CN110273339A - A kind of land subsidence crack resistence structure and its construction method - Google Patents

A kind of land subsidence crack resistence structure and its construction method Download PDF

Info

Publication number
CN110273339A
CN110273339A CN201910648988.5A CN201910648988A CN110273339A CN 110273339 A CN110273339 A CN 110273339A CN 201910648988 A CN201910648988 A CN 201910648988A CN 110273339 A CN110273339 A CN 110273339A
Authority
CN
China
Prior art keywords
ground
layer
concrete
construction method
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910648988.5A
Other languages
Chinese (zh)
Other versions
CN110273339B (en
Inventor
陈永波
陈建华
连航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Jiarong Construction Engineering Technology Co ltd
Original Assignee
Xiamen Dongxiang Engineering Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Dongxiang Engineering Design Co Ltd filed Critical Xiamen Dongxiang Engineering Design Co Ltd
Priority to CN201910648988.5A priority Critical patent/CN110273339B/en
Publication of CN110273339A publication Critical patent/CN110273339A/en
Application granted granted Critical
Publication of CN110273339B publication Critical patent/CN110273339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明的目的一是公开了一种地面下沉防开裂结构及其施工方法,属于建筑施工领域,其技术方案要点是S1:基层地面夯实;S2:在夯实后的基层地面上插入地梁,并对基层地面进行再次压实;S3:在地梁内部插设有竖直钢筋,在地梁上浇筑挡土墙;S4:在基层地面上铺设填料层;S5:在填料层的上方浇筑混凝土板层,在混凝土板层间留有结构缝,结构缝和地梁在同一竖直面内;S6:在混凝土板层的上方铺设有回填土层,并对回填土层进行压实;S7:在回填土层的上方浇筑一层混凝土固结层;达到避免地面出现大面积的开裂现象的效果,本发明的目的二是提供一种地面下沉防开裂结构,防止地面出现大面积的开裂现象。

The first object of the present invention is to disclose a ground subsidence anti-cracking structure and its construction method, which belong to the field of building construction. The key points of the technical solution are S1: tamping the base ground; S2: inserting ground beams on the tamped base ground, And re-compact the ground of the base; S3: insert vertical steel bars inside the ground beams, and pour retaining walls on the ground beams; S4: lay a filler layer on the base ground; S5: pour concrete above the filler layer As for the slab, there are structural joints between the concrete slabs, and the structural joints and the ground beams are in the same vertical plane; S6: A backfill soil layer is laid above the concrete slab, and the backfill soil layer is compacted; S7: Pour a layer of concrete consolidation layer above the backfill soil layer; achieve the effect of avoiding large-area cracking on the ground. The second object of the present invention is to provide a ground subsidence and anti-cracking structure to prevent large-area cracking on the ground. .

Description

一种地面下沉防开裂结构及其施工方法Ground sinking anti-cracking structure and construction method thereof

技术领域technical field

本发明涉及建筑施工领域,特别涉及一种地面下沉防开裂结构及其施工方法。The invention relates to the field of building construction, in particular to a ground subsidence anti-cracking structure and a construction method thereof.

背景技术Background technique

近年来,随着我国经济的不断发展和城市建设的开展,尤其是一些沿海城市土地需求不断扩大,对于沿海地区建筑主体结构,一般采用桩基础,将主体结构的载荷通过柱传入下部较好土质的持力层中,确保主体而机构的沉降满足规范的需求。In recent years, with the continuous development of my country's economy and the development of urban construction, especially in some coastal cities, the land demand continues to expand. For the main structure of buildings in coastal areas, pile foundations are generally used, and it is better to transfer the load of the main structure to the lower part through columns. In the soil bearing layer, ensure that the settlement of the main body and the mechanism meets the requirements of the code.

现有的一些施工中,为节省成本,在素土夯实后直接做100mm混凝土面层,但是由于该方法中混凝土面层以下土体还未固结,公共建筑物或房屋使用多年后,底层地面沉降量很大,而在柱周边承台位置处沉降较小,导致柱周边承台交接处的地面出现大面积的开裂现象和不均匀的沉降,不尽影响地面的美观性能,同时也会影响公共设施或房屋的安全使用。In some existing constructions, in order to save costs, a 100mm concrete surface layer is directly made after the plain soil is rammed. However, in this method, the soil below the concrete surface layer has not yet consolidated. After many years of use of public buildings or houses, the underlying ground The amount of settlement is large, but the settlement at the caps around the columns is small, resulting in large-scale cracking and uneven settlement on the ground at the junction of the caps around the columns, which not only affects the aesthetic performance of the ground, but also affects Safe use of public facilities or premises.

发明内容Contents of the invention

针对现有技术存在的不足,本发明的目的一是提供一种地面下沉防开裂施工方法,达到避免地面出现大面积的开裂现象的效果;本发明的目的二是提供一种地面下沉防开裂结构,防止地面出现大面积的开裂现象。In view of the deficiencies in the prior art, the first object of the present invention is to provide a ground subsidence anti-cracking construction method to achieve the effect of avoiding large-scale cracking on the ground; the second object of the present invention is to provide a ground subsidence anti-cracking method. Cracking structure to prevent large-scale cracking on the ground.

本发明的上述技术目的是通过以下技术方案得以实现的:Above-mentioned technical purpose of the present invention is achieved through the following technical solutions:

一种地面下沉防开裂施工方法,包括如下步骤:A ground subsidence anti-cracking construction method, comprising the following steps:

S1:基层地面夯实;S1: Compact the ground at the base level;

S2:在夯实后的基层地面上插入地梁,并对基层地面进行再次压实;S2: insert ground beams on the tamped base ground, and re-compact the base ground;

S3:在地梁内部插设有竖直钢筋,竖直钢筋直径为8mm,并在地梁上浇筑挡土墙;S3: A vertical steel bar is inserted inside the ground beam with a diameter of 8mm, and a retaining wall is poured on the ground beam;

S4:在基层地面上铺设填料层,并对填料层进行压实;填料层的厚度为450mm-550mm,填料层由碎石和粘性土组成,填料层干密度≥2.1t/m,碎石粒径≤50mm;S4: Lay a filler layer on the base floor and compact the filler layer; the thickness of the filler layer is 450mm-550mm, the filler layer is composed of gravel and cohesive soil, the dry density of the filler layer is ≥2.1t/m, and the gravel particles Diameter≤50mm;

S5:在填料层的上方浇筑混凝土板层,混凝土板层的厚度为120mm,同时在混凝土板层内埋设有多个加固钢筋,加固钢筋的直径为8mm,相邻加固钢筋间的距离为200mm,在浇筑混凝土板层时,在混凝土板层间留有结构缝,结构缝和地梁在同一竖直面内;S5: Concrete slab is poured above the filler layer. The thickness of the concrete slab is 120mm. At the same time, a number of reinforcement bars are embedded in the concrete slab. The diameter of the reinforcement bars is 8mm, and the distance between adjacent reinforcement bars is 200mm. When pouring concrete slabs, there are structural joints between the concrete slabs, and the structural joints and ground beams are in the same vertical plane;

S6:在混凝土板层的上方铺设有回填土层,并对回填土层进行压实;S6: A backfill soil layer is laid above the concrete slab layer, and the backfill soil layer is compacted;

S7:在回填土层的上方浇筑一层混凝土固结层。S7: Pour a layer of concrete consolidation layer above the backfill soil layer.

通过采用上述技术方案,将基层地面夯实,使得基层地面成为有力的持力层,然后再将地梁埋入基层地面内,插入地梁内部的竖直钢筋,不仅能够加强地梁与挡土墙之间的连接强度,同时还助于削弱施加在挡土墙上的外力,从而减少外力对地梁的冲击。然在基层地面上铺设的碎石和粘性土,提高基层地面得到承载能力,而粘性土压实后水稳定性好,强度较高,毛细作用大,使得填料层刚度一致,从而使得地面均匀沉降,防止地面出现大面积的开裂现象。碎石粒径≤50mm时,提高填料层的致密度,有助于地面均匀沉降,有效防止碎石粒径过大时,填料层的孔隙率过大,会导致地面受力不均,从而会影响地面的均匀沉降。By adopting the above-mentioned technical scheme, the ground of the base is tamped, so that the ground of the base becomes a strong bearing layer, and then the ground beams are buried in the ground of the base, and the vertical steel bars inserted into the ground beams can not only strengthen the ground beams and retaining walls At the same time, it also helps to weaken the external force applied to the retaining wall, thereby reducing the impact of external force on the ground beam. However, the gravel and cohesive soil laid on the base layer can improve the bearing capacity of the base layer, and the cohesive soil has good water stability, high strength and strong capillary action after compaction, so that the stiffness of the filling layer is consistent, so that the ground can evenly settle , to prevent large areas of cracking on the ground. When the particle size of the crushed stone is ≤50mm, the density of the filler layer is increased, which is helpful for the uniform settlement of the ground, and effectively prevents that when the particle size of the crushed stone is too large, the porosity of the filler layer is too large, which will lead to uneven force on the ground, which will cause Affects the uniform settlement of the ground.

混凝土板层的厚度为120mm时,能有效提高回填土层的承载能力,有效提高回填土层的使用寿命,同时混凝土板层内部的加固钢筋,不仅对混凝土板层起到加固作用,同时也能削弱部分地面载荷,使得地面能够均匀沉降。结构缝设置在回填土层的下方时,保证回填土层的承重力,同时还能避免回填土层载荷传递到地梁处,而影响地梁的稳定性以及地梁与基层地面间的连接强度,避免地面出现大面积的沉降裂缝。When the thickness of the concrete slab is 120mm, it can effectively improve the bearing capacity of the backfill soil layer and effectively increase the service life of the backfill soil layer. Weaken part of the ground load so that the ground can settle evenly. When the structural joints are set under the backfill soil layer, the bearing capacity of the backfill soil layer can be guaranteed, and at the same time, the load of the backfill soil layer can be prevented from being transmitted to the ground beam, which will affect the stability of the ground beam and the connection strength between the ground beam and the base ground. , to avoid large areas of subsidence cracks on the ground.

本发明进一步设置为,S4中,碎石和粘性土的比例为3:7。In the present invention, it is further set that in S4, the ratio of gravel to cohesive soil is 3:7.

通过采用上述技术方案,碎石和粘性土的比例为3:7时,保证填料层具有一定的坚固度,同时还使得填料层还具有一定的透水性,使得渗入填料层的水分能够均匀扩散,从而使得填料层的软硬程度一致,从而使得填料层能够均匀沉降,有效避免地面出现大面积的裂缝。By adopting the above technical scheme, when the ratio of gravel and cohesive soil is 3:7, the packing layer has a certain firmness, and at the same time, the packing layer also has a certain water permeability, so that the water infiltrated into the packing layer can be evenly diffused, Therefore, the softness and hardness of the filler layer are consistent, so that the filler layer can settle evenly, and effectively avoid large-area cracks on the ground.

本发明进一步设置为,S4中,填料层采用分层压实的方法,分层厚度为250mm,压实系数不小于0.95。In the present invention, it is further set that, in S4, the filler layer is compacted in layers, the thickness of the layers is 250 mm, and the compaction coefficient is not less than 0.95.

通过采用上述技术方案,填料层分层压实能有效提高填料层的承载能力,使得填料层能够均匀沉降,填料层分层压实的厚度过高时,位于底部的填料层不能紧密压紧,当分层压实的厚度过低时,会使得施工成本增加,因此分层压实的厚度为250mm时,既能保证填料层被压实,同时还节省施工成本。By adopting the above technical scheme, the layered compaction of the filler layer can effectively improve the bearing capacity of the filler layer, so that the filler layer can settle evenly. When the thickness of the layered compaction of the filler layer is too high, the filler layer at the bottom cannot be compacted tightly. When the thickness of the layered compaction is too low, the construction cost will be increased. Therefore, when the thickness of the layered compaction is 250mm, it can not only ensure that the packing layer is compacted, but also save the construction cost.

本发明进一步设置为,S4中,在填料层的上方铺设有一层厚度为15mm的弹性层,弹性层由环氧树脂和橡胶粉组成。The present invention is further provided that, in S4, an elastic layer with a thickness of 15 mm is laid on the filler layer, and the elastic layer is composed of epoxy resin and rubber powder.

通过采用上述技术方案,弹性层的设置能够有效削弱穿过混凝土板层的载荷,从而使得传递到填料层内部的载荷减小,填料层的沉降量也大大变小,防止出现不均匀沉降,环氧树脂和橡胶粉具有一定的弹性和抗冲击能力,能够有效削弱混凝土板层下方的载荷,使得整个地面能够均匀沉降,防止出现大面积的裂缝。By adopting the above technical scheme, the setting of the elastic layer can effectively weaken the load passing through the concrete slab, thereby reducing the load transmitted to the inside of the filler layer, and the settlement of the filler layer is also greatly reduced, preventing uneven settlement, and the ring Oxygen resin and rubber powder have certain elasticity and impact resistance, which can effectively weaken the load under the concrete slab, so that the entire ground can evenly settle and prevent large-scale cracks.

本发明进一步设置为,S5中,结构缝的宽度为30mm。In the present invention, it is further set that, in S5, the width of the structural seam is 30 mm.

通过采用上述技术方案,结构缝的宽度为30mm时,有效阻断地面上的载荷传送到地梁上,同时也方便工作人员施工。By adopting the above technical scheme, when the width of the structural joint is 30mm, it can effectively block the load on the ground from being transmitted to the ground beam, and it is also convenient for the workers to construct.

本发明进一步设置为,在竖直方向上,挡土墙设置在结构缝的一侧。The present invention is further provided that, in the vertical direction, the retaining wall is arranged on one side of the structural joint.

通过采用上述技术方案,挡土墙设置在结构缝的一侧后,结构缝能够阻断混凝土板层的水平力向挡土墙传递,减少对挡土墙在水平方向上的冲击力,防止挡土墙与地梁之间出现裂缝而影响回填土层面的稳定性,有效避免出现大面积的裂缝。By adopting the above technical scheme, after the retaining wall is arranged on one side of the structural joint, the structural joint can block the transmission of the horizontal force of the concrete slab to the retaining wall, reduce the impact force on the retaining wall in the horizontal direction, and prevent the The cracks between the earth wall and the ground beam will affect the stability of the backfill soil layer, and effectively avoid large-scale cracks.

本发明进一步设置为,在回填土层和混凝土固结层之间铺设有级配砂石层。The present invention is further provided that a graded sandstone layer is laid between the backfill soil layer and the concrete consolidation layer.

通过采用上述技术方案,回填土层与混凝土固结层之间的级配砂石层,进一步提高混凝土固结层的承载能力,同时级配砂石的选择还有助于提高砂石层的致密度,使得混凝土板层受力均匀,防止混凝土板层因受力不均而出现断裂现象。By adopting the above technical scheme, the graded sand and gravel layer between the backfilling soil layer and the concrete consolidation layer can further improve the bearing capacity of the concrete consolidation layer. The density makes the concrete slab evenly stressed and prevents the concrete slab from breaking due to uneven force.

本发明进一步设置为,在相邻挡土墙之间连接有水平的加固板,在挡土墙上预留有竖直的界面呈凸形的连接槽,加固板与连接槽配合使用。The present invention is further provided that a horizontal reinforcing plate is connected between adjacent retaining walls, and a vertical connecting groove with a convex interface is reserved on the retaining wall, and the reinforcing plate is used in conjunction with the connecting groove.

通过采用上述技术方案,挡土墙之间的加固板,有效防止单个挡土墙与地梁的连接处出现断裂,同时加固板还能削弱部分载荷,保证地面的均匀沉降,而挡土墙上预留的凸形的连接槽,有效防止挡土墙在水平方向的挤压力的作用下而使得加固板与挡土墙脱离,提高加固板的实用性。By adopting the above-mentioned technical scheme, the reinforcing plate between the retaining walls can effectively prevent the joint between a single retaining wall and the ground beam from breaking. The reserved convex connection groove effectively prevents the retaining wall from being detached from the retaining wall under the action of horizontal extrusion force, improving the practicability of the reinforcing plate.

本发明进一步设置为,相邻加固板的之间的距离为100mm。The present invention is further provided that the distance between adjacent reinforcement plates is 100 mm.

通过采用上述技术方案,相邻加固板之间的距离为100mm时,不仅能节省材料和施工成本,同时也有助于削弱填料层内部的载荷,有效避免地面出现大面积裂缝。By adopting the above technical scheme, when the distance between adjacent reinforcement plates is 100mm, it can not only save material and construction costs, but also help to weaken the load inside the packing layer, effectively avoiding large-area cracks on the ground.

本发明的目的二:提供一种地面下沉防开裂结构,从下至上依次包括基层地面、填料层、弹性层、混凝土板层、回填土层、砂石层和混凝土固结层,在基层地面与填料层之间设有地梁,地梁一端插入基层地面内,一端插入填料层内,在地梁上插设有竖直钢筋,并在地梁上浇筑挡土墙,在挡土墙上留设有连接槽,在连接槽内设有与之配合使用的加固板,在混凝土板层开设有结构缝。The second object of the present invention is to provide a ground subsidence and anti-cracking structure, which includes base ground, filler layer, elastic layer, concrete slab layer, backfill soil layer, sand and gravel layer and concrete consolidation layer from bottom to top. There is a ground beam between the ground beam and the filling layer. One end of the ground beam is inserted into the ground of the base layer, and the other end is inserted into the filling layer. Vertical steel bars are inserted on the ground beam, and a retaining wall is poured on the ground beam. On the retaining wall A connecting groove is left, and a reinforcing plate used in conjunction with it is arranged in the connecting groove, and structural joints are opened in the concrete slab.

综上所述,本发明具有以下有益效果:In summary, the present invention has the following beneficial effects:

1、地梁、挡土墙与结构缝的配合使用,既对混凝土固结层起到一定的支撑作用,使得混凝土固结层更加牢固,同时混凝土固结层的载荷向下传送的过程中,挡土墙和结构缝能够有效削弱载荷,减少地梁的承受力,使得整个地面能够均匀沉降,防止地面出现大面积的开裂现象;1. The combined use of ground beams, retaining walls and structural joints not only plays a certain role in supporting the concrete consolidation layer, but also makes the concrete consolidation layer stronger. At the same time, when the load of the concrete consolidation layer is transmitted downward, The retaining wall and structural joints can effectively weaken the load and reduce the bearing capacity of the ground beam, so that the entire ground can settle evenly and prevent large-scale cracking on the ground;

2、弹性层以及砂石层的配合使用,既能够进一步削弱向下传送的载荷,同时对混凝土固结层起到进一步的支撑,使得混凝土固结层的承受力更强,有效避免地面出现大面积的开裂现象;2. The combined use of the elastic layer and the sand and gravel layer can not only further weaken the load transmitted downwards, but also provide further support for the concrete consolidation layer, making the concrete consolidation layer stronger, and effectively avoiding large damage on the ground. Area cracking;

3、连接槽和加固板的配合使用,防止挡土墙与地梁的连接处出现裂缝而使得挡土墙与地梁出现错位,保证挡土墙对混凝土固结层的支撑作用,同时还能削弱载荷。3. The combined use of connecting grooves and reinforcement plates prevents cracks at the joints between the retaining wall and the ground beams, resulting in dislocation between the retaining wall and the ground beams, ensuring the supporting effect of the retaining wall on the concrete consolidation layer, and at the same time Weaken the load.

附图说明Description of drawings

图1是本发明的剖面结构示意图;Fig. 1 is the sectional structure schematic diagram of the present invention;

图2是旨在显示挡土墙上的连接槽和加固板时的部分结构示意图。Fig. 2 is a schematic diagram of part of the structure intended to show the connection grooves and reinforcement plates on the retaining wall.

图中,1、基层地面;2、地梁;21、挡土墙;211、连接槽;22、竖直钢筋;3、填料层;4、混凝土板层;41、加固钢筋;42、结构缝;5、回填土层;6、混凝土固结层;7、弹性层;8、砂石层;9、加固板。In the figure, 1. Base ground; 2. Ground beam; 21. Retaining wall; 211. Connection groove; 22. Vertical reinforcement; 3. Filling layer; 4. Concrete slab; 41. Reinforcement reinforcement; 42. Structural joint ; 5. Backfill soil layer; 6. Concrete consolidation layer; 7. Elastic layer; 8. Sand and gravel layer; 9. Reinforcement board.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.

实施例1Example 1

一种地面下沉防开裂结构,包括基层地面1,在基层地面1内部插设有竖直的地梁2,在基层地面1上铺设有填料层3,在填料层3的上方浇筑有混凝土板层4,在混凝土板层4的上方设有回填土层5,在回填土层5的上方浇筑有混凝土固结层6。A ground subsidence anti-cracking structure, comprising a base floor 1, a vertical ground beam 2 is inserted inside the base floor 1, a filler layer 3 is laid on the base floor 1, and a concrete slab is poured above the filler layer 3 Layer 4, a backfill soil layer 5 is provided above the concrete slab layer 4, and a concrete consolidation layer 6 is poured above the backfill soil layer 5.

如图1所示,地梁2的底端插入基层地面1内部,顶端伸出基层地面1,并与基层地面1表面之间留有距离,在地梁2上插设有竖直钢筋22,竖直钢筋22的底端插入地梁2内部,其顶端穿过填料层3和混凝土板层4位于回填土层5的下方,在地梁2上浇筑有混凝土挡土墙21,竖直钢筋22位于挡土墙21内,且挡土墙21的高度与竖直钢筋22的高度相同。As shown in Figure 1, the bottom end of the ground beam 2 is inserted into the interior of the base ground 1, and the top end protrudes from the base ground 1, leaving a distance from the surface of the base ground 1, and a vertical steel bar 22 is inserted on the ground beam 2, The bottom end of the vertical reinforcement 22 is inserted into the inside of the ground beam 2, and its top passes through the filler layer 3 and the concrete slab layer 4 and is positioned under the backfill soil layer 5. A concrete retaining wall 21 is poured on the ground beam 2, and the vertical reinforcement 22 It is located in the retaining wall 21, and the height of the retaining wall 21 is the same as that of the vertical steel bars 22.

挡土墙21和竖直钢筋22的设置,进一步削弱地梁2上的载荷,同时挡土墙21的设置还对混凝土固结层6起到一定的加强支撑作用,防止混凝土固结层6出现大面积的裂缝,同时竖直钢筋22插入地梁2内部后,使得挡土墙21和地梁2之间的连接更加牢固,防止挡土墙21与地梁2之间出现裂缝。The setting of the retaining wall 21 and the vertical steel bar 22 further weakens the load on the ground beam 2. At the same time, the setting of the retaining wall 21 also plays a certain role in strengthening the concrete consolidation layer 6 to prevent the concrete consolidation layer 6 from appearing. A large area of cracks, while the vertical reinforcement 22 is inserted into the inside of the ground beam 2, makes the connection between the retaining wall 21 and the ground beam 2 more firm, preventing cracks between the retaining wall 21 and the ground beam 2.

如图2所示,在挡土墙21上留设有竖直的连接槽211,连接槽211的截面呈凸形,连接槽211的高度小于挡土墙21的高度,且连接槽211的顶端与挡土墙21的顶端连通。在连接槽211内设有与之配合使用的水平的加固板9,加固板9的一端与其中一个的挡土墙21连接,另一端与相邻的另一个挡土墙21连接。As shown in Figure 2, a vertical connecting groove 211 is left on the retaining wall 21, the cross section of the connecting groove 211 is convex, the height of the connecting groove 211 is less than the height of the retaining wall 21, and the top of the connecting groove 211 It communicates with the top of the retaining wall 21. The connecting groove 211 is provided with a horizontal reinforcing plate 9 used in conjunction with it. One end of the reinforcing plate 9 is connected to one of the retaining walls 21 , and the other end is connected to the other adjacent retaining wall 21 .

相邻挡土墙21之间的加固板9对相邻的挡土墙21起到一定的限定作用,防止挡土墙21在外力的作用下出现倾斜而使得挡土墙21与地梁2之间出现断裂,同时加固板9的作用对填料层3内部的载荷还起到一定的削弱作用,使得基层地面1受力均匀,从而防止混凝土固结层6出现大面积的裂缝现象。The reinforcement plate 9 between the adjacent retaining walls 21 plays a certain role in limiting the adjacent retaining walls 21, preventing the retaining walls 21 from inclining under the action of external force and making the gap between the retaining walls 21 and the ground beams 2 At the same time, the effect of the reinforcing plate 9 also weakens the load inside the filler layer 3 to a certain extent, so that the force on the base layer 1 is uniform, thereby preventing large-area cracks in the concrete consolidation layer 6 .

回看图1,在填料层3与混凝土板层4之间铺设有弹性层7,弹性层7厚度为15mm,弹性层7由环氧树脂和橡胶粉组成。在混凝土板层4上留设有宽度为30mm的结构缝42,且在混凝土板层4内铺设有多个加固钢筋41,多个加固钢筋41间隔均匀设置在混凝土板层4内,结构缝42与地梁2在同一竖直面内,在竖直方向上,结构缝42位于挡土墙21的一侧并靠近挡土墙21。Looking back at Fig. 1, an elastic layer 7 is laid between the filler layer 3 and the concrete slab layer 4, the thickness of the elastic layer 7 is 15mm, and the elastic layer 7 is composed of epoxy resin and rubber powder. A structural joint 42 with a width of 30mm is left on the concrete slab 4, and a plurality of reinforcement bars 41 are laid in the concrete slab 4, and the plurality of reinforcement bars 41 are evenly arranged in the concrete slab 4, and the structural joint 42 In the same vertical plane as the ground beam 2 , in the vertical direction, the structural joint 42 is located on one side of the retaining wall 21 and is close to the retaining wall 21 .

弹性层7的设置进一步削弱传递到混凝土板层4上的载荷,保证基层地面1的稳定性,同时还能使得基层地面1均匀沉降,防止混凝土固结层6出现大面积的裂缝现象,同时结构缝42的设置,能够避免混凝土固结层6载荷直接传递到地梁2上,从而提高地梁2的使用寿命和承载能力。The setting of the elastic layer 7 further weakens the load transmitted to the concrete slab 4, ensures the stability of the base ground 1, and at the same time enables the base ground 1 to settle evenly, preventing large-area cracks in the concrete consolidation layer 6, while the structure The setting of the joint 42 can prevent the load of the concrete consolidation layer 6 from being directly transmitted to the ground beam 2, thereby improving the service life and bearing capacity of the ground beam 2.

回看图1,在回填土层5和混凝土固结层6之间铺设有级配砂石层8,并对砂石层8进行压紧。Looking back at Fig. 1, a graded sandstone layer 8 is laid between the backfill soil layer 5 and the concrete consolidation layer 6, and the sandstone layer 8 is compacted.

本实施例的使用过程如下:The use process of this embodiment is as follows:

在基层地面1上挖槽,将地梁2的底端埋入基层地面1内,并对基层地面1压实,然后将竖直钢筋22的底端插入地梁2内部,然后再在地梁2上浇筑挡土墙21,同时在浇筑的过程中,在挡土墙21上留有竖直的连接槽211,然后在基层地面1上铺设填料层3,当填料层3的高度到达连接槽211的底端后,再将加固板9的两端分别与相邻的两个挡土墙21进行连接,然后继续铺设填料层3,对填料层3压实后,在填料层3的上方铺设弹性层7,在弹性层7的上方浇筑混凝土板层4,并在混凝土板层4上留有结构缝42,在混凝土板层4上铺设回填土层5,在回填土层5的上方再铺设砂石层8,并对回填土层5和砂石层8进行压实,然后在砂石层8的上方浇筑混凝土固结层6。Dig grooves on the base ground 1, bury the bottom end of the ground beam 2 in the base ground 1, and compact the base ground 1, then insert the bottom end of the vertical steel bar 22 into the inside of the ground beam 2, and then place the bottom end of the ground beam 2 on the ground beam 2. Construct the retaining wall 21 on top, and at the same time, during the pouring process, leave a vertical connection groove 211 on the retaining wall 21, and then lay the filler layer 3 on the base ground 1. When the height of the filler layer 3 reaches the connection groove 211, then connect the two ends of the reinforcing plate 9 with the two adjacent retaining walls 21 respectively, then continue to lay the filler layer 3, after the filler layer 3 is compacted, lay on the top of the filler layer 3 The elastic layer 7 is to pour the concrete slab 4 above the elastic layer 7, and leave a structural joint 42 on the concrete slab 4, lay the backfill soil layer 5 on the concrete slab 4, and then lay the backfill soil layer 5 Sand and gravel layer 8, and compact the backfill soil layer 5 and sand and gravel layer 8, and then pour concrete consolidation layer 6 on top of the sand and gravel layer 8.

实施例2Example 2

一种地面下沉防开裂施工方法,包括如下步骤:A ground subsidence anti-cracking construction method, comprising the following steps:

S1:基层地面1处理,对基层地面1进行夯实;S1: Base ground 1 treatment, compacting the base ground 1;

S2:在夯实后的基层地面1上插设有地梁2,地梁2的底端部分位于基层地面1内,顶端位于基层地面1的上方,并与基层地面1的顶层间留有距离,然后对基层地面1进行再次压实;S2: A ground beam 2 is inserted on the tamped base ground 1, the bottom part of the ground beam 2 is located in the base ground 1, the top is located above the base ground 1, and there is a distance between the top layer of the base ground 1, Then carry out compaction again to base ground 1;

S3:在地梁2内部插设有竖直钢筋22,竖直钢筋22直径为8mm,并在地梁2上浇筑挡土墙21,浇筑时在挡土墙21上留有竖直的截面呈凸形的连接槽211;S3: A vertical steel bar 22 is inserted inside the ground beam 2, and the diameter of the vertical steel bar 22 is 8mm, and a retaining wall 21 is poured on the ground beam 2, and a vertical cross section is left on the retaining wall 21 during pouring. Convex connecting groove 211;

S4:在基层地面1上铺设填料层3,并对填料层3进行分层压实,分层厚度为250mm,压实系数不小于0.95;填料层3的厚度为450mm-550mm,其中优选的填料层3的厚度为500mm,填料层3由碎石和粘性土组成,碎石和粘性土的比例为3:7,填料层3干密度≥2.1t/m,碎石粒径≤50mm;S4: Lay the filler layer 3 on the base ground 1, and carry out layered compaction on the filler layer 3, the layer thickness is 250mm, and the compaction coefficient is not less than 0.95; the thickness of the filler layer 3 is 450mm-550mm, and the preferred filler The thickness of layer 3 is 500mm, the filler layer 3 is composed of gravel and cohesive soil, the ratio of gravel and cohesive soil is 3:7, the dry density of filler layer 3 is ≥2.1t/m, and the particle size of gravel is ≤50mm;

S5:在填料层3的上方铺设有厚度为15mm的弹性层7,弹性层7由环氧树脂和橡胶粉组成;S5: An elastic layer 7 with a thickness of 15 mm is laid on the filler layer 3, and the elastic layer 7 is composed of epoxy resin and rubber powder;

S6:在弹性层7的上方浇筑混凝土板层4,混凝土板层4的厚度为120mm,同时在混凝土板层4内埋设有多个加固钢筋41,加固钢筋41的直径为8mm,相邻加固钢筋41间的距离为200mm,在浇筑混凝土板层4时,在混凝土板层4间留有宽度为30mm的结构缝42,结构缝42和地梁2在同一竖直面内,在竖直方向上,结构缝42位于挡土墙21的一侧;S6: Concrete slab 4 is poured above the elastic layer 7. The thickness of the concrete slab 4 is 120 mm. At the same time, a plurality of reinforcement bars 41 are embedded in the concrete slab 4. The diameter of the reinforcement bars 41 is 8 mm. Adjacent reinforcement bars The distance between 41 is 200 mm. When pouring the concrete slab 4, a structural joint 42 with a width of 30 mm is left between the 4 concrete slabs. The structural joint 42 and the ground beam 2 are in the same vertical plane. , the structural joint 42 is located on one side of the retaining wall 21;

S7:在混凝土板层4的上方铺设有回填土层5,并对回填土层5进行压实;S7: A backfill soil layer 5 is laid above the concrete slab layer 4, and the backfill soil layer 5 is compacted;

S8:在回填土层5的上方铺设有级配砂石层8,并对级配砂石层8进行压紧;S8: laying a graded sandstone layer 8 above the backfill soil layer 5, and compacting the graded sandstone layer 8;

S9:在回填土层5的上方浇筑一层混凝土固结层6。S9: Pour a layer of concrete consolidation layer 6 above the backfill soil layer 5 .

本具体实施例仅仅是对本发明的解释,其并不是对本发明的限制,本领域技术人员在阅读完本说明书后可以根据需要对本实施例做出没有创造性贡献的修改,但只要在本发明的权利要求范围内都受到专利法的保护。This specific embodiment is only an explanation of the present invention, and it is not a limitation of the present invention. Those skilled in the art can make modifications to this embodiment without creative contribution as required after reading this specification, but as long as they are within the rights of the present invention All claims are protected by patent law.

Claims (10)

1. a kind of land subsidence crack resistence construction method, which comprises the steps of:
S1: basic ground (1) compacting;
S2: ground beam (2) are inserted into the basic ground (1) after compacting, and basic ground (1) is compacted again;
S3: being inserted with vertical reinforcing bar (22) inside ground beam (2), and vertical reinforcing bar (22) diameter is 8mm, and is poured on ground beam (2) Build retaining wall (21);
S4: packing layer (3) are laid on basic ground (1), and packing layer (3) is compacted;Packing layer (3) with a thickness of 450mm-550mm, packing layer (3) are made of rubble and cohesive soil, packing layer (3) dry density >=2.1t/m, and ballast grain sizes≤ 50mm;
S5: in the top casting concrete plate layer (4) of packing layer (3), Concrete cover (4) with a thickness of 120mm, while mixed It is embedded with multiple reinforced steels (41) in concrete board layer (4), the diameter of reinforced steel (41) is 8mm, adjacent reinforced steel (41) Between distance be 200mm, in casting concrete plate layer (4), there are structural joint (42), structural joints between Concrete cover (4) (42) and ground beam (2) is in same vertical plane;
S6: being equipped with back fill course (5) above Concrete cover (4), and is compacted to back fill course (5);
S7: a layer concrete bonding course (6) is poured above back fill course (5).
2. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in S4, rubble and viscous Property soil ratio be 3:7.
3. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in S4, packing layer (3) Using the method for compaction in layers, lift height 250mm, compacting factor is not less than 0.95.
4. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in S4, in packing layer (3) elastic layer (7) that a layer thickness is 15mm is equipped with above, elastic layer (7) is made of epoxy resin and rubber powder.
5. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in S5, structural joint (42) width is 30mm.
6. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in the vertical direction, Retaining wall (21) is arranged in the side of structural joint (42).
7. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in back fill course (5) Graded sand rock layers (8) are equipped between concrete bonding course (6).
8. a kind of land subsidence crack resistence construction method according to claim 1, it is characterised in that: in adjacent retaining wall (21) it is connected with horizontal securing plate (9) between, the link slot that vertical interface is in convex is reserved on retaining wall (21) (211), securing plate (9) is used cooperatively with link slot (211).
9. a kind of land subsidence crack resistence construction method according to claim 8, it is characterised in that: adjacent securing plate (9) The distance between be 100mm.
10. a kind of land subsidence crack resistence structure, it is characterised in that: from bottom to up successively include basic ground (1), packing layer (3), elastic layer (7), Concrete cover (4), back fill course (5), sand stone layer (8) and concrete bonding course (6), in basic ground (1) ground beam (2) are equipped between packing layer (3), ground beam (2) one end is inserted into basic ground (1), and packing layer (3) are inserted into one end It is interior, it is inserted on ground beam (2) vertical reinforcing bar (22), and pour retaining wall (21) on ground beam (2), is stayed on retaining wall (21) Equipped with link slot (211), it is equipped with the matched securing plate (9) used in link slot (211), is opened in Concrete cover (4) Equipped with structural joint (42).
CN201910648988.5A 2019-07-18 2019-07-18 Ground sinking anti-cracking structure and construction method thereof Active CN110273339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910648988.5A CN110273339B (en) 2019-07-18 2019-07-18 Ground sinking anti-cracking structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910648988.5A CN110273339B (en) 2019-07-18 2019-07-18 Ground sinking anti-cracking structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN110273339A true CN110273339A (en) 2019-09-24
CN110273339B CN110273339B (en) 2021-03-05

Family

ID=67964699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910648988.5A Active CN110273339B (en) 2019-07-18 2019-07-18 Ground sinking anti-cracking structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN110273339B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202672132U (en) * 2011-12-02 2013-01-16 四川省瑞云环境绿化工程有限公司 Reinforcing structure for basement backfilling
CN103174074A (en) * 2013-03-22 2013-06-26 浙江鸿安建设有限公司 Sedimentation control structure of passable road highway roadbed and construction method
CN103215870A (en) * 2013-04-15 2013-07-24 胜利油田胜利勘察设计研究院有限公司 See-through pile plate combined type sea inlet road structure
CN103334357A (en) * 2013-06-07 2013-10-02 上海嘉实(集团)有限公司 Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN203334154U (en) * 2013-06-07 2013-12-11 上海嘉实(集团)有限公司 Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN103774514A (en) * 2014-01-10 2014-05-07 江苏中瑞路桥建设有限公司 Prefabricated tube pile embankment structure and construction method thereof
CN105525605A (en) * 2014-10-27 2016-04-27 牟绍林 Basement backfill area reinforcing method
CN106284011A (en) * 2016-08-16 2017-01-04 桐城市永锦建筑工程有限公司 Roadbed construction method
CN207267989U (en) * 2017-09-18 2018-04-24 天津市东泽天润建筑有限公司 A kind of composite foundation

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202672132U (en) * 2011-12-02 2013-01-16 四川省瑞云环境绿化工程有限公司 Reinforcing structure for basement backfilling
CN103174074A (en) * 2013-03-22 2013-06-26 浙江鸿安建设有限公司 Sedimentation control structure of passable road highway roadbed and construction method
CN103215870A (en) * 2013-04-15 2013-07-24 胜利油田胜利勘察设计研究院有限公司 See-through pile plate combined type sea inlet road structure
CN103334357A (en) * 2013-06-07 2013-10-02 上海嘉实(集团)有限公司 Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN203334154U (en) * 2013-06-07 2013-12-11 上海嘉实(集团)有限公司 Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN103774514A (en) * 2014-01-10 2014-05-07 江苏中瑞路桥建设有限公司 Prefabricated tube pile embankment structure and construction method thereof
CN105525605A (en) * 2014-10-27 2016-04-27 牟绍林 Basement backfill area reinforcing method
CN106284011A (en) * 2016-08-16 2017-01-04 桐城市永锦建筑工程有限公司 Roadbed construction method
CN207267989U (en) * 2017-09-18 2018-04-24 天津市东泽天润建筑有限公司 A kind of composite foundation

Also Published As

Publication number Publication date
CN110273339B (en) 2021-03-05

Similar Documents

Publication Publication Date Title
CN211228591U (en) A steel fiber reinforced concrete gravity retaining wall protective structure
CN110700291A (en) Combined retaining structure and construction method thereof
CN101718086A (en) Concrete-enrockment mixed dam and construction method thereof
CN106676993B (en) Reinforced broken stone frame structure roadbed reinforcing system and reinforcing method thereof
CN107165013A (en) Geotechnical grid reinforcement foam concrete light road foundation fills structure and its method
CN111794030A (en) The method of widening the embankment foundation at the building through the embankment
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction
CN206625096U (en) A kind of reinforced rubble frame structure subgrade strengthening system
CN102493485A (en) Method for building slope protection retaining wall during filling
CN212001226U (en) Backfill miscellaneous soil composite foundation structure
CN106836034B (en) A flexible load-reducing system and construction method of high-fill cover slab culvert
CN209975287U (en) A kind of roadbed structure of mountain road in narrow construction work area
CN114688347B (en) A method for embedding flexible pipelines using controllable low-strength material prefabricated blocks
CN110593242A (en) Heavy-load ground foundation structure of seepage-proofing area of soft foundation and processing method thereof
CN110273339A (en) A kind of land subsidence crack resistence structure and its construction method
CN113089454B (en) A foundation pit trestle slope and construction method thereof
CN116180529A (en) A Reinforcement Structure Applicable to Disaster-Destroyed Subgrade in Mountainous Highway Bank Section
CN210797245U (en) Structure is backfilled to bridgehead abutment back of body
CN210086891U (en) A repair structure of an ancient city wall
CN209636588U (en) A reinforced subgrade pavement with geotechnical permeable pipe inside
CN209636573U (en) A kind of assembled self-balancing channel design system
CN209368603U (en) Abandoned rubber tire compacted gravel-concrete composite pile foundation
CN206625143U (en) A kind of high roadbed slab culvert flexibility off-load system
CN220520990U (en) A kind of deep mixed fill soil roadbed support structure
CN204456179U (en) Solidified earth barricade

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250409

Address after: No. 1601, Unit 1, Building 1, Furong Bay, Zhengshang Blue Ocean Harbor, No. 112 Erligang South Street, Guancheng Hui District, Zhengzhou City, Henan Province, China 450000

Patentee after: Zhengzhou Qiucheng Information Technology Co.,Ltd.

Country or region after: China

Address before: 361006 area a, Room 201, 635 Xinglong Road, Huli District, Xiamen City, Fujian Province

Patentee before: Xiamen Dongxiang Engineering Design Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250805

Address after: 730000 Gansu Province Lanzhou City Chengguan District Qingbaishi Street Baidao Ping Industrial Park No. 99

Patentee after: Gansu Jiarong Construction Engineering Technology Co.,Ltd.

Country or region after: China

Address before: No. 1601, Unit 1, Building 1, Furong Bay, Zhengshang Blue Ocean Harbor, No. 112 Erligang South Street, Guancheng Hui District, Zhengzhou City, Henan Province, China 450000

Patentee before: Zhengzhou Qiucheng Information Technology Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right