CN102383433A - Design method for large deep foundation pit of super high-rise building - Google Patents
Design method for large deep foundation pit of super high-rise building Download PDFInfo
- Publication number
- CN102383433A CN102383433A CN2011102419995A CN201110241999A CN102383433A CN 102383433 A CN102383433 A CN 102383433A CN 2011102419995 A CN2011102419995 A CN 2011102419995A CN 201110241999 A CN201110241999 A CN 201110241999A CN 102383433 A CN102383433 A CN 102383433A
- Authority
- CN
- China
- Prior art keywords
- district
- building
- construction
- foundation pit
- podium
- Prior art date
Links
- 238000010276 construction Methods 0.000 claims abstract description 86
- 241001310793 Podium Species 0.000 claims abstract description 73
- 230000002411 adverse Effects 0.000 claims description 21
- 239000010410 layers Substances 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 description 4
- 239000000428 dust Substances 0.000 description 3
- 238000005516 engineering processes Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000006011 modification reactions Methods 0.000 description 3
- 230000001276 controlling effects Effects 0.000 description 2
- 238000004880 explosion Methods 0.000 description 2
- 238000000034 methods Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000000875 corresponding Effects 0.000 description 1
- 230000003111 delayed Effects 0.000 description 1
- 230000002035 prolonged Effects 0.000 description 1
- 238000004062 sedimentation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Abstract
Description
Technical field
The present invention relates to the underground construction design field, relate in particular to a kind of method for designing of super highrise building deep big foundation pit.
Background technology
Along with the continuous development of urban construction, various types of underground constructions, deep-foundation pit engineering are more and more, and the construction method of deep foundation ditch of efficient, economy, energy-saving and environmental protection seems particularly important.At present, traditional construction method of deep foundation ditch is open type construction, and its method is to go along with sb. to guard him the back vertical cut or excavate with putting the slope greatly with supporting and protection structure.Dig to design elevation after-pouring steel bar concrete base plate, the basement structure of from bottom to top successively constructing is again treated to carry out the superstructure construction again after underground structure is accomplished, and this job practices is along practice construction.Opposite with suitable practice construction is contrary sequence method (Top-down method) construction; After space enclosing structure and engineering piles and stand column pile completion; Directly the construction underground structure top board; And then successively carry out the shoveling of each layer of below ground successively downwards, and successively carry out the construction of each layer basement floor downwards, all accomplish the excavation that just carries out lower floor's earthwork after this floor plate construction at every turn.
For the work items that comprises high building and multilayer podium in the super highrise building, high building district foundation ditch and podium district foundation ditch carry out along practice construction usually simultaneously, yet because high building district floor is a lot; The shared duration is long partially, accomplishes in the podium district when binding, and the high building district accomplishes also poor quite a lot of a period of time from construction; High building district and podium district are accomplished around; Prolonged the time of completion of whole construction project, in addition, high building district foundation ditch and podium district foundation ditch carry out causing the construction plant not enough along practice construction simultaneously; And the sedimentation relatively more easily of foundation ditch periphery, environment pollutions such as construction noise and airborne dust are serious; In addition, also have the part engineering to adopt and earlier the podium district carried out reverse construction, however the high building district duration that construction consumes in later stage delayed whole time of completion, make this foundation ditch design scheme also have drawback.
Summary of the invention
Technical problem to be solved by this invention has provided a kind of method for designing of super highrise building deep big foundation pit, how to plan as a whole to design the foundation ditch construction of high building district and the foundation ditch construction of podium district makes whole construction period be in best problem to solve.
In order to solve the problems of the technologies described above, technical scheme of the present invention is: the super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch; Said high building district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction; Said high building district foundation ditch is carried out suitable the construction, and said podium district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method.
Further, when said podium district foundation ditch carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity as said podium district foundation ditch.
Further, when said podium district foundation ditch was carried out adverse construction method, said high building structure was carried out the above construction in ground.
Further, return to build in the high building structure and said podium district foundation ditch is carried out adverse construction method after accomplishing basement roof, said each floor plate of high building structure basement is docked with each floor plate of basement in said podium district.。
Further, the superstructure number of plies in said high building district is more than or equal to 50 layers.
Further, the superstructure number of plies in said podium district is less than or equal to 8 layers.
The method for designing of super highrise building deep big foundation pit provided by the invention and since the duration that the high building district builds than podium district build long in time limit, therefore; Earlier high building district foundation ditch is carried out along constructing; Can guarantee that high building binds as early as possible, plan as a whole the high building district foundation ditch of design and build and the construction of podium district foundation ditch, make whole construction period be in a best time value; Simultaneously; When high building district foundation ditch is carried out operation, can utilize the podium district that does not begin as yet to construct as the construction plant, the problem that the construction plant that possibly run into when having solved high building district excavation of foundation pit is not enough; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method, to reduce high building district and the interval of podium district deadline; Thereby make the time of accomplishing the duration plan as a whole to reach best, in addition, the podium district carries out adverse construction method; The top board in podium district that can utilize completion is as the construction plant in high building district and podium district; Simultaneously, podium district foundation ditch adverse construction method can reduce construction noise, airborne dust etc., to avoid that explosion takes place when making in the construction supporting removal; Reduced the influence of engineering construction, fully implemented the requirement of green building technology surrounding enviroment.
Further, when said podium district foundation ditch carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity, help controlling the safety and stability of foundation pit enclosure structure structure as said podium district foundation ditch, thus the better protect surrounding enviroment.
Further, return to build in the high building structure and said podium district foundation ditch is carried out adverse construction method after accomplishing basement roof, said each floor plate of high building structure basement is docked with each floor plate of basement in said podium district., so that the structure level force transfer system is continuous between the zones of different, to guarantee the stable of whole building structure.
Description of drawings
Fig. 1 is the flow chart of steps of the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention;
Fig. 2 A~2D is a corresponding cross-sectional view in the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the method for designing of the super highrise building deep big foundation pit of the present invention's proposition is done further explain.According to following explanation and claims, advantage of the present invention and characteristic will be clearer.What need explanation is, accompanying drawing all adopts the form of simplifying very much and all uses non-ratio accurately, only is used for conveniently, the purpose of the aid illustration embodiment of the invention lucidly.
Core concept of the present invention is, a kind of method for designing of super highrise building deep big foundation pit is provided and since the duration that the high building district builds than podium district build long in time limit; Therefore, earlier high building district foundation ditch is carried out can guaranteeing that along constructing high building binds as early as possible; Planning as a whole the high building district foundation ditch of design builds and the construction of podium district foundation ditch; Make whole construction period be in a best time value, simultaneously, when high building district foundation ditch is carried out operation; Can utilize the podium district that does not begin as yet to construct as the construction plant, the problem that the construction plant that possibly run into when having solved high building district excavation of foundation pit is not enough; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method, to reduce high building district and the interval of podium district deadline; Thereby make the time of accomplishing the duration plan as a whole to reach best, in addition, the podium district carries out adverse construction method; The top board in podium district that can utilize completion is as the construction plant in high building district and podium district; Simultaneously, podium district foundation ditch adverse construction method can reduce construction noise, airborne dust etc., to avoid that explosion takes place when making in the construction supporting removal; Reduced the influence of engineering construction, fully implemented the requirement of green building technology surrounding enviroment.
Fig. 1 is the flow chart of steps of the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention.With reference to Fig. 1, the embodiment of the invention provides a kind of method for designing of super highrise building deep big foundation pit, comprises the steps:
S11, the super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch;
S12, said high building district foundation ditch is carried out the construction of pile foundation and foundation pit enclosure structure;
S13, said high building district foundation ditch is carried out along constructing, and said podium district foundation ditch is carried out pile foundation and foundation pit enclosure structure is constructed;
S14, treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method.
To combine generalized section being described in more detail below to the method for designing of the super highrise building deep big foundation pit of the embodiment of the invention.
Shown in Fig. 2 A; And integrating step S12; After carrying out step S11, said high building district foundation ditch 21 is carried out pile foundation and foundation pit enclosure structure construction, make and in high building district foundation ditch 21, form high building district's pile foundation 23 and high building district foundation pit enclosure structure 24; At this moment, podium district foundation ditch 22 is constructed.
Shown in Fig. 2 B, 2C; And integrating step S13; Said high building district foundation ditch 21 is carried out along constructing; The inwall of foundation ditch 21 is provided with a plurality of supports 25 along the high building district in along the process of doing construction, and carry out pile foundation and foundation pit enclosure structure construction to said podium district foundation ditch 22 this moment, makes and in podium district foundation ditch, forms podium district's pile foundation 26 and podium district foundation pit enclosure structure 27.Said high building district foundation ditch 21 carries out building construction along returning as basement structure, forms high building district each floor plate 28 of basement.
Shown in Fig. 2 D, and integrating step S14, treat the high building structure return build accomplish basement roof 28 ' after; Said podium district foundation ditch 22 is carried out adverse construction method; And, said high building district each floor plate 28 of basement dock with each floor plate 29 of basement in said podium district successively in the process that subinverse is done, high building district high building structure carries out constructing more than the ground in the time of podium district foundation ditch 22 adverse construction methods; Arrow is that high building district high building structure is carried out the direction of constructing more than the ground shown in Fig. 2 d; Also carry out the above construction in ground after foundation ditch 22 operations of podium district are accomplished, when said podium district foundation ditch 22 carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity as said podium district foundation ditch 22; Help controlling the safety and stability of foundation pit enclosure structure structure, thus the better protect surrounding enviroment.
Particularly; Return to build in the high building structure and accomplish basement roof 28 ' back said podium district foundation ditch 22 is carried out adverse construction method; Said basement roof 28 ' is docked with the top board 29 ' in said podium district; So that the structure level force transfer system between the zones of different is continuous, to guarantee the stable of whole building structure.
Further, the superstructure number of plies in said high building district is more than or equal to 50 layers, and the superstructure number of plies in said podium district is less than or equal to 8 layers.In the present embodiment; The building height in said high building district is 600 meters, and the building height in podium district is 24 meters, according to the building storey in high building district and podium district; And, plan as a whole to design foundation ditch construction of high building district and the foundation ditch construction of podium district according to the foundation depth and the area of the excavation of needs separately.
The embodiment of the invention is planned as a whole the high building district foundation ditch 21 of design and is built and 22 construction of podium district foundation ditch, and said high building district 21 on-stream times of foundation ditch and high building top out time of completion in advance, thereby shorten total duration of engineering.Make whole construction period be in a best time value.
Obviously, those skilled in the art can carry out various changes and modification to invention and not break away from the spirit and scope of the present invention.Like this, belong within the scope of claim of the present invention and equivalent technologies thereof if of the present invention these are revised with modification, then the present invention also is intended to comprise these changes and modification interior.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102419995A CN102383433A (en) | 2011-08-22 | 2011-08-22 | Design method for large deep foundation pit of super high-rise building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102419995A CN102383433A (en) | 2011-08-22 | 2011-08-22 | Design method for large deep foundation pit of super high-rise building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102383433A true CN102383433A (en) | 2012-03-21 |
Family
ID=45823234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102419995A CN102383433A (en) | 2011-08-22 | 2011-08-22 | Design method for large deep foundation pit of super high-rise building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102383433A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102839673A (en) * | 2012-09-19 | 2012-12-26 | 白福波 | Design method of side wall depth of foundation pit |
CN103195068A (en) * | 2013-04-03 | 2013-07-10 | 哈尔滨工业大学 | Method for determining foundation pit excavation depths through rock and soil constitutive broken lines |
CN103711128A (en) * | 2013-12-31 | 2014-04-09 | 上海建工七建集团有限公司 | Construction method for shallow foundation structural beam slab |
CN104514228A (en) * | 2013-09-29 | 2015-04-15 | 浙江宝业建设集团有限公司 | Large-chassis multi-tower building construction method and structure |
CN104594358A (en) * | 2015-01-07 | 2015-05-06 | 江苏中南建筑产业集团有限责任公司 | Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit |
CN105113514A (en) * | 2015-08-31 | 2015-12-02 | 广东省建筑设计研究院 | Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method |
CN104878763B (en) * | 2015-05-29 | 2016-08-24 | 朱奎 | Main building basement supporting construction with annex |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1804255A (en) * | 2005-12-16 | 2006-07-19 | 张国梁 | Reversed construction method for building |
KR100625115B1 (en) * | 2004-05-29 | 2006-09-20 | (주)새길이엔시 | downward reinforced-concrete underground structure using temporary assistant columns |
CN1982546A (en) * | 2005-12-12 | 2007-06-20 | 上海市第七建筑有限公司 | Direct local skirt border reversing construction for central island |
JP2009280957A (en) * | 2008-05-19 | 2009-12-03 | Shimizu Corp | Prestressed foundation beam and introduction method of prestress into foundation beam |
CN101736757A (en) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | Two-way synchronous construction method of tube structure of high-rise building |
-
2011
- 2011-08-22 CN CN2011102419995A patent/CN102383433A/en not_active Application Discontinuation
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100625115B1 (en) * | 2004-05-29 | 2006-09-20 | (주)새길이엔시 | downward reinforced-concrete underground structure using temporary assistant columns |
CN1982546A (en) * | 2005-12-12 | 2007-06-20 | 上海市第七建筑有限公司 | Direct local skirt border reversing construction for central island |
CN1804255A (en) * | 2005-12-16 | 2006-07-19 | 张国梁 | Reversed construction method for building |
JP2009280957A (en) * | 2008-05-19 | 2009-12-03 | Shimizu Corp | Prestressed foundation beam and introduction method of prestress into foundation beam |
CN101736757A (en) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | Two-way synchronous construction method of tube structure of high-rise building |
Non-Patent Citations (1)
Title |
---|
戴斌: "基坑工程顺逆结合设计方法", 《地下空间与工程学报》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102839673A (en) * | 2012-09-19 | 2012-12-26 | 白福波 | Design method of side wall depth of foundation pit |
CN102839673B (en) * | 2012-09-19 | 2014-10-15 | 白福波 | Design method of side wall depth of foundation pit |
CN103195068A (en) * | 2013-04-03 | 2013-07-10 | 哈尔滨工业大学 | Method for determining foundation pit excavation depths through rock and soil constitutive broken lines |
CN103195068B (en) * | 2013-04-03 | 2015-05-13 | 哈尔滨工业大学 | Method for determining foundation pit excavation depths through rock and soil constitutive broken lines |
CN104514228A (en) * | 2013-09-29 | 2015-04-15 | 浙江宝业建设集团有限公司 | Large-chassis multi-tower building construction method and structure |
CN103711128A (en) * | 2013-12-31 | 2014-04-09 | 上海建工七建集团有限公司 | Construction method for shallow foundation structural beam slab |
CN104594358A (en) * | 2015-01-07 | 2015-05-06 | 江苏中南建筑产业集团有限责任公司 | Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit |
CN104594358B (en) * | 2015-01-07 | 2017-01-18 | 江苏中南建筑产业集团有限责任公司 | Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit |
CN104878763B (en) * | 2015-05-29 | 2016-08-24 | 朱奎 | Main building basement supporting construction with annex |
CN105113514A (en) * | 2015-08-31 | 2015-12-02 | 广东省建筑设计研究院 | Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method |
CN105113514B (en) * | 2015-08-31 | 2017-01-04 | 广东省建筑设计研究院 | Using diaphram wall as the foundation pit system of vertical cantilever fulcrum and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100591862C (en) | Pit construction method adopting prefabricated support | |
CN105089061B (en) | Ultra-deep foundation pit supporting method | |
CN102127974B (en) | Design and construction method of additional cellar under existing building | |
CN102535474B (en) | A kind of construction method of deep-foundation pit excavation | |
CN101117805A (en) | Underground engineering one-pile multi-use semi reverse construction method | |
CN103195085B (en) | Downward story-adding basement and construction method thereof | |
CN101691751B (en) | Construction method for making ultra-long artificial excavating pile penetrate cave and ultra-long pile penetrating cave | |
CN1948633A (en) | Tray type excarvating contrary construction method | |
CN102900090A (en) | Non-inclined dry-operation open caisson capable of preventing water burst and land subsidence and construction method thereof | |
CN202194244U (en) | Positioning support for embedding of ultra-high steel-work pedestals | |
CN101914925A (en) | Basement by using optimized composite prefabricated arch wall as external wall | |
CN104879144A (en) | Underground excavation construction method for building underground space by array jacking pipes in soft soil area | |
RU2414563C1 (en) | Method to erect multistory subsurface structure | |
CN101509263A (en) | Digging method foundation pit structure of steel cover and plate cover, and construction method | |
KR101859367B1 (en) | Method for constructing vertical structure in vertical tunnel using top down method | |
CN101408025B (en) | Pit construction method by using major structure as bearing point | |
CN101672041A (en) | Top-down construction method of large underground structure outer wall | |
CN104563128B (en) | The asymmetric deep big foundation pit in soft clay area synchronizes support system and the implementation of excavation | |
CN103290849B (en) | Pit-in-pit supporting structure of half topdown construction method and construction method thereof | |
CN102653945B (en) | Foundation reinforcing and replacing structure and construction method thereof | |
CN103469733B (en) | A kind of from falling molding box joist steel Guan Beilei door opening support and bearing method thereof | |
CN105298507A (en) | Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion | |
CN102383443A (en) | Connection structures between foundation pit support piles and outer walls of basement and construction method | |
CN103775110A (en) | Underground excavation construction method for multilayer underground space of soft soil area | |
CN1982546A (en) | Direct local skirt border reversing construction for central island |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120321 |