CN219548382U - Empty layer hanging template system of granulating tower - Google Patents

Empty layer hanging template system of granulating tower Download PDF

Info

Publication number
CN219548382U
CN219548382U CN202320524862.9U CN202320524862U CN219548382U CN 219548382 U CN219548382 U CN 219548382U CN 202320524862 U CN202320524862 U CN 202320524862U CN 219548382 U CN219548382 U CN 219548382U
Authority
CN
China
Prior art keywords
hanging
keel
keels
formwork
modules
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202320524862.9U
Other languages
Chinese (zh)
Inventor
陈华
武燕
王丽
王子洲
董宇川
张全
闫雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebeisijian Construction Engineering Co ltd
Original Assignee
Hebeisijian Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebeisijian Construction Engineering Co ltd filed Critical Hebeisijian Construction Engineering Co ltd
Priority to CN202320524862.9U priority Critical patent/CN219548382U/en
Application granted granted Critical
Publication of CN219548382U publication Critical patent/CN219548382U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a granulating tower empty layer hanging template system, which consists of a plurality of hanging template modules, wherein each hanging template module comprises a bottom keel and side keels on two sides, a bottom die is paved on the bottom keel, hanging keels are arranged between the side keels on two sides, the end parts of two adjacent hanging template modules are fixedly connected with each other, a connecting keel is arranged at the top of the hanging template system, the connecting keels are connected with the hanging keels of all the hanging template modules, and a plurality of construction pull nodes are distributed on the hanging template system. The hanging template system is manufactured on the ground, so that overhead operation is reduced, construction safety is improved, modules of the hanging template system are partitioned according to the diameter of a prilling tower and the working performance of a tower crane, and the utilization rate of machinery is improved. The utility model can shorten the construction period, save a large number of turnover tools, reduce high-suspension operation, reduce construction difficulty and improve construction quality.

Description

造粒塔架空层吊挂模板体系Pelletizing tower overhead layer hanging formwork system

技术领域technical field

本实用新型涉及一种造粒塔施工技术,具体地说是一种造粒塔架空层吊挂模板体系。The utility model relates to a construction technology of a granulation tower, in particular to a formwork system for hanging an overhead layer of a granulation tower.

背景技术Background technique

造粒塔是塔式造粒技术中的关键设施,造粒塔内部构造较为复杂,施工难度高。尤其是塔内架空结构层靠近塔顶上部,架空高度均超过50米以上,造粒塔架空层为双层板结构,两侧为劲性梁。在造粒塔架空层施工中,一般方法为造粒塔主体采用桁架辐射梁构造内平台刚性联结滑升模板体系滑模到顶后,再将桁架内平台与滑模体系分离后下降到架空层高度,桁架内平台作为架空层施工的操作平台,在该平台上进行架空层模板支设、钢筋绑扎及混凝土浇筑,架空层施工完毕后再将桁架内平台卸落至地面。The prilling tower is the key facility in the tower prilling technology. The internal structure of the prilling tower is relatively complicated and the construction is difficult. In particular, the overhead structure layer in the tower is close to the upper part of the tower top, and the overhead height is more than 50 meters. The overhead layer of the granulation tower is a double-layer plate structure with stiff beams on both sides. In the construction of the empty layer of the granulation tower, the general method is that the main body of the granulation tower adopts the truss radiation beam structure, and the inner platform rigidly connects the sliding formwork system to the top. , the inner platform of the truss is used as the operating platform for the construction of the aerial layer, on which the formwork support of the aerial floor, the binding of steel bars and the pouring of concrete are carried out. After the construction of the aerial floor is completed, the inner platform of the truss is unloaded to the ground.

这种方法具有一定的缺点:(1)桁架内平台使用材料多,安装周期长;(2)滑模到顶后桁架内平台与滑模体系的分离、下降及架空层施工完毕后平台的拆除工艺都较为复杂,高空作业多;(3)桁架操作平台面积大、重量大,在各种操作中容易引发安全事故。This method has certain disadvantages: (1) The inner platform of the truss uses a lot of materials and the installation period is long; (2) The separation and lowering of the inner platform of the truss and the sliding form system after the sliding form reaches the top and the removal process of the platform after the construction of the overhead layer is completed (3) The truss operation platform has a large area and heavy weight, which is likely to cause safety accidents in various operations.

实用新型内容Utility model content

本实用新型的目的就是提供一种造粒塔架空层吊挂模板体系,以解决现有造粒塔架空层利用滑模体系设置的桁架内平台作为操作平台进行施工导致施工效率低、高空作业量多以及安全性差的问题。The purpose of this utility model is to provide a hanging formwork system for the overhead layer of the granulation tower to solve the problem of low construction efficiency and high-altitude operations caused by the construction of the truss inner platform set by the sliding form system as the operating platform for the existing granulation tower overhead layer. Many and poor security issues.

本实用新型是这样实现的:一种造粒塔架空层吊挂模板体系,由若干个吊挂模板模块组成,所述吊挂模板模块包括底部龙骨以及两侧的侧面龙骨,在所述底部龙骨上铺设有底模,在两侧的侧面龙骨之间设置有吊挂龙骨,相邻两个吊挂模板模块的端部相互固定连接,在吊挂模板体系的顶部设置有连系龙骨,所述连系龙骨与所有吊挂模板模块的吊挂龙骨连接,在吊挂模板体系上分布有若干构造拉结点。The utility model is realized in the following way: a suspended formwork system for the overhead layer of a granulation tower is composed of several suspended formwork modules, the suspended formwork modules include a bottom keel and side keels on both sides, There is a bottom form on the upper pavement, a hanging keel is set between the side keels on both sides, the ends of two adjacent hanging formwork modules are fixedly connected to each other, and a connecting keel is set on the top of the hanging formwork system. The connecting keel is connected to the hanging keel of all hanging formwork modules, and there are several structural tie points distributed on the hanging formwork system.

