CN109056786A - Face upward inclined road shoulder wall water drainage behind the wall system and construction method - Google Patents

Face upward inclined road shoulder wall water drainage behind the wall system and construction method Download PDF

Info

Publication number
CN109056786A
CN109056786A CN201810927732.3A CN201810927732A CN109056786A CN 109056786 A CN109056786 A CN 109056786A CN 201810927732 A CN201810927732 A CN 201810927732A CN 109056786 A CN109056786 A CN 109056786A
Authority
CN
China
Prior art keywords
barricade
wall
rubble
drain hole
loaded filter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810927732.3A
Other languages
Chinese (zh)
Inventor
赵乾文
程小亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wisdri Engineering and Research Incorporation Ltd
Wisdri Urban Construction Engineering Technology Co Ltd
Original Assignee
Wisdri Engineering and Research Incorporation Ltd
Wisdri Urban Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wisdri Engineering and Research Incorporation Ltd, Wisdri Urban Construction Engineering Technology Co Ltd filed Critical Wisdri Engineering and Research Incorporation Ltd
Priority to CN201810927732.3A priority Critical patent/CN109056786A/en
Publication of CN109056786A publication Critical patent/CN109056786A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses one kind to face upward inclined road shoulder wall water drainage behind the wall system comprising rubble or cobble loaded filter, dank material, permeable geotextiles, tapping pipe and gravel-sorted subbase;Rubble or cobble anti-filter are placed on the inside of barricade;Dank material be placed in rubble or cobble loaded filter and it is backfilled roadbed supported between, be in inverted triangle structure;Permeable geotextiles are arranged along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade;Tapping pipe has multiple, is respectively placed in the drain hole in barricade, and one end is connected with rubble or cobble loaded filter, and the other end is placed on the outside of barricade, for the water on the inside of barricade to be discharged;Gravel-sorted subbase is placed under road surface structare layer, dank material and it is backfilled roadbed supported on.The present invention also provides the construction methods for facing upward inclined road shoulder wall water drainage behind the wall system.The water after subgrade wall can be discharged by the present invention, it is ensured that the stability of roadbed and road shoulder barricade.

