CN106149731A - Main building basement construction method for supporting with annex - Google Patents

Main building basement construction method for supporting with annex Download PDF

Info

Publication number
CN106149731A
CN106149731A CN201610442856.3A CN201610442856A CN106149731A CN 106149731 A CN106149731 A CN 106149731A CN 201610442856 A CN201610442856 A CN 201610442856A CN 106149731 A CN106149731 A CN 106149731A
Authority
CN
China
Prior art keywords
main building
basement
construction
support
annex
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610442856.3A
Other languages
Chinese (zh)
Other versions
CN106149731B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiangyang Huayixin Construction Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610442856.3A priority Critical patent/CN106149731B/en
Publication of CN106149731A publication Critical patent/CN106149731A/en
Application granted granted Critical
Publication of CN106149731B publication Critical patent/CN106149731B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses the main building basement construction method for supporting of a kind of band annex, it is characterized in that construction procedure includes: (1) construction main building enclosure wall, pre-embedded steel slab waterstop;(2) construction annex enclosure wall and interim enclosure wall;(3) construction high-pressure rotary jet grouting pile;(4) construction main building support column;(5) middle part girder truss and the truss web of main building first support system, the then support of construction annulus are done;Carry out angle brace of constructing again;(6) earth excavation supports to second and arranges position;(7) middle part girder truss and the truss web of main building second support system, the then support of construction annulus are done;Carry out angle brace of constructing again;(8) earth excavation supports to the 3rd road and arranges position;(9) middle part girder truss and the truss web of main building the 3rd road support system, the then support of construction annulus are done;Carry out angle brace of constructing again;(10) earth excavation is to main building basement bottom board, pours basement bottom board concrete.

