CN106219419B - The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb - Google Patents
The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb Download PDFInfo
- Publication number
- CN106219419B CN106219419B CN201610831891.4A CN201610831891A CN106219419B CN 106219419 B CN106219419 B CN 106219419B CN 201610831891 A CN201610831891 A CN 201610831891A CN 106219419 B CN106219419 B CN 106219419B
- Authority
- CN
- China
- Prior art keywords
- tower crane
- exterior wall
- interior
- wall
- plug
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/20—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes with supporting couples provided by walls of buildings or like structures
- B66C23/24—Mobile wall cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/26—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
- B66C23/28—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C2700/00—Cranes
- B66C2700/03—Cranes with arms or jibs; Multiple cranes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Transportation (AREA)
- Jib Cranes (AREA)
Abstract
The present invention provides a kind of large-scale swing arm tower crane original position of high-rise building and is converted to plug-in construction method by interior climb, and the tower body of the tower crane is arranged between the interior wall and exterior wall of the Core Walls Structure by the joist mechanism;The joist mechanism includes the joist structure that two load girders and two load secondary beams are formed;The load girder is overlapped by the seat block teeth of its beam block teeth and the bracket bearing located at Core Walls Structure exterior wall and fixed;The construction method step includes:With the hithermost joist mechanism in the exterior wall top below lower supporting rod is set, lower supporting rod is vertically obliquely supported between the outboard end and interior wall of load girder;Contracting is lost above exterior wall to secondary high next joist mechanism;Abovementioned steps are re-covered untill exterior wall completely contracting mistake.The present invention solves interior climb by preceding solution and the technical problems such as speed slow, claim for eot is had bad luck when operating mode support system changes plug-in operating mode, reaches and is easy to tower crane being converted to plug-in, raising integral construction benefit by interior climb in situ.
Description
Technical field
Climbed technical field of construction the present invention relates to inside-climbing tower crane, and in particular to a kind of large-scale swing arm tower crane of high-rise building
Original position is converted to plug-in construction method by interior climb.
Background technology
Tower crane is as most important vertical transport instrument in Construction of High-rise, and the vertical transport instrument in high-building construction is most
Frequently with for outer attached self-standing crane, but because being limited by standard section of tower crane after depth of building is more than 200m
Outer attached derrick crane can not meet needs of constructing, simultaneously as the smaller influence in view of group towers work of Core Walls Structure.Therefore superelevation
Change in layer construction in use and climb arm tower crane, arm tower crane of inside creeping is that one kind is arranged on interior of building elevator or building
Tower crane between ladder, it can progressively be climbed upwards with construction progress.Arm tower crane of inside creeping needs three sets of load-bearing in work progress
For girder steel to form support system, most lower one of girder steel is used for load-bearing, and up one of girder steel is used for fixed tower and offset by the level of power
Influence.It is most upper together in the construction of building concrete masterplate to being used in turn when needing to climb again below tower crane, by the section that climbs,
Jacking cylinder, climb band and change step successively and reach the purpose that makes tower crane integrally climb.
Because the most important condition of tower crane climbing finishes for most upper one of steel girder erection, therefore girder steel has bad luck work and seems extremely heavy
Will.Simultaneously because the high-level structure construction period is more and more tighter, traditional method is to have bad luck girder steel using another tower crane auxiliary
Work, but also take the normal of another tower crane and have bad luck the time and hang time, cause when tower crane is constructed, two tower cranes can not be simultaneously
The problem of construction, tower crane is caused efficiently to be used and the technical problem such as claim for eot.
Constructed in addition, ultra-large type swing arm tower crane is continued on in each Super High.Ultra-large type movable arm tower suspender have from it is great,
The characteristics of single lifting capacity is big, large arm elevation angle height etc.;When rising to hundreds of meters of high space-times, ultra-large type swing arm tower crane can produce huge
Vertical load and horizontal loading.In order to resist the support of huge vertical and horizontal loading, at present ultra-large type boom-type tower crane
System has generally comprised main support crossbeam, secondary beam and brace etc..It is common mainly by two that wall-attaching equipment is climbed in existing tower crane
The support beam be arrangeding in parallel between two wall bodies to be located with setting the C-type steel of tower crane to collectively form;Wherein, the support beam
Both ends by being welded with the pre-buried steel corbel that is fixedly arranged on wall, so as to be attached on wall.
It is worth noting that, as high-rise building constantly breaks through new high degree, structure type is from tube-in-tube structure to bundled tube
The development of structure, bundled-tube structure constantly contract mistake with the rise of building, at tower crane positioning the contracting of structure lose and necessarily result in tower crane
The affected missing of vertical applied force point, and the difference for having that the contracting of single wall is lost, the contracting of double walls is lost, the contracting of three walls is lost is lost in bundled tube contracting, contracting is lost again
It is layered and stage by stage, causes the attachment point contractings of tower crane needs and lost or do not contracted and lose wall and the problem such as hinder.Meanwhile beam
The small space of barrel structure also results in inside-climbing tower crane support system and has bad luck difficulty.
The content of the invention
In view of the foregoing, the present invention provide a kind of large-scale swing arm tower crane original position of high-rise building by it is interior climb be converted to it is plug-in
Construction method, with climbed in solution operating mode support system have bad luck it is difficult, have bad luck more than rod member quantity caused by have bad luck speed slowly, work
The technical problems such as phase extension, reach and be easy to tower crane being converted to plug-in, raising integral construction benefit by interior climb in situ.
To achieve the above object, the present invention, which adopts the technical scheme that, provides a kind of high-rise building large-scale swing arm tower crane original
Position is converted to plug-in construction method by interior climb, when the tower crane climbs operating mode inside between the interior wall and exterior wall of Core Walls Structure;Its
In, the support system of the tower crane includes multigroup joist mechanism, and the tower body of the tower crane is arranged at institute by the joist mechanism
State between the interior wall of Core Walls Structure and exterior wall;The joist mechanism includes the joist knot that two load girders and two load secondary beams are formed
Structure;One end of each load girder is hinged by be hinged with the interior wall, and the other end is taken by bracket bearing and the exterior wall
Connect;The two loads secondary beam is connected between the two loads girder;Wherein, what the load girder was connected with the exterior wall is outer
Side bottom is provided with beam block teeth, and the bracket bearing corresponds to the beam block teeth and is provided with seat block teeth, and the load girder passes through its beam
The affixed positioning of seat block teeth of block teeth and the bracket bearing;The construction method step includes:
Diagonal brace setting steps:With the hithermost joist mechanism in the exterior wall top below lower supporting rod is set, make it is described under
Strut is vertically obliquely supported between outboard end and the interior wall of the load girder;Exterior wall contracting step-out is rapid:Contracting, which is become homeless, to be stated
Above exterior wall to secondary high next joist mechanism;Therefore abovementioned steps are re-covered untill exterior wall completely contracting mistake, by the tower crane
Operating mode is climbed out of located at the interior wall and exterior wall of Core Walls Structure between, changes to be formed located at Core Walls Structure interior wall by the joist mechanism
On plug-in operating mode.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
Be, methods described step further includes vertical diagonal brace and strengthens step, the step be with the hithermost support in exterior wall top
Upper connecting rod is set above beam mechanism, and the upper connecting rod vertically can obliquely be supported in described before or after exterior wall contracting step-out is rapid
Between the outboard end of load girder and the interior wall.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
Be, methods described step further includes horizontal diagonal brace setting steps, the step be with the hithermost support in exterior wall top
Beam mechanism sets triatic stay, and the triatic stay can be held horizontal skewed horizontal load before or after exterior wall contracting step-out is rapid in described
Advocate beam outboard end and the interior wall between.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
It is, the interior wall of the Core Walls Structure is connected with a side wall;Wherein, the support system of the tower crane includes the joist mechanism and turned
Angle supporting construction;The tower body of the tower crane is by the joist mechanism and corner support structure located at the interior wall and the side wall
Corner;The corner support structure include the parallel support beam located at joist mechanism outboard end and with the support
The lower supporting rod and triatic stay of beam connection;The construction method step includes:
Support beam setting steps:The support beam is abreast fixedly arranged under the load secondary beam of joist mechanism outboard end
Side;Diagonal brace setting steps:With the hithermost joist mechanism in the exterior wall top below lower supporting rod is set, erect the lower supporting rod
To being obliquely supported between the support beam and the interior wall;Exterior wall contracting step-out is rapid:Contracting, which is become homeless, states exterior wall to secondary high next
Above joist mechanism;Horizontal diagonal brace setting steps:In joist mechanism hithermost with the exterior wall top, triatic stay, institute are set
State triatic stay can before or after exterior wall contracting step-out is rapid horizontal skewed horizontal load in the interior wall and the support beam away from institute
Between the one end for stating side wall;Therefore abovementioned steps are re-covered untill exterior wall completely contracting mistake, by the tower crane by located at Core Walls Structure
Interior wall and exterior wall between in climb operating mode, the plug-in work to be formed on Core Walls Structure interior wall is changed by the joist mechanism
Condition.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
It is, methods described step further includes vertical diagonal brace and strengthens step, and the step is set in the top of the joist mechanism
Pull bar so that the upper connecting rod before or after exterior wall contracting step-out is rapid it is vertical be obliquely supported in the support beam and it is described in
Between wall.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
It is, the tower crane includes rotary supporting device, and a top platform is provided with above the rotary supporting device;Wherein, the tower
The top platform hung is provided with transporting device, and on the top platform, the other end is suspended at institute for described transporting device one end
State on the outside of rotary supporting device;The construction method step includes:
The support system component of the tower crane is hung by the transporting device to carry out having bad luck operation on vertical direction;Institute
The support system component for stating tower crane has bad luck work by the rotary supporting device cooperation transporting device progress horizontal direction
Industry.
The large-scale swing arm tower crane original position of high-rise building of the present invention is converted to the further improvement of plug-in construction method by interior climb
Be, the transporting device by setting hoist engine inside tower body, by steel wire rope from the hoist engine output after sequentially winding
In assembly pulley;Steel wire rope take-up or unwrapping wire described in the elevator Electrical Control are made, is existed with drawing the gib head being connected with the assembly pulley
Vertical direction top offset, carry out the vertical of tower crane support system rod member and have bad luck operation.
The present invention makes it have following beneficial effect as a result of above technical scheme:
(1) present invention can solve the problem that at present by the joist mechanism by setting two load secondary beams to form between load girder
Inside climb the support system of tower crane because construction space is narrow and small, have bad luck rod member quantity more than etc. cause support system to have bad luck the technology of difficulty to ask
Topic, and then the advantageous effects such as be easy to construct, save the duration, increase the benefit.
(2) present invention is overlapped by the end downside for being connected load girder with Core Walls Structure exterior wall with pre-buried steel corbel, energy
It is enough to provide tower crane stable attached wall intensity before contracting is lost, and be easy to advocate the bracket bearing self-supporting on beam when exterior wall contracts and lost
Remove, improve convenience for construction.
(3) present invention is connected by the joist mechanism with lower supporting rod, upper connecting rod and/or triatic stay, solves tower crane
Attached wall structure is realized and is easy in tower crane carries out in the original location because tower crane loses vertical applied force point caused by Core Walls Structure contracting is lost the problem of
Climb the technique effect for changing plug-in operating mode.
(4) present invention can solve the problem that ultra-large type tower crane by setting lower supporting rod and/or upper connecting rod in the joist mechanism
On leave behind support support system structural checking computation power transmission unstructured problem,.
(5) present invention solves tower crane and is located at Core Walls Structure wall by the cooperation of the joist mechanism and corner support structure
Construction space caused by body corner is narrow and small, the technical problem such as inconvenient.
(6) present invention has further speeded up the speed of having bad luck of support system, simultaneously by setting transporting device on tower crane
With the liberation auxiliary tower crane lifting time and hang the advantageous effects such as secondary, saving duration.
(7) the large-scale swing arm tower crane original position of high-rise building provided by the invention by it is interior climb be converted to plug-in construction method can
Be individually used for tower crane in climb, plug-in operating mode, simplify and optimize original support system, reduce the weight of support system,
Also reduce construction cost.
Brief description of the drawings
Fig. 1 (a), (b), (c) figure is that tower crane of the present invention climbs the construction process structure that change working is plug-in operating mode by interior
Schematic diagram.
Fig. 2 is the planar structure schematic diagram that operating mode is climbed inside by tower crane joist mechanism of the present invention.
Fig. 3 is the facade structures schematic diagram that operating mode is climbed inside by tower crane joist mechanism of the present invention.
Fig. 4 is the facade structures schematic diagram that tower crane joist mechanism of the present invention sets lower supporting rod in plug-in operating mode.
Fig. 5 is the facade structures schematic diagram that tower crane joist mechanism of the present invention sets upper connecting rod and lower supporting rod in plug-in operating mode.
Fig. 6 is the planar structure signal that tower crane of the present invention sets triatic stay in plug-in operating mode in joist mechanism both sides
Figure.
Fig. 7 is that tower crane support structure of the present invention is asymmetrically located at Core Walls Structure interior wall and the plug-in operating mode of side wall corner is put down
Face structural representation.
Fig. 8 is the facade structures schematic diagram of tower crane asymmetry supporting mechanism of the present invention.
Fig. 9 is the planar structure schematic diagram of tower crane asymmetry supporting mechanism of the present invention.
Figure 10 is that the mechanism of having bad luck of tower crane of the present invention is located at Slewing Support Mechanism and the surface structure schematic diagram on tower body top.
Figure 11 is that tower crane of the present invention has bad luck mechanism in the partial enlargement structural representation of Slewing Support Mechanism.
The corresponding relation of reference and part is as follows:
A- tower cranes;A1- tower bodies;A10- standard knots;The standard knots of A1a- first;The standard knots of A1b- second;A2- is turned round
Supporting arrangement;A21- top platforms;A22- side walls;A23- upper connecting parts;A24- lower supporting parts;10- Core Walls Structures;11- interior walls;
12- exterior walls;13- side walls;20- joists mechanism;21- load girders;211- connectors;212- positioning seats;213- is hinged
Bearing;214- bracket bearings;215- beam block teeth;216- seat block teeth;22- load secondary beams;23- diagonal brace connecting seats;231-
Horizontal seat;232- vertical supports;Portions under 233-;234- theravadas;24- lower supporting rods;Pivoting support is supportted under 241-;
25- upper connecting rods;251- pulls up pivoting support;26- triatic stays;261- mitered pivoting supports;30- corner support structures;
31- joists;311- load girders;312- load secondary beams;313- side joint pivoting supports;32- support beams;33- diagonal braces connect
Joint chair;331- horizontal seats;332- vertical supports;Portions under 333-;334- theravadas;34- lower supporting rods;Supportted under 341-
Pivoting support;35- upper connecting rods;351- pulls up pivoting support;36- triatic stays;361- mitered pivoting supports;40- loads
Secondary beam;41- hoist engines;411- steel wire ropes;12- exterior walls;43- assembly pulleys;The angle pulleies of 431- first;Second turn of 432-
To pulley;433- fixed pulleys;434- movable pulleys;435- gib heads;44- the inners mounting seat;45- outer ends mounting seat;451-
Semi-girder;452- web portion;46- stage casings mounting seat;47- crossbeams;48- raker beams.
Embodiment
For the benefit of to the understanding of the present invention, illustrated below in conjunction with drawings and Examples.
Fig. 1 to Figure 11 is referred to, the present invention provides a kind of large-scale swing arm tower crane original position of high-rise building and is converted to by interior climb
Plug-in construction method.
Such as Fig. 1 (a), (b), (c), sequentially show construction method of the present invention by tower crane A from interior change working of climbing to be plug-in
The flowage structure schematic diagram of operating mode.
Such as Fig. 1 (a), when the tower crane A climbs operating mode inside between the interior wall 11 and exterior wall 12 of Core Walls Structure 10;It is described
Tower crane A support system includes multigroup joist mechanism 20, and the tower body A1 of the tower crane A is arranged at institute by the joist mechanism 20
State between the interior wall 11 of Core Walls Structure 10 and exterior wall 12;Such as Fig. 2, Fig. 3, the joist mechanism 20 is held including two load girders 21 and two
The joist structure that power secondary beam 22 is formed;One end of each load girder 21 is be hinged by pivoting support 213 and the interior wall 11,
The other end is overlapped by bracket bearing 214 and the exterior wall 12;The two loads secondary beam 22 is connected to the two loads girder 21
Between;Wherein, the outboard end bottom that the load girder 21 is connected with the exterior wall 12 is provided with beam block teeth 215, the bracket branch
The corresponding beam block teeth 215 of seat 214 are provided with seat block teeth 216, and the load girder 21 passes through its beam block teeth 215 and the bracket branch
The seat block teeth 216 of seat 214 overlap stationary positioned.
It is that following construction method step is carried out by foregoing joist mechanism 20 with the present invention, to realize that tower crane original position is climbed by interior
Be converted to plug-in.The step includes:
Diagonal brace setting steps:Such as Fig. 1 (b), with the hithermost joist mechanism 20 in the top of exterior wall 12 below set
Lower supporting rod 24, make the lower supporting rod 24 be vertically obliquely supported in the outboard end of the load girder 21 and the interior wall 11 it
Between;
Exterior wall contracting step-out is rapid:Such as Fig. 1 (b), contracting, which is become homeless, states exterior wall 12 to the secondary high top of next joist mechanism 20;
Abovementioned steps are re-covered untill exterior wall 12 completely lose by contracting, such as Fig. 1 (c), by the tower crane A from located at Core Walls Structure
Operating mode is climbed between 10 interior wall 11 and exterior wall 12, is formed by the joist mechanism 20 conversion and is located at the interior wall 11 of Core Walls Structure 10
On plug-in operating mode.Such as Fig. 4, outboard end and lower support pivoting support of the skewed horizontal load of lower supporting rod 24 in the load girder 21
Between 241.