Description

Face upward inclined road shoulder wall water drainage behind the wall system and construction method
Technical field
The present invention relates to barricades to drain field, and in particular to one kind faces upward inclined road shoulder wall water drainage behind the wall system and construction party Method.
Background technique
In subgrade engineering, roadbed filling section generally requires setting road shoulder wall as subgrade structure object, to guarantee that roadbed is steady Fixed and road surface is complete, while reducing earth and rock works and occupied area, prevents current scour, is usually used in regulation landslide, landslide etc. Subgrade defect.China is in the high-speed developing period at present, can all build a large amount of side slope branch mark structure every year, and barricade is exactly most often The one kind seen is all very big to subgrade stability and safety effects if barricade goes wrong.
The unstable failure of subgrade is usually related with underground water, and current any drainage measure not yet can be solved thoroughly Certainly barricade drainage problem.General road shoulder wall water drainage behind the wall relies solely on the tapping pipe row that barricade wall is arranged at a certain distance Water, this kind of mode usually have the following problems: 1) lacking filter structure after barricade wall, tapping pipe is easy in the long-term use It is blocked by soil, causes water drainage behind the wall unsmooth, with the infiltration of rainwater, the rising suddenly of level of ground water, potential slide mass is full It can increase suddenly with area, the barricade coefficient of stability is caused to decline, eventually lead to barricade deformation and increase generation sliding rupture.2) barricade Rubble filter layer is set after wall, but is to indiscriminately imitate specification or rule of thumb simply laid, does not consider real construction quality The problem of, cause filter layer after wall not play a role, rock-soil layer impeded drainage causes ponding, causes load after wall to increase, significantly Reduce the stability of barrier wall structure.
Summary of the invention
Water after subgrade wall can be discharged the purpose of the present invention is to provide a kind of, it is ensured that the stability of road shoulder barricade Face upward inclined road shoulder wall water drainage behind the wall system and water discharge method.
The technical scheme adopted by the invention is that:
One kind facing upward inclined road shoulder wall water drainage behind the wall system comprising
Rubble or cobble loaded filter are placed on the inside of barricade;
Dank material, be placed in rubble or cobble loaded filter and it is backfilled roadbed supported between, be in inverted triangle structure;
Permeable geotextiles are arranged along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade;
Tapping pipe, has multiple, is respectively placed in the drain hole in barricade, one end is connected with rubble or cobble loaded filter Logical, the other end is placed on the outside of barricade, for the water on the inside of barricade to be discharged;
Gravel-sorted subbase is placed under road surface structare layer, dank material and it is backfilled roadbed supported on.
The present invention also provides another kinds to face upward inclined road shoulder wall water drainage behind the wall system comprising
Rubble or cobble loaded filter, have multiple, are placed on the inside of barricade, and be located at drain hole;
Dank material, be placed in barricade and it is backfilled roadbed supported between, be in inverted triangle structure;Rubble or cobble loaded filter and thoroughly Water-based material is in contact;
Permeable geotextiles are arranged along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade;
Tapping pipe, has multiple, is respectively placed in the drain hole in barricade, one end is connected with rubble or cobble loaded filter Logical, the other end is placed on the outside of barricade, for the water on the inside of barricade to be discharged;
Gravel-sorted subbase is placed under road surface structare layer, dank material and it is backfilled roadbed supported on.
According to the above scheme, the dank material is right angled triangle, and a vertical edges are close to gravel-sorted subbase, separately One vertical edges is on the inside of barricade, i.e., dank material is gradually increased from the bottom up.
According to the above scheme, the dank material is mainly made of medium coarse sand.
According to the above scheme, gutter is equipped on the outside of barricade, the water through tapping pipe outflow flows into gutter.
According to the above scheme, the tapping pipe is in quincunx laying.
According to the above scheme, the every expansion joint 20m indwelling 2cm wide of barricade is seamed into straight line, is filled out in expansion joint using plastic foamboard Fill it is closely knit, stretch seam surface use the ointment cementation of fissures;The gradient of barricade exterior wall is 1:0.5, and the gradient of barricade interior wall is 1:0.3, gear Wall uses concrete material or slabstone concrete material.
According to the above scheme, dank material is wrapped up by composite geo-membrane.
After underground water or ponding are by permeable geotextiles inside roadbed, into the water penetration material of composite geo-membrane package The fine grained soil contained in drainage is collected and crossed to material, dank material, crosses water after filter through dank material and passes through on the inside of barricade Rubble or cobble loaded filter further filter impurities in water, then again through permeable geotextiles filtering after enter barricade in lay Drain hole, and then water is discharged to outside roadbed, is discharged into culvert through gutter.
The present invention provides a kind of construction method for facing upward inclined road shoulder wall water drainage behind the wall system comprising following steps:
