CN105113514A - Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method - Google Patents

Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method Download PDF

Info

Publication number
CN105113514A
CN105113514A CN201510546683.5A CN201510546683A CN105113514A CN 105113514 A CN105113514 A CN 105113514A CN 201510546683 A CN201510546683 A CN 201510546683A CN 105113514 A CN105113514 A CN 105113514A
Authority
CN
China
Prior art keywords
foundation ditch
basement
regions
construction
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510546683.5A
Other languages
Chinese (zh)
Other versions
CN105113514B (en
Inventor
陈星�
黄伟江
林扑强
朱爱国
王仕琪
郭铁
汤刚毅
陈铸申
杨代恒
张小良
龙秀海
彭文蔚
区信明
余银银
谭堂州
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architectural Design and Research Institute of Guangdong Province
Original Assignee
Architectural Design and Research Institute of Guangdong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architectural Design and Research Institute of Guangdong Province filed Critical Architectural Design and Research Institute of Guangdong Province
Priority to CN201510546683.5A priority Critical patent/CN105113514B/en
Publication of CN105113514A publication Critical patent/CN105113514A/en
Application granted granted Critical
Publication of CN105113514B publication Critical patent/CN105113514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a foundation pit enclosure system using an underground diaphragm wall as a vertical cantilever supporting point and a construction method. The foundation pit enclosure system comprises a basement, wherein the basement is mainly formed by correspondingly connecting basements located in the peripheral region of a foundation pit and basements located in residual regions of the foundation pit through respective floor slabs. Each basement located in the peripheral region of the foundation pit comprises the underground diaphragm wall, lateral shear resisting walls and floor slabs, the underground diaphragm wall is arranged along the circumference of the inner wall of the foundation pit and serves as the peripheral edge of the peripheral region of the foundation pit, the inner edge of the peripheral region of the foundation pit serves as a boundary for the central region of the foundation pit and the peripheral region of the foundation pit, the lateral shear resisting walls are distributed in the peripheral region of the foundation pit, and the floor slabs are arranged on the lateral shear resisting walls and the underground diaphragm wall in a layered mode. The lateral shear resisting walls serve as supporting structures at an early stage and are also the constituent parts of a main body structure, so that the problem that temporary supports are needed to be erected in construction and then are needed to be removed in the prior art is solved, construction difficulty is simplified, a construction period is shortened, and construction cost is reduced.

Description

Using diaphragm wall as the foundation pit system of vertical cantilever fulcrum and construction method
Technical field
The present invention relates to basement top-down method and the Base hole supporting technology on the high-rise super large chassis of multitower, in particular to a kind of foundation pit system using diaphragm wall as vertical cantilever fulcrum, this foundation pit system can be used as super-giant foundation pit retaining design, relates to the construction method of this foundation pit system simultaneously.
Background technology
Foundation pit system ensures to face down from ground the general name of soil-baffling structure needed for the safety and stability of the underground space during Underground Construction that excavation formed and the measure such as groundwater control, environmental protection.Base pit engineering mainly comprises foundation pit system design and construction and soil excavation, and be a comprehensive very strong system engineering, it not only needs to use geotechnical engineering knowledge, also will use Structural Engineering knowledge.It relates to all construction programs such as prospecting in construction project, design, construction, monitoring and detection.
When engineering geology and hydrogeological conditions severe (as deep in soft layer, groundwater table is high), periphery place narrow space and in the strict base pit engineering of surrounding enviroment deformation requirements, foundation pit system generally takes diaphragm wall as main flow way.Its advantage is: (1) can make full use of the space within the scope of building line, and the rigidity of diaphragm wall is conducive to controlling foundation pit deformation; (2) diaphragm wall has vertical bearing capacity and antiseepage function, can be used as outer wall of basement, become a part for underground structure, also can be used for reverse construction, realizes on the ground and underground synchronous construction, thus the reduction of erection time; (3) antiseepage water isolating is good, and the excavation of foundation pit degree of depth is very large, and need block the aquifer of deep layer, when adopting other water-stop curtains to be difficult to meet the demands, adopts diaphragm wall then can meet the demands as water-retaining structure.
But, adopt the way of diaphragm wall can produce following problem when processing ultra-large type deep foundation ditch:
(1) due to ultra-large type deep foundation ditch very dark (the usual degree of depth is for being greater than 20 meters), need Pitch-based sphere support system, if foundation ditch is larger simultaneously, horizontal struts system needs to add interim vertical supporting (as stand column pile), this can cause stand column pile more, and more stand column pile can produce with major structure of construction and conflicts, cause constructional difficulties, so that claim for eot.(2) added vertical supporting and horizontal support make construction costs greatly promote, and during the excavation pit earthwork, foundation ditch is unearthed difficult.
Contrary sequence method is a kind of Underground Construction method, generally first along building basement external wall construction diaphragm wall or other the interim enclosure walls of surrounding's construction along foundation ditch, build or lay intermediate sup-poning pile and post at the relevant positions of interior of building simultaneously, as the vertical supporting bearing superstructure deadweight and working load before construction period to base plate back cover, then the beam and slab structure of ground one deck is constructed as the horizontal support of diaphragm wall or other enclosure walls, subsequently successively earth excavation and build each layer underground structure until base plate back cover downwards.Meanwhile, because the floor structure of ground one deck completes, for the construction of superstructure creates condition, therefore also upwards successively can carry out the construction of superstructure, upper and lower simultaneously the carrying out in ground like this is constructed until engineering terminates simultaneously.
Reverse construction has the safety of raising underground construction, reduces the wasting of resources, shortens total time of construction, affects the advantages such as little to surrounding enviroment, but its defect is: (1) construct from top to bottom, construction precision requires high, and technical difficulty is large, and node processing is complicated; (2) the systematicness of whole foundation ditch system is strong, needs design department and construction department to closely cooperate, constructs in strict accordance with design drawing, increases to coordinate dynamics between design department with construction department; (3) because shoveling carries out under top seal state, be also distributed with middlebearing column and the precipitation well-point pipe of some, difficulty of therefore cutting the earth in foundation ditch, the ground works duration is longer than along way, and whole construction costs is high; (4) Support Position is by the restriction of basement floor height, if the basement high compared with building, because basement area is comparatively large, therefore needs section and the arrangement of reinforcement separately establishing interim horizontal support or strengthen enclosure wall; (5) be temporary support as the bearing pile of vertical supporting and post, need when main structure construction to remove, increase difficulty of construction, improve construction cost.
Suitable way is successively dug when pit earthwork excavates to basement bottom board bottom surface absolute altitude, more upwards successively constructed by base plate.If foundation depth is darker and larger, need in the middle part of foundation ditch, arrange the cross binding such as bearing pile and crossbeam system, these support systems, as temporary support, will successively be removed in along the process done.
In sum, adopting respectively and respectively have pluses and minuses along way and contrary sequence method when constructing ultra-large type deep foundation ditch system, how to combine the two to play its sharpest edges, maximize favourable factors and minimize unfavourable ones, is current industry technical barrier urgently to be resolved hurrily.
Summary of the invention
First object of the present invention is to provide a kind of and simplifies difficulty of construction, shortens the ground works duration, without the need to setting up temporary support, significantly reducing the foundation pit system using diaphragm wall as vertical cantilever fulcrum of construction cost.
Second object of the present invention is to provide a kind of above-mentioned construction method using diaphragm wall as the foundation pit system of vertical cantilever fulcrum, adopt periphery inverse to do, in be in a good mood the constructure scheme doing to combine, have both contrary sequence method and the advantage along way.
First object of the present invention realizes by the following technical solutions: a kind of foundation pit system using diaphragm wall as vertical cantilever fulcrum, comprise at least one deck basement, it is characterized in that: described basement is formed by connecting by respective floor correspondence with the basement in all the other regions being positioned at foundation ditch primarily of the basement of the perimeter zone being positioned at foundation ditch, wherein, the basement being positioned at the perimeter zone of foundation ditch adopts reverse construction, and the basement being positioned at all the other regions of foundation ditch adopts along way construction, the basement being positioned at the perimeter zone of foundation ditch comprises diaphragm wall, anti-side shear wall and floor, described diaphragm wall is arranged along the inwall circumference of foundation ditch, described diaphragm wall is the outer rim of the perimeter zone of foundation ditch, the inner edge of the perimeter zone of foundation ditch is then the line of demarcation of the central area of foundation ditch and the perimeter zone of foundation ditch, described anti-side shear wall is distributed in the perimeter zone of foundation ditch, described floor layering is located on anti-side shear wall and diaphragm wall.
The present invention adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear in the perimeter zone of foundation ditch, each floor plate is made to become the horizontal support of diaphragm wall, simultaneously, anti-side shear wall is multidirectional stressed structure, both act as the side direction fulcrum that foundation ditch periphery is gone along with sb. to guard him, assume responsibility for again the vertical force of superstructure.Compared with the present invention constructs with existing employing contrary sequence method or along way, because anti-side shear wall can be used as braced structures in the early stage, and be again the ingredient of agent structure, so, overcome prior art to execute man-hour requirement and build the problem that temporary support then removes again, not only enormously simplify difficulty of construction, shorten the construction period, and because eliminate temporary support, considerably reduce construction cost.
Anti-side shear wall of the present invention is distributed in the local of the perimeter zone of foundation ditch, and the local of the perimeter zone of described foundation ditch is called the periphery regional area of foundation ditch, and namely all the other regions of described foundation ditch are the central area of foundation ditch and all the other regions of periphery of foundation ditch; Or described anti-side shear wall is according to the circle distribution of the perimeter zone of foundation ditch, namely all the other regions of described foundation ditch are the central areas of foundation ditch.
The periphery regional area of foundation ditch of the present invention adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear, can be unearthed from all the other regions of foundation ditch, and all the other regions can be used as back-pressure soil section lateral force resisting, need not establish temporary support again; Or the perimeter zone circumference along foundation ditch adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear, can be unearthed, all can significantly shorten the ground works duration from central area.
As a kind of preferred embodiment of the present invention, described anti-side shear wall near the perimeter zone of foundation ditch inner edge and all perpendicular to the metope of diaphragm wall corresponding thereto diametrically.The side direction soil power that diaphragm wall is subject to, perpendicular to the metope of diaphragm wall, farthest can be born in the long limit of anti-side shear wall, safer.
As a modification of the present invention, the cross section of described anti-side shear wall successively reduces to the first floor of major structure of construction from the backplane level of basement, and the anti-side shear wall being positioned at more than the major structure of construction first floor is all converted into post.Its principle is: the anti-side shear wall more than major structure of construction first floor (foundation ditch horizontal plane) only bears vertical force, and no longer serves as the side direction fulcrum that foundation ditch periphery goes along with sb. to guard him, and therefore its length is the shortest; And at the backplane level of basement, the side direction soil power that foundation pit side-wall (diaphragm wall) is subject to is maximum, the length of anti-side shear wall is also the longest.The anti-side shear wall more than major structure of construction first floor is post, not only economical, and the space of the first floor can be made larger.
As a further improvement on the present invention, described anti-side shear wall stretches in the base plate cushion cap of basement downwards, described base plate cushion cap is collar tie beam, described anti-side shear wall stretches in the centre bore of collar tie beam, described anti-side shear wall is on two metopes in basement floor layer and is respectively equipped with chemise, inner side and outer side in described chemise is respectively equipped with a row of horizontal muscle, be provided with a row in the inner side of every row of horizontal muscle and indulge muscle, horizontal bar corresponding in two row of horizontal muscle is by lacing wire drawknot, the reinforcing bar of base plate cushion cap comprises ringwise horizontal bar and wales the stirrup of horizontal bar, wherein, the inner side of stirrup is welded with the vertical muscle in chemise.
The both sides of the part that anti-side shear wall of the present invention stretches in base plate cushion cap are provided with beard muscle, and described beard muscle has the section of stretching out that a pair passes anti-side shear wall, and the section of stretching out of described beard muscle to stretch in base plate cushion cap anchoring or welds with the plate gluten of base plate cushion cap.
The present invention stretches on the metope of the part in base plate cushion cap at anti-side shear wall and on the metope of base plate cushion cap upper surface, is all wound around water-swellable waterstop with anti-side shear wall, and described water-swellable waterstop is positioned at inside chemise, effectively prevents the seepage of underground water.
Another object of the present invention realizes by the following technical solutions: a kind of above-mentioned construction method using diaphragm wall as the foundation pit system of vertical cantilever fulcrum, is characterized in that comprising the following steps:
(1) the building line along foundation ditch excavates for arranging the hole groove of diaphragm wall to the backplane level of basement, by the reinforcing bar cage hoisting of diaphragm wall in the groove of hole, then forms diaphragm wall to concrete perfusion in the groove of hole;
(2) below the multiple hole groove for arranging anti-side shear wall to the backplane level of basement of the perimeter zone of foundation ditch excavation, by the reinforcing bar cage hoisting of anti-side shear wall in tunnel, then form anti-side shear wall to concrete perfusion in the groove of hole;
(3) adopt reverse construction to be positioned at the basement of the perimeter zone of foundation ditch:
1. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative one deck of the basement of the perimeter zone of foundation ditch, and the earthwork is unearthed from all the other regions of foundation ditch;
2. the floor of the floor of the construction building agent structure first floor and negative one deck of basement, upwards to construct superstructure from the floor of the first floor meanwhile;
3. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative two layers of the basement of the perimeter zone of foundation ditch, and the earthwork is unearthed from all the other regions of foundation ditch, the floor of negative two layers of construction basement;
4. step is repeated 3., until complete the basement of the perimeter zone being positioned at foundation ditch, in construction period, the floor support top diaphragm wall of anti-side shear wall and successively construction downwards, make diaphragm wall as vertical cantilever fulcrum, the overall cantilever retaining structure formed the peripheral soil body;
(4) adopt the basement being positioned at all the other regions of foundation ditch along way construction:
1. carry out step (3) in 1. while step, the earthwork in all the other regions of excavation pit is to the backplane level of basement;
2. the basement being positioned at all the other regions of foundation ditch along way construction is adopted, during construction, reserving gaps between the corresponding floor of the basement of the basement in all the other regions of foundation ditch and the completed perimeter zone at foundation ditch;
(5) fill up described reserved gap, thus the basement of the basement being positioned at all the other regions of foundation ditch with the perimeter zone being positioned at foundation ditch is connected as one.
As one embodiment of the present invention, described anti-side shear wall is distributed in the local of foundation ditch perimeter zone, the local of described foundation ditch perimeter zone is called the periphery regional area of foundation ditch, all the other regions of described foundation ditch are made up of the central area of foundation ditch and all the other regions of periphery of foundation ditch, described step (4) in, adopt the basement being positioned at all the other regions along way construction specifically to comprise the following steps:
1. the earthwork of the central area of excavation pit, is unearthed from all the other regions of periphery of foundation ditch, and the earthwork in all the other regions of periphery of foundation ditch is as back-pressure soil section, and all the other regions of the periphery of foundation ditch are as the unearthed passage of the periphery regional area of foundation ditch and the central area of foundation ditch;
2. the basement being positioned at the central area of foundation ditch along way construction is adopted, the earthwork in all the other regions of periphery of excavation pit simultaneously, be unearthed from all the other regions of periphery of the foundation ditch of rear excavation, the basement being positioned at the central area of foundation ditch becomes the supporting-point of the interim horizontal support of the earthwork in all the other regions of periphery of excavating foundation ditch;
3. the basement in all the other regions of periphery along way construction foundation pit is adopted, reserving gaps between the basement in all the other regions of periphery of foundation ditch and the corresponding floor of the basement of the central area at foundation ditch;
4. fill up described reserved gap, thus the basement in all the other regions of periphery of foundation ditch and the basement of the central area of foundation ditch are connected as one.
The area of foundation ditch of the present invention is greater than or equal to 20,000 square metres, and the degree of depth of foundation ditch is greater than or equal to 15 meters.
Compared with prior art, the present invention has following significant effect:
(1) the present invention adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear in the perimeter zone of foundation ditch, each floor plate is made to become the horizontal support of diaphragm wall, simultaneously, anti-side shear wall is multidirectional stressed structure, both act as the side direction fulcrum that foundation ditch periphery is gone along with sb. to guard him, assume responsibility for again the vertical force of superstructure, compared with the present invention constructs with existing employing contrary sequence method or along way, because anti-side shear wall can be used as braced structures in the early stage, and be again the ingredient of agent structure, so, overcome prior art to execute man-hour requirement and build the problem that temporary support then removes again, not only enormously simplify difficulty of construction, shorten the construction period, and because eliminate temporary support, considerably reduce construction cost.
(2) the present invention adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear at the periphery regional area of foundation ditch, can be unearthed from all the other regions of foundation ditch, and all the other regions of foundation ditch adopt back-pressure soil balance external lateral earth pressure, temporary support need not be established again, or the present invention adopts diaphragm wall+floor+anti-side shear wall as the native water-stopping structure of gear along the circumference of the perimeter zone of foundation ditch, can be unearthed from central area, all can significantly shorten the ground works duration.
The cross section of anti-side shear wall of the present invention by the backplane level of basement to the successively indentation of the major structure of construction first floor, during to foundation ditch superstructure above water, anti-side shear wall transforms into post, now, only bear vertical force, the anti-side shear wall more than first floor is converted into cylinder, not only economical, and the space of the major structure of construction first floor can be made larger.
(4) the connected mode between the base plate cushion cap of anti-side shear wall and basement, can make the connection of base plate cushion cap and anti-side shear wall more firm.
(5) chemise is set on the metope of anti-side shear wall, and water expandable waterstop is set, and the reinforcing bar of base plate cushion cap adopt ring-shaped stirrup weld with the vertical muscle of anti-side shear wall make both form complete structure, effectively prevent the seepage of underground water.
(6) the area that the present invention is applicable to foundation ditch is greater than or equal to 20,000 square metres, and when the degree of depth of foundation ditch is greater than or equal to the situation of 15 meters, advantage is more remarkable.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
Fig. 1 is the top view of foundation pit system embodiment 1 diaphragm wall of the present invention and the distribution of anti-side shear wall;
Fig. 2 is the vertical face figure of foundation pit system embodiment 1 of the present invention in work progress;
Fig. 3 is that face figure is indulged in the local of foundation pit system embodiment 1 of the present invention;
Fig. 4 is the schematic diagram that the cross section of the embodiment of the present invention 1 anti-side shear wall successively reduces from bottom to up;
Fig. 5 is the schematic diagram that the embodiment of the present invention 1 anti-side shear wall is connected with the base plate cushion cap of basement.
Detailed description of the invention
Embodiment 1
The area that the present embodiment is applicable to foundation ditch is greater than or equal to 20,000 square metres, and the degree of depth of foundation ditch is greater than or equal to the situation of 15 meters.As shown in Figures 1 to 3, a kind of foundation pit system using diaphragm wall as vertical cantilever fulcrum, comprise at least one deck basement, basement is formed by connecting by respective floor correspondence with the basement in all the other regions being positioned at foundation ditch 1 primarily of the basement 31 of the perimeter zone 11 being positioned at foundation ditch 1, wherein, the basement 31 being positioned at the perimeter zone 11 of foundation ditch adopts reverse construction, and the basement being positioned at all the other regions of foundation ditch 1 adopts along way construction, the basement 31 being positioned at the perimeter zone 11 of foundation ditch comprises diaphragm wall 13, anti-side shear wall 14 and floor 15, diaphragm wall 13 is arranged along the inwall circumference of foundation ditch 1, namely diaphragm wall 13 is outer rims of the perimeter zone 11 of foundation ditch, the inner edge of the perimeter zone 11 of foundation ditch is then the central area 12 of foundation ditch 1 and the line of demarcation of the perimeter zone 11 of foundation ditch 1, anti-side shear wall 14 is distributed in the perimeter zone 11 of foundation ditch 1, in the present embodiment, anti-side shear wall 14 is according to the circle distribution of the perimeter zone 11 of foundation ditch, namely all the other regions of foundation ditch 1 are the central areas 12 of foundation ditch 1, floor 15 layering is located on anti-side shear wall 14 and diaphragm wall 13.Anti-side shear wall 14 near the perimeter zone 11 of foundation ditch 1 inner edge and all perpendicular to the metope of diaphragm wall 13 corresponding thereto diametrically.The side direction soil power that diaphragm wall is subject to, perpendicular to diaphragm wall 13, farthest can be born in the long limit of anti-side shear wall 14, safer.
As shown in Figure 4, the cross section of anti-side shear wall 14 successively reduces from backplane level 2 to the major structure of construction first floor 36 of basement, the anti-side shear wall 14 being positioned at the major structure of construction first floor more than 36 is all converted into post, not only economical, and the space of the major structure of construction first floor can be made larger.
As shown in Figure 5, anti-side shear wall 14 stretches in the base plate cushion cap 21 of the backplane level 2 of basement downwards, base plate cushion cap 21 is collar tie beam, anti-side shear wall 14 stretches in the centre bore of collar tie beam, anti-side shear wall 14 is on two metopes in basement floor layer 2 and is respectively equipped with chemise 16, inner side and outer side in chemise 16 is respectively equipped with a row of horizontal muscle 17, be provided with a row in the inner side of every row of horizontal muscle 17 and indulge muscle 18, horizontal bar corresponding in two row of horizontal muscle 17 is by lacing wire 19 drawknot, the reinforcing bar of base plate cushion cap 21 comprises ringwise horizontal bar 22 and wales the stirrup 23 of horizontal bar, wherein, the inner side of stirrup 23 is welded with the vertical muscle 18 in chemise 16.The both sides of the part that anti-side shear wall 14 stretches in base plate cushion cap 21 are provided with beard muscle 24, beard muscle 24 has the section of stretching out that a pair passes anti-side shear wall, the section of stretching out of beard muscle 24 to stretch in base plate cushion cap 21 anchoring or welds with the plate gluten of base plate cushion cap 21, anchoring shown in Fig. 5 of the present embodiment is specifically: due to construction error, the section of stretching out of beard muscle is not corresponding with the plate gluten of base plate cushion cap, therefore cannot weld together.
The metope that anti-side shear wall 14 stretches into the part in base plate cushion cap 21 is all wound around water-swellable waterstop 3 with anti-side shear wall 14 on the metope of base plate cushion cap 21 upper surface, and water-swellable waterstop 3 is positioned at inside chemise 16, the seepage of underground water effectively can be stoped.
An above-mentioned construction method using diaphragm wall as the foundation pit system of vertical cantilever fulcrum, specifically comprises the following steps:
(1) the building line along foundation ditch 1 excavates for arranging the hole groove of diaphragm wall 13 to the backplane level of basement, by the reinforcing bar cage hoisting of diaphragm wall 13 in the groove of hole, then forms diaphragm wall 13 to concrete perfusion in the groove of hole;
(2) below the multiple hole groove for arranging anti-side shear wall 14 to the backplane level of basement of the perimeter zone of foundation ditch 1 excavation, in the present embodiment, multiple anti-side shear wall 14 is according to the circle distribution of the perimeter zone of foundation ditch 1, by the reinforcing bar cage hoisting of anti-side shear wall 14 in the groove of hole, then form anti-side shear wall to concrete perfusion in the groove of hole;
(3) adopt reverse construction to be positioned at the basement 31 of the perimeter zone of foundation ditch 1:
1. along the inwall of diaphragm wall 13 and the inner side of anti-side shear wall 14, excavation is positioned at negative one deck 33 of the basement of the perimeter zone of foundation ditch 1, and the earthwork is unearthed from all the other regions of foundation ditch 1, is namely unearthed from the central area 12 of foundation ditch 1;
2. the floor of the floor of the construction building agent structure first floor and negative one deck of basement, upwards to construct superstructure from the floor of the first floor meanwhile;
3. along the inwall of diaphragm wall 13 and the inner side of anti-side shear wall 14, excavation is positioned at negative two layers of the basement of the perimeter zone of foundation ditch 1, and the earthwork is unearthed from the central area of foundation ditch 1, the floor of negative two layers of construction basement;
4. step is repeated 3., until complete the basement of the perimeter zone being positioned at foundation ditch 1, in work progress, the floor support top diaphragm wall 13 of anti-side shear wall 14 and successively construction downwards, make diaphragm wall 13 as vertical cantilever fulcrum, the overall cantilever retaining structure formed the peripheral soil body;
(4) adopt the basement 32 being positioned at the central area of foundation ditch 1 along way construction:
1. carry out step (3) in 1. while step, the earthwork of the central area 12 of excavation pit 1 is to the backplane level of basement;
2. the basement 32 being positioned at the central area 12 of foundation ditch 1 along way construction is adopted, negative two layer 34 and the basement bottom board layer 35 of the basement 32 of the central area 12 being positioned at foundation ditch 1 shown in Fig. 2, during construction, reserving gaps between the basement 32 in the central area 12 of foundation ditch 1 and the corresponding floor of the basement 31 of the completed perimeter zone 11 at foundation ditch 1;
(5) fill up described reserved gap, thus the basement 31 being positioned at the perimeter zone 11 of foundation ditch 1 is connected as one with the basement 32 of the central area 12 being positioned at foundation ditch 1.
Embodiment 2
The present embodiment answers Construction Party to the requirement of construction speed, first to construct a wherein high building, the position of this high building is the local of the perimeter zone of foundation ditch, be the periphery regional area of foundation ditch, all the other regions of foundation ditch are made up of the central area of foundation ditch and all the other regions of periphery of foundation ditch, therefore, the difference of the present embodiment and embodiment 1 is: anti-side shear wall is distributed in the periphery regional area of foundation ditch.
The construction method of the present embodiment foundation ditch system comprises the following steps:
(1) the building line along foundation ditch excavates for arranging the hole groove of diaphragm wall to the backplane level of basement, by the reinforcing bar cage hoisting of diaphragm wall in the groove of hole, then forms diaphragm wall to concrete perfusion in the groove of hole;
(2) below the multiple hole groove for arranging anti-side shear wall to the backplane level of basement of periphery regional area excavation of foundation ditch, by the reinforcing bar cage hoisting of anti-side shear wall in the groove of hole, then form anti-side shear wall to concrete perfusion in the groove of hole;
(3) adopt reverse construction to be positioned at the basement of the periphery regional area of foundation ditch:
1. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative one deck of the basement of the periphery regional area of foundation ditch, and the earthwork is unearthed from all the other regions of periphery of foundation ditch;
2. the floor of the floor of the construction building agent structure first floor and negative one deck of basement, upwards to construct superstructure from the floor of the first floor meanwhile;
3. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative two layers of the basement of the periphery regional area of foundation ditch, and the earthwork is unearthed from all the other regions of periphery, the floor of negative two layers of construction basement;
4. step is repeated 3., until complete the basement of the periphery regional area being positioned at foundation ditch, in construction period, the floor support top diaphragm wall of anti-side shear wall and successively construction downwards, make diaphragm wall as vertical cantilever fulcrum, the overall cantilever retaining structure formed the peripheral soil body;
(4) adopt the basement being positioned at all the other regions of foundation ditch along way construction:
1. carry out step (3) in 1. while step, the earthwork in all the other regions of excavation pit is to the backplane level of basement;
2. the basement being positioned at all the other regions of foundation ditch along way construction is adopted, during construction, reserving gaps between the basement in all the other regions of foundation ditch and the corresponding floor of the basement of the completed periphery regional area at foundation ditch;
Filling steps (4) in the gap reserved, connect as one with the basement in the basement making the periphery regional area being positioned at foundation ditch and all the other regions of being positioned at foundation ditch.
Step (4) in, adopt and be positioned at the basement in all the other regions of foundation ditch along way construction, specifically comprise the following steps:
1. the earthwork of the central area of excavation pit, is unearthed from all the other regions of periphery of foundation ditch, and the earthwork in all the other regions of periphery of foundation ditch is as back-pressure soil section, and all the other regions of the periphery of foundation ditch are the unearthed passage of the periphery regional area of foundation ditch and the central area of foundation ditch;
2. the basement being positioned at the central area of foundation ditch along way construction is adopted, and the earthwork in simultaneously all the other regions of periphery of excavation pit, be unearthed from all the other regions of periphery of the foundation ditch of rear excavation, the basement being positioned at the central area of foundation ditch becomes the supporting-point of the interim horizontal support of all the other regional earthworks of periphery excavating foundation ditch;
3. the basement being positioned at all the other regions of periphery of foundation ditch along way construction is adopted, reserving gaps between the basement in all the other regions of periphery of foundation ditch and the corresponding floor of the basement of the central area at foundation ditch;
4. fill up described reserved gap, thus the basement of the basement being positioned at all the other regions of periphery of foundation ditch with the central area being positioned at foundation ditch is connected as one.
Embodiments of the present invention are not limited thereto; according to foregoing of the present invention; according to ordinary technical knowledge and the customary means of this area; do not departing under the present invention's above-mentioned fundamental technics thought prerequisite; the present invention also has the amendment of other various ways, replacement or change, all drops within rights protection scope of the present invention.

Claims (10)

1. the foundation pit system using diaphragm wall as vertical cantilever fulcrum, comprise at least one deck basement, it is characterized in that: described basement is formed by connecting by respective floor correspondence with the basement in all the other regions being positioned at foundation ditch primarily of the basement of the perimeter zone being positioned at foundation ditch, wherein, the basement being positioned at the perimeter zone of foundation ditch adopts reverse construction, and the basement being positioned at all the other regions of foundation ditch adopts along way construction, the basement being positioned at the perimeter zone of foundation ditch comprises diaphragm wall, anti-side shear wall and floor, described diaphragm wall is arranged along the inwall circumference of foundation ditch, described diaphragm wall is the outer rim of foundation ditch perimeter zone, the inner edge of the perimeter zone of foundation ditch is then the line of demarcation of the central area of foundation ditch and the perimeter zone of foundation ditch, described anti-side shear wall is distributed in the perimeter zone of foundation ditch, described floor layering is located on anti-side shear wall and diaphragm wall.
2. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 1, described anti-side shear wall is distributed in the local of the perimeter zone of foundation ditch, the local of the perimeter zone of described foundation ditch is called the periphery regional area of foundation ditch, and all the other regions of described foundation ditch are made up of the central area of foundation ditch and all the other regions of periphery of foundation ditch; Or described anti-side shear wall is according to the circle distribution of the perimeter zone of foundation ditch, namely all the other regions of described foundation ditch are the central areas of foundation ditch.
3. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 2, is characterized in that: described anti-side shear wall near the perimeter zone of foundation ditch inner edge and all perpendicular to the metope of diaphragm wall corresponding thereto diametrically.
4. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 3, it is characterized in that: the cross section of described anti-side shear wall successively reduces to the first floor of major structure of construction from the backplane level of basement, and the anti-side shear wall being positioned at more than the major structure of construction first floor is all converted into post.
5. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 4, it is characterized in that: described anti-side shear wall stretches in the base plate cushion cap of basement downwards, described base plate cushion cap is collar tie beam, described anti-side shear wall stretches in the centre bore of collar tie beam, described anti-side shear wall is on two metopes in basement floor layer and is respectively equipped with chemise, inner side and outer side in described chemise is respectively equipped with a row of horizontal muscle, be provided with a row in the inner side of every row of horizontal muscle and indulge muscle, horizontal bar corresponding in two row of horizontal muscle is by lacing wire drawknot, the reinforcing bar of base plate cushion cap comprises ringwise horizontal bar and wales the stirrup of horizontal bar, wherein, the inner side of stirrup is welded with the vertical muscle in chemise.
6. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 5, it is characterized in that: the both sides of the part that anti-side shear wall stretches in base plate cushion cap are provided with beard muscle, described beard muscle has the section of stretching out that a pair passes anti-side shear wall, and the section of stretching out of described beard muscle to stretch in base plate cushion cap anchoring or welds with the plate gluten of base plate cushion cap.
7. the foundation pit system using diaphragm wall as vertical cantilever fulcrum according to claim 6, it is characterized in that: on the metope that anti-side shear wall stretches into the part in base plate cushion cap, on the metope of base plate cushion cap upper surface, be all wound around water-swellable waterstop with anti-side shear wall, and described water-swellable waterstop is positioned at inside chemise.
8. the construction method using diaphragm wall as the foundation pit system of vertical cantilever fulcrum according to claim 1, is characterized in that comprising the following steps:
(1) the building line along foundation ditch excavates for arranging the hole groove of diaphragm wall to the backplane level of basement, by the reinforcing bar cage hoisting of diaphragm wall in the groove of hole, then forms diaphragm wall to concrete perfusion in the groove of hole;
(2) below the multiple hole groove for arranging anti-side shear wall to the backplane level of basement of the perimeter zone of foundation ditch excavation, by the reinforcing bar cage hoisting of anti-side shear wall in the groove of hole, then form anti-side shear wall to concrete perfusion in the groove of hole;
(3) adopt reverse construction to be positioned at the basement of the perimeter zone of foundation ditch:
1. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative one deck of the basement of the perimeter zone of foundation ditch, and the earthwork is unearthed from all the other regions of foundation ditch;
2. the floor of the floor of the construction building agent structure first floor and negative one deck of basement, upwards to construct superstructure from the floor of the first floor meanwhile;
3. along the inwall of diaphragm wall and the inner side of anti-side shear wall, excavation is positioned at negative two layers of the basement of the perimeter zone of foundation ditch, and the earthwork is unearthed from all the other regions of foundation ditch, the floor of negative two layers of construction basement;
4. step is repeated 3., until complete the basement of the perimeter zone being positioned at foundation ditch, in construction period, the floor support top diaphragm wall of anti-side shear wall and successively construction downwards, make diaphragm wall as vertical cantilever fulcrum, the overall cantilever retaining structure formed the peripheral soil body;
(4) adopt the basement being positioned at all the other regions of foundation ditch along way construction:
1. carry out step (3) in 1. while step, the earthwork in all the other regions of excavation pit is to the backplane level of basement;
2. the basement being positioned at all the other regions of foundation ditch along way construction is adopted, during construction, reserving gaps between the basement in all the other regions of foundation ditch and the corresponding floor of the basement of the completed perimeter zone at foundation ditch;
(5) fill up described reserved gap, thus the basement of the basement being positioned at all the other regions of foundation ditch with the perimeter zone being positioned at foundation ditch is connected as one.
9. construction method according to claim 8, it is characterized in that: described anti-side shear wall is distributed in the local of the perimeter zone of foundation ditch, the local of the perimeter zone of described foundation ditch is called the periphery regional area of foundation ditch, all the other regions of described foundation ditch are made up of the central area of foundation ditch and all the other regions of periphery of foundation ditch, described step (4) in, adopt the basement being positioned at all the other regions of foundation ditch along way construction specifically to comprise the following steps:
1. the earthwork of the central area of excavation pit, is unearthed from all the other regions of periphery of foundation ditch, and the earthwork in all the other regions of periphery of foundation ditch is as back-pressure soil section, and all the other regions of the periphery of foundation ditch are as the unearthed passage of the periphery regional area of foundation ditch and the central area of foundation ditch;
2. the basement being positioned at the central area of foundation ditch along practice construction is adopted, and the earthwork in simultaneously all the other regions of periphery of excavation pit, be unearthed from all the other regions of periphery of the foundation ditch of rear excavation, the basement being positioned at the central area of foundation ditch becomes the supporting-point of the interim horizontal support of all the other regional earthworks of periphery excavating foundation ditch;
3. the basement being positioned at all the other regions of periphery of foundation ditch along practice construction is adopted, reserving gaps between the basement in all the other regions of periphery of foundation ditch and the corresponding floor of the basement of the central area at foundation ditch;
4. fill up described reserved gap, thus the basement of the basement being positioned at all the other regions of periphery of foundation ditch with the central area being positioned at foundation ditch is connected as one.
10. construction method according to claim 9, is characterized in that: the area of foundation ditch is greater than or equal to 20,000 square metres, and the degree of depth of foundation ditch is greater than or equal to 15 meters.
CN201510546683.5A 2015-08-31 2015-08-31 Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method Active CN105113514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510546683.5A CN105113514B (en) 2015-08-31 2015-08-31 Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510546683.5A CN105113514B (en) 2015-08-31 2015-08-31 Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method

Publications (2)

Publication Number Publication Date
CN105113514A true CN105113514A (en) 2015-12-02
CN105113514B CN105113514B (en) 2017-01-04

Family

ID=54661606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510546683.5A Active CN105113514B (en) 2015-08-31 2015-08-31 Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method

Country Status (1)

Country Link
CN (1) CN105113514B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522385A (en) * 2016-11-25 2017-03-22 北京崇建工程有限公司 Basement waterproof structure construction method and basement waterproof structure
CN108643195A (en) * 2018-06-27 2018-10-12 上海建工二建集团有限公司 The main body of foundation pit and the integral system of supporting construction and method
CN111485578A (en) * 2020-04-24 2020-08-04 安徽省建筑科学研究设计院 Stepped edge forward and backward building construction method
CN112593546A (en) * 2020-12-03 2021-04-02 中铁广州工程局集团有限公司 Construction method for underground diaphragm wall to penetrate through underground structure
JP7152291B2 (en) 2018-12-17 2022-10-12 株式会社竹中工務店 construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002275922A (en) * 2001-03-13 2002-09-25 Toda Constr Co Ltd Reversed placing method
KR20030051478A (en) * 2003-05-19 2003-06-25 주식회사 동아지질 The method of constructing support wall to use as pillar and slab
CN102383433A (en) * 2011-08-22 2012-03-21 同济大学建筑设计研究院(集团)有限公司 Design method for large deep foundation pit of super high-rise building
CN102425171A (en) * 2011-09-25 2012-04-25 湖南省勘测设计院 Forward-backward constructing method for central island of deep and large foundation pit
CN205000340U (en) * 2015-08-31 2016-01-27 广东省建筑设计研究院 Regard as foundation ditch of vertical cantilever fulcrum to go along with sb. to guard him system with underground continuous wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002275922A (en) * 2001-03-13 2002-09-25 Toda Constr Co Ltd Reversed placing method
KR20030051478A (en) * 2003-05-19 2003-06-25 주식회사 동아지질 The method of constructing support wall to use as pillar and slab
CN102383433A (en) * 2011-08-22 2012-03-21 同济大学建筑设计研究院(集团)有限公司 Design method for large deep foundation pit of super high-rise building
CN102425171A (en) * 2011-09-25 2012-04-25 湖南省勘测设计院 Forward-backward constructing method for central island of deep and large foundation pit
CN205000340U (en) * 2015-08-31 2016-01-27 广东省建筑设计研究院 Regard as foundation ditch of vertical cantilever fulcrum to go along with sb. to guard him system with underground continuous wall

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522385A (en) * 2016-11-25 2017-03-22 北京崇建工程有限公司 Basement waterproof structure construction method and basement waterproof structure
CN108643195A (en) * 2018-06-27 2018-10-12 上海建工二建集团有限公司 The main body of foundation pit and the integral system of supporting construction and method
JP7152291B2 (en) 2018-12-17 2022-10-12 株式会社竹中工務店 construction method
CN111485578A (en) * 2020-04-24 2020-08-04 安徽省建筑科学研究设计院 Stepped edge forward and backward building construction method
CN112593546A (en) * 2020-12-03 2021-04-02 中铁广州工程局集团有限公司 Construction method for underground diaphragm wall to penetrate through underground structure

Also Published As

Publication number Publication date
CN105113514B (en) 2017-01-04

Similar Documents

Publication Publication Date Title
CN105113514B (en) Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method
CN105089061B (en) Ultra-deep foundation pit supporting method
CN106522241A (en) Deep foundation pit supporting method of ultrahigh floor height type basement structure
CN104453274A (en) Method for supporting underground layer increasing of existing building by supporting structure and underpinning structure
CN210598987U (en) Subway station based on single-layer four-guide-hole and middle-guide-hole inner pile foundation
CN102864780A (en) Supporting structure and supporting method of foundation pit
CN103103988A (en) Foundation ditch construction method of horizontal bracing structure of central island floor slaps
CN205242436U (en) Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex
CN104631466A (en) Construction method of structural system with structural floors as horizontal braces
CN102031785A (en) Foundation pit supporting technique for replacing temporary enclosing purlin by using plate belt of permanent structure
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN104947681A (en) Super large super deep basement ground pit construction method
CN109505298A (en) A kind of self-balancing foundation pit enclosure method
CN104652444A (en) Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation
CN208517810U (en) A kind of temporary trestle bridge for deep big foundation pit excavation construction
CN101498133B (en) Method and supporting construction for enlarging basement top-down method earth excavation space
CN205000340U (en) Regard as foundation ditch of vertical cantilever fulcrum to go along with sb. to guard him system with underground continuous wall
CN106758890A (en) Campshed box culvert structure and its construction method
CN107503355B (en) Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof
CN205024712U (en) Modular tower crane basis
CN107313430A (en) The deep big foundation pit subregion construction method of three face Nearby Structures
CN103122642A (en) Construction method of vertical post support change
CN109403339A (en) The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
CN103924599A (en) Method for processing support steel column construction not in place in foundation pits
CN104594367B (en) A kind of combined type cofferdam structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: No.97 Liuhua Road, Liwan District, Guangzhou City, Guangdong Province 510010

Patentee after: Guangdong Architectural Design and Research Institute Co., Ltd

Address before: Guangzhou City, Guangdong province 510010 Liuhua Road No. 97

Patentee before: ARCHITECTURAL DESIGN Research Institute OF GUANGDONG PROVINCE

CP03 Change of name, title or address