Description

Main building basement construction method for supporting with annex
Technical field
The present invention relates to a kind of basement construction method for supporting, particularly to the main building basement supporting construction side of band annex Method.
Background technology
Along with the development of urban construction, skyscraper occurs like the mushrooms after rain, for the skyscraper of commercial function, main Building is the most interdependent with podium and builds, and main building can connect with annex basement.When basement construction, excavation area can be very big, On the one hand the tau-effect meeting cut the earth is it is obvious that there will be the bad phenomenon such as the earthwork protuberance when cutting the earth;On the other hand, cut the earth the time Can be the longest, the main building construction period can be the longest.Owing to the main building duration is controlling node, the main building construction period determines whole The delivery time of engineering.Construction period can be the longest traditionally, and construction safety is difficult to obtain guarantee.
Summary of the invention
The present invention is to provide the main building basement construction method for supporting of a kind of band annex, solves problem of the prior art.
To this end, the present invention arranges interim enclosure wall between basement main building and annex, make main building basement and annex ground Lower room forms two independent spaces.Owing to the main building basement construction time is controlling node, after interim enclosure wall completes First construction main building basement, main building basement uses constructs along method, basement bottom board of the most first constructing, then executes from the bottom to top Work, annex basement of constructing again after main building basement roof completes, annex basement uses inverse method to construct, under i.e. first construction ground Ceiling plate, then carry out constructing in order to the construction of basement annex does not disturb main building structure sheaf to construct from top to bottom, basement Synchronize to carry out main building basement construction during annex construction.
Arranging interim enclosure wall between main building and annex, interim enclosure wall width is 700~900mm, and interim enclosure wall is deep Degree is 1.5~2 times of foundation depth, interim enclosure wall concrete strength be C30 or more than, main building enclosure wall does not only has supporting Performance doubles as outer wall of basement, and main building enclosure wall width is 700~900mm, the main building enclosure wall degree of depth be foundation depth 1.8~ 2.5 times, main building enclosure wall concrete strength be C30 or more than.After treating basement construction, patch oil inside main building enclosure wall Felt, does bricking wall inside malthoid, to meet basement antiseepage requirement.Annex enclosure wall width is 700~900mm, and annex is gone along with sb. to guard him The wall degree of depth is 1.8~2.5 times of foundation depth, annex enclosure wall concrete strength be C30 or more than.Main building enclosure wall and skirt Building arranges 2 high-pressure rotary jet grouting piles outside enclosure wall handing-over position, solves the seepage problem of antiseepage weak part.Go along with sb. to guard him at main building Wall, annex enclosure wall and go along with sb. to guard him temporarily wall chase section seam crossing use 2 high-pressure rotary jet grouting piles squeegee as antiseepage, main building enclosure wall turns Angular position and annex enclosure wall rotation angle position are also provided with 2 high-pressure rotary jet grouting piles.Main building enclosure wall, annex enclosure wall and enclose temporarily Revetment crossover sites arranges steel plate water stopper, and steel plate water-stopping tape thickness is 3~5mm, arranges annulus support, circle inside main building enclosure wall Central shoring width is 500~700mm, height be 700~900mm, annulus support concrete strength be C30 or more than.Annulus support with Arranging angle brace between main building enclosure wall, angle brace uses concrete support or steel support.Truss support body is set in the middle part of main building enclosure wall System, truss support system can alleviate the horizontal force suffered by annulus support significantly.Truss support system includes girder truss and truss abdomen Bar.Girder truss width is 400~600mm, height be 500~700mm, girder truss concrete strength be C30 or more than, truss Web member width is 300~500mm, height be 500~700mm, truss web concrete strength be C30 or more than.Girder truss Bottom arranges support column to maintain Stability in Plane, and support column uses steel column, and steel column uses two channel-section steels to be spliced, and steel column is inserted Enter cast-in-situ bored pile.Annex top board indwelling soil outlet, annex soil outlet area is 30~100m2, turned welt is set up in soil outlet corner Beam improves the stress state in corner, turns under turned welt beam, and turned welt depth of beam is 250~300mm, and width is 200mm.Annex is every 50 ~70m arranges a soil outlet, soil outlet is arranged on elevator & stairs and the region that punches of structure design as far as possible.
Depths, the local such as elevator, sump carries out compaction grouting process, and slip casting width is 3m, and slip casting thickness is 5m.
Construction procedure includes:
(1) construction main building enclosure wall, pre-embedded steel slab waterstop;
(2) construction annex enclosure wall and interim enclosure wall;
(3) construction high-pressure rotary jet grouting pile;
In order to improve anti-seepage effect, rotary churning pile rig uses hydraulic power head, and unit head is being led by the elevator machine travel that works Moving on tower, the revolution of unit head is driven through reduction box by fluid power motor, it is achieved revolution and the swing of different angles, utilizes and bores Machine is drilled into soil layer precalculated position the Grouting Pipe with nozzle, makes serosity become high-pressure spray with high pressure equipment and penetrates from nozzle, Lifting limit, rotation limit, limit injection serosity, makes serosity and grogs Forced Mixing, forms induration after grout cures in soil.Rotary churning pile Slip casting form uses and swings injection.The high-pressure water pressure of rotary churning pile is 30MPa, flow 90L/min;Compressed air pressure is 0.6 ~0.8MPa, flow is 6m3/h;Cement mortar pressure is 5MPa, and flow is 80~100L/min.Cement slurry density is 1.60g/ Em, the cement mortar ratio of mud is 0.8;30m with lower portion promote speed be 6~8cm/min, 30m with upper bit promote speed be 8~ 10em/min。
(4) construction main building support column;
(5) middle part girder truss and the truss web of main building first support system, the then support of construction annulus are done;Execute again Work angle brace;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss and the truss web of main building second support system, the then support of construction annulus are done;Execute again Work angle brace;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss and the truss web of main building the 3rd road support system, the then support of construction annulus are done;Execute again Work angle brace;
(10) earth excavation is to main building basement bottom board, pours basement bottom board concrete;
(11) remove girder truss and truss web and annulus during the 3rd road supports to support and angle brace;
(12) the 3rd road support zone basement floorslab concrete is poured;
(13) remove girder truss and truss web and annulus during second supports to support and angle brace;
(14) second support zone basement floorslab concrete is poured;
(15) main building basement roof concrete is poured;
(16) annex concrete roof, indwelling soil outlet are poured;
(17) the excavation annex earthwork is to one layer of basement floor, pours basement floorslab concrete;
