CN106229889A - A kind of transmission line of electricity lifting device for aerial wires - Google Patents

A kind of transmission line of electricity lifting device for aerial wires Download PDF

Info

Publication number
CN106229889A
CN106229889A CN201610603277.2A CN201610603277A CN106229889A CN 106229889 A CN106229889 A CN 106229889A CN 201610603277 A CN201610603277 A CN 201610603277A CN 106229889 A CN106229889 A CN 106229889A
Authority
CN
China
Prior art keywords
lift lever
gripper shoe
support tube
connecting plate
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610603277.2A
Other languages
Chinese (zh)
Other versions
CN106229889B (en
Inventor
刘金旭
岳东
邓果
唐双
邓昌干
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Sichuan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Sichuan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Sichuan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610603277.2A priority Critical patent/CN106229889B/en
Publication of CN106229889A publication Critical patent/CN106229889A/en
Application granted granted Critical
Publication of CN106229889B publication Critical patent/CN106229889B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses a kind of power transmission line lifting device for aerial wires, including supporting seat, it is hinged with lift lever in the middle part of seat supporting, it is provided with tightener at lift lever end, support tube it is provided with in the middle part of connecting plate, gripper shoe one end is connected with lift lever, and it is interior and hinged with support tube by bearing pin that the gripper shoe other end is placed in support tube, is provided with for the freely through opening of gripper shoe along support tube axis direction section on its external wall.Utilize and support seat, lift lever, gripper shoe, connecting plate, support tube and tightener one lifting structures of composition, and the line mode that carries of the direct abandoning tradition of this lifting structures, the hook on tightener is utilized to be clamped by the wire of landing on insulator, manually swing up and down spanner to realize moving up and down of hook, i.e. drive wire to rise, then make wire coiling again on the insulator by manual adjustment.

