 | 2017-12-01 | 华中科技大学 | A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction |
CN108385460A (en) * | 2018-01-22 | 2018-08-10 | 中国十七冶集团有限公司 | The construction method of road base course on a kind of basement roof |
CN108560344A (en) * | 2018-04-28 | 2018-09-21 | 长沙理工大学 | A kind of old road base punishment depth determination method based on PFWD modulus |
CN108611932A (en) * | 2018-05-15 | 2018-10-02 | 中铁第六勘察设计院集团有限公司 | It is a kind of pass through pool, fish pond location multiply road railway high-fill roadbed construction method |
CN109183539A (en) * | 2018-09-05 | 2019-01-11 | 辽宁工程技术大学 | A kind of soft soil roadbed construction method |
CN109537385A (en) * | 2018-10-23 | 2019-03-29 | 中交公局第七工程有限公司 | Construction process for filling foundation with silt |
CN109750572A (en) * | 2019-03-13 | 2019-05-14 | 岩土科技股份有限公司 | A kind of steelframe geotechnique frame is used for the construction method of dirt road base instead of block stone |
CN109778986A (en) * | 2017-11-15 | 2019-05-21 | 北京建工路桥集团有限公司 | A kind of prestressed concrete pipe road preventing differential settlement and its construction method |
CN110144783A (en) * | 2019-04-26 | 2019-08-20 | 福建省昊立建设工程有限公司 | A kind of roadbed construction method |
CN110184870A (en) * | 2019-06-17 | 2019-08-30 | 中交第三公路工程局有限公司 | Subtropical mountains highway mixture roadbed filling method |
CN110273339A (en) * | 2019-07-18 | 2019-09-24 | 厦门东翔工程设计有限公司 | A kind of land subsidence crack resistence structure and its construction method |
CN110499682A (en) * | 2019-08-02 | 2019-11-26 | 广州市绿化公司 | A kind of two pass formula jogging track and construction method |
CN110593292A (en) * | 2019-09-05 | 2019-12-20 | 广州市花木公司 | Foundation cushion structure and construction method |
CN110670437A (en) * | 2019-10-16 | 2020-01-10 | 王伟 | Method for reinforcing and treating soft foundation of newly-built highway engineering |
CN111041930A (en) * | 2019-12-25 | 2020-04-21 | 华润建筑有限公司 | Expressway anti-scouring roadbed pavement and construction method |
CN111535103A (en) * | 2020-04-15 | 2020-08-14 | 上海蓝彬新材料科技有限公司 | Municipal roadbed construction method |
CN112227123A (en) * | 2020-10-23 | 2021-01-15 | 中民集团第二工程有限公司 | Construction method for backfilling road subgrade by matching excavator |
CN112227124A (en) * | 2020-10-26 | 2021-01-15 | 温州展业建设工程有限公司 | Construction method for highway subgrade treatment |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10317307A (en) * | 1997-05-19 | 1998-12-02 | Dia Consultant:Kk | Construction method for road |
CN103806433A (en) * | 2014-03-06 | 2014-05-21 | 四川雅豪房地产开发有限公司 | Foundation backfill reinforcement method |
CN104894937A (en) * | 2015-04-10 | 2015-09-09 | 成军 | Construction method for mucky soft soil roadbase tubular pile |
CN205223768U (en) * | 2015-12-17 | 2016-05-11 | 杨继峰 | Road subgrade sedimentation preventing facility |
CN105648867A (en) * | 2016-03-02 | 2016-06-08 | 杭州江润科技有限公司 | Comprehensive ecological roadbed system and construction method |
-
2016
- 2016-08-16 CN CN201610674178.3A patent/CN106284011B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10317307A (en) * | 1997-05-19 | 1998-12-02 | Dia Consultant:Kk | Construction method for road |
CN103806433A (en) * | 2014-03-06 | 2014-05-21 | 四川雅豪房地产开发有限公司 | Foundation backfill reinforcement method |
CN104894937A (en) * | 2015-04-10 | 2015-09-09 | 成军 | Construction method for mucky soft soil roadbase tubular pile |
CN205223768U (en) * | 2015-12-17 | 2016-05-11 | 杨继峰 | Road subgrade sedimentation preventing facility |
CN105648867A (en) * | 2016-03-02 | 2016-06-08 | 杭州江润科技有限公司 | Comprehensive ecological roadbed system and construction method |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419630A (en) * | 2017-06-13 | 2017-12-01 | 华中科技大学 | A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction |
CN107419630B (en) * | 2017-06-13 | 2023-06-20 | 华中科技大学 | Soft soil foundation high-filling embankment capable of effectively controlling post-construction settlement and construction method |
CN109778986A (en) * | 2017-11-15 | 2019-05-21 | 北京建工路桥集团有限公司 | A kind of prestressed concrete pipe road preventing differential settlement and its construction method |
CN108385460A (en) * | 2018-01-22 | 2018-08-10 | 中国十七冶集团有限公司 | The construction method of road base course on a kind of basement roof |
CN108560344A (en) * | 2018-04-28 | 2018-09-21 | 长沙理工大学 | A kind of old road base punishment depth determination method based on PFWD modulus |
CN108560344B (en) * | 2018-04-28 | 2020-04-17 | 长沙理工大学 | Old roadbed treatment depth determination method based on PFWD modulus |
CN108611932A (en) * | 2018-05-15 | 2018-10-02 | 中铁第六勘察设计院集团有限公司 | It is a kind of pass through pool, fish pond location multiply road railway high-fill roadbed construction method |