Further, construction party of the present invention can strengthen step by vertical diagonal brace, improve joist mechanism 20 in vertical side
Upward attached wall structural strength.Such as Fig. 5, upper connecting rod 25 is set above joist mechanism 20, the upper connecting rod 25 can contract in exterior wall
Vertically obliquely it is supported between the outboard end and the interior wall 11 of the load girder 21 before or after step-out is rapid.Wherein,
It is to be located at upper connecting rod 25 with the top of exterior wall 12 most when being carried out before vertical diagonal brace reinforcement step is rapid in exterior wall contracting step-out
The close top of joist mechanism 20, and upper connecting rod 25 sequentially is set after exterior wall 12 is lost in each contracting;When vertical diagonal brace strengthens step
When exterior wall contracting step-out is carried out afterwards suddenly, then the sequence of construction for visually implementing Construction Condition progress upper connecting rod 25 adjusts.
In addition, construction party of the present invention can improve joist mechanism 20 in level further by horizontal diagonal brace setting steps
Attached wall structural strength on direction.Such as Fig. 6, triatic stay is set in joist mechanism 20 hithermost with the top of exterior wall 12
26, the triatic stay 26 can before or after exterior wall contracting step-out is rapid horizontal skewed horizontal load in the outside of the load girder 21
Between end and the interior wall 11.Wherein, it is by triatic stay when horizontal diagonal brace setting steps are carried out before exterior wall contracting step-out is rapid
26 are located at the top of joist mechanism 20 hithermost with the top of exterior wall 12, and sequentially set water after exterior wall 12 is lost in each contracting
Support bar 26;When horizontal diagonal brace setting steps are carried out afterwards suddenly in exterior wall contracting step-out, then visually implement Construction Condition and enter water-filling
Support the sequence of construction adjustment of bar 26.
Specifically, referring back to the structural configuration for shown in Fig. 2 to Fig. 6, illustrating joist mechanism 20 of the present invention.The joist machine
Structure 20 includes load girder 21, load secondary beam 22, diagonal brace rod member and corresponding beam body and rod member quantity to tie-beam body end portion
And the pre-buried more several pivoting supports being fixed on the wall of Core Walls Structure 10.In the present embodiment, the diagonal brace rod member is to oblique branch
Support between the load girder 21 and the interior wall 11 of Core Walls Structure 10, the bearing of trend according to raker beam is divided into located at the load
Upper connecting rod 25, the lower supporting rod 24 of the upper and lower sides of girder 21, and the triatic stay 26 located at the horizontal outer side of load girder 21;With
The pivoting support that the upper connecting rod 25, lower supporting rod 24, triatic stay 26 connect is sequentially that pull-up pivoting support 251, lower support are be hinged
Bearing 241, mitered pivoting support 261.
The pivoting support 213 is defaulted on the identical height and position of the interior wall 11;The pivoting support 213, which has, to hang down
The pre-embedded steel slab and second splint directly to connect, the pivoting support 213 are embedded on the interior wall 11 in advance by the pre-embedded steel slab.
As shown in Figure 2 and Figure 3, pivoting support 213 of the invention has roughly the same with pivoting support 241,251,261
Structural form;Illustrate its specific structure by taking the pivoting support 213 as an example.In the present embodiment, the pivoting support 213
Pre-embedded steel slab and clamping plate are to be vertically arranged and the harden structure of vertical connection, the pivoting support 213 are additionally provided with horizontal rib, to
Strengthen the overall structure support strength of pivoting support.
As shown in figure 3, the bracket bearing 214 is defaulted on the identical height and position of the exterior wall 12;The bracket branch
Seat 214 is embedded on the exterior wall 12 in advance by the pre-embedded steel slab.
The load girder 21 has two and is abreast arranged on the wall of Core Walls Structure 10;Each load girder 21 has
There are the medial extremity being connected with interior wall 11 and the outboard end being connected with exterior wall 12;The end face of the medial extremity is provided with a connection piece
211, the medial extremity of the load girder 21 is welded and fixed by the connector 31 and the pivoting support 213;The outside
The end bottom side at end connects fixation with the bracket bearing 214.The otic placode of the load girder 21 is inserted in the pivoting support
Between 213 second splint, the otic placode connects fixation with the second splint.
As shown in figure 3, the outboard end weldering of the load girder 21 is provided with positioning seat 212, the bottom of the positioning seat 212 is set
There are beam block teeth 215;The bracket bearing 214 has the pre-embedded steel slab being vertically arranged and carries seat, and the load seat top surface is provided with seat tooth
Block 216;The bracket bearing 214 is embedded on the exterior wall 12 in advance by the pre-embedded steel slab;The outside of the load girder 21
End is arranged on the load seat of the bracket bearing 214, and the load girder 21 passes through its beam block teeth 215 and the bracket bearing
214 seat block teeth 216 connect positioning.
The quantity of the load secondary beam 22 is two, and the level of two loads secondary beam 22 and abreast connection are mounted on described
Between two load girders 21, mount structure of the function equivalent to existing c-type frame is formed to enclose to set with the two loads girder 21, with
It is located setting tower crane.
Therefore the outboard end of the load girder 21 is with two bracket bearings 214 by being connected or being connected with diagonal brace rod member,
Operating mode or plug-in operating mode are climbed to be formed in tower crane.