Description

A kind of transmission line of electricity lifting device for aerial wires
Technical field
The present invention relates to circuit charity field, be specifically related to a kind of power transmission line lifting device for aerial wires.
Background technology
In rural power grids construction line transformation process, often meet angle pole, top lever, as exhausted in wire landing during stringing The edge period of the day from 11 p.m. to 1 a.m, is difficult on lifting wire to insulator by manpower, and the big span of the biggest circuit, circuit deadweight and tension force reach thousands of Kilogram, general way is to carry line after loose ends again, but this operating type method wastes many man power and materials virtually.
Summary of the invention
Present invention aim at providing a kind of power transmission line lifting device for aerial wires, convenient wire in rural power grids construction line is transformed Fast lifting, on insulator, reduces manpower and material resources cost.
The present invention is achieved through the following technical solutions:
A kind of power transmission line lifting device for aerial wires, including supporting seat, is hinged with lift lever in the middle part of described support seat, and is promoting Lever end is provided with tightener, also includes connecting plate and gripper shoe, is provided with support tube, gripper shoe one end in the middle part of described connecting plate Being connected with lift lever, it is interior and hinged with support tube by bearing pin that the gripper shoe other end is placed in support tube, and along described support tube Axis direction section on its external wall is provided with for the freely through opening of gripper shoe.In prior art, transform at rural power grids construction line Wire easily landing from insulator during stringing, the most common line mode that carries, manually swash to electric pole or steel tower, utilize Hand or shoulder carry out upper act to the wire of landing, but for gear away from circuit big, that diameter of wire is thick, it is conducted oneself with dignity and opens Power reaches metric ton, and depending merely on manpower cannot promote such cable, and easilys lead to workmen and sustain damage; For such problem, inventor supports seat by installing on electric pole or steel tower, utilize support seat, lift lever, gripper shoe, Connecting plate, support tube and tightener one lifting structures of composition, tightener is also ratchet tightener, is come real by rotating spanner The rotation of existing ratchet, to drive tightening up or diastole of the steel cable being connected with hook, and the direct abandoning tradition of this lifting structures Put forward line mode, utilize the hook on tightener to be clamped by the wire of landing on insulator, manually swing up and down spanner to realize Moving up and down of hook, i.e. drives wire to rise, then makes wire coiling again on the insulator by manual adjustment.
Concrete mode of operation is as follows: by bolt, support seat and connecting plate are fixed on the conjunction on electric pole or steel tower Right position is put, and ensures connecting plate and support between seat and leave spacing, is in heeling condition meeting lift lever, is now placed in carrying Hook, just to wire, is articulated on wire by the tightener on liter lever top, and now the steel cable on tightener is in diastole state, Manually swing spanner so that steel cable drives wire to begin to move up, until wire location and insulator are positioned at same On horizontal line, manually stir wire and be allowed to again be wound on insulator outer wall.Wherein, lift lever is hinged with support seat, and Gripper shoe is hinged with support tube, and i.e. for different lifting wires, the angle of inclination of lift lever can arbitrarily adjust, in side Just, on the premise of operator's construction, the circuit that the wire of major diameter or span are bigger can quickly be carried by lift lever Rise, and, the gross weight of whole line lifter is less than 10 kilograms, and workmen's load during climbing is relatively small, greatly Save greatly the wire manpower and materials when promoting.
Also include the circuit cross-arm of two parallel distributions, circuit cross-arm has multiple installing hole being distributed side by side, and The fixing hole coordinated with installing hole is had at described two ends.Prop up as the stress of lift lever owing to supporting seat and connecting plate Support member, when supporting seat and being fixed on the support on electric pole or steel tower, connecting plate and support seat interval are arranged, and i.e. cause even Fishplate bar is not easily found and suitably installs station when installing, and now by arranging the circuit cross-arm of two parallel distributions, and utilizes Installing hole on circuit cross-arm coordinates with the fixing hole at connecting plate two ends, causes the two ends of connecting plate to be fastened, passes through connecting plate And support the seat common support to lift lever so that lift lever when the circuit that lifting deadweight and tension force are bigger more Stable.
Described opening is just to described lift lever.As preferably, lift lever when stress, support tube and gripper shoe conduct The midfoot support component of lift lever, the direction of opening just to lift lever, adjusts its heeling condition facilitating lift lever Meanwhile, support tube does not has the side of opening to carry out spacing to gripper shoe in loading process, it is to avoid gripper shoe drives and promotes thick stick Bar bearing pin on support tube moves down, and i.e. prevents wire support of lift lever in lifting process suddenly to lose efficacy and caused There is security incident, improve the safe and reliable degree of lift lever.
Using described lift lever with support seat pin joint as starting point, described gripper shoe is arranged on three points of lift lever One of at length.As preferably, gripper shoe is arranged at 1/3rd length of lift lever so that on lift lever top The force application location that the height residing for tightener of suspension is optimal with hand during operator's normal stand is identical, to ensure at wire During lifting, operator possess the active force output effect of maximum, to improve the raising efficiency of wire.
Described support seat and connecting plate lay respectively at the both sides up and down of described circuit cross-arm.By supporting seat and connecting plate Shift to install so that the support force at lift lever is installed and more balances, improve the safe and reliable of station residing for operator Degree, to meet the requirement of safe construction.
The present invention compared with prior art, has such advantages as and beneficial effect:
1, different lifting wires, the angle of inclination of lift lever can arbitrarily be adjusted by the present invention, facilitating operator On the premise of construction, lift lever can carry out fast lifting to the circuit that the wire of major diameter or span are bigger, and, whole The gross weight of line lifter is less than 10 kilograms, and workmen's load during climbing is relatively small, is greatly saved wire Manpower and materials when promoting;
2, in the present invention, lift lever is when stress, and support tube and gripper shoe are as the midfoot support component of lift lever, opening Direction just to lift lever, while facilitating lift lever to adjust its heeling condition, support tube does not has the side energy of opening Gripper shoe is carried out spacing by loading process, it is to avoid gripper shoe drives lift lever bearing pin on support tube to move down, I.e. prevent wire support of lift lever in lifting process suddenly to lose efficacy and cause occurring security incident, improve lift lever Safe and reliable degree;
3, gripper shoe is arranged at 1/3rd length of lift lever by the present invention so that hangs on lift lever top is tight Height residing for the line device force application location optimal with hand during operator's normal stand is identical, to ensure to grasp when lifting wire The active force output effect of maximum is possessed, to improve the raising efficiency of wire as personnel.
Accompanying drawing explanation
Accompanying drawing described herein is used for providing being further appreciated by the embodiment of the present invention, constitutes of the application Point, it is not intended that the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is present configuration schematic diagram.
The parts title of labelling and correspondence in accompanying drawing:
1-support seat, 2-support tube, 3-gripper shoe, 4-connecting plate, 5-circuit cross-arm, 6-lift lever, 7-hook, 8-spanner, 9-tightener.
Detailed description of the invention
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with embodiment and accompanying drawing, to this Invention is described in further detail, and the exemplary embodiment of the present invention and explanation thereof are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment 1
As it is shown in figure 1, the present embodiment includes supporting seat 1, in the middle part of described support seat 1, it is hinged with lift lever 6, and is promoting thick stick Bar 6 end is provided with tightener 9, also includes connecting plate 4 and gripper shoe 3, is provided with support tube 2, gripper shoe in the middle part of described connecting plate 4 3 one end are connected with lift lever 6, and it is interior and hinged with support tube 2 by bearing pin that gripper shoe 3 other end is placed in support tube 2, and along institute State support tube 2 axis direction section on its external wall to be provided with for the freely through opening of gripper shoe 3.
Concrete mode of operation is as follows: support seat 1 and connecting plate 4 are fixed on electric pole or steel tower by bolt Correct position, and ensure connecting plate 4 and support between seat 1 and leave spacing, is in heeling condition, now meeting lift lever 6 It is positioned at the tightener 9 on lift lever 6 top just to wire, hook 7 is articulated on wire, now at the steel cable on tightener 9 In diastole state, artificial swing spanner 8 so that steel cable drives wire to begin to move up, until wire location is with exhausted Edge is positioned on same level line, manually stirs wire and is allowed to again be wound on insulator outer wall.Wherein, lift lever 6 with Supporting seat 1 hinged, and gripper shoe 3 is hinged with support tube 2, i.e. for different lifting wires, the angle of inclination of lift lever 6 can Arbitrarily adjusting, on the premise of facilitating operator to construct, lift lever 6 can be bigger to the wire of major diameter or span Circuit carry out fast lifting, and, the gross weight of whole line lifter be less than 10 kilograms, workmen climbing during Load relatively small, be greatly saved the wire manpower and materials when promoting.
The present embodiment also includes the circuit cross-arm 5 of two parallel distributions, has and multiple be distributed side by side on circuit cross-arm 5 Installing hole, and the fixing hole coordinated with installing hole is had at described two ends.Owing to supporting seat 1 and connecting plate 4 as lifting Lever 6 by force support, when supporting seat 1 and being fixed on the support on electric pole or steel tower, connecting plate 4 with support seat 1 Interval is arranged, and i.e. causes connecting plate 4 to be not easily found when installing and suitably installs station, now by arranging two parallel distributions Circuit cross-arm 5, and utilize the installing hole on circuit cross-arm 5 to coordinate with the fixing hole at connecting plate 4 two ends, cause connecting plate 4 Two ends are fastened, the common support to lift lever 6 by connecting plate 4 and support seat 1 so that lift lever 6 is in lifting certainly When weight and the bigger circuit of tension force more stable.
As preferably, lift lever 6 is when stress, and support tube 2 and gripper shoe 3 are as the midfoot support structure of lift lever 6 Part, the direction of opening is just to lift lever 6, and while facilitating lift lever 6 to adjust its heeling condition, support tube 2 is not opened Gripper shoe 3 can be carried out spacing in loading process by the side of mouth, it is to avoid gripper shoe 3 drives lift lever 6 on support tube 2 Bearing pin moves down, and i.e. prevents wire support of lift lever 6 in lifting process suddenly to lose efficacy and causes occurring security incident, Improve the safe and reliable degree of lift lever 6.
As preferably, gripper shoe 3 is arranged at 1/3rd length of lift lever 6 so that on lift lever 6 top The force application location that the height residing for tightener 9 of suspension is optimal with hand during operator's normal stand is identical, to ensure leading When line promotes, operator possess the active force output effect of maximum, to improve the raising efficiency of wire.
As preferably, by supporting shifting to install of seat 1 and connecting plate 4 so that the support force at installation lift lever 6 More balance, improve the safety reliability of station residing for operator, to meet the requirement of safe construction.
Above-described detailed description of the invention, has been carried out the purpose of the present invention, technical scheme and beneficial effect further Describe in detail, be it should be understood that the detailed description of the invention that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, all within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. done, all should comprise Within protection scope of the present invention.

Claims (5)

1. a power transmission line lifting device for aerial wires, including supporting seat (1), it is characterised in that: hinged at described support seat (1) middle part There is lift lever (6), and be provided with tightener (9) at lift lever (6) end, also include connecting plate (4) and gripper shoe (3), Described connecting plate (4) middle part is provided with support tube (2), and gripper shoe (3) one end is connected with lift lever (6), gripper shoe (3) other end It is placed in support tube (2) interior and hinged with support tube (2) by bearing pin, and along described support tube (2) axis direction on its external wall Section is provided with for gripper shoe (3) freely through opening.
A kind of power transmission line lifting device for aerial wires the most according to claim 1, it is characterised in that: also include two parallel distributions Circuit cross-arm (5), circuit cross-arm (5) has multiple installing hole being distributed side by side, and at the two ends of described connecting plate (4) Have the fixing hole coordinated with installing hole.
A kind of power transmission line lifting device for aerial wires the most according to claim 1, it is characterised in that: described opening just carries described Rise lever (6).
A kind of power transmission line lifting device for aerial wires the most according to claim 1, it is characterised in that: with described lift lever (6) It is arranged at 1/3rd length of lift lever (6) as starting point, described gripper shoe (3) with the pin joint supporting seat (1).
A kind of power transmission line lifting device for aerial wires the most according to claim 2, it is characterised in that: described support seat (1) and company Fishplate bar (4) lays respectively at the both sides up and down of described circuit cross-arm (5).
CN201610603277.2A 2016-07-28 2016-07-28 A kind of transmission line of electricity lifting device for aerial wires Active CN106229889B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610603277.2A CN106229889B (en) 2016-07-28 2016-07-28 A kind of transmission line of electricity lifting device for aerial wires

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610603277.2A CN106229889B (en) 2016-07-28 2016-07-28 A kind of transmission line of electricity lifting device for aerial wires

Publications (2)

Publication Number Publication Date
CN106229889A true CN106229889A (en) 2016-12-14
CN106229889B CN106229889B (en) 2017-11-10

Family

ID=57534026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610603277.2A Active CN106229889B (en) 2016-07-28 2016-07-28 A kind of transmission line of electricity lifting device for aerial wires

Country Status (1)

Country Link
CN (1) CN106229889B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368488A (en) * 2018-11-09 2019-02-22 国网山东省电力公司枣庄供电公司 A kind of crane lifting lead wire assistor and method
CN110601074A (en) * 2019-10-12 2019-12-20 国网新疆电力有限公司伊犁供电公司 Portable wire lifting device
CN111162485A (en) * 2020-02-26 2020-05-15 陈利新 Electric overhead line laying traction machine and construction method
CN111555186A (en) * 2020-05-26 2020-08-18 傅开峰 Wire transferring machine for ascending wire and distributing wire in communication engineering
CN113725778A (en) * 2021-09-01 2021-11-30 广西电网有限责任公司贵港供电局 Insulation formula wire lifting means on pole

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3140486U (en) * 2008-01-15 2008-03-27 関西電力株式会社 Overhead wire lifting device
JP4349604B2 (en) * 2001-03-22 2009-10-21 中部電力株式会社 Derrick device for top work of transmission tower
CN201729625U (en) * 2010-06-08 2011-02-02 刘跃星 Building indoor hoister
CN202193584U (en) * 2011-08-12 2012-04-18 河南省电力公司周口供电公司 Pole top lifter
CN103683088A (en) * 2012-09-12 2014-03-26 新疆电力公司昌吉电业局 Line bracing tool
CN104283156A (en) * 2014-10-17 2015-01-14 国网四川省电力公司攀枝花供电公司 Wire lifting device for power distribution line
CN104692299A (en) * 2013-12-04 2015-06-10 国家电网公司 Telescopic hydraulic lifting device of cable trench cover plates
CN204873764U (en) * 2015-05-27 2015-12-16 四川省劲腾环保建材有限公司 A board device of hollow partition plate

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4349604B2 (en) * 2001-03-22 2009-10-21 中部電力株式会社 Derrick device for top work of transmission tower
JP3140486U (en) * 2008-01-15 2008-03-27 関西電力株式会社 Overhead wire lifting device
CN201729625U (en) * 2010-06-08 2011-02-02 刘跃星 Building indoor hoister
CN202193584U (en) * 2011-08-12 2012-04-18 河南省电力公司周口供电公司 Pole top lifter
CN103683088A (en) * 2012-09-12 2014-03-26 新疆电力公司昌吉电业局 Line bracing tool
CN104692299A (en) * 2013-12-04 2015-06-10 国家电网公司 Telescopic hydraulic lifting device of cable trench cover plates
CN104283156A (en) * 2014-10-17 2015-01-14 国网四川省电力公司攀枝花供电公司 Wire lifting device for power distribution line
CN204873764U (en) * 2015-05-27 2015-12-16 四川省劲腾环保建材有限公司 A board device of hollow partition plate

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368488A (en) * 2018-11-09 2019-02-22 国网山东省电力公司枣庄供电公司 A kind of crane lifting lead wire assistor and method
CN110601074A (en) * 2019-10-12 2019-12-20 国网新疆电力有限公司伊犁供电公司 Portable wire lifting device
CN111162485A (en) * 2020-02-26 2020-05-15 陈利新 Electric overhead line laying traction machine and construction method
CN111162485B (en) * 2020-02-26 2020-09-18 广西汉锐电气有限公司 Electric overhead line laying traction machine and construction method
CN111555186A (en) * 2020-05-26 2020-08-18 傅开峰 Wire transferring machine for ascending wire and distributing wire in communication engineering
CN111555186B (en) * 2020-05-26 2021-11-16 国网甘肃省电力公司陇南供电公司 Wire transferring machine for ascending wire and distributing wire in communication engineering
CN113725778A (en) * 2021-09-01 2021-11-30 广西电网有限责任公司贵港供电局 Insulation formula wire lifting means on pole

Also Published As

Publication number Publication date
CN106229889B (en) 2017-11-10

Similar Documents

Publication Publication Date Title
CN106229889A (en) A kind of transmission line of electricity lifting device for aerial wires
CN204760890U (en) Wire hoisting device in distribution lines construction
CN104953507A (en) Device and method for lifting wire during distribution line construction
CN101177959A (en) Curtain wall unit hanging equipment and construction method thereof
CN103613031A (en) Simple transformer hoisting device
CN205955358U (en) Group's tower device of interior floated armful of pole of acting as go -between
CN105936470A (en) Wind power generator automatic turning lifter and mounting method
CN101649683A (en) Method for hoisting power transmission iron tower by assembly holding pole technology
CN104037658B (en) Pendency glass insulator strings promotes system
CN105366565A (en) Auxiliary hoisting device for high-tension cable tower
CN217555571U (en) Multifunctional hoisting device for hoisting materials on electric pole
CN204737645U (en) Hoisting accessory
CN205442567U (en) Steel -pipe pole operation platform
CN216638769U (en) Portable cement pole adjustable hoisting support
CN107143198B (en) A method of UHV transmission steel tower is found suitable for mountain area sternness location group
CN202625662U (en) Self-balancing amplitude modulation hold pole
CN210393401U (en) Hoisting and positioning device for stand column
CN210182910U (en) Simple insulator lifting device for concrete pole
CN209200516U (en) Unmanned plane hang take flexible ladder arrangement
CN208516850U (en) A kind of cement rod-type power transmission line overhead ground wire auxiliary device
CN206538115U (en) A kind of portable transformer upper air installing instrument
CN202190023U (en) Wire bracing device for overhead wire
CN201536236U (en) Bracket for hoisting heavy objects on object like an electrical pole
CN206219042U (en) Overlength storehouse plate hoist device
CN109881880A (en) Double rod type platform becomes Auxiliary equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant