CN106120563A - Cast-in-situ box girder Combined movable mould bases and construction method thereof - Google Patents
Cast-in-situ box girder Combined movable mould bases and construction method thereof Download PDFInfo
- Publication number
- CN106120563A CN106120563A CN201610551185.4A CN201610551185A CN106120563A CN 106120563 A CN106120563 A CN 106120563A CN 201610551185 A CN201610551185 A CN 201610551185A CN 106120563 A CN106120563 A CN 106120563A
- Authority
- CN
- China
- Prior art keywords
- traversing
- jack
- platform
- longitudinal
- bailey beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种现浇箱梁复合式移动模架,属于房屋建筑工程领域,尤其涉及一种基于复合式移动模架现浇箱梁的施工方法。The invention relates to a composite mobile formwork for a cast-in-place box girder, which belongs to the field of building construction engineering, and in particular to a construction method for a cast-in-place box girder based on a composite mobile formwork.
背景技术Background technique
预应力混凝土梁桥在我国中小跨径桥梁中占据主导地位,其施工方法除常用的满铺支架法逐孔浇筑、整孔预制架设外,还大量采用移动模架逐孔浇筑,有力促进了桥梁施工的机械化进程。Prestressed concrete girder bridges occupy a dominant position in my country's small and medium-span bridges. In addition to the commonly used full pavement method of pouring hole by hole and whole hole prefabricated erection, the construction method also uses a large number of mobile formwork to pour hole by hole, which effectively promotes bridge construction. The mechanization process of construction.
传统现浇箱梁支撑模架适应性不强、施工效率低、模架及模板支架需要重复拆除。为适应预应力混凝土梁不同的结构体系和构造特征,各具特色的新型移动模架纷纷涌现,梁模合一型移动模架就是其中的一种。The traditional cast-in-place box girder supporting formwork has poor adaptability, low construction efficiency, and the formwork and formwork brackets need to be removed repeatedly. In order to adapt to the different structural systems and structural characteristics of prestressed concrete beams, new mobile formworks with different characteristics have emerged one after another, and the beam-mold-integrated mobile formwork is one of them.
发明内容Contents of the invention
本发明的目的在于针对传统现浇箱梁支撑模架适应性不强、施工效率低、模架及模板支架需要重复拆除等缺点,提出了一种现浇箱梁复合式移动模架及其施工方法,该现浇箱梁复合式移动模架包括可移动纵向贝雷梁、可分离式模板与模架合一移动模架、纵移和横移轨道等复合式移动模架。The purpose of the present invention is to propose a cast-in-place box girder composite mobile formwork and its construction in view of the shortcomings of the traditional cast-in-place box girder support formwork, such as poor adaptability, low construction efficiency, and repeated removal of the formwork and formwork brackets. According to the method, the cast-in-place box girder composite mobile formwork includes a movable longitudinal Bailey beam, a detachable formwork and a formwork integrated mobile formwork, and a composite mobile formwork such as longitudinal and lateral movement tracks.
为了实现上述技术目的,本发明采用了以下技术方案:In order to realize above-mentioned technical purpose, the present invention adopts following technical scheme:
现浇箱梁复合式移动模架,其特征在于,所述复合式移动模架主要包括:牛腿支撑托架、横移轨道、滑轮组平台、纵向贝雷梁、横向贝雷梁、外模支架、横移平台、横移千斤顶A、纵移千斤顶和横移千斤顶B;牛腿支撑托架上设置横移轨道,横移轨道外侧设置限位块A;滑轮组平台放置在横移轨道上,滑轮组平台上面设置纵向滑轮A;纵向贝雷梁放置在滑轮组平台上,纵向贝雷梁上设置横移平台轨道;外模支架底部设置横移平台,外模支架放置在横移平台轨道上;纵向贝雷梁与横向贝雷梁铰接固定连接在一起。The cast-in-place box girder composite mobile formwork is characterized in that the composite mobile formwork mainly includes: corbel support brackets, traversing tracks, pulley block platforms, longitudinal Bailey beams, transverse Bailey beams, and outer mold supports , traversing platform, traversing jack A, longitudinal jack and traversing jack B; the traversing track is set on the corbel support bracket, and the limit block A is set on the outside of the traversing track; the pulley block platform is placed on the traversing track, and the pulley block The longitudinal pulley A is set on the platform; the longitudinal Bailey beam is placed on the pulley block platform, and the traverse platform track is set on the longitudinal Bailey beam; the traverse platform is arranged at the bottom of the outer mold support, and the outer mold support is placed on the traverse platform track; The thunder beam is hinged and fixedly connected with the transverse Bailey beam.
所述的滑轮组平台与横移轨道侧面设置横移千斤顶A,横移千斤顶A一端通过连接件A固定在滑轮组平台,另一端通过连接件B固定在横移轨道。A traversing jack A is arranged on the side of the pulley block platform and the traversing track, and one end of the traversing jack A is fixed on the pulley block platform through a connecting piece A, and the other end is fixed on the traversing track through a connecting piece B.
所述的牛腿支撑托架通过预埋件固定在墩柱上并配合墩旁托架拉杆将对侧牛腿支撑托架对拉在一起。The corbel support brackets are fixed on the pier columns through embedded parts and cooperate with the bracket pull rods beside the pier to pull the pairs of corbel support brackets on opposite sides together.
所述的滑轮组平台与纵向贝雷梁之间设置千斤顶。A jack is arranged between the pulley block platform and the longitudinal Bailey beam.
所述的纵向贝雷梁底部设置纵移导轨梁。The longitudinal guide rail beam is arranged at the bottom of the longitudinal Bailey beam.
所述的纵向贝雷梁底部纵向方向设置纵移千斤顶;纵移千斤顶底座固定在滑轮组平台上,另一端通过连接件E固定在纵移导轨梁上。A longitudinal jack is arranged at the bottom of the longitudinal Bailey beam; the base of the longitudinal jack is fixed on the pulley block platform, and the other end is fixed on the longitudinal guide rail beam through the connector E.
所述的横移平台底部设置横移千斤顶B,横移千斤顶B一端通过连接件C固定在横移平台,另一端通过连接件D固定在横移平台轨道上。A traversing jack B is arranged at the bottom of the traversing platform, and one end of the traversing jack B is fixed on the traversing platform through a connecting piece C, and the other end is fixed on the track of the traversing platform through a connecting piece D.
所述的外模支架为两侧对称分离式结构,两侧底模板通过螺栓固定在一起。The outer mold support is a two-sided symmetrical and separated structure, and the bottom templates on both sides are fixed together by bolts.
所述的横向贝雷梁顶部设置支撑螺旋顶,支撑螺旋顶上设置垫块。A supporting spiral top is provided on the top of the transverse Bailey beam, and cushion blocks are arranged on the supporting spiral top.
基于复合式移动模架现浇箱梁的施工方法,其特征在于包括以下步骤:The construction method based on the composite mobile formwork cast-in-place box girder is characterized in that it comprises the following steps:
步骤一、牛腿支撑托架安装:根据设计要求在墩柱指定位置预埋预埋件,待墩柱强度达到设计要求后,将牛腿支撑托架通过预埋件固定在墩柱上并配合墩旁托架拉杆进一步固定牛腿支撑托架;Step 1. Installation of corbel support bracket: according to the design requirements, pre-embed the embedded parts at the designated position of the pier column. After the strength of the pier column meets the design requirements, fix the corbel support bracket on the pier column through the embedded parts and cooperate The bracket pull rod beside the pier further fixes the corbel support bracket;
步骤二、横移平台安装:先将横移轨道通过螺栓固定在牛腿支撑托架,然后将平台滑轮组放置在横移轨道上,将横移千斤顶A安装就位;Step 2. Installation of the traversing platform: first fix the traversing track to the corbel support bracket through bolts, then place the platform pulley block on the traversing track, and install the traversing jack A in place;
步骤三、贝雷梁安装:纵向贝雷梁和横向贝雷梁预先在地面组装好,通过吊车将纵向贝雷梁吊至滑轮组平台上,底部设置顶升千斤顶和纵移千斤顶,待两侧纵向贝雷梁安装就位后,将横向贝雷梁吊装至指定位置通过铰接接头与纵向贝雷梁连接;Step 3. Bailey beam installation: the longitudinal Bailey beam and the transverse Bailey beam are pre-assembled on the ground, and the longitudinal Bailey beam is hoisted to the pulley block platform by a crane. After the Bailey beam is installed in place, the horizontal Bailey beam is hoisted to the designated position and connected with the longitudinal Bailey beam through a hinged joint;
步骤四、模架安装:根据设计要求在纵向贝雷梁上焊接横移平台轨道,将预先制作好的外模支架吊装至横移平台轨道上,控制横移千斤顶A至指定位置后再控制横移千斤顶B将外模支架向内侧横移至指定位置,通过螺栓将两侧的外模支架固定在一起,控制千斤顶使整体结构顶升至指定位置并调节支撑螺旋顶使其受力;Step 4. Formwork installation: Weld the traverse platform track on the longitudinal Bailey beam according to the design requirements, hoist the prefabricated outer mold support onto the traverse platform track, control the traverse jack A to the designated position and then control the traverse Move the jack B to move the outer mold bracket inward to the specified position, fix the outer mold brackets on both sides together with bolts, control the jack to lift the whole structure to the specified position and adjust the supporting screw top to make it bear the force;
步骤五、钢筋笼吊装及混凝土浇筑:将预先绑扎成型的钢筋笼吊装至模板内,待内模全部安装完毕后浇筑混凝土并养护;Step 5, hoisting of reinforcement cage and concrete pouring: hoist the pre-bound reinforcement cage into the formwork, pour concrete and maintain it after all the inner molds are installed;
步骤六、拆模:待养护达到设计要求后,控制千斤顶收缩使其整体结构下降,在重力的作用下使其自动脱模,然后拆除两侧外模支架间的所有连接螺栓,再控制横移千斤顶B使外模支架移动至指定位置。Step 6. Formwork removal: After the maintenance meets the design requirements, control the shrinkage of the jack to lower the overall structure, and automatically demould it under the action of gravity, then remove all the connecting bolts between the outer mold supports on both sides, and then control the lateral movement Jack B moves the outer mold support to the designated position.
步骤七、过孔及下一段箱梁施工:拆除铰接接头并配合牵引钢丝绳使其与一侧纵向贝雷梁分离,牵引至另一侧纵向贝雷梁并临时固定,控制横移千斤顶A使滑轮组平台横移至指定位置,再控制纵移千斤顶使纵向贝雷梁纵移实现过孔,过孔至指定位置后进行下一段箱梁施工。Step 7. Construction of the via hole and the next section of box girder: Remove the hinged joint and cooperate with the traction wire rope to separate it from the longitudinal Bailey beam on one side, pull it to the longitudinal Bailey beam on the other side and fix it temporarily, and control the traverse jack A to make the pulley block The platform moves horizontally to the designated position, and then controls the longitudinal jack to move the vertical Bailey beam to realize the passage. After passing the hole to the designated position, the next section of box girder construction will start.
本发明具有以下特点和有益效果:The present invention has following characteristics and beneficial effect:
(1)模板与支架合一,两侧模架拆除时可以分离,可实现模架顺利过孔。(1) The formwork and the bracket are integrated, and the formwork on both sides can be separated when it is removed, so that the formwork can pass through the hole smoothly.
(2)贝雷主梁放置在纵移平台上,通过控制千斤顶可实现贝雷主梁纵移,不需要对贝雷主梁进行重复拆除。(2) The Bailey main beam is placed on the longitudinal movement platform, and the Bailey main beam can be moved longitudinally by controlling the jack, without repeated demolition of the Bailey main beam.
(3)横向贝雷梁与纵向贝雷主梁铰接在一起,过孔前拆除一部分铰接接头,配合钢丝绳将横向贝雷梁牵引至纵向贝雷梁处并临时固定,不影响过孔施工。(3) The transverse Bailey beam and the longitudinal Bailey main beam are hinged together. Part of the hinged joints are removed before the hole is passed, and the transverse Bailey beam is pulled to the longitudinal Bailey beam with the wire rope and fixed temporarily, without affecting the construction of the hole.
附图说明Description of drawings
图1是基于复合式移动模架现浇箱梁施工状态的剖面图;Fig. 1 is the sectional view of the construction state of the cast-in-place box girder based on the composite movable formwork;
图2是基于复合式移动模架现浇箱梁拆模状态的剖面图;Fig. 2 is a sectional view of the demoulding state of the cast-in-place box girder based on the composite mobile formwork;
图3是中部横向贝雷梁处横向剖面图;Figure 3 is a transverse cross-sectional view of the central transverse Bailey beam;
图4是2-2截面图;Fig. 4 is a 2-2 sectional view;
图5是1-1截面图;Fig. 5 is 1-1 sectional view;
图6是横向贝雷梁拆除时状态图;Figure 6 is a state diagram when the transverse Bailey beam is removed;
图7是纵向贝雷梁横移时状态图;Fig. 7 is a state diagram when the longitudinal Bailey beam moves laterally;
图中:1.牛腿支撑托架,2.预埋件,3.墩旁托架拉杆,4.横移轨道,5.限位块A,6.滑轮组平台,7.横移千斤顶A,8.连接件A,9.连接件B,10.滑轮A,11.纵向贝雷梁,12.纵移千斤顶底座,13.千斤顶,14.横向贝雷梁,15.外模支架,16.横移平台,17.滑轮A,18.横移平台轨道,19.横移千斤顶B,20.连接件C,21.连接件D,22.背架,23.外侧模板,24.底模板,25.螺栓,26.挡板模,27.护栏,28.支撑螺旋顶,29.垫块,30.铰接接头,31.内模,32.液压支撑,33.限位块B,34.纵移导轨梁,35.纵移千斤顶,36.连接件E,37.墩柱,38.箱梁,39.牵引钢丝绳。In the figure: 1. Corbel supporting bracket, 2. Embedded parts, 3. Bracket pull rod beside the pier, 4. Traversing track, 5. Limiting block A, 6. Pulley block platform, 7. Traversing jack A, 8. Connector A, 9. Connector B, 10. Pulley A, 11. Longitudinal Bailey beam, 12. Vertical jack base, 13. Jack, 14. Transverse Bailey beam, 15. Outer mold support, 16. Traverse platform, 17. pulley A, 18. traverse platform track, 19. traverse jack B, 20. connector C, 21. connector D, 22. back frame, 23. outer formwork, 24. bottom formwork, 25. Bolt, 26. Baffle form, 27. Guardrail, 28. Supporting screw top, 29. Pad block, 30. Articulated joint, 31. Internal mold, 32. Hydraulic support, 33. Limiting block B, 34. Longitudinal Move the guide rail beam, 35. longitudinally moving jack, 36. connector E, 37. pier column, 38. box girder, 39. traction wire rope.
具体实施方式detailed description
下面结合附图并通过实施例对本发明作进一步详细说明,以下实施例是对本发明的解释并不局限于以下实施例。The present invention will be further described in detail below with reference to the accompanying drawings and examples. The following examples are explanations of the present invention and are not limited to the following examples.
图1是基于复合式移动模架现浇箱梁施工状态的剖面图。如图1所示的复合式移动模架,主要包括:牛腿支撑托架1、横移轨道4、滑轮组平台6、纵向贝雷梁11、横向贝雷梁14、外模支架15、横移平台16、横移千斤顶A7、纵移千斤顶35、横移千斤顶B19、挡板模26和护栏27。Figure 1 is a cross-sectional view of the construction state of a cast-in-place box girder based on a composite mobile formwork. The composite mobile formwork shown in Figure 1 mainly includes: corbel support bracket 1, traversing track 4, pulley block platform 6, longitudinal Bailey beam 11, transverse Bailey beam 14, outer mold support 15, traversing Platform 16, traversing jack A7, longitudinal jack 35, traversing jack B19, baffle mold 26 and guardrail 27.
牛腿支撑托架1上设置横移轨道4,横移轨道4外侧设置限位块A5;滑轮组平台6放置在横移轨道4上,滑轮组平台6上面设置纵向滑轮A10;纵向贝雷梁11放置在滑轮组平台6上,纵向贝雷梁11上设置横移平台轨道18;外模支架15底部设置横移平台16,外模支架15放置在横移平台轨道18上;纵向贝雷梁11与横向贝雷梁14铰接固定连接在一起。滑轮组平台6与横移轨道4侧面设置横移千斤顶A7,横移千斤顶A7一端通过连接件A8固定在滑轮组平台6,另一端通过连接件B9固定在横移轨道4。The traversing track 4 is set on the corbel support bracket 1, and the limit block A5 is set on the outside of the traversing track 4; the pulley block platform 6 is placed on the traversing track 4, and the longitudinal pulley A10 is set on the pulley block platform 6; the longitudinal Bailey beam 11 is placed On the pulley block platform 6, the transverse movement platform track 18 is set on the longitudinal Bailey beam 11; the transverse movement platform 16 is arranged at the bottom of the outer mold support 15, and the outer mold support 15 is placed on the transverse movement platform track 18; the longitudinal Bailey beam 11 and the transverse movement platform The Bailey beams 14 are hinged and fixedly connected together. A traversing jack A7 is arranged on the side of the pulley block platform 6 and the traversing track 4, and one end of the traversing jack A7 is fixed on the pulley block platform 6 through the connecting piece A8, and the other end is fixed on the traversing track 4 through the connecting piece B9.
牛腿支撑托架1通过预埋件2固定在墩柱37上并配合墩旁托架拉杆3将对侧牛腿支撑托架1对拉在一起。滑轮组平台6与纵向贝雷梁11之间设置千斤顶13。纵向贝雷梁11底部设置纵移导轨梁34。The corbel support bracket 1 is fixed on the pier column 37 through the embedded part 2 and cooperates with the bracket pull rod 3 beside the pier to pull the pair of corbel support brackets 1 on the opposite side together. A jack 13 is arranged between the pulley block platform 6 and the longitudinal Bailey beam 11 . A vertical guide rail beam 34 is arranged at the bottom of the longitudinal Bailey beam 11 .
横移平台16底部设置横移千斤顶B19,横移千斤顶B19一端通过连接件C20固定在横移平台16,另一端通过连接件D21固定在横移平台轨道18上。The bottom of the traversing platform 16 is provided with a traversing jack B19, one end of the traversing jack B19 is fixed on the traversing platform 16 through the connecting piece C20, and the other end is fixed on the traversing platform track 18 through the connecting piece D21.
外模支架15为两侧对称分离式结构,两侧底模板24通过螺栓25固定在一起。The outer mold support 15 is a two-sided symmetrical separated structure, and the bottom templates 24 on both sides are fixed together by bolts 25 .
图2是基于复合式移动模架现浇箱梁拆模状态的剖面图,控制千斤顶13收缩使其整体结构下降,在重力的作用下使其自动脱模,然后拆除两侧外模支架15间的所有连接螺栓25,再控制横移千斤顶B19使外模支架15移动至指定位置。Fig. 2 is a sectional view of the demoulding state of the cast-in-place box girder based on the composite mobile formwork. Control the shrinkage of the jack 13 to lower the overall structure, and automatically demould it under the action of gravity, and then remove the 15 outer mold supports on both sides. All the connecting bolts 25, and then control the traverse jack B19 to move the outer mold support 15 to the designated position.
图3是中部横向贝雷梁处横向剖面图,横向贝雷梁14顶部设置支撑螺旋顶28,支撑螺旋顶28上设置垫块29。Fig. 3 is a transverse sectional view of the transverse Bailey beam in the middle, a supporting spiral top 28 is arranged on the top of the transverse Bailey beam 14, and a spacer 29 is arranged on the supporting spiral top 28.
图4是图2的2-2截面图,纵向贝雷梁11底部纵向方向设置纵移千斤顶35;纵移千斤顶35底座固定在滑轮组平台6上,另一端通过连接件E36固定在纵移导轨梁34上。Fig. 4 is the 2-2 sectional view of Fig. 2, the longitudinal direction of the bottom of the longitudinal Bailey beam 11 is provided with a longitudinal movement jack 35; the base of the longitudinal movement jack 35 is fixed on the pulley block platform 6, and the other end is fixed on the longitudinal movement guide rail beam through the connector E36 34 on.
图5是图1的1-1截面图,横向贝雷梁14与纵向贝雷梁11通过铰接接头30连接在一起。FIG. 5 is a sectional view of 1-1 in FIG. 1 , the transverse Bailey beam 14 and the longitudinal Bailey beam 11 are connected together through a hinged joint 30 .
上述基于复合式移动模架现浇箱梁的主要施工过程如下:The main construction process of the above-mentioned cast-in-place box girder based on composite mobile formwork is as follows:
步骤一、牛腿支撑托架安装:根据设计要求在墩柱37指定位置预埋预埋件2,待墩柱强度达到设计要求后,将牛腿支撑托架1通过预埋件2固定在墩柱37上并配合墩旁托架拉杆进一步固定牛腿支撑托架1;Step 1. Installation of the corbel support bracket: pre-embed the embedded part 2 at the designated position of the pier column 37 according to the design requirements. After the pier column strength meets the design requirements, fix the corbel support bracket 1 on the pier through the embedded part 2 On the column 37 and cooperate with the bracket pull rod next to the pier to further fix the corbel supporting bracket 1;
步骤二、横移平台安装:先将横移轨道4通过螺栓固定在牛腿支撑托架1,然后将平台滑轮组6放置在横移轨道4上,将横移千斤顶A7安装就位;Step 2. Installation of the traversing platform: first fix the traversing track 4 to the corbel support bracket 1 through bolts, then place the platform pulley block 6 on the traversing track 4, and install the traversing jack A7 in place;
步骤三、贝雷梁安装:纵向贝雷梁11和横向贝雷梁14预先在地面组装好,通过吊车将纵向贝雷梁11吊至滑轮组平台6上,底部设置顶升千斤顶13和纵移千斤顶35,待两侧纵向贝雷梁11安装就位后,将横向贝雷梁14吊装至指定位置通过铰接接头30与纵向贝雷梁11连接;Step 3, Bailey beam installation: the longitudinal Bailey beam 11 and the transverse Bailey beam 14 are pre-assembled on the ground, and the longitudinal Bailey beam 11 is hoisted to the pulley block platform 6 by a crane, and the jacking jack 13 and the vertical moving jack are installed at the bottom 35. After the longitudinal Bailey beams 11 on both sides are installed in place, the transverse Bailey beam 14 is hoisted to a designated position and connected to the longitudinal Bailey beam 11 through the hinged joint 30;
步骤四、模架安装:根据设计要求在纵向贝雷梁11上焊接横移平台轨道18,将预先制作好的外模支架15吊装至横移平台轨道18上,控制横移千斤顶A7至指定位置后再控制横移千斤顶B19将外模支架15向内侧横移至指定位置,通过螺栓25将两侧的外模支架15固定在一起,控制千斤顶13使整体结构顶升至指定位置并调节支撑螺旋顶28使其受力;Step 4. Formwork installation: Weld the traverse platform rail 18 on the longitudinal Bailey beam 11 according to the design requirements, hoist the prefabricated outer mold support 15 onto the traverse platform rail 18, and control the traverse jack A7 to the designated position Then control the traverse jack B19 to move the outer mold support 15 inwardly to the designated position, fix the outer mold supports 15 on both sides together through bolts 25, control the jack 13 to raise the overall structure to the designated position and adjust the support screw Top 28 makes it stressed;
步骤五、钢筋笼吊装及混凝土浇筑:将预先绑扎成型的钢筋笼吊装至模板内,待内模31全部安装完毕后浇筑混凝土并养护;Step 5, hoisting of reinforcement cage and concrete pouring: hoisting the pre-bound reinforcement cage into the formwork, pouring concrete and curing after all the inner molds 31 are installed;
步骤六、拆模:待养护达到设计要求后,控制千斤顶13收缩使其整体结构下降,在重力的作用下使其自动脱模,然后拆除两侧外模支架15间的所有连接螺栓25,再控制横移千斤顶B19使外模支架15移动至指定位置;Step 6, demoulding: After the maintenance meets the design requirements, control the shrinkage of the jack 13 to lower the overall structure, and automatically demould it under the action of gravity, then remove all the connecting bolts 25 between the outer mold supports 15 on both sides, and then Control the traverse jack B19 to move the outer mold support 15 to the designated position;
步骤七、过孔及下一段箱梁施工:拆除铰接接头30并配合牵引钢丝绳39使其与一侧纵向贝雷梁11分离,牵引至另一侧纵向贝雷梁11并临时固定,控制横移千斤顶A7使滑轮组平台6横移至指定位置,再控制纵移千斤顶35使纵向贝雷梁11纵移实现过孔,过孔至指定位置后进行下一段箱梁施工。Step 7. Construction of the via hole and the next section of box girder: remove the hinged joint 30 and cooperate with the traction wire rope 39 to separate it from the longitudinal Bailey beam 11 on one side, pull it to the longitudinal Bailey beam 11 on the other side and fix it temporarily, and control the lateral movement The jack A7 moves the pulley block platform 6 laterally to the designated position, and then controls the longitudinal moving jack 35 to make the vertical Bailey beam 11 move longitudinally to realize the passage, and then proceed to the next section of box girder construction after passing the hole to the designated position.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610551185.4A CN106120563B (en) | 2016-07-14 | 2016-07-14 | Construction method based on Combined movable mould bases cast-in-situ box girder |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610551185.4A CN106120563B (en) | 2016-07-14 | 2016-07-14 | Construction method based on Combined movable mould bases cast-in-situ box girder |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106120563A true CN106120563A (en) | 2016-11-16 |
| CN106120563B CN106120563B (en) | 2017-09-08 |
Family
ID=57283201
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610551185.4A Active CN106120563B (en) | 2016-07-14 | 2016-07-14 | Construction method based on Combined movable mould bases cast-in-situ box girder |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106120563B (en) |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107059646A (en) * | 2017-06-15 | 2017-08-18 | 中国十七冶集团有限公司 | A kind of angle-table bracket construction method of cast-in-place large span gate-type pier capping beam |
| CN107542037A (en) * | 2017-09-28 | 2018-01-05 | 谢晓燕 | A kind of new supporting bracket of bridge construction |
| CN107794845A (en) * | 2017-11-28 | 2018-03-13 | 中铁建大桥工程局集团第六工程有限公司 | A kind of Cast-in-situ Beam steel structure support whole lateral moving device and method |
| CN107882065A (en) * | 2017-10-31 | 2018-04-06 | 上海建工七建集团有限公司 | Beams of concrete construction operating platform and its erection method above a kind of Gui Hang areas |
| CN107988920A (en) * | 2018-01-25 | 2018-05-04 | 中交公局厦门工程有限公司 | A kind of stent transverse direction integral translation device and its construction method |
| CN108316156A (en) * | 2018-04-18 | 2018-07-24 | 中铁十九局集团第七工程有限公司 | Moving die plate and its construction method |
| CN108360380A (en) * | 2018-01-18 | 2018-08-03 | 中建三局第建设工程有限责任公司 | A kind of bridge pier column construction operation platform and its construction method |
| CN108425323A (en) * | 2018-03-23 | 2018-08-21 | 中铁建大桥工程局集团第四工程有限公司 | A kind of cast-in-place box beam assembled moving template |
| CN109457619A (en) * | 2018-12-11 | 2019-03-12 | 中交第二航务工程局有限公司 | A kind of mobile bracket of composite multi-functional for concrete girder cast-in-place construction |
| CN110306432A (en) * | 2019-04-11 | 2019-10-08 | 中铁六局集团天津铁路建设有限公司 | Removable lateral form bracing system and construction method when adjacent bridge construction |
| CN110700099A (en) * | 2019-10-11 | 2020-01-17 | 中国十七冶集团有限公司 | Face horizontal slipform concreting device of free surface |
| CN110847045A (en) * | 2019-11-20 | 2020-02-28 | 成都建工路桥建设有限公司 | Large-spread-arm bent cap self-propelled portal template system for urban viaduct and construction method |
| CN111088760A (en) * | 2019-12-26 | 2020-05-01 | 中交武汉港湾工程设计研究院有限公司 | Large-height large-cantilever concrete structure prefabricated construction support and installation method thereof |
| CN111395176A (en) * | 2020-03-24 | 2020-07-10 | 保利长大工程有限公司 | Construction method for lowering and dismantling movable formwork based on convenience |
| CN111531689A (en) * | 2020-06-01 | 2020-08-14 | 中交四航局第二工程有限公司 | Die assembling and disassembling trolley for box girder outer side die plate and die assembling and disassembling method thereof |
| CN112140290A (en) * | 2020-09-15 | 2020-12-29 | 中铁大桥局上海工程有限公司 | A kind of prefabricated bridge deck steel form supporting device and its prefabricated bridge deck pouring method |
| CN112281664A (en) * | 2020-10-22 | 2021-01-29 | 中铁八局集团第一工程有限公司 | Slip form construction method for cast-in-situ of large-span simply supported beam |
| CN113914217A (en) * | 2021-09-15 | 2022-01-11 | 江苏月生达机械制造有限公司 | Integral self-propelled outer mold track |
| CN113957807A (en) * | 2021-12-06 | 2022-01-21 | 中铁四局集团有限公司 | Adjustable width moving die carrier structure suitable for cast-in-place construction of curve bridge |
| CN115559217A (en) * | 2022-10-26 | 2023-01-03 | 中铁广州工程局集团有限公司 | A construction method of outsourcing concrete for the arch ring of a rigid skeleton concrete arch bridge |
| CN116446292A (en) * | 2023-04-13 | 2023-07-18 | 中交二公局第二工程有限公司 | Left-right transverse movement device and method for concrete box girder movable formwork |
| CN116815650A (en) * | 2023-07-17 | 2023-09-29 | 中铁大桥局上海工程有限公司 | Precast box girder transverse movement construction method and construction system |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101210419A (en) * | 2007-12-21 | 2008-07-02 | 中铁大桥局股份有限公司 | Small radius curved concrete box girder construction machine with internal and external girder system and its construction method |
| CN101333801A (en) * | 2007-06-25 | 2008-12-31 | 中铁二十局集团有限公司 | Cast-in-situ beam-making construction method of assembled support |
| CN102979038A (en) * | 2012-12-12 | 2013-03-20 | 广东省长大公路工程有限公司 | Cast-in-place box beam mobile bracket with increased width |
| WO2014200443A1 (en) * | 2013-06-11 | 2014-12-18 | Nrs Consulting Co., Ltd. | Self-launching movable scaffolding system |
| CN105735141A (en) * | 2016-05-05 | 2016-07-06 | 中铁上海工程局集团有限公司 | Gliding device with box beam side template and construction method thereof |
| CN205975365U (en) * | 2016-07-14 | 2017-02-22 | 德州市公路工程总公司 | Cast -in -situ box girder combined type moving die carrier |
-
2016
- 2016-07-14 CN CN201610551185.4A patent/CN106120563B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101333801A (en) * | 2007-06-25 | 2008-12-31 | 中铁二十局集团有限公司 | Cast-in-situ beam-making construction method of assembled support |
| CN101210419A (en) * | 2007-12-21 | 2008-07-02 | 中铁大桥局股份有限公司 | Small radius curved concrete box girder construction machine with internal and external girder system and its construction method |
| CN102979038A (en) * | 2012-12-12 | 2013-03-20 | 广东省长大公路工程有限公司 | Cast-in-place box beam mobile bracket with increased width |
| WO2014200443A1 (en) * | 2013-06-11 | 2014-12-18 | Nrs Consulting Co., Ltd. | Self-launching movable scaffolding system |
| CN105735141A (en) * | 2016-05-05 | 2016-07-06 | 中铁上海工程局集团有限公司 | Gliding device with box beam side template and construction method thereof |
| CN205975365U (en) * | 2016-07-14 | 2017-02-22 | 德州市公路工程总公司 | Cast -in -situ box girder combined type moving die carrier |
Cited By (31)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107059646A (en) * | 2017-06-15 | 2017-08-18 | 中国十七冶集团有限公司 | A kind of angle-table bracket construction method of cast-in-place large span gate-type pier capping beam |
| CN107542037B (en) * | 2017-09-28 | 2018-12-04 | 谢志坚 | A kind of supporting bracket of bridge construction |
| CN107542037A (en) * | 2017-09-28 | 2018-01-05 | 谢晓燕 | A kind of new supporting bracket of bridge construction |
| CN107882065A (en) * | 2017-10-31 | 2018-04-06 | 上海建工七建集团有限公司 | Beams of concrete construction operating platform and its erection method above a kind of Gui Hang areas |
| CN107794845A (en) * | 2017-11-28 | 2018-03-13 | 中铁建大桥工程局集团第六工程有限公司 | A kind of Cast-in-situ Beam steel structure support whole lateral moving device and method |
| CN107794845B (en) * | 2017-11-28 | 2024-03-15 | 中铁建大桥工程局集团第六工程有限公司 | Integral transverse moving device and method for steel structure bracket for cast-in-situ beam |
| CN108360380B (en) * | 2018-01-18 | 2020-07-10 | 中建三局第一建设工程有限责任公司 | A kind of bridge pier column construction work platform and construction method thereof |
| CN108360380A (en) * | 2018-01-18 | 2018-08-03 | 中建三局第建设工程有限责任公司 | A kind of bridge pier column construction operation platform and its construction method |
| CN107988920A (en) * | 2018-01-25 | 2018-05-04 | 中交公局厦门工程有限公司 | A kind of stent transverse direction integral translation device and its construction method |
| CN108425323A (en) * | 2018-03-23 | 2018-08-21 | 中铁建大桥工程局集团第四工程有限公司 | A kind of cast-in-place box beam assembled moving template |
| CN108316156A (en) * | 2018-04-18 | 2018-07-24 | 中铁十九局集团第七工程有限公司 | Moving die plate and its construction method |
| CN108316156B (en) * | 2018-04-18 | 2023-10-03 | 中铁十九局集团广州工程有限公司 | Mobile formwork and its construction method |
| CN109457619A (en) * | 2018-12-11 | 2019-03-12 | 中交第二航务工程局有限公司 | A kind of mobile bracket of composite multi-functional for concrete girder cast-in-place construction |
| CN109457619B (en) * | 2018-12-11 | 2023-12-19 | 中交第二航务工程局有限公司 | A multi-functional movable support of complex for cast-in-situ construction of concrete girder |
| CN110306432A (en) * | 2019-04-11 | 2019-10-08 | 中铁六局集团天津铁路建设有限公司 | Removable lateral form bracing system and construction method when adjacent bridge construction |
| CN110700099A (en) * | 2019-10-11 | 2020-01-17 | 中国十七冶集团有限公司 | Face horizontal slipform concreting device of free surface |
| CN110847045A (en) * | 2019-11-20 | 2020-02-28 | 成都建工路桥建设有限公司 | Large-spread-arm bent cap self-propelled portal template system for urban viaduct and construction method |
| CN110847045B (en) * | 2019-11-20 | 2024-09-03 | 成都建工路桥建设有限公司 | Self-propelled portal template system for large-span arm bent cap of urban viaduct and construction method |
| CN111088760A (en) * | 2019-12-26 | 2020-05-01 | 中交武汉港湾工程设计研究院有限公司 | Large-height large-cantilever concrete structure prefabricated construction support and installation method thereof |
| CN111395176A (en) * | 2020-03-24 | 2020-07-10 | 保利长大工程有限公司 | Construction method for lowering and dismantling movable formwork based on convenience |
| CN111531689A (en) * | 2020-06-01 | 2020-08-14 | 中交四航局第二工程有限公司 | Die assembling and disassembling trolley for box girder outer side die plate and die assembling and disassembling method thereof |
| CN112140290B (en) * | 2020-09-15 | 2022-02-18 | 中铁大桥局上海工程有限公司 | A kind of prefabricated bridge deck pouring method |
| CN112140290A (en) * | 2020-09-15 | 2020-12-29 | 中铁大桥局上海工程有限公司 | A kind of prefabricated bridge deck steel form supporting device and its prefabricated bridge deck pouring method |
| CN112281664A (en) * | 2020-10-22 | 2021-01-29 | 中铁八局集团第一工程有限公司 | Slip form construction method for cast-in-situ of large-span simply supported beam |
| CN113914217A (en) * | 2021-09-15 | 2022-01-11 | 江苏月生达机械制造有限公司 | Integral self-propelled outer mold track |
| CN113957807A (en) * | 2021-12-06 | 2022-01-21 | 中铁四局集团有限公司 | Adjustable width moving die carrier structure suitable for cast-in-place construction of curve bridge |
| CN113957807B (en) * | 2021-12-06 | 2024-05-14 | 中铁四局集团有限公司 | Width-adjustable movable formwork structure suitable for cast-in-situ construction of curve bridge |
| CN115559217A (en) * | 2022-10-26 | 2023-01-03 | 中铁广州工程局集团有限公司 | A construction method of outsourcing concrete for the arch ring of a rigid skeleton concrete arch bridge |
| CN115559217B (en) * | 2022-10-26 | 2025-08-26 | 中铁广州工程局集团有限公司 | A construction method for outer concrete wrapping of the arch ring of a rigid skeleton concrete arch bridge |
| CN116446292A (en) * | 2023-04-13 | 2023-07-18 | 中交二公局第二工程有限公司 | Left-right transverse movement device and method for concrete box girder movable formwork |
| CN116815650A (en) * | 2023-07-17 | 2023-09-29 | 中铁大桥局上海工程有限公司 | Precast box girder transverse movement construction method and construction system |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106120563B (en) | 2017-09-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106120563B (en) | Construction method based on Combined movable mould bases cast-in-situ box girder | |
| CN103015325B (en) | Construction method of cast-in-place concrete crash barrier with eaves | |
| CN113235472B (en) | A trolley for pouring concrete for slab culvert | |
| CN101781878B (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
| WO2022142193A1 (en) | Construction method for large-span thin-wall concrete sound barrier pouring trolley | |
| CN102691270B (en) | Efficient and quick movable mould frame | |
| CN102140779A (en) | Movable cast-in-situ support and movable construction method of box girder cast-in-situ support | |
| CN101581073A (en) | Downlink movable mould frame and walking method thereof | |
| CN108103945B (en) | A kind of whole landing mould bases of cast-in-situ box girder | |
| CN107044090A (en) | A kind of construction method of dual deck bridge | |
| CN205975365U (en) | Cast -in -situ box girder combined type moving die carrier | |
| CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
| CN217151958U (en) | Tunnel center ditch pouring trolley | |
| CN206035507U (en) | Rectangle box culvert and for tunnel construction platform truck | |
| CN214993219U (en) | Concrete placement platform truck is contained to apron | |
| CN202658534U (en) | Efficient and fast moving formwork | |
| CN108005684B (en) | Separated steel mould trolley and construction method thereof | |
| CN105887884A (en) | Single-side type rock anchor beam concrete pouring trolley | |
| CN105887885A (en) | Symmetric rock anchor beam concrete pouring trolley | |
| CN205152807U (en) | Downgoing movable formwork bridge construction machine is demolishd and is hoisted construction structures with girder | |
| CN116695589B (en) | Integral assembling and lifting construction method for guy rope hanging basket structure | |
| CN219548382U (en) | Empty layer hanging template system of granulating tower | |
| CN218580491U (en) | Automatic internal mold device for continuous beam pouring construction | |
| CN116084350A (en) | Novel intensive construction process for prefabricated aqueduct | |
| CN205669205U (en) | A kind of unilateral formula rock anchorage beam concreting chassis |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: No. 159, Jinghua Avenue, Dezhou Economic and Technological Development Zone, Shandong Province Patentee after: Deda Transportation Construction and Development Group Co.,Ltd. Address before: No. 159, Jinghua Avenue, Dezhou Economic and Technological Development Zone, Shandong Province Patentee before: DEZHOU ROAD ENGINEERING Corp. |