相邻两个所述吊挂模板模块端部的侧面龙骨通过连接龙骨连接固定为一体。The side keels at the ends of two adjacent hanging formwork modules are connected and fixed as a whole by connecting keels.

所述构造拉结点包括拉杆和设于所述拉杆上端的拉环,所述拉杆穿过所述底模,所述拉杆的上下两端分别与吊挂龙骨和底部龙骨焊接,在拉杆上套有套管,所述套管位于所述吊挂龙骨和底部龙骨之间。The structural tie points include a pull rod and a pull ring arranged at the upper end of the pull rod, the pull rod passes through the bottom mold, the upper and lower ends of the pull rod are respectively welded to the hanging keel and the bottom keel, There is a bushing which is located between the hanger joist and the bottom joist.

所述底部龙骨为主龙骨和副龙骨形成的网格结构。The bottom keel is a grid structure formed by the main keel and the auxiliary keel.

所述底模为不锈钢材质,在所述底模的上表面设置V型的钢筋。The bottom mold is made of stainless steel, and V-shaped steel bars are arranged on the upper surface of the bottom mold.

本实用新型还公开了一种超高造粒塔架空层施工方法,包括以下步骤。The utility model also discloses a construction method for the superhigh granulation tower overhead layer, which comprises the following steps.

a.将制作完成的两个劲性梁钢骨架利用塔吊安装到造粒塔圆仓的预定位置。a. Install the finished two stiff beam steel skeletons to the predetermined position of the round silo of the prilling tower by tower crane.

b.在造粒塔圆仓内地面进行吊挂模板模块底部龙骨及侧面龙骨的制作和焊接,并在吊挂模板模块的底部安装底模。b. Make and weld the bottom keel and side keel of the hanging formwork module on the ground in the round silo of the prilling tower, and install the bottom mold at the bottom of the hanging formwork module.

c.利用塔吊对吊挂模板模块依次分块吊装至劲性梁钢骨架下部,在两侧的侧面龙骨之间焊接吊挂龙骨,吊挂龙骨横跨在两个劲性梁钢骨架的上部。c. Use the tower crane to hoist the hanging formwork modules to the lower part of the stiff beam steel frame in turn, weld the hanging keel between the side keels on both sides, and the hanging keel spans the upper part of the two stiff beam steel frames.

d.所有的吊挂模板模块均安装就位后,将相邻两个吊挂模板模块相互连接成整体。d. After all the hanging formwork modules are installed in place, connect two adjacent hanging formwork modules to form a whole.

e.安装通长连系龙骨将所有的吊挂龙骨连接成整体。e. Install the long connecting keel to connect all the hanging keels into a whole.

f.在吊挂模板体系上设置构造拉结点,构造拉结点通过钢丝绳与圆仓的仓壁连接。f. Set up structural anchor points on the hanging formwork system, and the structural anchor points are connected to the silo wall of the round silo through steel wire ropes.

g.在底模与吊挂龙骨之间绑扎架空层劲性梁钢筋和架空层底板钢筋。g. Bind the stiff beam reinforcement of the overhead floor and the bottom plate reinforcement of the overhead floor between the bottom form and the hanging keel.

h.进行架空层底板混凝土浇筑,浇筑标高至底板上表面。h. Carry out concrete pouring for the bottom slab of the elevated floor, and the pouring level shall reach the upper surface of the bottom slab.

i.支设劲性梁侧向模板及架空层上层板模板,绑扎架空层上层板钢筋。i. Support the lateral formwork of the stiffened beam and the upper slab formwork of the overhead floor, and bind the steel bars of the upper slab of the aerial floor.

j.浇筑劲性梁及架空层上层板混凝土。j. Pour stiff beams and concrete on the upper slab of the elevated floor.

k.将吊挂模板模块依次分块拆除下放至地面。k. Remove the hanging formwork modules in turn and lower them to the ground.

所述构造拉结点包括拉杆和设于所述拉杆上端的拉环,所述拉杆穿过所述底模,所述拉杆的上下两端分别与吊挂龙骨和底部龙骨焊接,在拉杆上套有套管,所述套管位于所述吊挂龙骨和底部龙骨之间。The structural tie points include a pull rod and a pull ring arranged at the upper end of the pull rod, the pull rod passes through the bottom mold, the upper and lower ends of the pull rod are respectively welded to the hanging keel and the bottom keel, There is a bushing which is located between the hanger joist and the bottom joist.

所述吊挂模板体系沿所述劲性梁钢骨架的长度方向划分为若干个模块。The hanging formwork system is divided into several modules along the length direction of the stiff beam steel skeleton.

在步骤c中,进行吊挂龙骨施工时,初步校核吊挂模板模块的标高及轴线位置后,先进行两端位置吊挂龙骨的焊接;两端吊挂龙骨焊接完成后,校核每个吊挂龙骨位置处标高及位置,校核无误后进行中间部位吊挂龙骨的焊接。In step c, when carrying out the construction of the hanging keel, after initially checking the elevation and axis position of the hanging formwork module, first weld the hanging keel at both ends; after the welding of the hanging keel at both ends is completed, check each The elevation and position of the hanging keel should be checked and corrected before welding of the hanging keel in the middle.

在步骤d中,相邻两个吊挂模板模块端部的侧面龙骨通过连接龙骨焊接固定为一体。In step d, the side keels at the ends of two adjacent hanging formwork modules are fixed as a whole by welding the connecting keels.

在步骤j中,浇筑前对劲性梁内凿毛表面进行浇水湿润,并将碎渣清理干净;浇筑架空层上层板混凝土前,架空层底板混凝土强度不得低于设计强度的60%;浇筑完成后,对混凝土进行养护,养护时间不少于7天。In step j, before pouring, water and moisten the chiseled surface of the stiffening beam, and clean up the slag; before pouring the concrete on the upper slab of the elevated floor, the concrete strength of the bottom slab of the elevated floor shall not be lower than 60% of the design strength; the pouring is completed Finally, the concrete is cured, and the curing time is not less than 7 days.

在步骤k中,将吊挂模板模块按照先安装的后拆除、后安装的先拆除的顺序依次整体拆除下放到地面。In step k, the hanging formwork modules are dismantled as a whole and lowered to the ground in sequence in the order of firstly installed and then dismantled, and later installed firstly dismantled.

在步骤k中,吊挂模板模块的骨架拆除时,一端用塔吊吊住,另一端用倒链连接,将构造拉结点和吊挂龙骨切割后慢慢下放倒链使吊挂模板模块的骨架垂直,然后塔吊整体把吊挂模板模块的骨架下放至地面,在地面进行骨架的解体。In step k, when the skeleton of the hanging formwork module is removed, one end is suspended with a tower crane, and the other end is connected with an inverted chain. Vertically, then the tower crane as a whole lowers the skeleton of the hanging formwork module to the ground, and disintegrates the skeleton on the ground.

采用本实用新型的吊挂模板体系进行造粒塔架空层的施工,吊挂模板体分模块在地面进行加工,加工好后依次吊装至预定位置的劲性梁钢骨架上,将各个模块相互连接固定为一体并设置构造拉结点后,在吊挂模板体系上绑扎钢筋并浇筑架空层,架空层浇筑完毕后,将吊挂模板模块依次拆除下放,从而完成架空层的施工。The suspended formwork system of the utility model is used for the construction of the overhead layer of the granulation tower. The suspended formwork body is processed on the ground in sub-modules. After processing, it is hoisted to the rigid beam steel frame at the predetermined position in turn, and the modules are connected to each other. After fixing as a whole and setting the structural tie points, the steel bars are bound on the hanging formwork system and the overhead layer is poured. After the overhead layer is poured, the hanging formwork modules are removed and lowered in order to complete the construction of the overhead layer.

吊挂模板体系分为多个模块进行制作、起吊、安装、拆除以及下放,能够避免起吊过程中由于重量过大导致安全事故。本实用新型采用吊挂模板体系,吊挂模板体系是在圆仓滑模施工结束后进行的,吊挂模板体系通过塔吊进行吊装,无需通过滑模体系将其抬升,从而降低了滑模施工的难度,且吊挂模板体系相对于桁架内平台来说结构简单,制作和安装周期短,吊挂模板体系的上升、下降以及拆除都比较简单。吊挂模板体系只需覆盖矩形的架空层区域即可,无需像桁架内平台那样覆盖整个圆仓内部,从而大大节省材料且减轻整体的质量。吊挂模板体系通过构造拉结点减少模板体系的挠度值,在浇筑时能够保证架空层的水平度。The hanging formwork system is divided into multiple modules for fabrication, lifting, installation, dismantling and lowering, which can avoid safety accidents caused by excessive weight during the lifting process. The utility model adopts a hanging formwork system. The hanging formwork system is carried out after the construction of the round warehouse sliding formwork is completed. The hanging formwork system is hoisted by a tower crane without lifting it through the sliding formwork system, thereby reducing the construction cost of the sliding formwork. Compared with the inner platform of the truss, the structure of the hanging formwork system is simple, the production and installation period is short, and the lifting, lowering and dismantling of the hanging formwork system are relatively simple. The hanging formwork system only needs to cover the rectangular overhead floor area, and does not need to cover the entire interior of the silo like the inner platform of the truss, thus greatly saving materials and reducing the overall quality. The hanging formwork system reduces the deflection value of the formwork system by constructing tie points, which can ensure the levelness of the overhead floor during pouring.

采用本实用新型吊挂模板体系能够减少架空层施工过程中的高空作业,提高施工效率且提高施工过程中的安全性。Adoption of the hanging formwork system of the utility model can reduce high-altitude operations in the construction process of the overhead floor, improve construction efficiency and improve safety in the construction process.

附图说明Description of drawings

图1是造粒塔架空层的剖面图。Figure 1 is a cross-sectional view of the overhead layer of the prilling tower.

图2是本实用新型吊挂模板模块的横剖面图。Fig. 2 is a cross-sectional view of the hanging formwork module of the present invention.

图3是本实用新型吊挂模板模块的纵剖面图。Fig. 3 is a longitudinal sectional view of the hanging formwork module of the present invention.

图4是本实用新型吊挂模板模块划分平面图。Fig. 4 is a divisional plan view of the hanging formwork module of the present invention.

图5是本实用新型吊挂模板相邻模板连接结构图。Fig. 5 is a connection structure diagram of adjacent formworks of the hanging formwork of the utility model.

图6是本实用新型构造拉结点的结构图。Fig. 6 is a structural diagram of the utility model structure pull node.

图7是本实用新型吊挂模板体系的整体布置图。Fig. 7 is an overall layout diagram of the hanging formwork system of the present invention.

图中:1、造粒塔架空层;2、主龙骨;3、副龙骨;4、侧面龙骨;5、连接龙骨;6、吊挂龙骨;7、连系龙骨;8、构造拉结点;9、钢丝绳;10、造粒塔圆仓;1-1、劲性梁;1-2、架空层底板;1-3、架空层上层板;8-1、拉杆;8-2、拉环;8-3、套管。In the figure: 1. Pelletizing tower overhead floor; 2. Main keel; 3. Auxiliary keel; 4. Side keel; 5. Connecting keel; 6. Hanging keel; 7. Connecting keel; 9. Steel wire rope; 10. Round silo of prilling tower; 1-1, stiff beam; 1-2, bottom plate of overhead floor; 1-3, upper plate of overhead floor; 8-1, pull rod; 8-2, pull ring; 8-3. Casing.

具体实施方式Detailed ways

如图1所示,造粒塔架空层1为中空结构,架空层包括两侧的劲性梁1-1以及两个劲性梁1-1之间的架空层底板1-2和架空层上层板1-3,且在劲性梁1-1上部设有上翻梁。架空层位于造粒塔圆仓10内部且靠近塔顶的位置,高度较高,跨度较大,在施工时具有一定的难度。As shown in Figure 1, the overhead floor 1 of the prilling tower is a hollow structure, and the overhead floor includes stiff beams 1-1 on both sides, and the bottom plate 1-2 of the overhead floor between the two stiff beams 1-1 and the upper layer of the overhead floor plate 1-3, and an upturning beam is provided on the upper part of the stiff beam 1-1. The overhead layer is located inside the silo 10 of the prilling tower and close to the top of the tower. It has a high height and a large span, and it is difficult to construct.

本实用新型的造粒塔架空层吊挂模板体系由若干个吊挂模板模块组成,吊挂模板模块如图2、图3所示,吊挂模板模块包括底部龙骨以及两侧的侧面龙骨4,在底部龙骨上铺设有底模,在两侧的侧面龙骨4之间设置有吊挂龙骨6,相邻两个吊挂模板模块的端部相互固定连接,在吊挂模板体系的顶部设置有连系龙骨7,连系龙骨7与所有吊挂模板模块的吊挂龙骨6连接,在吊挂模板体系上分布有若干构造拉结点8。The hanging formwork system of the overhead layer of the granulation tower of the utility model is composed of several hanging formwork modules, the hanging formwork modules are shown in Figure 2 and Figure 3, the hanging formwork modules include the bottom keel and the side keels 4 on both sides A bottom formwork is laid on the bottom keel, and a hanging keel 6 is arranged between the side keels 4 on both sides. The ends of two adjacent hanging formwork modules are fixedly connected to each other, and a connection The tie keel 7 is connected with the hanging keel 6 of all hanging formwork modules, and a number of structural tie points 8 are distributed on the hanging formwork system.

如图5所示,在相邻两个模块之间,两个模块端部的侧面龙骨4通过连接龙骨5焊接固定为一体。两个侧面龙骨4之间焊接有上中下三个连接龙骨5,从而将相邻的两个模块牢固地固定在一起。As shown in FIG. 5 , between two adjacent modules, the side keels 4 at the ends of the two modules are welded and fixed as a whole by connecting keels 5 . Three upper, middle and lower connecting keels 5 are welded between the two side keels 4, thereby firmly fixing two adjacent modules together.

如图6所示,构造拉结点8包括拉杆8-1和设于拉杆8-1上端的拉环8-2,拉杆8-1穿过底模,拉杆8-1的上下两端分别与吊挂龙骨6和底部龙骨焊接,在拉杆8-1上套有套管8-3,套管8-3位于吊挂龙骨6和底部龙骨之间。As shown in Figure 6, the structure pull node 8 includes a pull rod 8-1 and a pull ring 8-2 located at the upper end of the pull rod 8-1, the pull rod 8-1 passes through the bottom mold, and the upper and lower ends of the pull rod 8-1 are respectively connected to The hanging keel 6 is welded to the bottom keel, and a sleeve 8-3 is sleeved on the pull rod 8-1, and the sleeve 8-3 is located between the hanging keel 6 and the bottom keel.

套管8-3为PVC管,通过PVC管使得在浇筑架空层混凝土时,混凝土不会与拉杆8-1接触,便于后续工序中拉杆8-1能从混凝土中顺利拆除。Sleeve 8-3 is a PVC pipe, through which the concrete will not contact the pull rod 8-1 when pouring the concrete for the overhead floor, so that the pull rod 8-1 can be smoothly removed from the concrete in the follow-up process.

在使用时,拉环8-3通过钢丝绳9和造粒塔圆仓10的仓壁连接,且钢丝绳9处于拉紧状态,拉环8-3受到拉力,构造拉结点8将拉力传导至吊挂龙骨6和底部龙骨,从而控制该构造拉结点8位置的竖向形变位移。When in use, the pull ring 8-3 is connected to the wall of the prilling tower round bin 10 through the steel wire rope 9, and the steel wire rope 9 is in a tensioned state, the pull ring 8-3 is subjected to tension, and the construction pull node 8 transmits the tension to the suspension. Hang the keel 6 and the bottom keel, thereby controlling the vertical deformation and displacement of the structure's tie point 8.

其中,底部龙骨包括主龙骨2和副龙骨3,主龙骨2和副龙骨3形成网格结构,为了便于铺设底模,在主龙骨2和副龙骨3形成的网格结构上还设置次龙骨。Wherein, the bottom keel includes main keel 2 and auxiliary keel 3, and main keel 2 and auxiliary keel 3 form a grid structure.

底模为不锈钢材质,铺设在底部龙骨上,在后续的浇筑架空层时作为架空层的底部模板。The bottom mold is made of stainless steel, laid on the bottom keel, and used as the bottom formwork of the skyline during subsequent pouring of the skyline.