Earth excavation is carried out according to " subregion, point title, balance " principle;In making hole, earth excavation level of approximation declines, it is ensured that Support system uniform stressed, prevents the outer unstability of support system plane.
(18) the excavation annex earthwork is to two layers of basement floor, pours basement floorslab concrete;
(19) the excavation annex earthwork is to three layers of basement floor, pours basement floorslab concrete;
(20) the excavation annex earthwork is to three layers of basement bottom board position, pours underplate concrete.
The present invention, by main building and the line production of annex construction, accelerates construction speed, and safe condition obtains again and changes Kind, shortening to save with cost in the duration has obvious effect.
Accompanying drawing explanation
Fig. 1 is the main building basement supporting construction schematic diagram of band annex.
In each accompanying drawing: 1, main building enclosure wall, 2, interim enclosure wall, 3, annulus support, 4, girder truss, 5, truss web, 6, Dagger, 7, high-pressure rotary jet grouting pile, 8, annex enclosure wall, 9, steel plate water stopper, 10, soil outlet, 11, angle brace.
Detailed description of the invention
Certain engineering is 16 layers of main building, is frame cylinder shear wall structure, annex be 3-tier architecture, main building and annex be 3 layers of underground Room, cutting depth is 11.2m, and engineering pile is cast-in-situ bored pile, and the cast-in-situ bored pile degree of depth is 48m.
Arranging interim enclosure wall 2 between the present embodiment main building and annex, interim enclosure wall 2 width is 800mm, goes along with sb. to guard him temporarily Wall 2 degree of depth is the 20m of foundation depth, and interim enclosure wall 2 concrete strength is C30, and main building enclosure wall 1 does not only have supporting performance and holds concurrently Making outer wall of basement, main building enclosure wall 1 width is 800mm, and main building enclosure wall 1 degree of depth is 25m, main building enclosure wall 1 strong concrete Degree is C30.After treating basement construction, paste malthoid inside main building enclosure wall 1, inside malthoid, do bricking wall.Annex enclosure wall 8 Width is 800mm, and annex enclosure wall 8 degree of depth is 25m, and annex enclosure wall 1 concrete strength is C30.Main building enclosure wall 1 and annex Enclosure wall 8 joins and arranges 2 high-pressure rotary jet grouting piles 7 outside position, solves the seepage problem of antiseepage weak part.At main building enclosure wall 1, annex enclosure wall 8 and interim enclosure wall 2 groove section seam crossing use 2 high-pressure rotary jet grouting piles 7 to squeegee as antiseepage, main building enclosure wall 1 rotation angle position and annex enclosure wall 8 rotation angle position are also provided with 2 high-pressure rotary jet grouting piles 7.Main building enclosure wall 1, annex enclosure wall 8 with And enclosure wall 2 crossover sites arranges steel plate water stopper 9 temporarily, steel plate water stopper 9 thickness is 4mm, arranges inside main building enclosure wall 1 Annulus support 3, it is 600mm that annulus supports 3 width, and height is 800mm, and it is C30 that annulus supports 3 concrete strengths.Annulus support 3 is enclosed with main building Arranging angle brace 11 between revetment 1, angle brace 11 uses concrete to support.Arranging truss support system in the middle part of main building enclosure wall 1, truss props up Annulus support horizontal force suffered by 3 can be alleviated significantly in support body system.Truss support system includes girder truss 4 and truss web 5.Truss Beam 4 width is 500mm, and height is 600mm, and girder truss 4 concrete strength is C30, and truss web 5 width is 400mm, and height is 600mm, truss web 5 concrete strength is C30.Girder truss 4 bottom arranges support column 6 to maintain Stability in Plane, support column 6 Using steel column, steel column uses two channel-section steels to be spliced, and steel column inserts cast-in-situ bored pile.Annex top board indwelling soil outlet, annex Soil outlet area is 70m2, soil outlet corner is set up turned welt beam and is improved the stress state in corner, turns over, turned welt depth of beam under turned welt beam For 250mm, width is 200mm.Annex arranges a soil outlet 10 every 60m, soil outlet 10 be arranged on as far as possible elevator & stairs and The region that punches of structure design.Depths, the local such as elevator, sump carries out compaction grouting process, and slip casting width is 3m, slip casting Thickness is 5m.
Construction procedure includes:
(1) construction main building enclosure wall 1, pre-embedded steel slab waterstop 9;
(2) construction annex enclosure wall 8 and interim enclosure wall 2;
(3) construction high-pressure rotary jet grouting pile 7;
In order to improve anti-seepage effect, rotary churning pile rig uses hydraulic power head, and unit head is being led by the elevator machine travel that works Moving on tower, the revolution of unit head is driven through reduction box by fluid power motor, it is achieved revolution and the swing of different angles, utilizes and bores Machine is drilled into soil layer precalculated position the Grouting Pipe with nozzle, makes serosity become high-pressure spray with high pressure equipment and penetrates from nozzle, Lifting limit, rotation limit, limit injection serosity, makes serosity and grogs Forced Mixing, forms induration after grout cures in soil.Rotary churning pile Slip casting form uses and swings injection.The high-pressure water pressure of rotary churning pile is 30MPa, flow 90L/min;Compressed air pressure is 0.7MPa, flow is 6m3/h;Cement mortar pressure is 5MPa, and flow is 90L/min.Cement slurry density is 1.60g/em, cement mortar The ratio of mud is 0.8;30m is with lower portion lifting speed as 7em/min, and 30m promotes speed as 9cm/min with upper bit.
(4) construction main building support column 6;
(5) middle part girder truss 4 and the truss web 5 of main building first support system, then construction annulus support 3 are done;Enter again Row construction angle brace 11;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss 4 and the truss web 5 of main building second support system, then construction annulus support 3 are done;Enter again Row construction angle brace 11;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss 4 and the truss web 5 of main building the 3rd road support system, then construction annulus support 3 are done;Enter again Row construction angle brace 11;
(10) earth excavation is to main building basement bottom board, pours basement bottom board concrete;
(11) girder truss 4 and truss web 5 and annulus support 3 and angle brace 11 during the 3rd road supports are removed;
(12) the 3rd road support zone basement floorslab concrete is poured;
(13) girder truss 4 and truss web 5 and annulus support 3 and angle brace 11 during second supports are removed;
(14) second support zone basement floorslab concrete is poured;
(15) main building basement roof concrete is poured;
(16) annex concrete roof, indwelling soil outlet 10 are poured;
(17) the excavation annex earthwork is to one layer of basement floor, pours basement floorslab concrete;
Earth excavation is carried out according to " subregion, point title, balance " principle;In making hole, earth excavation level of approximation declines, it is ensured that Support system uniform stressed, prevents the outer unstability of support system plane.
(18) the excavation annex earthwork is to two layers of basement floor, pours basement floorslab concrete;
(19) the excavation annex earthwork is to three layers of basement floor, pours basement floorslab concrete;
(20) the excavation annex earthwork is to three layers of basement bottom board position, pours underplate concrete.
Through Site Detection this basement Stability Analysis of Structures in work progress, main building supporting displacement is less than 13mm, and annex props up Protecting displacement and be less than 10mm, support beam structure is stable, and phenomenon without exception occurs.

Claims (4)

1. a main building basement construction method for supporting for band annex, is characterized in that construction procedure includes:
(1) construction main building enclosure wall, pre-embedded steel slab waterstop;
(2) construction annex enclosure wall and interim enclosure wall;
(3) construction high-pressure rotary jet grouting pile;
(4) construction main building support column;
(5) middle part girder truss and the truss web of main building first support system, the then support of construction annulus are done;Carry out angle of constructing again Support;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss and the truss web of main building second support system, the then support of construction annulus are done;Carry out angle of constructing again Support;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss and the truss web of main building the 3rd road support system, the then support of construction annulus are done;Carry out angle of constructing again Support;
(10) earth excavation is to main building basement bottom board, pours basement bottom board concrete;
(11) remove girder truss and truss web and annulus during the 3rd road supports to support and angle brace;
(12) the 3rd road support zone basement floorslab concrete is poured;
(13) remove girder truss and truss web and annulus during second supports to support and angle brace;
(14) second support zone basement floorslab concrete is poured;
(15) main building basement roof concrete is poured;
(16) annex concrete roof, indwelling soil outlet are poured;
(17) the excavation annex earthwork is to one layer of basement floor, pours basement floorslab concrete;
Earth excavation is carried out according to " subregion, point title, balance " principle;In making hole, earth excavation level of approximation declines, it is ensured that support System uniform stressed, prevents the outer unstability of support system plane;
(18) the excavation annex earthwork is to two layers of basement floor, pours basement floorslab concrete;
(19) the excavation annex earthwork is to three layers of basement floor, pours basement floorslab concrete;
(20) the excavation annex earthwork is to three layers of basement bottom board position, pours underplate concrete.
The main building basement construction method for supporting of band annex the most according to claim 1, is characterized in that rotary churning pile rig is adopted With hydraulic power head, unit head is moved on king-tower by the elevator machine travel that works, the revolution of unit head by fluid power motor through subtracting Speed case drives, it is achieved revolution and the swing of different angles, utilizes rig that the Grouting Pipe with nozzle is drilled into soil layer precalculated position, Make serosity become high-pressure spray with high pressure equipment to penetrate from nozzle, lifting limit, rotation limit, limit injection serosity, make serosity strong with grogs System mixing, forms induration in soil after grout cures;Rotary churning pile slip casting form uses and swings injection.
The main building basement construction method for supporting of band annex the most according to claim 1, is characterized in that the high pressure of rotary churning pile Water pressure is 30MPa, flow 90L/min;Compressed air pressure is 0.6~0.8MPa, and flow is 6m3/h;Cement mortar pressure is 5MPa, flow is 80~100L/min.Cement slurry density is 1.60g/cm, and the cement mortar ratio of mud is 0.8;30m carries with lower portion Lifting speed is 6~8cm/min, and it is 8~10cm/min that 30m promotes speed with upper bit.
The main building basement construction method for supporting of band annex the most according to claim 1, is characterized in that treating basement construction After, paste malthoid inside main building enclosure wall, do bricking wall inside malthoid, to meet basement antiseepage requirement.
CN201610442856.3A 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex Active CN106149731B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610442856.3A CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610442856.3A CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex
CN201510309657.0A CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201510309657.0A Division CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex

Publications (2)

Publication Number Publication Date
CN106149731A true CN106149731A (en) 2016-11-23
CN106149731B CN106149731B (en) 2018-08-10

Family

ID=53946424

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510309657.0A Active CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex
CN201610442856.3A Active CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510309657.0A Active CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex

Country Status (1)

Country Link
CN (2) CN104878763B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804085B (en) * 2016-04-19 2017-08-25 江苏东合南岩土科技股份有限公司 Multiple-unit well shaft type underground three-dimensional garage subregion construction method
CN111042099B (en) * 2019-12-19 2024-09-13 中国地质大学(武汉) Water collecting well with replaceable water filtering structure
CN111270684B (en) * 2020-03-24 2024-09-03 中铁第四勘察设计院集团有限公司 Disassembly-free support rod piece, foundation pit support system and subway station construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060059812A1 (en) * 2004-08-30 2006-03-23 Simmons Robert J Column base to podium slab anchoring
CN101666095A (en) * 2009-09-11 2010-03-10 朱奎 Irregular foundation pit support and construction method
CN101718094A (en) * 2009-11-10 2010-06-02 朱奎 Construction method for retaining and protecting foundation pit of building with basemen

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006026384A2 (en) * 2004-08-30 2006-03-09 Simmons Robert J Column base to podium slab anchoring
CN100582383C (en) * 2005-12-05 2010-01-20 黄威力 Construction method of setting site for pile base and structure in foundation pit
CN102383433A (en) * 2011-08-22 2012-03-21 同济大学建筑设计研究院(集团)有限公司 Design method for large deep foundation pit of super high-rise building
CN102505695B (en) * 2011-10-09 2014-12-03 浙江荣邦房地产开发有限公司 Construction method for deep foundation pit of three-dimensional garage
CN103306304A (en) * 2013-06-19 2013-09-18 泰兴市第一建筑安装工程有限公司 Basic structure of construction elevator

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060059812A1 (en) * 2004-08-30 2006-03-23 Simmons Robert J Column base to podium slab anchoring
CN101666095A (en) * 2009-09-11 2010-03-10 朱奎 Irregular foundation pit support and construction method
CN101718094A (en) * 2009-11-10 2010-06-02 朱奎 Construction method for retaining and protecting foundation pit of building with basemen

Also Published As

Publication number Publication date
CN106149731B (en) 2018-08-10
CN104878763A (en) 2015-09-02
CN104878763B (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN105951848B (en) Ultra-deep foundation pit supports Non-intermittent combined type transformational structure and construction method
CN205742213U (en) Foundation pit supporting construction
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN209040150U (en) A kind of rigid frame formula peg board retaining wall
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN114575355B (en) Soil protection construction method
CN106592605A (en) Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN104878763B (en) Main building basement supporting construction with annex
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN107489106A (en) A kind of rocky bed subaqueous bearing platform construction method
CN104695446B (en) Basement construction method for supporting
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN104153347B (en) Preparing structure and the construction method thereof of underground continuous wall width breach
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN104963348A (en) Soft soil area tower crane foundation construction supporting structure and construction method thereof
CN210216452U (en) Old excavation supporting system reinforced structure
CN208763446U (en) Increase the supporting construction for building the underground space under a kind of existing building group
CN207846454U (en) Overhanging type unilateral side wall mixed reinforcement and replacing structure
CN216339582U (en) Combined inclined support for foundation pit support
CN216586567U (en) Pit-in-pit miniature pile supporting structure
CN206667263U (en) A kind of foundation pit supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201201

Address after: Room 012, 17 / F, building 4, Hongxing international area a, Dengcheng Avenue, high tech Development Zone, Xiangyang City, Hubei Province

Patentee after: Hubei Jianxi Technology Co., Ltd

Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39

Patentee before: Zhu Kui

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201224

Address after: 1709, 17 / F, A4 office building, Hongxing Macalline, fanwei Road, Xiangyang high tech Zone, Hubei Province, 441000

Patentee after: Xiangyang HUAYIXIN Construction Co.,Ltd.

Address before: 441004 room 012, 17 / F, building 4, Hongxing International Zone A, Dengcheng Avenue, high tech Development Zone, Xiangyang City, Hubei Province

Patentee before: Hubei Jianxi Technology Co., Ltd

TR01 Transfer of patent right