Step 1: preparation of construction
Construction survey setting-out should be carried out before Retaining wall;
Step 2: detection bearing capacity
After removing stratum surface soil, excavates barricade foundation pit and detect hole bottom bearing capacity, if hole bottom bearing capacity is unsatisfactory for requiring, It carries out hole bottom and changes filling out graded broken stone and reaching design requirement bearing capacity;
Step 3: pouring barricade
It can carry out wall after the completion of construction retaining wall foundation to pour, retaining wall should be segmented and pour, and every 20m indwelling 2cm wide stretches Contracting seam, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Barricade exterior wall Face is constructed by the inclined-plane of 1:0.5, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, barricade using concrete material or Slabstone concrete material;
In barricade building process, drain hole is arranged after building to certain altitude in barricade, and first row drain hole should be higher than that ditch Bottom 0.3m is arranged, and the waterproof compacting soil layer of one layer of 20cm thickness should be laid with below first row drain hole water inlet;It is higher by barricade Above ground portion should be layered setting drain hole, and sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement, pre-buried φ 10cmPVC in hole up and down Pipe;
Step 4: backfilled roadbed supported soil
After barricade pours, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, are formed back on the inside of barricade Roadbed is filled out, compactness is greater than 96%;The gradient of roadbed side slope is 1:0.2;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are solid It is scheduled on side slope of backfilled roadbed supported and barricade;
Step 6: backfill rubble or cobble loaded filter
On the inside of barricade, the rubble or cobble loaded filter that a slice width degree is 30cm are backfilled along wall height;
Step 7: backfill dank material
Rubble or cobble loaded filter and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
Step 8: building road surface waterproof layer
The gravel-sorted subbase of 15cm thickness is built on dank material;
Step 9: completing the laying of road surface structare layer.
The present invention also provides the construction methods that another kind faces upward inclined road shoulder wall water drainage behind the wall system comprising following steps:
Step 1: preparation of construction
Construction survey setting-out should be carried out before Retaining wall;
Step 2: detection bearing capacity
After removing stratum surface soil, excavates barricade foundation pit and detect hole bottom bearing capacity, if hole bottom bearing capacity is unsatisfactory for requiring, It carries out hole bottom and changes filling out graded broken stone and reaching design requirement bearing capacity;
Step 3: pouring barricade
It can carry out wall after the completion of construction retaining wall foundation to pour, retaining wall should be segmented and pour, and every 20m indwelling 2cm wide stretches Contracting seam, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Barricade exterior wall Face is constructed by the inclined-plane of 1:0.5, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, barricade using concrete material or Slabstone concrete material;
In barricade building process, drain hole is arranged after building to certain altitude in barricade, and first row drain hole should be higher than that ditch Bottom 0.3m is arranged, and the waterproof compacting soil layer of one layer of 20cm thickness should be laid with below first row drain hole water inlet;It is higher by barricade Above ground portion should be layered setting drain hole, and sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement, pre-buried φ 10cmPVC in hole up and down Pipe;
Step 4: backfilled roadbed supported soil
After barricade pours, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, are formed back on the inside of barricade Roadbed is filled out, compactness is greater than 96%;The gradient of roadbed side slope is 1:0.3;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are solid It is scheduled on side slope of backfilled roadbed supported and barricade;
Step 6: backfill dank material
Barricade and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
When backfilling dank material, the rubble or cobble loaded filter of setting 30cm × 30cm, is each let out on the inside of barricade The corresponding rubble in water hole or cobble loaded filter;
Step 7: building road surface waterproof layer
The gravel-sorted subbase of 15cm thickness is built on dank material;
Step 8: completing the laying of road surface structare layer.
The beneficial effects of the present invention are:
By setting dank material, permeable geotextiles, rubble or cobble loaded filter etc., the particulate contained in drainage is crossed Soil prevents obstruction drain hole, overcomes the problem of drain hole is easy blocking, guarantees that underground water and ponding can be arranged rapidly in roadbed Roadbed out reduces the influence to roadbed and barricade;
Dank material can accommodate the water of certain volume, so can alleviate roadbed water pressure in a certain range, reduce road The water pressure of base and barricade influences, it is ensured that the stability of roadbed and road shoulder barricade;
Gravel-sorted subbase is set, to prevent water on road surface structare layer from flowing into roadbed, ensure that roadbed and The stability of road shoulder barricade;
Convenient and quick construction, quality are easy to control.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples, in attached drawing:
Fig. 1 is the structure that inclined road shoulder wall water drainage behind the wall system (being suitable for the higher situation of level of ground water) is faced upward in embodiment 1 Schematic diagram;