CN109183539A (en) * | 2018-09-05 | 2019-01-11 | 辽宁工程技术大学 | A kind of soft soil roadbed construction method |
CN109537385A (en) * | 2018-10-23 | 2019-03-29 | 中交公局第七工程有限公司 | Construction process for filling foundation with silt |
CN109750572A (en) * | 2019-03-13 | 2019-05-14 | 岩土科技股份有限公司 | A kind of steelframe geotechnique frame is used for the construction method of dirt road base instead of block stone |
CN110144783A (en) * | 2019-04-26 | 2019-08-20 | 福建省昊立建设工程有限公司 | A kind of roadbed construction method |
CN110144783B (en) * | 2019-04-26 | 2020-04-28 | 福建省昊立建设工程有限公司 | Roadbed construction method |
CN110184870A (en) * | 2019-06-17 | 2019-08-30 | 中交第三公路工程局有限公司 | Subtropical mountains highway mixture roadbed filling method |
CN110273339A (en) * | 2019-07-18 | 2019-09-24 | 厦门东翔工程设计有限公司 | A kind of land subsidence crack resistence structure and its construction method |
CN110499682A (en) * | 2019-08-02 | 2019-11-26 | 广州市绿化公司 | A kind of two pass formula jogging track and construction method |
CN110593292A (en) * | 2019-09-05 | 2019-12-20 | 广州市花木公司 | Foundation cushion structure and construction method |
CN110670437A (en) * | 2019-10-16 | 2020-01-10 | 王伟 | Method for reinforcing and treating soft foundation of newly-built highway engineering |
CN110670437B (en) * | 2019-10-16 | 2021-12-10 | 陕西建工东方蓝海岩土集团有限公司 | Method for reinforcing and treating soft foundation of newly-built highway engineering |
CN111041930A (en) * | 2019-12-25 | 2020-04-21 | 华润建筑有限公司 | Expressway anti-scouring roadbed pavement and construction method |
CN111535103A (en) * | 2020-04-15 | 2020-08-14 | 上海蓝彬新材料科技有限公司 | Municipal roadbed construction method |
CN112227123A (en) * | 2020-10-23 | 2021-01-15 | 中民集团第二工程有限公司 | Construction method for backfilling road subgrade by matching excavator |
CN112227124A (en) * | 2020-10-26 | 2021-01-15 | 温州展业建设工程有限公司 | Construction method for highway subgrade treatment |
Also Published As
Publication number | Publication date |
---|---|
CN106284011B (en) | 2018-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106284011B (en) | Roadbed construction method | |
CN106320123B (en) | Construction of Soft Soil Subgrade method | |
CN101343852B (en) | Method for filling highroad roadbed by waste steel slags | |
CN204059124U (en) | A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure | |
CN109056786A (en) | Face upward inclined road shoulder wall water drainage behind the wall system and construction method | |
CN104131555B (en) | A kind of outsourcing water penetration concrete reinforced pipe crushed stone grouting pile and construction method thereof | |
CN107419630A (en) | A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction | |
CN203383119U (en) | Novel widening structure of highway embankment | |
CN101634143A (en) | Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay | |
CN108560542B (en) | Waste tire coated building slag bidirectional reinforcement and construction method thereof | |
CN103334357B (en) | Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method | |
CN103981876B (en) | For deep soft foundation river course be close to combined member and the construction method that river embankment is built together | |
CN110144783B (en) | Roadbed construction method | |
CN206902488U (en) | A kind of soft soil foundation high-filled embankment of effectively control settlement after construction | |
CN203393530U (en) | Anti-floating lightweight high-fill embankment structure | |
CN110093823B (en) | Construction method of soft soil roadbed | |
CN108412016A (en) | Underground tube body assures construction method | |
CN104480956B (en) | A kind of minor diameter mold-bagged concrete pile composite foundation | |
CN109610429A (en) | Sedimentation treatment method under a kind of Collapsible Loess District prevention gas collection station ground and terrace | |
CN107881987A (en) | Deep covering layer top panel Rockfill Dam based moisture barrier structure | |
CN104099936A (en) | Cascading waterfall waterscape structure on artificial stacked mountain and construction method thereof | |
CN116377780A (en) | Mountain highway high-fill roadbed filling construction method | |
CN111794030A (en) | Method for widening dyke foundation at through-dyke building | |
CN108824412B (en) | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination | |
CN106592363A (en) | Construction method for municipal soft soil roadbed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200331 Address after: 102600 No. 1 Building, No. 13 Keyuan Road, Daxing District, Beijing Patentee after: CHINA ZHONGHUA GEOTECHNICAL ENGINEERING GROUP Co.,Ltd. Address before: 231400 Anhui city of Anqing province Tongcheng city longmian Street sand road Tongcheng Yongjin Construction Engineering Company Limited Patentee before: TONGCHENG YONGJIN BUILDING ENGINEERING Co.,Ltd. |