其中,主龙骨2、副龙骨3、侧面龙骨4、连接龙骨5、吊挂龙骨6以及连系龙骨7都为C型钢。Among them, the main keel 2, the auxiliary keel 3, the side keel 4, the connecting keel 5, the hanging keel 6 and the connecting keel 7 are all C-shaped steel.

使用本实用新型的超高造粒塔架空层施工方法具体包括以下步骤。The superhigh granulation tower overhead layer construction method of the utility model specifically includes the following steps.

a.将制作完成的两个劲性梁1-1钢骨架利用塔吊安装到造粒塔圆仓10的预定位置。a. Install the finished two stiff beams 1-1 steel skeletons to the predetermined position of the round bin 10 of the prilling tower with a tower crane.

劲性梁1-1钢骨架由工字钢制成,且劲性梁1-1钢骨架在造粒塔圆仓10内的地面进行加工制作,制作完成后使用塔吊起吊到预定的劲性梁1-1位置并固定安装在造粒塔圆仓10上。两个劲性梁1-1钢骨架的高度和位置根据图纸确定。The steel skeleton of the stiff beam 1-1 is made of I-beam, and the steel skeleton of the stiff beam 1-1 is processed and manufactured on the ground in the round silo 10 of the prilling tower. 1-1 position and fixedly installed on the round bin 10 of the prilling tower. The height and position of the two stiff beams 1-1 steel skeleton shall be determined according to the drawings.

两个劲性梁1-1钢骨架水平布置且相互平行,劲性梁1-1钢骨架的两端固定安装在造粒塔圆仓10的仓壁上,两个劲性梁1-1钢骨架以及之间的区域便是造粒塔架空层1的设计位置。The two stiff beams 1-1 steel skeletons are arranged horizontally and parallel to each other. The skeleton and the area between are the design positions of the prilling tower overhead layer 1.

b.在造粒塔圆仓10内地面进行吊挂模板模块底部龙骨及侧面龙骨4的制作和焊接,并在吊挂模板模块的底部安装底模。b. Make and weld the bottom keel and side keel 4 of the hanging formwork module on the ground in the round bin 10 of the prilling tower, and install the bottom mold at the bottom of the hanging formwork module.

如图4所示,吊挂模板体系沿劲性梁1-1钢骨架的长度方向划分为若干个模块,在地面依次制作各个模块。As shown in Figure 4, the hanging formwork system is divided into several modules along the length direction of the steel frame of the stiff beam 1-1, and each module is fabricated sequentially on the ground.

底模为不锈钢底模,底模铺设在底部龙骨上,作为架空层浇筑时架空层底面的模板。由于底模在架空层浇筑完成后留在架空层上,为了保证连接的牢固性,在底模的上表面设置V型的钢筋,浇筑架空层后,底模上V型的钢筋嵌入架空层的混凝土中。The bottom mold is a stainless steel bottom mold, and the bottom mold is laid on the bottom keel, which is used as a template for the bottom surface of the skyline when pouring the skyline. Since the bottom form stays on the overhead floor after the pouring of the empty floor is completed, in order to ensure the firmness of the connection, a V-shaped steel bar is placed on the upper surface of the bottom form. in concrete.

c.利用塔吊对吊挂模板模块依次分块吊装至劲性梁1-1钢骨架下部,在模块两侧的侧面龙骨4之间焊接吊挂龙骨6,吊挂龙骨6横跨在两个劲性梁1-1钢骨架的上部。c. Use the tower crane to hoist the hanging formwork modules to the lower part of the steel frame of the stiff beam 1-1 in sequence, and weld the hanging keel 6 between the side keels 4 on both sides of the module, and the hanging keel 6 spans the two stiffeners The upper part of the beam 1-1 steel skeleton.

吊挂模板模块吊装到位后,两个劲性梁1-1钢骨架刚好位于两侧的侧面龙骨4之间,底部龙骨位于劲性梁1-1钢骨架的下方,而后续安装的吊挂龙骨6位于劲性梁1-1钢骨架的上方,侧面龙骨4、底部龙骨以及吊挂龙骨6围成矩形框架结构,两个劲性梁1-1钢骨架位于该框架结构内,从而由劲性梁1-1钢骨架支撑整个吊挂模板模块。After the hanging formwork module is hoisted in place, the two stiff beams 1-1 steel frames are just located between the side keels 4 on both sides, the bottom keel is located under the stiff beam 1-1 steel frames, and the hanging keels installed later 6 is located above the steel frame of the stiff beam 1-1, and the side keel 4, the bottom keel and the hanging keel 6 form a rectangular frame structure, and the two steel frames of the stiff beam 1-1 are located in the frame structure, so that the The beam 1-1 steel skeleton supports the entire hanging formwork module.

进行水平的吊挂龙骨6施工时,初步校核吊挂模板模块的标高及轴线位置后,先进行模块两端位置吊挂龙骨6的焊接;两端吊挂龙骨6焊接完成后,校核每个吊挂龙骨6位置处标高及位置,校核无误后进行中间部位吊挂龙骨6的焊接。When carrying out horizontal hanging keel 6 construction, after initially checking the elevation and axis position of the hanging formwork module, first carry out welding of the hanging keel 6 at both ends of the module; after the welding of the hanging keel 6 at both ends is completed, check each The elevation and position of each hanging keel 6 position, after checking and correcting, carry out the welding of the hanging keel 6 in the middle.

d.所有的吊挂模板模块均安装就位后,将相邻两个吊挂模板模块相互固定连接成整体。d. After all the hanging formwork modules are installed in place, two adjacent hanging formwork modules are fixedly connected to each other to form a whole.

e.安装通长连系龙骨7将所有的吊挂龙骨6连接成整体。e. Install the through-length connecting keel 7 to connect all the hanging keels 6 into a whole.

连系龙骨7有若干个,连系龙骨7的长度方向与劲性梁1-1钢骨架的长度方向一致,连系龙骨7的长度贯穿所有的吊挂模板模块,从而将所有的吊挂龙骨6连接成整体,通过连系龙骨7进一步增加吊挂模板体系连接的牢固性同时增强吊挂模板体系的受力能力。There are several connecting keels 7, and the length direction of the connecting keels 7 is consistent with the length direction of the steel frame of the stiff beam 1-1. The length of the connecting keels 7 runs through all the hanging formwork modules, so that all the hanging keels 6 are connected as a whole, and the firmness of the connection of the hanging formwork system is further increased by connecting the keel 7, and the force bearing capacity of the hanging formwork system is enhanced at the same time.

f.在吊挂模板体系上设置构造拉结点8,构造拉结点8通过钢丝绳9与圆仓的仓壁连接。f. Set the structural tie point 8 on the hanging formwork system, and the structural tie point 8 is connected with the warehouse wall of the round warehouse through the steel wire rope 9.

安装好构造拉结点8后吊挂模板整体安装完毕。After installing the structural tie point 8, the overall installation of the hanging formwork is completed.

构造拉结点8的位置和数量根据需要确定,通过构造拉结点8控制整个吊挂模板体系的挠度,防止浇筑时架空层的水平度不满足标准。The position and quantity of the structural tie points 8 are determined according to the needs, and the deflection of the entire hanging formwork system is controlled through the structural tie points 8, so as to prevent the levelness of the overhead floor from not meeting the standard during pouring.

如图6所示,构造拉结点8包括拉杆8-1和设于拉杆8-1上端的拉环8-2,拉杆8-1穿过底模,拉杆8-1的上下两端分别与吊挂龙骨6和底部龙骨焊接,在拉杆8-1上套接有套管8-3,套管8-3位于吊挂龙骨6和底部龙骨之间。As shown in Figure 6, the structure pull node 8 includes a pull rod 8-1 and a pull ring 8-2 located at the upper end of the pull rod 8-1, the pull rod 8-1 passes through the bottom mold, and the upper and lower ends of the pull rod 8-1 are respectively connected to The hanging keel 6 is welded to the bottom keel, and a sleeve 8-3 is sleeved on the pull rod 8-1, and the sleeve 8-3 is located between the hanging keel 6 and the bottom keel.

如图7所示,拉环8-2通过钢丝绳9和造粒塔圆仓10的仓壁连接,且钢丝绳9处于拉紧状态,拉环8-2受到拉力,构造拉结点8将拉力传导至吊挂龙骨6和底部龙骨,从而控制该构造拉结点8位置的竖向形变位移。As shown in Figure 7, the pull ring 8-2 is connected to the wall of the prilling tower round bin 10 through a steel wire rope 9, and the steel wire rope 9 is in a tensioned state, the pull ring 8-2 is subjected to tension, and the construction pull node 8 transmits the pull force To the hanging keel 6 and the bottom keel, so as to control the vertical deformation displacement at the position of the tie point 8 of the structure.

套管8-3为PVC管,通过PVC管使得在浇筑架空层混凝土时,混凝土不会与拉杆8-1接触,便于后续工序中拉杆8-1能从混凝土中顺利拆除。Sleeve 8-3 is a PVC pipe, through which the concrete will not contact the pull rod 8-1 when pouring the concrete for the overhead floor, so that the pull rod 8-1 can be smoothly removed from the concrete in the follow-up process.

g.在底模与吊挂龙骨6之间绑扎架空层劲性梁1-1钢筋和架空层底板1-2钢筋。g. Bind the steel bar 1-1 of the stiff beam of the aerial floor and the steel bar 1-2 of the bottom plate of the aerial floor between the bottom form and the hanging keel 6.

h.进行架空层底板1-2混凝土浇筑,浇筑标高至底板上表面。h. Carry out 1-2 concrete pouring on the bottom slab of the elevated floor, and the pouring level shall reach the upper surface of the bottom slab.

i.支设劲性梁1-1侧向模板及架空层上层板1-3模板,绑扎架空层上层板1-3钢筋。i. Support the stiff beam 1-1 lateral formwork and the upper slab 1-3 formwork of the overhead floor, and bind the steel bars 1-3 of the upper slab of the aerial floor.

j.浇筑劲性梁1-1及架空层上层板1-3混凝土。j. Pouring the concrete of the stiff beam 1-1 and the upper slab 1-3 of the elevated floor.

浇筑前对劲性梁1-1内凿毛表面进行浇水湿润,并将碎渣清理干净;浇筑架空层上层板1-3混凝土前,架空层底板1-2混凝土强度不得低于设计强度的60%;浇筑完成后,对混凝土进行养护,养护时间不少于7天。Before pouring, water and moisten the chiseled surface of the stiffened beam 1-1, and clean up the debris; before pouring the concrete of the upper slab 1-3 of the elevated floor, the concrete strength of the bottom slab 1-2 of the elevated floor shall not be lower than 60% of the design strength %; After the pouring is completed, the concrete should be cured, and the curing time should not be less than 7 days.

k.将吊挂模板模块依次分块拆除下放至地面。k. Remove the hanging formwork modules in turn and lower them to the ground.

将吊挂模板模块按照先安装的后拆除、后安装的先拆除的顺序依次将各个模块整体拆除下放到地面。The hanging formwork modules are dismantled and lowered to the ground in sequence in the order of the first installation and then dismantling, and the last installation and first dismantling.

吊挂模板模块的骨架拆除时,一端用塔吊吊住,另一端用倒链连接,将构造拉结点8和吊挂龙骨6切割后,便可将吊挂模板模块的骨架从浇筑好的架空层上拆除,慢慢下放倒链使吊挂模板模块的骨架垂直,然后塔吊整体把吊挂模板模块的骨架下放至地面,在地面进行骨架的解体。When the skeleton of the hanging formwork module is removed, one end is suspended by a tower crane, and the other end is connected by an inverted chain. After cutting the structural tie point 8 and the hanging keel 6, the skeleton of the hanging formwork module can be lifted from the poured Remove the upper layer, slowly lower the chain to make the skeleton of the hanging formwork module vertical, and then lower the skeleton of the hanging formwork module to the ground by the tower crane as a whole, and disassemble the skeleton on the ground.

采用本实用新型的吊挂模板体系进行造粒塔架空层1的施工,吊挂模板体系分模块在地面进行加工,加工好后依次吊装至预定位置的劲性梁1-1钢骨架上,将各个模块相互连接固定为一体并设置构造拉结点8后,在吊挂模板体系上绑扎钢筋并浇筑架空层,架空层浇筑完毕后,将吊挂模板模块依次拆除下放,从而完成架空层的施工。The hanging formwork system of the utility model is used to construct the empty layer 1 of the granulation tower. The hanging formwork system is processed on the ground in sub-modules. After each module is connected and fixed as a whole and the structural tie point 8 is set, steel bars are bound on the hanging formwork system and the overhead floor is poured. After the overhead floor is poured, the hanging formwork modules are removed and lowered one by one to complete the construction of the overhead floor .

劲性梁1-1钢骨架和各个吊挂模板模块都是在地面进行制作焊接的,从而减少高空作业。吊挂模板体系分为多个模块进行制作、起吊、安装、拆除以及下放,能够避免起吊过程中由于重量过大导致安全事故。本实用新型采用吊挂模板体系,吊挂模板体系是在圆仓滑模施工结束后进行的,吊挂模板体系通过塔吊进行吊装,无需通过滑模体系将其抬升,从而降低了滑模施工的难度,且吊挂模板体系相对于桁架内平台来说结构简单,制作和安装周期短,吊挂模板体系的上升、下降以及拆除都比较简单。吊挂模板体系只需覆盖矩形的架空层区域即可,无需像桁架内平台那样覆盖整个圆仓内部,从而大大节省材料且减轻整体的质量。吊挂模板体系通过构造拉结点8减少模板体系的挠度值,在浇筑时能够保证架空层的水平度。The steel frame of the stiff beam 1-1 and each hanging formwork module are fabricated and welded on the ground, thereby reducing work at heights. The hanging formwork system is divided into multiple modules for fabrication, lifting, installation, dismantling and lowering, which can avoid safety accidents caused by excessive weight during the lifting process. The utility model adopts a hanging formwork system. The hanging formwork system is carried out after the construction of the round warehouse sliding formwork is completed. The hanging formwork system is hoisted by a tower crane without lifting it through the sliding formwork system, thereby reducing the construction cost of the sliding formwork. Compared with the inner platform of the truss, the structure of the hanging formwork system is simple, the production and installation period is short, and the lifting, lowering and dismantling of the hanging formwork system are relatively simple. The hanging formwork system only needs to cover the rectangular overhead floor area, and does not need to cover the entire interior of the silo like the inner platform of the truss, thus greatly saving materials and reducing the overall quality. The hanging formwork system reduces the deflection value of the formwork system by constructing tie points 8, which can ensure the levelness of the overhead floor during pouring.

本实用新型的吊挂模板体系在地面制作,减少高空作业,提高了施工的安全性。采用本施工方法,施工速度快,缩短了工期。采用本方法施工,节省了大量的周转工具。吊挂模板体系的模块根据造粒塔直径及塔吊工作性能进行分块,提高了机械的使用率。采用本施工方法,减少高悬空作业,降低施工难度,提高了施工质量。The hanging formwork system of the utility model is made on the ground, which reduces high-altitude operations and improves construction safety. By adopting the construction method, the construction speed is fast and the construction period is shortened. Adopting this method for construction saves a lot of turnover tools. The modules of the hanging formwork system are divided into blocks according to the diameter of the prilling tower and the working performance of the tower crane, which improves the utilization rate of the machine. By adopting the construction method, the high suspended work is reduced, the construction difficulty is reduced, and the construction quality is improved.

吊挂模板使用的型钢可以考虑后续屋面钢梁使用的材料选用合适的型钢,进一步降低成本。吊挂模板的安装、拆除利用现场塔吊就可以完成,不需要另外进场起重设备。吊挂模板的模块化制作、起吊及安装拆除降低了施工难度。采用劲性梁1-1骨架承重,节省了大量的模板支撑系统材料。The profile steel used for the hanging formwork can consider the material used for the subsequent roof steel beams to select appropriate profile steel to further reduce costs. The installation and dismantling of the suspended formwork can be completed by using the on-site tower crane, without the need for additional lifting equipment entering the site. The modular fabrication, lifting, installation and dismantling of the hanging formwork reduces the difficulty of construction. The rigid beam 1-1 skeleton is used for load bearing, which saves a lot of formwork support system materials.

Claims (5)

1.一种造粒塔架空层吊挂模板体系,其特征在于,由若干个吊挂模板模块组成,所述吊挂模板模块包括底部龙骨以及两侧的侧面龙骨,在所述底部龙骨上铺设有底模,在两侧的侧面龙骨之间设置有吊挂龙骨,相邻两个吊挂模板模块的端部相互固定连接,在吊挂模板体系的顶部设置有连系龙骨,所述连系龙骨与所有吊挂模板模块的吊挂龙骨连接,在吊挂模板体系上分布有若干构造拉结点。1. A granulation tower overhead layer hanging formwork system is characterized in that it is composed of several hanging formwork modules, and the hanging formwork modules include bottom keels and side keels on both sides, and are laid on the bottom keels There is a bottom mold, and a hanging keel is set between the side keels on both sides, and the ends of two adjacent hanging formwork modules are fixedly connected to each other, and a connecting keel is set on the top of the hanging formwork system. The keel is connected to the hanging keel of all hanging formwork modules, and there are several structural tie points distributed on the hanging formwork system. 2.根据权利要求1所述的造粒塔架空层吊挂模板体系,其特征在于,相邻两个所述吊挂模板模块端部的侧面龙骨通过连接龙骨连接固定为一体。2. The suspended formwork system for the overhead layer of the prilling tower according to claim 1, wherein the side keels at the ends of two adjacent suspended formwork modules are connected and fixed as one by connecting keels. 3.根据权利要求1所述的造粒塔架空层吊挂模板体系,其特征在于,所述构造拉结点包括拉杆和设于所述拉杆上端的拉环,所述拉杆穿过所述底模,所述拉杆的上下两端分别与吊挂龙骨和底部龙骨焊接,在拉杆上套有套管,所述套管位于所述吊挂龙骨和底部龙骨之间。3. The suspended formwork system for the overhead layer of the prilling tower according to claim 1, wherein the construction tie point includes a pull rod and a pull ring arranged at the upper end of the pull rod, and the pull rod passes through the bottom The upper and lower ends of the pull rod are respectively welded to the hanging keel and the bottom keel, and a sleeve is sleeved on the pull rod, and the sleeve is located between the hanging keel and the bottom keel. 4.根据权利要求1所述的造粒塔架空层吊挂模板体系,其特征在于,所述底部龙骨为主龙骨和副龙骨形成的网格结构。4. The suspended formwork system for the overhead layer of the prilling tower according to claim 1, wherein the bottom keel is a grid structure formed by the main keel and the auxiliary keel. 5.根据权利要求1所述的造粒塔架空层吊挂模板体系,其特征在于,所述底模为不锈钢材质,在所述底模的上表面设置V型的钢筋。5. The suspended formwork system for the overhead layer of the prilling tower according to claim 1, wherein the bottom mold is made of stainless steel, and a V-shaped steel bar is arranged on the upper surface of the bottom mold.
CN202320524862.9U 2023-03-17 2023-03-17 Empty layer hanging template system of granulating tower Withdrawn - After Issue CN219548382U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320524862.9U CN219548382U (en) 2023-03-17 2023-03-17 Empty layer hanging template system of granulating tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320524862.9U CN219548382U (en) 2023-03-17 2023-03-17 Empty layer hanging template system of granulating tower

Publications (1)

Publication Number Publication Date
CN219548382U true CN219548382U (en) 2023-08-18

Family

ID=87737489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320524862.9U Withdrawn - After Issue CN219548382U (en) 2023-03-17 2023-03-17 Empty layer hanging template system of granulating tower

Country Status (1)

Country Link
CN (1) CN219548382U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116357070A (en) * 2023-03-17 2023-06-30 河北省第四建筑工程有限公司 Suspension formwork system for the overhead layer of the granulation tower and construction method for the overhead layer of the ultra-high granulation tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116357070A (en) * 2023-03-17 2023-06-30 河北省第四建筑工程有限公司 Suspension formwork system for the overhead layer of the granulation tower and construction method for the overhead layer of the ultra-high granulation tower
CN116357070B (en) * 2023-03-17 2025-07-29 河北省第四建筑工程有限公司 Granulating tower empty layer hanging template system and ultrahigh granulating tower empty layer construction method

Similar Documents

Publication Publication Date Title
CN105625195B (en) Wave forms steel web SCC engineering methods movable hanging basket and its construction method
CN203188121U (en) Cast-in-place bridge floor suspending mold of half-through or through arch bridge
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
KR20140084107A (en) Self-Launching Movable Scaffolding System
CN114770706B (en) A kind of light T-beam prefabricated equipment and prefabricated installation and construction method
CN105908902A (en) Positioning frame for prefabricated pier column reinforcing bar cages and construction method of pier column reinforcing bar cages
CN108518071B (en) Installation method of double-layer large-span steel structure corridor
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN115653095A (en) Method for quickly building assembled frame structure
CN205653708U (en) Work platform that inclined plane climbed follows
CN112554535B (en) A construction method for a large-scale silo roof without a support frame
CN214573768U (en) A self-climbing slipform pouring system for the second-stage concrete pouring of the door slot
CN219548382U (en) Empty layer hanging template system of granulating tower
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN107299713A (en) A kind of circular cone roofing integrally-lifting steel truss and its construction
CN103993739A (en) Method for constructing stiff beam of spraying layer of prilling tower
CN116357070A (en) Suspension formwork system for the overhead layer of the granulation tower and construction method for the overhead layer of the ultra-high granulation tower
CN204475184U (en) Urban light rail viaduct mountain type U beam Construction Supporting System
CN201588172U (en) Integral single-tower non-dorsal-cord cable-stayed-bridge king tower lifting template
CN107965193B (en) Roof construction method for large diameter silo structure
CN218323497U (en) A prefabricated pier column reinforcement cage
CN116927093A (en) Pier column steel cage construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20230818

Effective date of abandoning: 20250729

AV01 Patent right actively abandoned

Granted publication date: 20230818

Effective date of abandoning: 20250729

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned