CN104878763A - Basement supporting structure of main building with podium building - Google Patents

Basement supporting structure of main building with podium building Download PDF

Info

Publication number
CN104878763A
CN104878763A CN201510309657.0A CN201510309657A CN104878763A CN 104878763 A CN104878763 A CN 104878763A CN 201510309657 A CN201510309657 A CN 201510309657A CN 104878763 A CN104878763 A CN 104878763A
Authority
CN
China
Prior art keywords
enclosure wall
main building
annex
basement
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510309657.0A
Other languages
Chinese (zh)
Other versions
CN104878763B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan Wantai Building Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610442856.3A priority Critical patent/CN106149731B/en
Priority to CN201510309657.0A priority patent/CN104878763B/en
Publication of CN104878763A publication Critical patent/CN104878763A/en
Application granted granted Critical
Publication of CN104878763B publication Critical patent/CN104878763B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a basement supporting structure of a main building with a podium building. The basement supporting structure is characterized in that a temporary enclosure wall is arranged between the main building and the podium building, and two high-pressure jet grouting piles are arranged on each of the outer sides of the joints between a main building enclosure wall and a podium building enclosure wall, so that the problem of water seepage at the positions weak in seepage-proof performance is solved; two high-pressure jet grouting piles are used at each of the trough-section seam positions of the main building enclosure wall, the podium building enclosure wall and the temporary enclosure wall for seepage-proof seam filling, and two high-pressure jet grouting piles are also arranged at each of the corner positions of the main building enclosure wall and the podium building enclosure wall; steel plate water-stop belts are arranged at the cross positions of the main building enclosure wall, the podium building enclosure wall and the temporary enclosure wall, a circular-ring brace is arranged on the inner side of the main building enclosure wall, and angle braces are arranged between the circular-ring brace and the main building enclosure wall and are made of concrete or steel; a truss supporting system is arranged in the middle of the main building enclosure wall, supporting columns are arranged on the lower portions of truss girders so as to maintain stability in a plane, concrete outlets are formed in a top plate of the podium building, and flanging beams are arranged at four corners of the concrete outlets additionally.

Description

With the main building basement supporting and protection structure of annex
Technical field
The present invention relates to a kind of basement supporting and protection structure, be particularly with the main building basement supporting and protection structure of annex.
Background technology
Along with the development of urban construction, highrise building occurs like the mushrooms after rain, and for the highrise building of commercial function, main building is usual and podium is interdependent and build, and main building can be communicated with annex basement.When basement construction, excavation area can be very large, and the tau-effect of cutting the earth on the one hand clearly, can there will be the bad phenomenon such as the earthwork protuberance during shoveling; On the other hand, the time of shoveling can be very long, and the main building construction period can be corresponding very long.Because the main building duration is controlling node, the main building construction period determines delivery time of whole engineering.Construction period can be very long traditionally, and construction safety is difficult to obtain guarantee.
Summary of the invention
The present invention is to provide a kind of main building basement supporting and protection structure with annex, solves the problem of prior art.
For this reason, the present invention arranges interim enclosure wall between basement main building and annex, makes main building basement and annex basement form two independently spaces.Because the main building basement construction time is controlling node, first to construct after interim enclosure wall completes main building basement, main building basement adopts along method construction, namely first to construct basement bottom board, construct from the bottom to top again, to construct again after main building basement roof completes annex basement, annex basement adopts inverse method construction, namely first to construct basement roof, construct from top to bottom again, object is in order to the construction of basement annex does not disturb main building deck to construct, and synchronously carries out main building basement construction during the construction of basement annex.
Interim enclosure wall is set between main building and annex, interim enclosure wall width is 700 ~ 900mm, the interim enclosure wall degree of depth is 1.5 ~ 2 times of foundation depth, interim enclosure wall concrete strength be C30 or more than, main building enclosure wall not only has supporting performance to double as outer wall of basement, main building enclosure wall width is 700 ~ 900mm, and the main building enclosure wall degree of depth is 1.8 ~ 2.5 times of foundation depth, main building enclosure wall concrete strength be C30 or more than.After treating basement construction, inside main building enclosure wall, paste malthoid, inside malthoid, do bricking wall, to meet basement antiseepage requirement.Annex enclosure wall width is 700 ~ 900mm, and the annex enclosure wall degree of depth is 1.8 ~ 2.5 times of foundation depth, annex enclosure wall concrete strength be C30 or more than.Main building enclosure wall and annex enclosure wall handing-over position arranged outside 2 high-pressure rotary jet grouting piles, solve the seepage problem of antiseepage weak part.At main building enclosure wall, annex enclosure wall with go along with sb. to guard him wall chase section seam crossing and adopt 2 high-pressure rotary jet grouting piles to squeegee as antiseepage temporarily, main building enclosure wall rotation angle position and annex enclosure wall rotation angle position also arrange 2 high-pressure rotary jet grouting piles.Main building enclosure wall, annex enclosure wall and interim enclosure wall crossover sites arrange steel plate water stopper, steel plate water-stopping tape thickness is 3 ~ 5mm, arranges annulus support inside main building enclosure wall, and annulus support width is 500 ~ 700mm, be highly 700 ~ 900mm, annulus support concrete strength be C30 or more than.Arrange angle brace between annulus support and main building enclosure wall, angle brace adopts concrete support or steel support.Arrange truss support system in the middle part of main building enclosure wall, truss support system can alleviate the horizontal force suffered by annulus support greatly.Truss support system comprises girder truss and truss web.Girder truss width is 400 ~ 600mm, is highly 500 ~ 700mm, girder truss concrete strength be C30 or more than, truss web width is 300 ~ 500mm, is highly 500 ~ 700mm, truss web concrete strength be C30 or more than.Girder truss bottom arranges support column to maintain Stability in Plane, and support column adopts steel column, and steel column adopts two channel-section steels to be spliced, and steel column inserts bored pile.Annex top board indwelling soil outlet, annex soil outlet area is 30 ~ 100m 2, the stress state that turned welt beam improves bight is set up in soil outlet corner, turns under turned welt beam, and turned welt depth of beam is 250 ~ 300mm, and width is 200mm.Annex arranges a soil outlet every 50 ~ 70m, and soil outlet is arranged on the region that punches of elevator & stairs and structure design as far as possible.
Compaction grouting process is carried out in depths, the local such as elevator shaft, collecting well, and slip casting width is 3m, and slip casting thickness is 5m.
Construction sequence comprises:
(1) construction main building enclosure wall, pre-embedded steel slab waterstop;
(2) construction annex enclosure wall and interim enclosure wall;
(3) construction high-pressure rotary jet grouting pile;
In order to improve anti-seepage effect, rotary churning pile rig adopts hydraulic power head, unit head is moved on king-tower by the elevator machine travel that works, the revolution of unit head is driven through reduction box by fluid power motor, realizes the swing of revolution and different angles, utilizes rig that the Grouting Pipe with special nozzle is drilled into soil layer precalculated position, make slurries become high-pressure spray with high-tension apparatus to penetrate from nozzle, slurries are sprayed on lifting limit, rotation limit, limit, make slurries and grogs Forced Mixing, form induration after grout cures in soil.Rotary churning pile slip casting form adopts to swing sprays.High-pressure water pressure is 30MPa, flow 90L/min; Compressed air pressure is 0.6 ~ 0.8MPa, and flow is 6m 3/ h; Cement paste pressure is 5MPa, and flow is 80 ~ 100L/min.Cement slurry density is 1.60g/cm, and cement paste water/binder ratio is 0.8; 30m is that 6 ~ 8cm/min, more than 30m position hoisting velocity is for 8 ~ 10cm/min with lower portion hoisting velocity.
(4) construction main building support column;
(5) middle part girder truss and the truss web of main building first support system is done, annulus support of then constructing; Carry out construction angle brace again;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss and the truss web of main building second support system is done, annulus support of then constructing; Carry out construction angle brace again;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss and the truss web of main building the 3rd road support system is done, annulus support of then constructing; Carry out construction angle brace again;
(10) earth excavation is to main building basement bottom board, builds basement bottom board concrete;
(11) remove the 3rd road support in girder truss and truss web and annulus support and angle brace;
(12) the 3rd road support zone basement floorslab concrete is built;
(13) remove second support in girder truss and truss web and annulus support and angle brace;
(14) second support zone basement floorslab concrete is built;
(15) main building basement roof concrete is built;
(16) annex concrete roof is built, indwelling soil outlet;
(17) excavate the annex earthwork to one deck basement floor, build basement floorslab concrete;
Soil excavation carries out according to " subregion, point title, balance " principle; Soil excavation level of approximation in hole is declined, guarantees support system uniform stressed, prevent the outer unstability of support system plane.
(18) excavate the annex earthwork to two layer basement floor, build basement floorslab concrete;
(19) excavate the annex earthwork to three layer basement floor, build basement floorslab concrete;
(20) excavate the annex earthwork to three layer basement bottom board position, build underplate concrete.
The continuous productive process that the present invention is constructed by main building and annex, accelerate construction speed, safe condition obtains improvement again, and saving in duration shortening and cost has obvious effect.
Accompanying drawing explanation
Fig. 1 is the main building basement supporting and protection structure schematic diagram of band annex.
In each accompanying drawing: 1, main building enclosure wall, 2, interim enclosure wall, 3, annulus support, 4, girder truss, 5, truss web, 6, support column, 7, high-pressure rotary jet grouting pile, 8, annex enclosure wall, 9, steel plate water stopper, 10, soil outlet, 11, angle brace.
Detailed description of the invention
Certain engineering is 16 layers of main building, and be frame cylinder shear wall structure, annex is 3-tier architecture, and main building and annex are 3 layers of basement, and cutting depth is 11.2m, and engineering pile is bored pile, and the bored pile degree of depth is 48m.
Interim enclosure wall 2 is set between the present embodiment main building and annex, interim enclosure wall 2 width is 800mm, interim enclosure wall 2 degree of depth is the 20m of foundation depth, interim enclosure wall 2 concrete strength is C30, main building enclosure wall 1 not only has supporting performance to double as outer wall of basement, main building enclosure wall 1 width is 800mm, and main building enclosure wall 1 degree of depth is 25m, and main building enclosure wall 1 concrete strength is C30.After treating basement construction, inside main building enclosure wall 1, paste malthoid, inside malthoid, do bricking wall.Annex enclosure wall 8 width is 800mm, and annex enclosure wall 8 degree of depth is 25m, and annex enclosure wall 1 concrete strength is C30.Main building enclosure wall 1 and annex enclosure wall 8 join position arranged outside 2 high-pressure rotary jet grouting piles 7, solve the seepage problem of antiseepage weak part.Adopt 2 high-pressure rotary jet grouting piles 7 to squeegee as antiseepage at main building enclosure wall 1, annex enclosure wall 8 and interim enclosure wall 2 groove section seam crossing, main building enclosure wall 1 rotation angle position and annex enclosure wall 8 rotation angle position also arrange 2 high-pressure rotary jet grouting piles 7.Main building enclosure wall 1, annex enclosure wall 8 and interim enclosure wall 2 crossover sites arrange steel plate water stopper 9, steel plate water stopper 9 thickness is 4mm, and arrange annulus support 3 inside main building enclosure wall 1, it is 600mm that annulus supports 3 width, be highly 800mm, it is C30 that annulus supports 3 concrete strengths.Arrange angle brace 11 between annulus support 3 and main building enclosure wall 1, angle brace 11 adopts concrete to support.Arrange truss support system in the middle part of main building enclosure wall 1, truss support system can alleviate the horizontal force of annulus support suffered by 3 greatly.Truss support system comprises girder truss 4 and truss web 5.Girder truss 4 width is 500mm, is highly 600mm, and girder truss 4 concrete strength is C30, and truss web 5 width is 400mm, is highly 600mm, and truss web 5 concrete strength is C30.Girder truss 4 bottom arranges support column 6 to maintain Stability in Plane, and support column 6 adopts steel column, and steel column adopts two channel-section steels to be spliced, and steel column inserts bored pile.Annex top board indwelling soil outlet, annex soil outlet area is 70m 2, the stress state that turned welt beam improves bight is set up in soil outlet corner, turns under turned welt beam, and turned welt depth of beam is 250mm, and width is 200mm.Annex arranges a soil outlet 10 every 60m, and soil outlet 10 is arranged on the region that punches of elevator & stairs and structure design as far as possible.Compaction grouting process is carried out in depths, the local such as elevator shaft, collecting well, and slip casting width is 3m, and slip casting thickness is 5m.
Construction sequence comprises:
(1) construction main building enclosure wall 1, pre-embedded steel slab waterstop 9;
(2) construction annex enclosure wall 8 and interim enclosure wall 2;
(3) construction high-pressure rotary jet grouting pile 7;
In order to improve anti-seepage effect, rotary churning pile rig adopts hydraulic power head, unit head is moved on king-tower by the elevator machine travel that works, the revolution of unit head is driven through reduction box by fluid power motor, realizes the swing of revolution and different angles, utilizes rig that the Grouting Pipe with special nozzle is drilled into soil layer precalculated position, make slurries become high-pressure spray with high-tension apparatus to penetrate from nozzle, slurries are sprayed on lifting limit, rotation limit, limit, make slurries and grogs Forced Mixing, form induration after grout cures in soil.Rotary churning pile slip casting form adopts to swing sprays.High-pressure water pressure is 30MPa, flow 90L/min; Compressed air pressure is 0.7MPa, and flow is 6m 3/ h; Cement paste pressure is 5MPa, and flow is 90L/min.Cement slurry density is 1.60g/cm, and cement paste water/binder ratio is 0.8; 30m with lower portion hoisting velocity for 7cm/min, more than 30m position hoisting velocity is for 9cm/min.
(4) construction main building support column 6;
(5) middle part girder truss 4 and the truss web 5 of main building first support system is done, annulus support 3 of then constructing; Carry out construction angle brace 11 again;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss 4 and the truss web 5 of main building second support system is done, annulus support 3 of then constructing; Carry out construction angle brace 11 again;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss 4 and the truss web 5 of main building the 3rd road support system is done, annulus support 3 of then constructing; Carry out construction angle brace 11 again;
(10) earth excavation is to main building basement bottom board, builds basement bottom board concrete;
(11) remove the 3rd road support in girder truss 4 and truss web 5 and annulus support 3 and angle brace 11;
(12) the 3rd road support zone basement floorslab concrete is built;
(13) remove second support in girder truss 4 and truss web 5 and annulus support 3 and angle brace 11;
(14) second support zone basement floorslab concrete is built;
(15) main building basement roof concrete is built;
(16) annex concrete roof is built, indwelling soil outlet 10;
(17) excavate the annex earthwork to one deck basement floor, build basement floorslab concrete;
Soil excavation carries out according to " subregion, point title, balance " principle; Soil excavation level of approximation in hole is declined, guarantees support system uniform stressed, prevent the outer unstability of support system plane.
(18) excavate the annex earthwork to two layer basement floor, build basement floorslab concrete;
(19) excavate the annex earthwork to three layer basement floor, build basement floorslab concrete;
(20) excavate the annex earthwork to three layer basement bottom board position, build underplate concrete.
Through this basement of Site Detection Stability Analysis of Structures in work progress, main building supporting displacement is no more than 13mm, and annex supporting displacement is no more than 10mm, and support beam structure is stablized, and phenomenon without exception occurs.

Claims (5)

1. the main building basement supporting and protection structure with annex, it is characterized in that between main building and annex, arranging interim enclosure wall, interim enclosure wall width is 700 ~ 900mm, the interim enclosure wall degree of depth is 1.5 ~ 2 times of foundation depth, interim enclosure wall concrete strength be C30 or more than, main building enclosure wall not only has supporting performance to double as outer wall of basement, main building enclosure wall width is 700 ~ 900mm, the main building enclosure wall degree of depth is 1.8 ~ 2.5 times of foundation depth, main building enclosure wall concrete strength be C30 or more than; Annex enclosure wall width is 700 ~ 900mm, and the annex enclosure wall degree of depth is 1.8 ~ 2.5 times of foundation depth, annex enclosure wall concrete strength be C30 or more than; Main building enclosure wall and annex enclosure wall handing-over position arranged outside 2 high-pressure rotary jet grouting piles, solve the seepage problem of antiseepage weak part; At main building enclosure wall, annex enclosure wall with go along with sb. to guard him wall chase section seam crossing and adopt 2 high-pressure rotary jet grouting piles to squeegee as antiseepage temporarily, main building enclosure wall rotation angle position and annex enclosure wall rotation angle position also arrange 2 high-pressure rotary jet grouting piles; Main building enclosure wall, annex enclosure wall and interim enclosure wall crossover sites arrange steel plate water stopper, steel plate water-stopping tape thickness is 3 ~ 5mm, arranges annulus support inside main building enclosure wall, and annulus support width is 500 ~ 700mm, be highly 700 ~ 900mm, annulus support concrete strength be C30 or more than; Arrange angle brace between annulus support and main building enclosure wall, angle brace adopts concrete support or steel support; Arrange truss support system in the middle part of main building enclosure wall, truss support system comprises girder truss and truss web; Girder truss width is 400 ~ 600mm, is highly 500 ~ 700mm, girder truss concrete strength be C30 or more than, truss web width is 300 ~ 500mm, is highly 500 ~ 700mm, truss web concrete strength be C30 or more than; Girder truss bottom arranges support column to maintain Stability in Plane, and support column adopts steel column, and steel column adopts two channel-section steels to be spliced, and steel column inserts bored pile; Annex top board indwelling soil outlet, annex soil outlet area is 30 ~ 100m 2, the stress state that turned welt beam improves bight is set up in soil outlet corner, turns under turned welt beam, and turned welt depth of beam is 250 ~ 300mm, and width is 200mm; Annex arranges a soil outlet every 50 ~ 70m, and soil outlet is arranged on the region that punches of elevator & stairs and structure design as far as possible; Compaction grouting process is carried out in depths, the local such as elevator shaft, collecting well, and slip casting width is 3m, and slip casting thickness is 5m.
2. the main building basement supporting and protection structure of band annex according to claim 1, is characterized in that construction sequence comprises:
(1) construction main building enclosure wall, pre-embedded steel slab waterstop;
(2) construction annex enclosure wall and interim enclosure wall;
(3) construction high-pressure rotary jet grouting pile;
(4) construction main building support column;
(5) middle part girder truss and the truss web of main building first support system is done, annulus support of then constructing; Carry out construction angle brace again;
(6) earth excavation supports to second and arranges position;
(7) middle part girder truss and the truss web of main building second support system is done, annulus support of then constructing; Carry out construction angle brace again;
(8) earth excavation supports to the 3rd road and arranges position;
(9) middle part girder truss and the truss web of main building the 3rd road support system is done, annulus support of then constructing; Carry out construction angle brace again;
(10) earth excavation is to main building basement bottom board, builds basement bottom board concrete;
(11) remove the 3rd road support in girder truss and truss web and annulus support and angle brace;
(12) the 3rd road support zone basement floorslab concrete is built;
(13) remove second support in girder truss and truss web and annulus support and angle brace;
(14) second support zone basement floorslab concrete is built;
(15) main building basement roof concrete is built;
(16) annex concrete roof is built, indwelling soil outlet;
(17) excavate the annex earthwork to one deck basement floor, build basement floorslab concrete;
Soil excavation carries out according to " subregion, point title, balance " principle; Soil excavation level of approximation in hole is declined, guarantees support system uniform stressed, prevent the outer unstability of support system plane;
(18) excavate the annex earthwork to two layer basement floor, build basement floorslab concrete;
(19) excavate the annex earthwork to three layer basement floor, build basement floorslab concrete;
(20) excavate the annex earthwork to three layer basement bottom board position, build underplate concrete.
3. the main building basement supporting and protection structure of band annex according to claim 1, it is characterized in that rotary churning pile rig adopts hydraulic power head, unit head is moved on king-tower by the elevator machine travel that works, the revolution of unit head is driven through reduction box by fluid power motor, realize the swing of revolution and different angles, utilize rig that the Grouting Pipe with special nozzle is drilled into soil layer precalculated position, make slurries become high-pressure spray with high-tension apparatus to penetrate from nozzle, slurries are sprayed on lifting limit, rotation limit, limit, make slurries and grogs Forced Mixing, after grout cures, in soil, form induration; Rotary churning pile slip casting form adopts to swing sprays.
4. the main building basement supporting and protection structure of band annex according to claim 1, is characterized in that high-pressure water pressure is 30MPa, flow 90L/min; Compressed air pressure is 0.6 ~ 0.8MPa, and flow is 6m 3/ h; Cement paste pressure is 5MPa, and flow is 80 ~ 100L/min.Cement slurry density is 1.60g/cm, and cement paste water/binder ratio is 0.8; 30m is that 6 ~ 8cm/min, more than 30m position hoisting velocity is for 8 ~ 10cm/min with lower portion hoisting velocity.
5. the main building basement supporting and protection structure of band annex according to claim 1, after it is characterized in that treating basement construction, pastes malthoid inside main building enclosure wall, does bricking wall inside malthoid, to meet basement antiseepage requirement.
CN201510309657.0A 2015-05-29 2015-05-29 Main building basement supporting construction with annex Active CN104878763B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610442856.3A CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex
CN201510309657.0A CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510309657.0A CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201610442856.3A Division CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex

Publications (2)

Publication Number Publication Date
CN104878763A true CN104878763A (en) 2015-09-02
CN104878763B CN104878763B (en) 2016-08-24

Family

ID=53946424

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510309657.0A Active CN104878763B (en) 2015-05-29 2015-05-29 Main building basement supporting construction with annex
CN201610442856.3A Active CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610442856.3A Active CN106149731B (en) 2015-05-29 2015-05-29 Main building basement construction method for supporting with annex

Country Status (1)

Country Link
CN (2) CN104878763B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804085A (en) * 2016-04-19 2016-07-27 江苏东合南岩土科技股份有限公司 Divisional construction method of multi-unit shaft-type underground stereo garage
CN111042099A (en) * 2019-12-19 2020-04-21 中国地质大学(武汉) Water collecting well with replaceable water filtering structure
CN111270684A (en) * 2020-03-24 2020-06-12 中铁第四勘察设计院集团有限公司 Disassembly-free support rod piece, foundation pit supporting system and construction method of subway station

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060059812A1 (en) * 2004-08-30 2006-03-23 Simmons Robert J Column base to podium slab anchoring
WO2006026384A2 (en) * 2004-08-30 2006-03-09 Simmons Robert J Column base to podium slab anchoring
CN100582383C (en) * 2005-12-05 2010-01-20 黄威力 Construction method of setting site for pile base and structure in foundation pit
CN101666095B (en) * 2009-09-11 2011-11-23 温州市金誉建设监理有限公司 Irregular foundation pit support and construction method
CN101718094B (en) * 2009-11-10 2011-02-02 朱奎 Construction method for retaining and protecting foundation pit of building with basemen
CN102383433A (en) * 2011-08-22 2012-03-21 同济大学建筑设计研究院(集团)有限公司 Design method for large deep foundation pit of super high-rise building
CN102505695B (en) * 2011-10-09 2014-12-03 浙江荣邦房地产开发有限公司 Construction method for deep foundation pit of three-dimensional garage
CN103306304A (en) * 2013-06-19 2013-09-18 泰兴市第一建筑安装工程有限公司 Basic structure of construction elevator

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804085A (en) * 2016-04-19 2016-07-27 江苏东合南岩土科技股份有限公司 Divisional construction method of multi-unit shaft-type underground stereo garage
CN111042099A (en) * 2019-12-19 2020-04-21 中国地质大学(武汉) Water collecting well with replaceable water filtering structure
CN111270684A (en) * 2020-03-24 2020-06-12 中铁第四勘察设计院集团有限公司 Disassembly-free support rod piece, foundation pit supporting system and construction method of subway station

Also Published As

Publication number Publication date
CN106149731B (en) 2018-08-10
CN104878763B (en) 2016-08-24
CN106149731A (en) 2016-11-23

Similar Documents

Publication Publication Date Title
CN106223360B (en) Using the open cut cast in place and precast construction subway station construction method of stake supporting system
CN205742213U (en) Foundation pit supporting construction
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN104963689A (en) Three-step seven-procedure excavation method for tunnel
CN103088830A (en) Construction method for composite outer wall structure of ultra-deep basement
CN111119904A (en) Construction method of soft surrounding rock karst section tunnel
CN112253162A (en) Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
CN106149731B (en) Main building basement construction method for supporting with annex
CN101560766A (en) Grid-like underground continuous wall plate and production method thereof
CN203160254U (en) Pit support structure
CN105386779B (en) The counterfort method of large underground structure is built in shallow embedding rock stratum
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN104695446B (en) Basement construction method for supporting
CN101725147A (en) Construction process of first-inserting last-jetting type steel churning pile enclosing structure under low net space
CN115467690B (en) New structure system of shallow-buried large-span underground excavation subway station and construction method thereof
CN216339582U (en) Combined inclined support for foundation pit support
CN116464060A (en) Construction method for accelerating high-span region structure at high-low span position of basement bottom plate
CN206873459U (en) A kind of large-span steel-reinforced concrete foundation ditch support system
CN107012948A (en) A kind of basement floor building structural and its construction method
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN106917331A (en) The road structure and its construction method of a kind of deep-lying karst area water sealing consolidation
CN204982907U (en) Take main building basement of annex to strut structure
CN209742904U (en) Solidification structure suitable for rich water collapsible loess tunnel
CN110258675B (en) Reinforcing and correcting method for strip foundation box type composite foundation of building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 236000 Room 403, unit 2, building 3, Chengmei jadeite mansion, Zhenge North Road, Yingshang County, Fuyang City, Anhui Province

Patentee after: Zhu Kui

Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39

Patentee before: Zhu Kui

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39

Patentee after: Zhu Kui

Address before: 236000 Room 403, unit 2, building 3, Chengmei jadeite mansion, Zhenge North Road, Yingshang County, Fuyang City, Anhui Province

Patentee before: Zhu Kui

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhu Kui

Inventor after: Zhang Longxing

Inventor before: Zhu Kui

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201105

Address after: Room c3009, third floor, new Bund Fuxing City, No.32 Binhai Avenue, Binhai street, Longhua District, Haikou City, Hainan Province 570105

Patentee after: HAINAN WANTAI BUILDING ENGINEERING Co.,Ltd.

Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39

Patentee before: Zhu Kui