Fig. 2 is the structure that inclined road shoulder wall water drainage behind the wall system (being suitable for the lower situation of level of ground water) is faced upward in embodiment 2 Schematic diagram;
Fig. 3 is drain hole arrangement schematic diagram;
Fig. 4 substrate backfills schematic diagram;
Fig. 5 substrate, which is changed, fills out processing schematic;
Fig. 6 sloping area embedded depth of foundation value table;
Wherein, 1, rubble or cobble loaded filter, 2, dank material, 3, cohesive soil, 4, permeable geotextiles, 5, barricade, 6, tapping pipe, 7, road surface structare layer, 8, gravel-sorted subbase, 9, barricade substrate change and fill out metalling, 10, retaining wall foundation, 11, return Fill out roadbed.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not For limiting the present invention.
Embodiment 1, referring to Fig. 1, Fig. 3-Fig. 6, one kind facing upward inclined road shoulder wall water drainage behind the wall system comprising rubble or ovum Stone loaded filter 1, dank material 2, permeable geotextiles 4, tapping pipe 6, gravel-sorted subbase 8.Rubble or cobble loaded filter 1 Width be 30cm, be placed in the inside of barricade 5, upper part is road surface structare layer 7, and its underpart is cohesive soil 3.Dank material 2 is main It to be made of medium coarse sand, be wrapped up by composite geo-membrane, is placed between rubble or cobble loaded filter 1 and backfilled roadbed supported 11, in Triangular structure of right angle, for a vertical edges close to gravel-sorted subbase 8, another vertical edges is close to 5 inside of barricade, i.e., permeable Property material 2 is gradually increased from the bottom up.Permeable geotextiles 4 are along backfilled roadbed supported 11 side slope, 3 upper surface of cohesive soil at 5 bottom of barricade And 5 inside wall of barricade setting.Tapping pipe 6 have it is multiple, be in quincunx laying, be respectively placed in the drain hole in barricade 5, one End is connected with rubble or cobble loaded filter 1, and the other end is placed in 5 outside of barricade, for the water of 5 inside of barricade to be discharged. Gravel-sorted subbase 8 is placed under road surface structare layer 7, on dank material 2 and backfilled roadbed supported 11.
The present embodiment is equipped with gutter on the outside of barricade 5, and the water flowed out through tapping pipe 6 flows into gutter.Barricade 5 Every expansion joint 20m indwelling 2cm wide, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches is using oil The cream cementation of fissures;The gradient of 5 exterior wall of barricade is 1:0.5, and the gradient of barricade interior wall is 1:0.3, and barricade uses concrete material or slabstone Concrete material.
In the present invention, dank material is filled according to θ angular region after barricade wall, underground water or ponding pass through inside roadbed After permeable geotextiles 4, into the dank material 2 of composite geo-membrane package, contain in the collection of dank material 2 and excessively drainage Fine grained soil, the rubble or cobble loaded filter 1 passed through on the inside of barricade through the water after filter of dank material 2 is further to cross drainage Then middle impurity enters the tapping pipe 6 laid in barricade 5 after the filtering of permeable geotextiles 4 again, and then water is discharged to outside roadbed, Culvert is discharged into through gutter.
The above-mentioned construction method for facing upward inclined road shoulder wall water drainage behind the wall system, anti-close to 5 side rubble of barricade or cobble Filtering layer be along wall height lay, the specific steps of which are as follows:
Step 1: preparation of construction
Barricade 5 should carry out construction survey setting-out before constructing, and construction lofting calculates the coordinate of every section of barricade according to design drawing And elevation setting-out, on the spot, flat field, basialveolar line carry out slope by soil property on the spot and rock stratum;
Step 2: detection bearing capacity
After removing stratum surface soil, excavates barricade foundation pit and detect hole bottom bearing capacity and pressed if hole bottom bearing capacity is met the requirements It is excavated according to Fig. 4, if hole bottom bearing capacity is unsatisfactory for requiring, carries out hole bottom and change and fill out graded broken stone, formed barricade substrate and change and fills out Metalling 9 reaches design requirement bearing capacity;To hillside retaining wall, base toe length of embedment and flap back gauge should accord with simultaneously Close Fig. 6 design requirement;
Step 3: pouring barricade
It can carry out wall after the completion of construction retaining wall foundation 10 to pour, retaining wall should be segmented by design requirement and be poured, every 20m The expansion joint indwelling 2cm wide, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches is filled using ointment Seam;Barricade wall face is constructed by the inclined-plane of 1:0.5, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, and barricade is using mixed Solidifying soil material or slabstone concrete material;
In barricade building process, barricade presses design requirement size positions and drain hole is arranged after building to certain altitude, the One excretion water hole should be higher than that bottom of trench 0.3m is arranged, and the waterproof rammer of one layer of 20cm thickness should be laid with below first row drain hole water inlet Real soil layer;It should be layered setting drain hole in barricade part above ground level, sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement up and down, Pre-buried φ 10cmPVC pipe in hole;
Step 4: backfilled roadbed supported soil
After barricade pours 7 days, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, shape on the inside of barricade At backfilled roadbed supported 11, compactness is greater than 96%;The gradient of roadbed side slope is 1:0.2;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are solid It is scheduled on side slope of backfilled roadbed supported and barricade;
Step 6: backfill rubble or cobble loaded filter
On the inside of barricade, the rubble or cobble loaded filter that a slice width degree is 30cm are backfilled along wall height;
Step 7: backfill dank material
Rubble or cobble loaded filter and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
Step 8: building road surface waterproof layer
The gravel-sorted subbase of 15cm thickness is built on dank material;
Step 9: completing the laying of road surface structare layer.
Embodiment 2 ,-Fig. 6, one kind facing upward inclined road shoulder wall water drainage behind the wall system referring to fig. 2 comprising rubble or cobble are anti- Filtering layer 1, dank material 2, permeable geotextiles 4, tapping pipe 6, gravel-sorted subbase 8.Rubble or cobble loaded filter 1 have more It is a, it is placed in 5 inside of barricade, and be located at drain hole.Dank material 2 is mainly made of medium coarse sand, by composite geo-membrane Package, is placed between barricade 5 and backfilled roadbed supported 11, is in chamfer triangular structure, a vertical edges are close to graded broken stone base Layer 8, another vertical edges is close to 5 inside of barricade, i.e., dank material 2 is gradually increased from the bottom up.Rubble or cobble anti-filter Layer 1 is on dank material 2;Permeable geotextiles 4 along backfilled roadbed supported 11 side slope, the cohesive soil 3 at 5 bottom of barricade upper surface and The setting of 5 inside wall of barricade, and be fixed on 5 inside of barricade and backfilled roadbed supported 11.Tapping pipe 6 has multiple, is respectively placed in barricade 5 In interior drain hole, one end is connected with rubble or cobble loaded filter 1, and the other end is placed in 5 outside of barricade, for that will keep off The water discharge of 5 inside of wall.Gravel-sorted subbase 8 is placed under road surface structare layer 7, on dank material 2 and backfilled roadbed supported 11.? Dank material 2 is equipped between gravel-sorted subbase 8 and barricade 5, i.e. dank material 2 is placed in the inside structure sheaf 7 and gradation Under granular sub-base 8.Gutter is equipped on the outside of barricade 5, the water through tapping pipe outflow flows into gutter.
The every expansion joint 20m indwelling 2cm wide of barricade 5, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, stretches Contracting seam surface uses the ointment cementation of fissures;The gradient of barricade exterior wall is 1:0.5, and the gradient of barricade interior wall is 1:0.3, and barricade uses coagulation Soil material or slabstone concrete material.
The above-mentioned construction method for facing upward inclined road shoulder wall water drainage behind the wall system, when lower suitable for level of ground water, in the implementation In example, lays, specifically comprise the following steps: along drain hole close to barricade side rubble or cobble loaded filter
Step 1: preparation of construction
Should carry out construction survey setting-out before Retaining wall, construction lofting according to design drawing calculate every section of barricade coordinate and In on the spot, flat field, basialveolar line carry out slope by soil property on the spot and rock stratum for elevation setting-out;
Step 2: detection bearing capacity
After removing stratum surface soil, to excavate barricade foundation pit and detect hole bottom bearing capacity, satisfaction is then excavated according to Fig. 4, if Hole bottom bearing capacity is unsatisfactory for requiring, then carries out hole bottom according to Fig. 5 and change filling out graded broken stone and reaching design requirement bearing capacity;To mountain Slope retaining wall, base toe length of embedment and flap back gauge should meet Fig. 6 design requirement simultaneously;
Step 3: pouring barricade
It can carry out wall after the completion of construction retaining wall foundation to pour, retaining wall should be segmented and pour, and every 20m indwelling 2cm wide stretches Contracting seam, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Barricade exterior wall Face is constructed by the inclined-plane of 1:0.5, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, barricade using concrete material or Slabstone concrete material;
In barricade building process, barricade presses design requirement size positions and drain hole is arranged after building to certain altitude, the One excretion water hole should be higher than that bottom of trench 0.3m is arranged, and the waterproof rammer of one layer of 20cm thickness should be laid with below first row drain hole water inlet Real soil layer;It should be layered setting drain hole in barricade part above ground level, sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement up and down, Pre-buried φ 10cmPVC pipe in hole;
Step 4: backfilled roadbed supported soil
After barricade pours 7 days, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, shape on the inside of barricade At backfilled roadbed supported, compactness is greater than 96%;The gradient of roadbed side slope is 1:0.3;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are solid It is scheduled on side slope of backfilled roadbed supported and barricade;
Step 6: backfill dank material
Barricade and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
When backfilling dank material, the rubble or cobble loaded filter of setting 30cm × 30cm, is each let out on the inside of barricade The corresponding rubble in water hole or cobble loaded filter;
Step 7: building road surface waterproof layer
After above each layer is completed and passes through examination, the gravel-sorted subbase of 15cm thickness is built on dank material;
Step 8: completing the laying of road surface structare layer after gravel-sorted subbase is checked and accepted.
In the present invention, the high H of barricade wall need to be less than 8m.Drain hole is inclined to set.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (9)

1. one kind faces upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: including
Rubble or cobble loaded filter are placed on the inside of barricade;
Dank material, be placed in rubble or cobble loaded filter and it is backfilled roadbed supported between, be in inverted triangle structure;
Permeable geotextiles are arranged along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade;
Tapping pipe, has multiple, is respectively placed in the drain hole in barricade, and one end is connected with rubble or cobble loaded filter, Its other end is placed on the outside of barricade, for the water on the inside of barricade to be discharged;
Gravel-sorted subbase is placed under road surface structare layer, dank material and it is backfilled roadbed supported on.
2. one kind faces upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: including
Rubble or cobble loaded filter, have multiple, are placed on the inside of barricade, and be located at drain hole;
Dank material, be placed in barricade and it is backfilled roadbed supported between, be in inverted triangle structure;Rubble or cobble loaded filter and water penetration Material is in contact;
Permeable geotextiles are arranged along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade;
Tapping pipe, has multiple, is respectively placed in the drain hole in barricade, and one end is connected with rubble or cobble loaded filter, Its other end is placed on the outside of barricade, for the water on the inside of barricade to be discharged;
Gravel-sorted subbase is placed under road surface structare layer, dank material and it is backfilled roadbed supported on.
3. according to claim 1 or 2 face upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: the water penetration material Material is right angled triangle, and a vertical edges are close to gravel-sorted subbase, another vertical edges is close to barricade inside, i.e. water penetration Material is gradually increased from the bottom up.
4. according to claim 3 face upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: the dank material Mainly it is made of medium coarse sand.
5. according to claim 1 or 2 face upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: set on the outside of barricade There is gutter, the water through tapping pipe outflow flows into gutter.
6. according to claim 1 or 2 face upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: the tapping pipe is in Quincunx laying.
7. according to claim 1 or 2 face upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that: the every 20m indwelling of barricade The expansion joint 2cm wide, is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Gear The gradient of wall exterior wall is 1:0.5, and the gradient of barricade interior wall is 1:0.3, and barricade uses concrete material or slabstone concrete material.
8. a kind of construction method for facing upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that include the following steps:
Step 1: preparation of construction
Construction survey setting-out should be carried out before Retaining wall;
Step 2: detection bearing capacity
After removing stratum surface soil, excavates barricade foundation pit and detect hole bottom bearing capacity, be unsatisfactory for requiring if cheating bottom bearing capacity, carry out Hole bottom, which is changed, to be filled out graded broken stone and reaches design requirement bearing capacity;
Step 3: pouring barricade
Wall can be carried out after the completion of construction retaining wall foundation to pour, retaining wall should be segmented and pour, every expansion joint 20m indwelling 2cm wide, It is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Barricade wall face presses 1: 0.5 inclined-plane is constructed, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, and barricade is mixed using concrete material or slabstone Solidifying soil material;
In barricade building process, drain hole is arranged after building to certain altitude in barricade, and first row drain hole should be higher than that bottom of trench 0.3m is arranged, and the waterproof compacting soil layer of one layer of 20cm thickness should be laid with below first row drain hole water inlet;It is higher by ground in barricade Face part should be layered setting drain hole, and sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement, pre-buried φ 10cmPVC in hole up and down Pipe;
Step 4: backfilled roadbed supported soil
After barricade pours, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, form backfill road on the inside of barricade Base, compactness are greater than 96%;The gradient of roadbed side slope is 1:0.2;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are fixed on On side slope of backfilled roadbed supported and barricade;
Step 6: backfill rubble or cobble loaded filter
On the inside of barricade, the rubble or cobble loaded filter that a slice width degree is 30cm are backfilled along wall height;
Step 7: backfill dank material
Rubble or cobble loaded filter and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
Step 8: building road surface waterproof layer
The gravel-sorted subbase of 15cm thickness is built on dank material;
Step 9: completing the laying of road surface structare layer.
9. a kind of construction method for facing upward inclined road shoulder wall water drainage behind the wall system, it is characterised in that include the following steps:
Step 1: preparation of construction
Construction survey setting-out should be carried out before Retaining wall;
Step 2: detection bearing capacity
After removing stratum surface soil, excavates barricade foundation pit and detect hole bottom bearing capacity, be unsatisfactory for requiring if cheating bottom bearing capacity, carry out Hole bottom, which is changed, to be filled out graded broken stone and reaches design requirement bearing capacity;
Step 3: pouring barricade
Wall can be carried out after the completion of construction retaining wall foundation to pour, retaining wall should be segmented and pour, every expansion joint 20m indwelling 2cm wide, It is seamed into straight line, uses plastic foamboard to fill in expansion joint closely knit, the seam surface that stretches uses the ointment cementation of fissures;Barricade wall face presses 1: 0.5 inclined-plane is constructed, and inner wall surface pours concrete from formwork by the gradient of 1:0.3, and barricade is mixed using concrete material or slabstone Solidifying soil material;
In barricade building process, drain hole is arranged after building to certain altitude in barricade, and first row drain hole should be higher than that bottom of trench 0.3m is arranged, and the waterproof compacting soil layer of one layer of 20cm thickness should be laid with below first row drain hole water inlet;It is higher by ground in barricade Face part should be layered setting drain hole, and sluicing 2.5 × 2.5m of pitch of holes arranges interlaced arrangement, pre-buried φ 10cmPVC in hole up and down Pipe;
Step 4: backfilled roadbed supported soil
After barricade pours, after intensity reaches 75%, the qualified soil of back-filling in layers and compaction in layers, form backfill road on the inside of barricade Base, compactness are greater than 96%;The gradient of roadbed side slope is 1:0.3;
Step 5: being laid with permeable geotextiles
One layer of permeable geotextiles are laid with along wall on the inside of side slope of backfilled roadbed supported, barricade bottom and barricade, permeable geotextiles are fixed on On side slope of backfilled roadbed supported and barricade;
Step 6: backfill dank material
Barricade and it is backfilled roadbed supported between backfill dank material, and it is closely knit;
When backfilling dank material, the rubble or cobble loaded filter of setting 30cm × 30cm, each drain hole on the inside of barricade A corresponding rubble or cobble loaded filter;
Step 7: building road surface waterproof layer
The gravel-sorted subbase of 15cm thickness is built on dank material;
Step 8: completing the laying of road surface structare layer.
CN201810927732.3A 2018-08-15 2018-08-15 Face upward inclined road shoulder wall water drainage behind the wall system and construction method Pending CN109056786A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810927732.3A CN109056786A (en) 2018-08-15 2018-08-15 Face upward inclined road shoulder wall water drainage behind the wall system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810927732.3A CN109056786A (en) 2018-08-15 2018-08-15 Face upward inclined road shoulder wall water drainage behind the wall system and construction method

Publications (1)

Publication Number Publication Date
CN109056786A true CN109056786A (en) 2018-12-21

Family

ID=64686013

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810927732.3A Pending CN109056786A (en) 2018-08-15 2018-08-15 Face upward inclined road shoulder wall water drainage behind the wall system and construction method

Country Status (1)

Country Link
CN (1) CN109056786A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826227A (en) * 2019-01-03 2019-05-31 中交隧道工程局有限公司 A kind of preparation method and its retaining wall of the bilateral slope mortar flag stone retaining wall of high mountain
CN109972654A (en) * 2019-05-08 2019-07-05 贵州智华建设工程有限责任公司 A J-type anchor high retaining wall and its construction method
CN110042859A (en) * 2019-05-14 2019-07-23 中建五局土木工程有限公司 Retaining wall anti-filter body and its construction method
CN110374136A (en) * 2019-08-12 2019-10-25 广东电网有限责任公司 Soil-baffling structure suitable for the electrical building building on soft geological
CN110714479A (en) * 2019-11-01 2020-01-21 河北工业大学 Structure of water-permeable gravity retaining wall with embedded gravel column and construction method thereof
CN110777905A (en) * 2019-11-06 2020-02-11 中国建筑第八工程局有限公司 Delayed overflow structure for sponge city front pond
CN111074937A (en) * 2020-01-27 2020-04-28 贵州星隆迪岩土工程有限公司 Second-story landscape retaining wall with pile support and construction method
CN111074938A (en) * 2020-02-06 2020-04-28 贵州星隆迪岩土工程有限公司 Landscape retaining wall and construction method
CN111206617A (en) * 2020-03-25 2020-05-29 贵州星隆迪岩土工程有限公司 High pile bearing platform retaining wall and construction method
CN111501458A (en) * 2020-04-26 2020-08-07 中建八局第二建设有限公司 Paving method of stone-filled roadbed
CN111719910A (en) * 2020-05-20 2020-09-29 中国建筑第八工程局有限公司 Retaining wall partition type beam field structure and construction method thereof
CN112095384A (en) * 2020-09-14 2020-12-18 中交二公局第四工程有限公司 Construction method for preventing and treating freezing-thawing instability of roadbed slope in plateau frozen soil area
CN113106799A (en) * 2021-04-15 2021-07-13 核工业南方工程总公司 Roadbed structure of road and bridge engineering and construction method thereof
CN113529785A (en) * 2021-07-22 2021-10-22 水利部交通运输部国家能源局南京水利科学研究院 Soil retaining structure suitable for eliminating frost heaving effect in cold region and construction method
CN114960692A (en) * 2022-06-14 2022-08-30 鞍山三冶建筑工程有限公司 Backfill method for reducing influence of water on basement exterior wall
CN115354685A (en) * 2022-08-08 2022-11-18 中冶南方城市建设工程技术有限公司 Mountain area is along waterproof and integrative outlet structure of drainage of river barricade
CN118065406A (en) * 2024-04-22 2024-05-24 北京建工四建工程建设有限公司 Sinking type temporary slope building for easily-degraded slope

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030031084A (en) * 2003-03-27 2003-04-18 김광호 Drainge system of revetment and its construction method
CN103669398A (en) * 2013-12-26 2014-03-26 中国水电顾问集团中南勘测设计研究院有限公司 Integrated type road cutting retaining wall
CN205804401U (en) * 2016-06-28 2016-12-14 宇航交通建设集团有限公司 Retaining wall and the soil protection structure comprising this retaining wall
CN106638200A (en) * 2016-12-06 2017-05-10 同济大学 Roadbed antifreezing and drained water interception facility and construction method suitable for seasonally frozen-ground region
CN207295758U (en) * 2017-09-26 2018-05-01 福州市规划设计研究院 The prefabricated drainage system for facing upward inclined retaining wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030031084A (en) * 2003-03-27 2003-04-18 김광호 Drainge system of revetment and its construction method
CN103669398A (en) * 2013-12-26 2014-03-26 中国水电顾问集团中南勘测设计研究院有限公司 Integrated type road cutting retaining wall
CN205804401U (en) * 2016-06-28 2016-12-14 宇航交通建设集团有限公司 Retaining wall and the soil protection structure comprising this retaining wall
CN106638200A (en) * 2016-12-06 2017-05-10 同济大学 Roadbed antifreezing and drained water interception facility and construction method suitable for seasonally frozen-ground region
CN207295758U (en) * 2017-09-26 2018-05-01 福州市规划设计研究院 The prefabricated drainage system for facing upward inclined retaining wall

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中交第二公路勘察设计研究院有限公司: "《公路挡土墙设计与施工技术细则》", 31 March 2008, 人民交通出版社 *
孟琳编: "《房屋建筑学》", 31 January 2008, 北京理工大学出版社出版社 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826227A (en) * 2019-01-03 2019-05-31 中交隧道工程局有限公司 A kind of preparation method and its retaining wall of the bilateral slope mortar flag stone retaining wall of high mountain
CN109972654A (en) * 2019-05-08 2019-07-05 贵州智华建设工程有限责任公司 A J-type anchor high retaining wall and its construction method
CN110042859B (en) * 2019-05-14 2023-12-29 中建五局土木工程有限公司 Retaining wall reverse filter body and construction method thereof
CN110042859A (en) * 2019-05-14 2019-07-23 中建五局土木工程有限公司 Retaining wall anti-filter body and its construction method
CN110374136A (en) * 2019-08-12 2019-10-25 广东电网有限责任公司 Soil-baffling structure suitable for the electrical building building on soft geological
CN110714479A (en) * 2019-11-01 2020-01-21 河北工业大学 Structure of water-permeable gravity retaining wall with embedded gravel column and construction method thereof
CN110777905A (en) * 2019-11-06 2020-02-11 中国建筑第八工程局有限公司 Delayed overflow structure for sponge city front pond
CN110777905B (en) * 2019-11-06 2025-01-21 中国建筑第八工程局有限公司 Delayed overflow structure for sponge city front pond
CN111074937A (en) * 2020-01-27 2020-04-28 贵州星隆迪岩土工程有限公司 Second-story landscape retaining wall with pile support and construction method
CN111074938A (en) * 2020-02-06 2020-04-28 贵州星隆迪岩土工程有限公司 Landscape retaining wall and construction method
CN111206617A (en) * 2020-03-25 2020-05-29 贵州星隆迪岩土工程有限公司 High pile bearing platform retaining wall and construction method
CN111501458A (en) * 2020-04-26 2020-08-07 中建八局第二建设有限公司 Paving method of stone-filled roadbed
CN111719910A (en) * 2020-05-20 2020-09-29 中国建筑第八工程局有限公司 Retaining wall partition type beam field structure and construction method thereof
CN111719910B (en) * 2020-05-20 2021-08-10 中国建筑第八工程局有限公司 Retaining wall partition type beam field structure and construction method thereof
CN112095384A (en) * 2020-09-14 2020-12-18 中交二公局第四工程有限公司 Construction method for preventing and treating freezing-thawing instability of roadbed slope in plateau frozen soil area
CN113106799A (en) * 2021-04-15 2021-07-13 核工业南方工程总公司 Roadbed structure of road and bridge engineering and construction method thereof
CN113529785A (en) * 2021-07-22 2021-10-22 水利部交通运输部国家能源局南京水利科学研究院 Soil retaining structure suitable for eliminating frost heaving effect in cold region and construction method
CN113529785B (en) * 2021-07-22 2022-06-17 水利部交通运输部国家能源局南京水利科学研究院 A soil retaining structure and construction method suitable for eliminating frost heave effect in cold regions
CN114960692A (en) * 2022-06-14 2022-08-30 鞍山三冶建筑工程有限公司 Backfill method for reducing influence of water on basement exterior wall
CN114960692B (en) * 2022-06-14 2024-04-26 鞍山三冶建筑工程有限公司 A backfill method to reduce the impact of water on basement exterior walls
CN115354685A (en) * 2022-08-08 2022-11-18 中冶南方城市建设工程技术有限公司 Mountain area is along waterproof and integrative outlet structure of drainage of river barricade
CN118065406A (en) * 2024-04-22 2024-05-24 北京建工四建工程建设有限公司 Sinking type temporary slope building for easily-degraded slope

Similar Documents

Publication Publication Date Title
CN109056786A (en) Face upward inclined road shoulder wall water drainage behind the wall system and construction method
CN103410167B (en) Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN100510278C (en) Ecological protection method for sand-filling road foundation hollow block
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN103283335B (en) Filling reclamation method for reclaiming coal mining subsidence lands by Yellow River sediment
CN102747662A (en) Construction method for sand-filling subgrade
CN106320123A (en) Construction method of soft soil roadbed
CN105569058A (en) Expansive soil cutting structure and construction method thereof
CN101914882B (en) Structure and construction method of low embankment in silty soil area with high groundwater level
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN110144783B (en) Roadbed construction method
CN112392127B (en) A dendritic embedded flexible ecological slope drainage ditch and construction method
CN116377780A (en) Mountain highway high-fill roadbed filling construction method
CN109610429A (en) Sedimentation treatment method under a kind of Collapsible Loess District prevention gas collection station ground and terrace
CN205399440U (en) Inflation dirt road moat structure
CN203960699U (en) Road cutting type protecting immersion road structure
CN106192880B (en) The box harbour of L-type and its method of construction
CN107700514A (en) A kind of processing method on weak base foundation selection structural shape
CN110528540A (en) A kind of the draining anti-slide pile structure and its construction method of embedded pile
CN217922839U (en) High-speed railway buried high embankment structure in deep and thick miscellaneous fill-up area
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN104846803A (en) Foundation soil consolidation method
CN108316077A (en) One kind underlies shallow embedding cave dwelling roadbed treatment structures and method
CN210421127U (en) Tunnel engineering back pressure backfill structure for treating shallow buried bias voltage diseases
CN207700204U (en) A kind of french drain structure for Slope Prevention

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221

RJ01 Rejection of invention patent application after publication