CN106917331A - The road structure and its construction method of a kind of deep-lying karst area water sealing consolidation - Google Patents

The road structure and its construction method of a kind of deep-lying karst area water sealing consolidation Download PDF

Info

Publication number
CN106917331A
CN106917331A CN201710259214.4A CN201710259214A CN106917331A CN 106917331 A CN106917331 A CN 106917331A CN 201710259214 A CN201710259214 A CN 201710259214A CN 106917331 A CN106917331 A CN 106917331A
Authority
CN
China
Prior art keywords
slurries
solution cavity
road structure
lying
deep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710259214.4A
Other languages
Chinese (zh)
Other versions
CN106917331B (en
Inventor
何忠明
杨煜
吴贺鹏
杨卓栋
范海山
刘帅
李奕瑯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201710259214.4A priority Critical patent/CN106917331B/en
Publication of CN106917331A publication Critical patent/CN106917331A/en
Application granted granted Critical
Publication of CN106917331B publication Critical patent/CN106917331B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/34Foundations for sinking or earthquake territories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Hydrology & Water Resources (AREA)
  • Architecture (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of road structure of deep-lying karst area water sealing consolidation, it mainly includes:Roadbed (1), concrete cast-in-place slab (2), drilling (3), slurries radiation area (4), current (5), prestressing force longeron (6), solution cavity (7), isolated footing (8), prestressed cross beams (9), Grouting Pipe (12), slurries radiating aperture (13);The present invention is first isolated current (5) with solution cavity (7) by slurries radiation area (4) using curtain grouting technology, to prevent the development of solution cavity;Then in solution cavity (7) top roadbed region using prestressing force longeron (6), prestressed cross beams (9) for the pressure that supports roadbed (1) to be applied on concrete cast-in-place slab (2), while by isolated footing (8) for prestressed girder provides support force;The present invention can effectively punish large-scale solution cavity of the depth more than 10m, while current can effectively be separated, prevent the development of solution cavity, it is ensured that the stability of road structure, and simple, economic and reliable of constructing, and have broad application prospects.

Description

The road structure and its construction method of a kind of deep-lying karst area water sealing consolidation
Technical field
The present invention relates to the road engineering technical field in civil engineering, particularly with regard to a kind of deep-lying karst area sealing The road structure and its construction method of reinforcing.
Background technology
In road project, some karst regions are inevitably passed through, solution cavity is one of karst region most typically harm, Construction to road causes serious threat;Collapsing for solution cavity will cause property to damage to engineering that is built or building Lose, or even injure personal safety, huge negative effect is caused to society, karst collapse has become karst area mainly pacifies One of full hidden danger.The formation of solution cavity is the result that is formed of erosion of the water received for a long time by limestone, and limestone is in water and titanium dioxide Calcium bicarbonate is generated in the presence of carbon soluble in water, then solution cavity forms and constantly develops and expand.Traditional solution cavity administers skill Art mainly has:Slip casting, rockfill, pile foundation etc., slurry injection technique is only applicable to small-sized solution cavity, and slip casting expense is carried out to large-scale solution cavity Costliness, and technical operation is complicated;The Treating technology that rockfills is only applicable to shallow solution cavity, and for deeper solution cavity, digging process is cumbersome, And workload is huge, and certain destruction is caused to local environment;Pile foundation as a kind of conventional punishment solution cavity technology, Its technical requirements is higher, and pile foundation position can not efficiently be laid, while the continuous erosion with current to solution cavity, The development of solution cavity certainly will be caused to expand, original pile foundation can not effectively maintain the long-time stability of road structure.
The content of the invention
For problem above, road structure and its construction the invention discloses a kind of deep-lying karst area water sealing consolidation Method:The road structure mainly include roadbed (1), concrete cast-in-place slab (2), drilling (3), slurries radiation area (4), current (5), Prestressing force longeron (6), solution cavity (7), isolated footing (8), prestressed cross beams (9), Grouting Pipe (12), slurries radiating aperture (13);Its In, described prestressed cross beams (9) and prestressing force longeron (6) are interlaced, in sphere of movements for the elephants shape lay, prestressed girder two ends with Isolated footing (8) is connected;Concrete cast-in-place slab (2) is between prestressed girder and roadbed (1).
The road structure and its construction method of a kind of described deep-lying karst area water sealing consolidation, it is characterised in that institute The drilling (3) stated is sprayed by slurries radiating aperture (13) from Grouting Pipe (12) between current (5) and solution cavity (7) to surrounding Slip casting forms slurries radiation area (4).
The road structure and its construction method of a kind of described deep-lying karst area water sealing consolidation, it is characterised in that institute The concrete strength that the concrete cast-in-place slab (2) and prestressed girder and isolated footing (8) stated are used is C30, described drilling (3) diameter D=100mm, Grouting Pipe (12) diameter D=30mm, slurries radiation area (13) radius R=1.5m, the slip casting of use is initially pressed Power is 1 ~ 3MPa, and final grouting pressure is 6 ~ 8MPa.
The road structure and its construction method of a kind of described deep-lying karst area water sealing consolidation, it is characterised in that institute The curtain-grouting material stated uses Portland cement list slurries, double slurries and chemical pulp, is aided with superfine cement and waterglass Double slurries, ratio of mud W:C=0.6:1~0.8:1, while adding a certain amount of additive(Waterproofing agent, accelerator, swelling agent etc.), According to the performance requirement under different condition, the various performance indications of slurries are adjusted.
Beneficial effect of the present invention:The steady in a long-term of road structure can not only effectively be ensured using above road structure Property, and the development again of solution cavity can also be prevented, release threat of the solution cavity to road project;Present invention use plate-beam- Isolated footing is structure as a whole, and the power that road surface is applied to roadbed is dexterously disperseed to give each isolated footing, it is ensured that solution cavity is not Disturbed by external force;Prestressing force longeron and prestressed cross beams intersect, the pressure that common support cast in place concrete plate applies, and And use prestressed girder simple structure, material-saving to install simple;The present invention is noted between current and solution cavity using curtain simultaneously Slurry technology, erosion of the cut-off current to solution cavity, has saved grouting cost and working procedure;Can efficiently, accurately administer karst The harm in area.
Brief description of the drawings
Fig. 1 is the road structure schematic diagram of specific implementation process of the present invention
Fig. 2 is the plan of road structure of the present invention
Fig. 3 is slip casting procedure structure schematic diagram of the present invention
Fig. 4 is bored grouting process chart of the present invention
Description of reference numerals:1. roadbed, 2. concrete cast-in-place slab, 3. drilling, 4. slurries radiation area, 5. current, 6. in advance should Power longeron, 7. solution cavity, 8. isolated footing, 9. prestressed cross beams, 10. steel pipe, 11. sandstones, 12. Grouting Pipes, 13. slurries Radiating aperture.
Specific embodiment
Road structure of the present invention and implementation steps are described further below in conjunction with the accompanying drawings.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of road structure of deep-lying karst area water sealing consolidation of the invention and its construction Method, the road structure include roadbed (1), concrete cast-in-place slab (2), drilling (3), slurries radiation area (4), current (5), in advance should Power longeron (6), solution cavity (7), isolated footing (8), prestressed cross beams (9), steel pipe (10), sandstone (11), Grouting Pipe (12), slurries Radiating aperture (13);Wherein described prestressed cross beams (9) and prestressing force longeron (6) are interlaced, are laid in sphere of movements for the elephants shape, in advance should Casting concrete Bars In Poured Concrete Slab (2) above power beam, by isolated footing (8) for prestressed girder provides holding power;In Grouting Pipe (12) Slurries are sprayed by slurries radiating aperture (13) to surrounding, form slurries radiating aperture (13);Described curtain grouting technology uses Fig. 4 Grouting process.
Or the 1st, in road construction project Road Detection project, first using high-density electric, geological radar technology, hole The advanced detection techniques such as interior acoustic CT technology, determine the particular location and size of solution cavity (7), while determining the position of current (5) And flow direction.
2nd, after determining the particular location of solution cavity (7) and current (5), using curtain grouting technology in current (5) and solution cavity (7) Between drilled (3), drilling (3) in Grouting Pipe (12) by slurry material by slurries radiating aperture (13) to surrounding spray, Form slurries radiation area (4), isolation current (5).
3rd, the bored grouting equipment that uses as shown in figure 3, grouting process is as shown in figure 4, slip casting initial pressure is 1 ~ 3MPa, Final grouting pressure is 6 ~ 8MPa, first note single liquid cement mortar, afterwards note dual slurry, whole process work as slip casting through using chemical pulp, if When effect is not up to actual requirement, supplement slip casting should be carried out to its region, reach anti-, draining requirement.
4th, cleaning solution cavity (7) top roadbed (1) region, and flattened, be compacted, lay prestressed cross beams (9) and in advance should Power longeron (6) so that prestressed girder is interlaced, is laid in sphere of movements for the elephants shape, and at prestressed girder two ends, depth below is buried Isolated footing (8), prestressed cross beams (9) and prestressing force longeron (6) are connected with each other with basic (8).
5th, prestressed material marched into the arena first, resetted, counterdie is installed in the advance position laid, according to the spy of component load-bearing Point assembling reinforcement, and bellows is installed, prestressed cross beams (9) reinforcing bar and longeron (6) reinforcing bar are interlaced, in sphere of movements for the elephants shape cloth If then, longeron horizontal to prestressing force together carries out casting concrete, and is conserved, and prestressed stretch-draw is finally carried out, before tensioning Carry out anchorage inspection, equipment calibration and check concrete quality, after the completion of prestressed stretch-draw, slurry seal, sealing off and covering anchorage are carried out to duct.
6 and then concrete cast-in-place slab (2) is laid on prestressed cross beams (9) and prestressing force longeron (6) top, and to coagulation Native Bars In Poured Concrete Slab (2) carries out maintenance treatment, illustrates that part is not prior art known to those skilled in the art in detail herein.

Claims (4)

1. the road structure and its construction method of a kind of deep-lying karst area water sealing consolidation, it is characterised in that the road structure Mainly include:Roadbed (1), concrete cast-in-place slab (2), drilling (3), slurries radiation area (4), current (5), prestressing force longeron (6), Solution cavity (7), isolated footing (8), prestressed cross beams (9), Grouting Pipe (12), slurries radiating aperture (13);Wherein, described prestressing force Crossbeam (9) and prestressing force longeron (6) are interlaced, in sphere of movements for the elephants shape lay, prestressed girder two ends with isolated footing (8) phase Even;Concrete cast-in-place slab (2) is between prestressed girder and roadbed (1).
2. the road structure and its construction method of a kind of deep-lying karst area according to claim 1 water sealing consolidation, its Be characterised by, described drilling (3) between current (5) and solution cavity (7), by Grouting Pipe (12) by slurries radiating aperture (13) Slurries radiation area (4) are formed to surrounding jet groutinl.
3. the road structure and its construction method of a kind of deep-lying karst area according to claim 1 water sealing consolidation, its It is characterised by, the concrete strength that described concrete cast-in-place slab (2) and prestressed girder and isolated footing (8) are used is C30, Drilling (3) diameter D=100mm of use, Grouting Pipe (12) diameter D=30mm, slurries radiation area (13) radius R=1.5m, use Slip casting initial pressure is 1 ~ 3MPa, and final grouting pressure is 6 ~ 8MPa.
4. the road structure and its construction method of a kind of deep-lying karst area according to claim 1 water sealing consolidation, its It is characterised by, described curtain-grouting material uses Portland cement list slurries, double slurries and chemical pulp, is aided with ultra-fine water Mud and the double slurries of waterglass, ratio of mud W:C=0.6:1~0.8:1, while adding a certain amount of additive(Waterproofing agent, accelerator, Swelling agent etc.), according to the performance requirement under different condition, adjust the various performance indications of slurries.
CN201710259214.4A 2017-04-20 2017-04-20 Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof Expired - Fee Related CN106917331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710259214.4A CN106917331B (en) 2017-04-20 2017-04-20 Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710259214.4A CN106917331B (en) 2017-04-20 2017-04-20 Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof

Publications (2)

Publication Number Publication Date
CN106917331A true CN106917331A (en) 2017-07-04
CN106917331B CN106917331B (en) 2020-04-07

Family

ID=59568147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710259214.4A Expired - Fee Related CN106917331B (en) 2017-04-20 2017-04-20 Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof

Country Status (1)

Country Link
CN (1) CN106917331B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166471A (en) * 2017-12-28 2018-06-15 中建六局土木工程有限公司 A kind of complicated geological converts beam construction method
CN112982051A (en) * 2021-02-20 2021-06-18 温俊魁 Roadbed suitable for karst landform and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102080382A (en) * 2010-11-30 2011-06-01 济南大学 Building foundation adaptable to goaf foundation deformation
CN202247575U (en) * 2011-09-09 2012-05-30 中铁二院工程集团有限责任公司 Structure for strengthening roadbed in high-speed railway station turnout area with highly developed karst
CN105696427A (en) * 2016-04-06 2016-06-22 中铁第四勘察设计院集团有限公司 Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof
CN206736650U (en) * 2017-04-20 2017-12-12 长沙理工大学 A kind of road structure of deep-lying karst area water sealing consolidation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102080382A (en) * 2010-11-30 2011-06-01 济南大学 Building foundation adaptable to goaf foundation deformation
CN202247575U (en) * 2011-09-09 2012-05-30 中铁二院工程集团有限责任公司 Structure for strengthening roadbed in high-speed railway station turnout area with highly developed karst
CN105696427A (en) * 2016-04-06 2016-06-22 中铁第四勘察设计院集团有限公司 Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof
CN206736650U (en) * 2017-04-20 2017-12-12 长沙理工大学 A kind of road structure of deep-lying karst area water sealing consolidation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166471A (en) * 2017-12-28 2018-06-15 中建六局土木工程有限公司 A kind of complicated geological converts beam construction method
CN108166471B (en) * 2017-12-28 2019-12-27 中建六局土木工程有限公司 Construction method of complicated geological transfer beam
CN112982051A (en) * 2021-02-20 2021-06-18 温俊魁 Roadbed suitable for karst landform and construction method
CN112982051B (en) * 2021-02-20 2024-04-26 温俊魁 Roadbed suitable for karst landform and construction method

Also Published As

Publication number Publication date
CN106917331B (en) 2020-04-07

Similar Documents

Publication Publication Date Title
Cui et al. Mitigation of geohazards during deep excavations in karst regions with caverns: a case study
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN109538216B (en) Tunnel construction process for crossing mining and subsidence areas
CN108252719B (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN110566223B (en) Deep-buried PBA subway station section design method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN111365005A (en) Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation
CN102296631A (en) Top-down construction method of cyclone well
RU2291253C1 (en) Method for existent building, building structure and underground service line protection in construction affected zone
CN206736650U (en) A kind of road structure of deep-lying karst area water sealing consolidation
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN106917331A (en) The road structure and its construction method of a kind of deep-lying karst area water sealing consolidation
CN102535518B (en) Plugging method of large seam of underground diaphragm wall
CN207176700U (en) A kind of solid matter perfusion inner support of pile foundation ditch permanent support structure under complex environment
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN109024609A (en) A kind of foundation pit supporting construction and its construction method based on old campshed
CN107191196A (en) Through the anti-skidding shearing resistance administration structure of the inter-laminar dislocation band of great burying underground chamber and construction method
RU2685607C1 (en) Method for safe undermining of ground objects by an underground structure in complex engineering-geological conditions
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN207177912U (en) Through the anti-skidding shearing resistance administration structure of the inter-laminar dislocation band of great burying underground chamber
CN207846429U (en) A kind of phreatic high, high basement rock go out the foundation pit supporting system shown up
CN104878763B (en) Main building basement supporting construction with annex
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200407

Termination date: 20210420

CF01 Termination of patent right due to non-payment of annual fee