Such as Fig. 4 to Fig. 6, the outboard end of the load girder 21 is provided with diagonal brace connecting seat 23, and the diagonal brace connecting seat 23 wraps
Horizontal seat 231 and vertical support 232 are included, the vertical support 232 is further formed with the theravada of portions 233 and one
234;Described one end of lower supporting rod 24 is connected with the lower portions 233, and the other end is connected by lower support pivoting support 241 with interior wall 11
Connect;Described one end of upper connecting rod 25 is connected with the theravada 234, and the other end is connected by pulling up pivoting support 251 with interior wall 11;
Described one end of triatic stay 26 is connected with the horizontal seat 231, the other end by the mitered pivoting support 261 with it is described interior
Wall 11 connects.
Such as Fig. 7 to Fig. 9, show that tower crane A of the present invention is arranged at the interior wall 11 of Core Walls Structure 10 and applying during 13 corner of side wall
Work scheme.Such as Fig. 7, the interior wall 11 of the Core Walls Structure 10 is connected with a side wall 13;The support system of the tower crane A includes the support
Beam mechanism 20 and corner support structure 30;The tower body A1 of the tower crane A passes through the joist mechanism 20 and corner support structure 30
Located at the corner of the interior wall 11 and the side wall 13;The corner support structure 30 is located at the joist mechanism including parallel
The support beam 32 of 20 outboard ends and the lower supporting rod 34 and triatic stay 36 being connected with the support beam 32;
Therefore the present invention carries out following construction method step by foregoing joist mechanism 20 and corner support structure 30, with
Realize tower crane original position by it is interior climb be converted to plug-in when, the tower crane A that corner is connected to being located at interior wall 11 with side wall 13 is set up tiltedly
Strut member is to improve plug-in tower crane A overall construction intensity.The step includes:
Support beam setting steps:Such as Fig. 8, the support beam 32 is abreast fixedly arranged on the outboard end of joist mechanism 20
The downside of load secondary beam 22;
Diagonal brace setting steps:Such as Fig. 8, with the hithermost joist mechanism 20 in the top of exterior wall 12 below lower supporting rod is set
34, the lower supporting rod 34 is vertically obliquely supported between the support beam 32 and the interior wall 11;
Exterior wall contracting step-out is rapid:Such as Fig. 1 (b), contracting, which is become homeless, states exterior wall 12 to the secondary high top of next joist mechanism 20;
Horizontal diagonal brace setting steps:Such as Fig. 7 to Fig. 9, set with the hithermost joist mechanism 20 in the top of exterior wall 12
Triatic stay 36, the triatic stay 36 can before or after exterior wall contracting step-out is rapid horizontal skewed horizontal load in the interior wall 11 with
Between the one end of the support beam 32 away from the side wall 13;
Abovementioned steps are re-covered untill exterior wall 12 completely lose by contracting, by the tower crane A by the interior wall 11 located at Core Walls Structure 10
Operating mode is climbed between exterior wall 12, the plug-in work formed by the joist mechanism 20 conversion on the interior wall 11 of Core Walls Structure 10
Condition.
It is by horizontal brace when the horizontal diagonal brace setting steps are carried out before exterior wall contracting step-out is rapid in the present embodiment
Bar 36 is located at the top of joist mechanism 20 hithermost with the top of exterior wall 12, and is sequentially set after exterior wall 12 is lost in each contracting
Triatic stay 36;When horizontal diagonal brace setting steps are carried out afterwards suddenly in exterior wall contracting step-out, then visually implement Construction Condition progress
The sequence of construction adjustment of triatic stay 36.
Further, construction party of the present invention can strengthen step by vertical diagonal brace, improve joist mechanism 20 in vertical side
Upward attached wall structural strength.Such as Fig. 8, upper connecting rod 35 is set above joist mechanism 20, the upper connecting rod 35 can contract in exterior wall
Vertically obliquely it is supported between the outboard end and the interior wall 11 of the load girder 21 before or after step-out is rapid.Wherein,
It is to be located at upper connecting rod 35 with the top of exterior wall 12 most when being carried out before vertical diagonal brace reinforcement step is rapid in exterior wall contracting step-out
The close top of joist mechanism 20, and upper connecting rod 35 sequentially is set after exterior wall 12 is lost in each contracting;When vertical diagonal brace strengthens step
When exterior wall contracting step-out is carried out afterwards suddenly, then the sequence of construction for visually implementing Construction Condition progress upper connecting rod 35 adjusts.
Specifically, referring back to the structural configuration for shown in Fig. 7 to Fig. 9, illustrating corner support structure 30 of the present invention.Described turn
Angle supporting construction 30 includes joist 31, support beam 32, diagonal brace connecting seat 33, diagonal brace rod member and corresponding beam body and rod member quantity is used
With tie-beam body end portion and the pre-buried more several pivoting supports being fixed on the wall of Core Walls Structure 10.In the present embodiment, the joist
31 be to be enclosed by the two load girders 311 and two load secondary beams 312 with joist mechanism 20 identical components and set the structure formed;The branch
Support beam 32 is connected parallel to the ground of load secondary beam 312 with its both ends with the two loads girder 311.
Such as Fig. 8, Fig. 9, the both ends end of the support beam 32 is respectively provided with a diagonal brace connecting seat 33, the diagonal brace connecting seat 33
Including horizontal seat 331 and vertical support 332, the vertical support 332 is further formed with the theravada of portions 333 and one
334.The diagonal brace rod member includes lower supporting rod 34, upper connecting rod 35 and triatic stay 36, described one end of lower supporting rod 34 and the lower seat
Portion 333 is connected, and the other end is connected by lower support pivoting support 341 with interior wall 11;Described one end of upper connecting rod 35 and the theravada
334 connections, the other end are connected by pulling up pivoting support 351 with interior wall 11;Described one end of triatic stay 36 and the horizontal branch
Seat 331 is connected, and the other end is connected by mitered pivoting support 361 with interior wall 11.
In the present embodiment, the lower support pivoting support 341 of the corner support structure 30, pull-up pivoting support 351 and tiltedly
Pivoting support 361 is connect, lower support pivoting support 241, pull-up pivoting support 251 and mitered pivoting support 261 with joist mechanism 20
Position is set with identical function with suitable structure and corresponding group, and interior wall is arranged at for corner support structure 30 to be consolidated
On 11.
Such as Figure 10, Figure 11, show that tower crane A of the present invention includes the rotary supporting device A2 at the top of tower body A1, described time
Turn to be provided with a top platform A21 above supporting arrangement A2;The top platform A21 of the tower crane A is provided with transporting device 40, described
On the top platform A21, the other end is suspended on the outside of the rotary supporting device A2 one end of transporting device 40.
Therefore foregoing joist mechanism 20 of the present invention and corner support structure 30 carry out following apply by the transporting device 40
Work method and step, with realize tower crane original position by it is interior climb be converted to plug-in when, entered using the transporting device 40 located at tower crane A itself
The support system component of row composition joist mechanism 20 and corner support structure 30 has bad luck operation, to realize that tower crane voluntarily has bad luck steel
The purpose of beam.The step includes:
Such as Figure 11, the support system component of the tower crane A is hung by the transporting device 40 to be carried out on vertical direction
Have bad luck operation;
Such as Figure 10, the support system component of the tower crane A coordinates the transporting device by the rotary supporting device A2
40 progress horizontal directions have bad luck operation.
In the present embodiment, the transporting device 40 is by setting hoist engine 41 inside tower body A1, by steel wire rope 411
Assembly pulley 43 is sequentially set around from after the hoist engine 41 output;Make the automatically controlled take-up of steel wire rope 411 of the hoist engine 41 or
Unwrapping wire, to draw the in the vertical direction displacement of gib head 435 being connected with the assembly pulley 43, carry out tower crane A support system rod members
Vertical have bad luck operation.
Specifically, referring back to the structural configuration for shown in Figure 10, Figure 11, illustrating transporting device 40 of the present invention.It is described to have bad luck
Device 40 mainly includes from nose girder 42 and assembly pulley 43, wherein, it is described to pass through inner mounting seat 44, stage casing mounting seat from nose girder 42
46th, crossbeam 47 and raker beam 48, which stretch out, is vacantly arranged at the outside of the rotary supporting device A2;The assembly pulley 43 is then
Turned to by outer end mounting seat 45 described in being arranged at from the end of nose girder 42.
As shown in Figure 10, Figure 11, it is described that there is the inner being connected with the top platform A21 from nose girder 42, and hang and set
Outer end on the outside of the rotary supporting device A2;The assembly pulley 43 of the transporting device 40 includes the first angle pulley 431, the
Two angle pulleies 432, fixed pulley 433 and movable pulley 434, wherein, first angle pulley 431 is located at the top platform
On A21, second angle pulley 432 is located at the self-conductance located at the outside end from nose girder 42, the fixed pulley 433
Beam 42 is close to the downside of its outer end;The movable pulley 434 is connected with a gib head 435 and is suspended to second angle pulley 432
The downside between the fixed pulley 433.
Such as Figure 10, form and one is provided with the standard knot A10 of the tower body A1 to install the installation foundation of hoist engine 41, institute
State and steel wire rope 411 is arranged with hoist engine 41, the one end of steel wire rope 411 winding is connected on the hoist engine 41, the other end
Sequentially the first angle pulley 431, the second angle pulley 432, movable pulley 434 and fixed pulley 433 described in pile warp;Whereby, the volume
Machine 41 is raised by electrically controlling the unwrapping wire of steel wire rope 411 or take-up, so as to draw the in the vertical direction displacement of movable pulley 434,
After being hung on the gib head 435 to be formed the component of tower crane support system, matching somebody with somebody for assembly pulley 43 and hoist engine 41 is utilized
Close, operation is had bad luck in the steel construction hanging for completing tower crane selve support system.
In the present embodiment, it is the first standard knot A1a to define the standard knot A10 being connected with the rotary supporting device A2,
And below the first standard knot A1a and connected standard knot A10 is the second standard knot A1b;It is preferably, described
Hoist engine 41 and its installation foundation are in the first standard knot A1a or the second standard knot A1b, to avoid steel wire rope 411
Hauling distance is long, influences the operation that tower crane itself hanging is had bad luck.
It is described to be preferably H profile steel from nose girder 42 in the present embodiment.It is described to be provided with the inner peace from the inner of nose girder 42
Fill seat 44, the top platform A21 for being fixedly arranged on the rotary supporting device A2 by the inner mounting seat 44 from nose girder 42
On;It is described to be provided with the stage casing mounting seat 46, the stage casing mounting seat 46 and the rotary supporting device from the stage casing of nose girder 42
The crossbeam 47 laterally set is connected between A2 and the angularly disposed raker beam 48 connects.
Specifically, the top platform A21 the week side of boss of the rotary supporting device A2 is formed with side wall A22, the side wall A22
Provided with upper connecting part A23 and lower supporting part A24;One end of the crossbeam 47 is connected with the bottom of the stage casing mounting seat 46, the other end
It is connected with the side wall A22 and upper connecting part A23;The bottom of one end of the raker beam 48 and the stage casing mounting seat 46 and described
One end connection of crossbeam 47, the other end are connected with the side wall A22.In the present embodiment, the upper connecting part A23 is by the top
Portion's platform A21 top plate peripheries protrude out to be formed beyond the side wall A22, the lower supporting part A24 be fixedly arranged on by welding it is described
The plate body that extends laterally on side wall A22 is formed.
Therefore the present invention has following technique effect by preceding art technical scheme:
1st, by the cooperation of joist mechanism 20 and corner support structure 30, solves part Core Walls Structure outer barrel (exterior wall 12) contracting
Lose the contradiction for causing Super High project tower crane to position, reduce influence of the problems such as tower crane shifts in the air to the duration, save cost,
Reduce potential safety hazard;
2nd, by the cooperation of joist mechanism 20, corner support structure 30 and transporting device 40, high-rise building side is embodied
The optimal uniqueness of case, suits measures to local conditions, response structure variation characteristic, embodies green construction;
3rd, by joist mechanism 20, reduce and the rod member quantity that operating mode support system is had bad luck is climbed in tower crane;
4th, operating mode and plug-in operating mode support system organic integration are climbed by interior, realizes and directly change;
5th, realize that tower crane voluntarily has bad luck selve support system and climbs band;And
6th, tower crane support system weight is reduced, optimizes calculating process and stress form, saves duration, cost, is created
Benefit is made.
The present invention is described in detail above in association with drawings and Examples, those skilled in the art can basis
Described above makes many variations example to the present invention.Thus, some details in embodiment should not form limitation of the invention,
The present invention will be used as protection scope of the present invention using the scope that appended claims define.
Claims (7)
1. a kind of large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb, the tower crane climbs work inside
During condition between the interior wall and exterior wall of Core Walls Structure;It is characterized in that:
The support system of the tower crane includes multigroup joist mechanism, and the tower body of the tower crane is arranged at institute by the joist mechanism
State between the interior wall of Core Walls Structure and exterior wall;The joist mechanism includes the joist knot that two load girders and two load secondary beams are formed
Structure;One end of each load girder is hinged by pivoting support and the interior wall, the other end by bracket bearing with it is described outer
Wall overlaps;The two loads secondary beam is connected between the two loads girder;Wherein, the load girder is connected with the exterior wall
Outboard end bottom be provided with beam block teeth, the bracket bearing corresponds to the beam block teeth and is provided with seat block teeth, and the load girder passes through
The affixed positioning of seat block teeth of its beam block teeth and the bracket bearing;
The construction method step includes:
Diagonal brace setting steps:With the hithermost joist mechanism in the exterior wall top below lower supporting rod is set, make the lower supporting rod
Vertically obliquely it is supported between outboard end and the interior wall of the load girder;
Exterior wall contracting step-out is rapid:Contracting, which is become homeless, to be stated above exterior wall to secondary high next joist mechanism;
Abovementioned steps are re-covered untill exterior wall completely contracting mistake, by the tower crane between the interior wall and exterior wall of Core Walls Structure
Operating mode is inside climbed, the plug-in operating mode to be formed on Core Walls Structure interior wall is changed by the joist mechanism.
2. the large-scale swing arm tower crane original position of high-rise building according to claim 1 is converted to plug-in construction method by interior climb;
It is characterized in that:
Vertical diagonal brace strengthens step:Upper connecting rod is set above joist mechanism, and the upper connecting rod can be before exterior wall contracting step-out be rapid
Or vertically obliquely it is supported between outboard end and the interior wall of the load girder afterwards.
3. the large-scale swing arm tower crane original position of high-rise building according to claim 1 or 2 is converted to plug-in construction party by interior climb
Method;It is characterized in that:
Horizontal diagonal brace setting steps:In joist mechanism hithermost with the exterior wall top, triatic stay, the horizontal brace are set
Bar can be in horizontal skewed horizontal load before or after exterior wall contracting step-out is rapid between the outboard end and the interior wall of the load girder.
4. the large-scale swing arm tower crane original position of high-rise building according to claim 1 is converted to plug-in construction method by interior climb,
The interior wall of the Core Walls Structure is connected with a side wall;It is characterized in that:
The support system of the tower crane includes the joist mechanism and corner support structure;The tower body of the tower crane passes through the support
Beam mechanism and corner support structure are located at the corner of the interior wall and the side wall;The corner support structure includes parallel set
Support beam and the lower supporting rod and triatic stay that are connected with the support beam in joist mechanism outboard end;
The construction method step includes:
Support beam setting steps:The support beam is abreast fixedly arranged on the downside of the load secondary beam of joist mechanism outboard end;
Diagonal brace setting steps:With the hithermost joist mechanism in the exterior wall top below lower supporting rod is set, make the lower supporting rod
Vertically obliquely it is supported between the support beam and the interior wall;
Exterior wall contracting step-out is rapid:Contracting, which is become homeless, to be stated above exterior wall to secondary high next joist mechanism;
Horizontal diagonal brace setting steps:In joist mechanism hithermost with the exterior wall top, triatic stay, the horizontal brace are set
Bar can before or after exterior wall contracting step-out is rapid horizontal skewed horizontal load in the interior wall and the support beam away from the side wall
Between one end;
Abovementioned steps are re-covered untill exterior wall completely contracting mistake, by the tower crane by between the interior wall and exterior wall of Core Walls Structure
Operating mode is inside climbed, the plug-in operating mode to be formed on Core Walls Structure interior wall is changed by the joist mechanism.
5. the large-scale swing arm tower crane original position of high-rise building according to claim 4 is converted to plug-in construction method by interior climb,
It is characterized in that:
Vertical diagonal brace strengthens step:Upper connecting rod is set in the top of the joist mechanism, lost so that the upper connecting rod contracts in exterior wall
Vertically obliquely it is supported between the support beam and the interior wall before or after step.
6. the large-scale swing arm tower crane original position of high-rise building according to claim 1 or 4 is converted to plug-in construction party by interior climb
Method, the tower crane include rotary supporting device, a top platform are provided with above the rotary supporting device;It is characterized in that:
The top platform of the tower crane is provided with transporting device, and described transporting device one end is another on the top platform
End is suspended on the outside of the rotary supporting device;
The construction method step includes:
The support system component of the tower crane is hung by the transporting device to carry out having bad luck operation on vertical direction;
The support system component of the tower crane coordinates the transporting device to carry out horizontal direction by the rotary supporting device
Have bad luck operation.
7. the large-scale swing arm tower crane original position of high-rise building according to claim 6 is converted to plug-in construction method by interior climb,
It is characterized in that:
The transporting device is sequentially set around by setting hoist engine inside tower body, by steel wire rope from after hoist engine output
Assembly pulley;Steel wire rope take-up or unwrapping wire described in the elevator Electrical Control are made, with traction with the gib head that the assembly pulley is connected perpendicular
Nogata shifts up, and carries out the vertical of tower crane support system rod member and has bad luck operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610831891.4A CN106219419B (en) | 2016-09-19 | 2016-09-19 | The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610831891.4A CN106219419B (en) | 2016-09-19 | 2016-09-19 | The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106219419A CN106219419A (en) | 2016-12-14 |
CN106219419B true CN106219419B (en) | 2018-02-06 |
Family
ID=58075707
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610831891.4A Active CN106219419B (en) | 2016-09-19 | 2016-09-19 | The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106219419B (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107598562B (en) * | 2017-08-02 | 2019-12-03 | 威海新特重工股份有限公司 | It is a kind of with bracket and its installation method of climbing in fixed cage |
CN108002255B (en) * | 2017-12-28 | 2024-02-09 | 上海建工四建集团有限公司 | Cantilever tower crane climbing beam supporting system and using method thereof |
CN109335971A (en) * | 2018-12-19 | 2019-02-15 | 中建局集团第三建筑有限公司 | Auxiliary circulating transfer device for movable arm type tower crane support system and construction method thereof |
CN109592572B (en) * | 2019-01-22 | 2020-08-04 | 太原科技大学 | Construction equipment and construction method for reinforced concrete wind power tower |
CN110127538A (en) * | 2019-05-16 | 2019-08-16 | 中铁建设集团有限公司 | Adhere to outside a kind of super high-rise building from climbing tower-crane high-altitude integral translation system |
CN110116966A (en) * | 2019-06-18 | 2019-08-13 | 上海建工四建集团有限公司 | A kind of movable arm tower crane climbs boom device and its application method |
CN110589690B (en) * | 2019-08-06 | 2021-03-26 | 上海宝冶集团有限公司 | Climbing method of internal climbing tower crane in narrow space |
CN110577157B (en) * | 2019-09-30 | 2020-07-03 | 中核华兴达丰机械工程有限公司 | Ultrahigh-rise external hanging movable arm tower crane support frame and construction method thereof |
CN112591628B (en) * | 2021-03-02 | 2021-05-25 | 上海建工集团股份有限公司 | Lateral tower crane supporting device and using method |
CN113401815B (en) * | 2021-06-17 | 2022-07-12 | 中建一局集团建设发展有限公司 | High-altitude conversion system of core tube tower crane of super high-rise building and construction method thereof |
CN114560408B (en) * | 2022-03-11 | 2024-09-06 | 上海建工四建集团有限公司 | Jacking structure and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000248632A (en) * | 1999-03-03 | 2000-09-12 | Kumagai Gumi Co Ltd | Floor climbing method of tower crane |
CN201116267Y (en) * | 2007-10-17 | 2008-09-17 | 上海市机械施工有限公司 | Externally hung supporting device for internally climbing tower crane |
CN203794504U (en) * | 2014-03-31 | 2014-08-27 | 广东庞源工程机械有限公司 | Internal-climbing plug-in tower crane support structure |
CN203903834U (en) * | 2014-06-27 | 2014-10-29 | 四川锦城建筑机械有限责任公司 | Internal-climbing tower crane |
CN204848023U (en) * | 2015-06-15 | 2015-12-09 | 中国建筑第八工程局有限公司 | Braced system that climbing tower hung in external |
-
2016
- 2016-09-19 CN CN201610831891.4A patent/CN106219419B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000248632A (en) * | 1999-03-03 | 2000-09-12 | Kumagai Gumi Co Ltd | Floor climbing method of tower crane |
CN201116267Y (en) * | 2007-10-17 | 2008-09-17 | 上海市机械施工有限公司 | Externally hung supporting device for internally climbing tower crane |
CN203794504U (en) * | 2014-03-31 | 2014-08-27 | 广东庞源工程机械有限公司 | Internal-climbing plug-in tower crane support structure |
CN203903834U (en) * | 2014-06-27 | 2014-10-29 | 四川锦城建筑机械有限责任公司 | Internal-climbing tower crane |
CN204848023U (en) * | 2015-06-15 | 2015-12-09 | 中国建筑第八工程局有限公司 | Braced system that climbing tower hung in external |
Also Published As
Publication number | Publication date |
---|---|
CN106219419A (en) | 2016-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106219419B (en) | The large-scale swing arm tower crane original position of high-rise building is converted to plug-in construction method by interior climb | |
CN104652807B (en) | Self-circulation construction system and method for internal climbing tower supporting steel beam in hydraulic climbing formwork system | |
CN201826525U (en) | Climbing shuttering system device for buildings | |
CN106437130A (en) | Inner roof external climbing type formwork construction platform for super high-rise building construction | |
CN102661054B (en) | Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method | |
CN103643800B (en) | The erection & lift system of buckling-restrained bracing member and construction method thereof | |
CN106759909B (en) | Bearing structure system and its construction method are hung up under one kind | |
CN106400951A (en) | Synchronous construction method for horizontal and vertical structures of super high-rise building | |
CN105442839A (en) | Erecting method of cantilever structure formwork bent | |
CN114215170B (en) | Lifting method for ultrahigh-altitude giant-suspension multilayer conjoined structure | |
CN101503908B (en) | Construction method for spacing suspension cable structural template support platform | |
CN107720575B (en) | A kind of towing type construction method for hanging of tower crane support system | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN115492399A (en) | Construction method for installing and adjusting hanging steel structure from bottom to top | |
CN106567542A (en) | Super high-rise double tower building steel structure corridor assembling method | |
CN103132702A (en) | Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method | |
CN203547125U (en) | Column type overall steel platform hydraulic creeping formwork | |
CN113062584A (en) | Multipoint elevator shaft construction lifting platform and construction method | |
CN111847272A (en) | Supporting method of tower crane for reconstruction of existing building | |
CN209618736U (en) | Jacking apparatus is climbed in a kind of derrick crane | |
CN117005664A (en) | Electric translation type hanging basket | |
CN215291319U (en) | Multi-point elevator shaft construction lifting platform | |
CN209924407U (en) | Combined working platform for steel structure high-altitude installation | |
CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
CN111591909A (en) | Mast crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |