CN111042835B - A tunnel cable trench and water trench construction trolley and construction method thereof - Google Patents
A tunnel cable trench and water trench construction trolley and construction method thereof Download PDFInfo
- Publication number
- CN111042835B CN111042835B CN201911357509.0A CN201911357509A CN111042835B CN 111042835 B CN111042835 B CN 111042835B CN 201911357509 A CN201911357509 A CN 201911357509A CN 111042835 B CN111042835 B CN 111042835B
- Authority
- CN
- China
- Prior art keywords
- ditch
- die
- sliding sleeve
- construction
- translation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/40—Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域Technical Field
本发明涉及一种隧道施工设备,具体讲是一种隧道线缆沟和水沟施工台车及其施工方法。The invention relates to a tunnel construction device, in particular to a tunnel cable trench and water trench construction trolley and a construction method thereof.
背景技术Background technique
隧道是埋置于地层内的工程建筑物,是人类利用地下空间的一种形式;隧道可分为交通隧道、水工隧道、市政隧道、矿山隧道。在隧道中线缆沟和水沟施工,一般是在隧道衬砌完成后再单独浇筑线缆沟和水沟;Tunnels are engineering structures buried in the ground, and are a form of human use of underground space. Tunnels can be divided into traffic tunnels, hydraulic tunnels, municipal tunnels, and mining tunnels. The cable trenches and water ditches in the tunnels are usually constructed separately after the tunnel lining is completed.
而传统的线缆沟和水沟浇筑虽然也是采用台车辅助浇筑,但传统的浇筑方式一部台车仅配置一套模板,且从混凝土开始浇筑到凝固的整个过程中,台车与模板不能分离,不能够实现多组模板同时循环作业,施工效率低。Although the traditional pouring of cable trenches and water ditches also uses a trolley to assist in pouring, in the traditional pouring method, one trolley is only equipped with one set of formwork, and the trolley and the formwork cannot be separated during the entire process from concrete pouring to solidification, and multiple sets of formwork cannot be operated in a cycle at the same time, resulting in low construction efficiency.
发明内容Summary of the invention
因此,为了克服上述不足,本发明在此提供一种设计合理,结构简单,使用方便用于隧道线缆沟和水沟施工的台车,通过合理的设计台车,在施工时能够缩短水沟和线缆沟的施工周期,降低成本,克服传统效率低,质量不稳定的问题,合理的设计台车,能够实现施工循环作业,提高效率。Therefore, in order to overcome the above-mentioned shortcomings, the present invention provides a trolley with reasonable design, simple structure and easy use for the construction of tunnel cable trenches and water ditches. By reasonably designing the trolley, the construction period of the water ditches and cable trenches can be shortened and the cost can be reduced during construction. The problems of low efficiency and unstable quality in the traditional way can be overcome. The reasonable design of the trolley can realize the construction cycle operation and improve the efficiency.
本发明是这样实现的,构造一种隧道线缆沟和水沟施工台车, 包括具有行走机构的主桁架,所述行走机构包括主动部分和具有转向功能的从动部分,所述主桁架两侧的立柱外侧安装有能够上下升降的悬挂装置,该悬挂装置通过悬吊机构连接有成套的且定位即用的模具组。The present invention is implemented in this way: a tunnel cable trench and water ditch construction trolley is constructed, including a main truss with a walking mechanism, the walking mechanism includes an active part and a driven part with a steering function, and a suspension device that can be lifted up and down is installed on the outer side of the columns on both sides of the main truss. The suspension device is connected to a complete set of mold groups that are positioned and ready for use through the suspension mechanism.
优选的,所述悬挂装置包括悬梁、滑柱、滑套和拉杆,所述悬梁内端以铰接方式与滑套连接,所述拉杆的上端以铰接方式连接于滑套上端,而拉杆的下端以铰接方式与悬梁外端连接,所述滑套套于滑柱外围,而滑柱竖直固定安装于立柱外侧;Preferably, the suspension device comprises a suspension beam, a sliding column, a sliding sleeve and a pull rod, the inner end of the suspension beam is connected to the sliding sleeve in an articulated manner, the upper end of the pull rod is connected to the upper end of the sliding sleeve in an articulated manner, and the lower end of the pull rod is connected to the outer end of the suspension beam in an articulated manner, the sliding sleeve is sleeved on the outer periphery of the sliding column, and the sliding column is vertically fixedly installed on the outer side of the column;
在所述立柱外侧固定安装有升降油缸,该升降油缸的活塞杆连接于滑套,而缸体固定连接于立柱。A lifting cylinder is fixedly installed on the outer side of the column, a piston rod of the lifting cylinder is connected to the sliding sleeve, and a cylinder body is fixedly connected to the column.
优选的,所述悬吊机构包括平移滑套,平移油缸和吊梁,所述平移滑套套于悬梁,所述平移油缸一端连接于悬梁,而另一端连接于平移滑套,通过平移油缸伸缩运动带动平移滑套横向移动,所述吊梁上端连接于横向滑套,下端连接于模具组。Preferably, the suspension mechanism includes a translation sleeve, a translation cylinder and a suspension beam, the translation sleeve is sleeved on the suspension beam, one end of the translation cylinder is connected to the suspension beam, and the other end is connected to the translation sleeve, the translation sleeve is driven to move laterally through the telescopic movement of the translation cylinder, the upper end of the suspension beam is connected to the transverse sleeve, and the lower end is connected to the mold group.
优选的,所述模具组包括模板组和定位架,所述模板组通过位置调整机构安装于定位架下方;Preferably, the mold set includes a template set and a positioning frame, and the template set is installed below the positioning frame through a position adjustment mechanism;
所述定位架上端通过吊梁连接于平移滑套;The upper end of the positioning frame is connected to the translation sleeve through a suspension beam;
所述定位架两端为与地面接触端,且在该地面接触端安装有高度可调的调节支腿。The two ends of the positioning frame are ground contact ends, and height-adjustable adjustment legs are installed on the ground contact ends.
优选的,所述模板组包括水沟模板组和线缆沟模板组,Preferably, the template group includes a water ditch template group and a cable ditch template group.
所述水沟模板组包括两侧的水沟侧模板,两个所述水沟侧模板底部两端以铰接方式连接,同时在两端还设置有保持两个水沟侧模板相对位置的限位板;The ditch template group includes ditch side templates on both sides, the two ends of the bottom of the two ditch side templates are connected in a hinged manner, and at the same time, limit plates are provided at both ends to maintain the relative positions of the two ditch side templates;
所述线缆沟模板组包括两侧的线缆沟侧模板,在两个所述线缆沟侧模板的两端安装有保持两模板相对位置的限位板。The cable groove template group comprises cable groove side templates on both sides, and limiting plates for maintaining the relative positions of the two templates are installed at both ends of the two cable groove side templates.
优选的,所述位置调整机构包括数个竖直花篮螺栓,该竖直花篮螺栓上部连接于定位架,下端与模板组连接,在相邻竖直花篮螺栓的顶端之间连接有横向花篮螺栓,Preferably, the position adjustment mechanism comprises a plurality of vertical turnbuckle bolts, the upper portion of the vertical turnbuckle bolts is connected to the positioning frame, the lower end is connected to the template assembly, and a transverse turnbuckle bolt is connected between the top ends of adjacent vertical turnbuckle bolts.
所述模板组的高度通过竖直花篮螺栓调节,而横向位置通过横向花篮螺栓调节。The height of the formwork set is adjusted by vertical turnbuckles, while the lateral position is adjusted by transverse turnbuckles.
优选的,所述模板包括两侧的水沟侧模板,两个所述水沟侧模板底部两端以铰接方式连接,同时在两端还设置有保持两个水沟侧模板相对位置的限位板;Preferably, the template includes ditch side templates on both sides, the two ends of the bottom of the two ditch side templates are connected in a hinged manner, and limit plates are also provided at both ends to maintain the relative positions of the two ditch side templates;
所述线缆沟模板组件包括两侧的线缆沟侧模板,在两个所述线缆沟侧模板的两端安装有保持两模板相对位置的限位板。The cable groove template assembly comprises cable groove side templates on both sides, and limiting plates for maintaining the relative positions of the two templates are installed at both ends of the two cable groove side templates.
优选的,所述吊梁与模具组的采用花篮螺栓或电动葫芦或手动葫芦连接。Preferably, the hanging beam is connected to the mold assembly by using a basket bolt or an electric hoist or a manual hoist.
一种采用隧道线缆沟和水沟的施工方法,包括如下步骤:A construction method using a tunnel cable trench and a water trench comprises the following steps:
步骤一、准备多组模具组,通过带有行走机构的主桁架将一组模具组吊装到施工位置,并通过定位架安装好该模具组,在此过程中主桁架两侧是同时施工;Step 1: prepare multiple sets of mold groups, hoist one set of mold groups to the construction location through the main truss with a walking mechanism, and install the mold group through the positioning frame. During this process, both sides of the main truss are constructed simultaneously;
步骤二、一组工作人员向安装好的模具组中浇筑混凝土,在浇筑时,该组模具组是与主桁架脱离的,在浇筑的同时主桁架再吊装另一组模具组,并将新吊的模具组吊装到指定位置,并对其进行定位和拼接;Step 2: A group of workers pour concrete into the installed mold set. During the pouring, the mold set is separated from the main truss. During the pouring, the main truss hoists another mold set, and hoists the newly hoisted mold set to the designated position, and positions and splices it.
步骤三、向新安装的模具组进行混泥土浇筑,在浇筑时,可继续重复步骤二,实现循环浇筑,同时两侧同时施工;Step 3: Pour concrete into the newly installed mold set. During the pouring, step 2 can be repeated to achieve cyclic pouring, and construction can be carried out on both sides at the same time;
步骤四、拆卸前端混凝土凝固后的模具组,通过主桁架整体吊装,将其吊装到后端继续安装,并重复步骤二;Step 4: Dismantle the mold set after the front concrete solidifies, hoist it as a whole through the main truss, hoist it to the rear end for further installation, and repeat step 2;
步骤五、重复步骤三和步骤四,直到整个隧道段浇筑完成。Step 5. Repeat steps 3 and 4 until the entire tunnel section is cast.
在该方法中,所述步骤二和步骤四吊装过程如下:平移油缸的伸缩运动带动平移滑套在悬梁移动,平移滑套再通过吊梁带动模具组在横向方向移动;所述悬梁在竖直方向移动时,通过升降油缸带动滑套在滑柱上移动,从而通过悬梁带动模具组竖直方向移动。In this method, the lifting process of step two and step four is as follows: the telescopic movement of the translation cylinder drives the translation sleeve to move on the suspension beam, and the translation sleeve then drives the mold group to move in the lateral direction through the suspension beam; when the suspension beam moves in the vertical direction, the lifting cylinder drives the sleeve to move on the sliding column, thereby driving the mold group to move in the vertical direction through the suspension beam.
在该方法中,吊装模具组时,线缆沟侧模板和水沟侧模板通过限位板保持形状,保持形状的模具板再通过吊梁安装于定位架,安装有模具板的定位架再通过吊梁与平移滑套连接;In this method, when the mold group is hoisted, the cable trench side mold and the water trench side mold are kept in shape by the limit plate, and the mold plate with the shape is then installed on the positioning frame through the hanging beam, and the positioning frame with the mold plate installed is then connected to the translation sliding sleeve through the hanging beam;
在安装组装好的模板时,通过位置调整机构调节其高度。所述模板组的高度通过竖直花篮螺栓调节,而横向位置通过横向花篮螺栓调节。When installing the assembled formwork, its height is adjusted by the position adjustment mechanism. The height of the formwork group is adjusted by the vertical turnbuckle bolts, while the lateral position is adjusted by the lateral turnbuckle bolts.
本发明具有如下有益效果:The present invention has the following beneficial effects:
本发明设计合理,结构简单,使用方便,通过合理的设计台车,在施工时能够缩短水沟和线缆沟的施工周期,降低成本,克服传统效率低,质量不稳定的问题,合理的设计台车,能够实现施工循环作业,提高效率。The present invention has reasonable design, simple structure and is easy to use. Through the reasonable design of the trolley, the construction period of the water ditch and the cable trench can be shortened during construction, the cost can be reduced, and the problems of low efficiency and unstable quality in the traditional way can be overcome. The reasonable design of the trolley can realize the construction cycle operation and improve the efficiency.
合理的设计台车,该台车包括悬挂装置和悬吊装置,其中悬挂装置能够上下移动,所述悬吊装置能够实现模具组的吊装,并且带动其左右移动;从而方便模板组的位置调节;Reasonable design of the trolley, which includes a suspension device and a hanging device, wherein the suspension device can move up and down, and the hanging device can realize the hoisting of the mold group and drive it to move left and right; thereby facilitating the position adjustment of the template group;
所述悬挂装置包括包括悬梁、滑柱、滑套和拉杆,所述悬梁内端以铰接方式与滑套连接,所述拉杆的上端以铰接方式连接于滑套上端,而拉杆的下端以铰接方式与悬梁外端连接,所述滑套套于滑柱外围,而滑柱竖直固定安装于立柱外侧;在所述立柱外侧固定安装有升降油缸,该升降油缸的活塞杆连接于滑套,而缸体固定连接于立柱。在使用时,升降油缸带动滑套在导杆上移动,同时移动件带动悬梁上下移动,从而便于模板组的吊装。The suspension device includes a suspension beam, a sliding column, a sliding sleeve and a pull rod. The inner end of the suspension beam is connected to the sliding sleeve in an articulated manner, the upper end of the pull rod is connected to the upper end of the sliding sleeve in an articulated manner, and the lower end of the pull rod is connected to the outer end of the suspension beam in an articulated manner. The sliding sleeve is sleeved on the outer periphery of the sliding column, and the sliding column is vertically fixedly installed on the outer side of the column; a lifting cylinder is fixedly installed on the outer side of the column, the piston rod of the lifting cylinder is connected to the sliding sleeve, and the cylinder body is fixedly connected to the column. When in use, the lifting cylinder drives the sliding sleeve to move on the guide rod, and the moving part drives the suspension beam to move up and down, thereby facilitating the hoisting of the template group.
所述悬吊装置包括平移滑套,平移油缸和吊梁,所述平移滑套套于悬梁,所述平移油缸一端连接于悬梁,而另一端连接于平移滑套,通过平移油缸伸缩运动带动平移滑套横向移动,所述吊梁上端连接于横向滑套,下端连接于模板组;在使用时平移油缸的伸缩运动带动平移滑套在悬梁移动,平移滑套再通过吊梁带动模板组在横向方向移动,从而实现模板组的左右方向位置调整。The suspension device includes a translation sleeve, a translation cylinder and a suspension beam. The translation sleeve is sleeved on the suspension beam. One end of the translation cylinder is connected to the suspension beam, and the other end is connected to the translation sleeve. The translation sleeve is driven to move laterally through the telescopic movement of the translation cylinder. The upper end of the suspension beam is connected to the transverse sleeve, and the lower end is connected to the template group. When in use, the telescopic movement of the translation cylinder drives the translation sleeve to move on the suspension beam, and the translation sleeve then drives the template group to move in the transverse direction through the suspension beam, thereby realizing the left and right position adjustment of the template group.
其中和的设计模板组,该模块组能够成组吊装和安装,在安装时,仅需定位即可,而且定位方便,组装后的模板不会变形,相邻模板之间设置有限位板,该限位板能够保持模板之间的间距不变,并且还设置有定位架,该定位架能够实现各个模板间的相对位置调整,同时在该定位架的底部还设置有可调节的支腿,能够实现模板高度的微调。The template group designed by and can be hoisted and installed in groups. During installation, it only needs to be positioned, and the positioning is convenient. The assembled template will not be deformed. Limiting plates are arranged between adjacent templates, which can keep the distance between the templates unchanged, and a positioning frame is also provided, which can realize the relative position adjustment between each template. At the same time, adjustable legs are arranged at the bottom of the positioning frame to realize fine adjustment of the template height.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1是本发明在隧道施工状态示意图;FIG1 is a schematic diagram of the present invention in a tunnel construction state;
图2是本发明在隧道吊装模板组时的状态示意图;FIG2 is a schematic diagram of the state of the present invention when the template group is hoisted in the tunnel;
图3是图2中M的局部放大示意图;FIG3 is a partial enlarged schematic diagram of M in FIG2;
图4是本发明模板组安装状态示意图;FIG4 is a schematic diagram of the template assembly installation state of the present invention;
图5是本发明台车示意图;FIG5 is a schematic diagram of a trolley of the present invention;
图6是本发明定位架主视图;FIG6 is a front view of the positioning frame of the present invention;
图7是本发明定位架的俯视图。FIG. 7 is a top view of the positioning frame of the present invention.
具体实施方式Detailed ways
下面将结合附图1-图7对本发明进行详细说明,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The present invention will be described in detail below in conjunction with Figures 1 to 7 to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
如图1-图7所示,本发明在此提供一种隧道线缆沟和水沟施工台车, 包括具有行走机构的主桁架17,所述行走机构包括主动部分19和具有转向功能的从动部分18,所述主桁架两侧的立柱6外侧安装有能够上下升降的悬挂装置,该悬挂装置通过悬吊机构连接有成套的且定位即用的模具组。As shown in Figures 1 to 7, the present invention provides a tunnel cable trench and water ditch construction trolley, including a main truss 17 with a walking mechanism, the walking mechanism includes an active part 19 and a driven part 18 with a steering function, and a suspension device capable of being lifted up and down is installed on the outer side of the columns 6 on both sides of the main truss. The suspension device is connected to a complete set of mold groups that are positioned and ready for use through the suspension mechanism.
在该实施例中,所述悬挂装置包括悬梁9、滑柱13、滑套14和拉杆12,所述悬梁内端以铰接方式与滑套14连接,所述拉杆的上端以铰接方式连接于滑套上端,而拉杆的下端以铰接方式与悬梁外端连接,所述滑套14套于滑柱外围,而滑柱竖直固定安装于立柱外侧;该拉杆为可调节的丝杆千斤。In this embodiment, the suspension device includes a suspension beam 9, a sliding column 13, a sliding sleeve 14 and a pull rod 12. The inner end of the suspension beam is connected to the sliding sleeve 14 in a hinged manner, the upper end of the pull rod is connected to the upper end of the sliding sleeve in a hinged manner, and the lower end of the pull rod is connected to the outer end of the suspension beam in a hinged manner. The sliding sleeve 14 is sleeved on the outer periphery of the sliding column, and the sliding column is vertically fixed on the outside of the column; the pull rod is an adjustable screw jack.
在所述立柱外侧固定安装有升降油缸,该升降油缸的活塞杆连接于滑套,而缸体固定连接于立柱。A lifting cylinder is fixedly installed on the outer side of the column, a piston rod of the lifting cylinder is connected to the sliding sleeve, and a cylinder body is fixedly connected to the column.
在该实施例中,所述悬吊机构包括平移滑套10,平移油缸11和吊梁8,所述平移滑套10套于悬梁9,所述平移油缸一端连接于悬梁,而另一端连接于平移滑套10,通过平移油缸伸缩运动带动平移滑套横向移动,所述吊梁8上端连接于横向滑套,下端连接于模具组。In this embodiment, the suspension mechanism includes a translation sleeve 10, a translation cylinder 11 and a suspension beam 8. The translation sleeve 10 is sleeved on the suspension beam 9. One end of the translation cylinder is connected to the suspension beam, and the other end is connected to the translation sleeve 10. The translation sleeve is driven to move laterally through the telescopic movement of the translation cylinder. The upper end of the suspension beam 8 is connected to the transverse sleeve, and the lower end is connected to the mold group.
在该实施例中,所述模具组包括模板组和定位架5,所述模板组通过位置调整机构安装于定位架下方;In this embodiment, the mold set includes a template set and a positioning frame 5, and the template set is installed below the positioning frame through a position adjustment mechanism;
所述定位架5上端通过吊梁8连接于平移滑套10;The upper end of the positioning frame 5 is connected to the translation sleeve 10 through the suspension beam 8;
所述定位架5两端为与地面接触端,且在该地面接触端安装有高度可调的调节支腿1。该调节支腿包括螺母和螺栓,通过螺栓插入定位架的高度可调,实现支腿高度可调,适应多种地面。The two ends of the positioning frame 5 are ground contact ends, and the ground contact ends are equipped with height-adjustable adjustment legs 1. The adjustment legs include nuts and bolts, and the height of the bolts are inserted into the positioning frame to adjust the height of the legs, so that the height of the legs can be adjusted to adapt to various ground surfaces.
在该实施例中,所述模板组包括水沟模板组和线缆沟模板组,In this embodiment, the template group includes a water ditch template group and a cable ditch template group.
所述水沟模板组包括两侧的水沟侧模板7,两个所述水沟侧模板底部两端以铰接方式连接,同时在两端还设置有保持两个水沟侧模板相对位置的限位板4;The ditch template group includes ditch side templates 7 on both sides, the two ends of the bottom of the two ditch side templates are connected in a hinged manner, and at both ends, limit plates 4 are provided to maintain the relative positions of the two ditch side templates;
所述线缆沟模板组包括两侧的线缆沟侧模板3,在两个所述线缆沟侧模板的两端安装有保持两模板相对位置的限位板。The cable trench template group includes cable trench side templates 3 on both sides, and limiting plates for maintaining the relative positions of the two templates are installed at both ends of the two cable trench side templates.
在该实施例中,所述位置调整机构包括数个竖直花篮螺栓2,该竖直花篮螺栓上部连接于定位架,下端与模板组连接,在相邻竖直花篮螺栓的顶端之间连接有横向花篮螺栓,In this embodiment, the position adjustment mechanism includes a plurality of vertical turnbuckle bolts 2, the upper portion of the vertical turnbuckle bolts is connected to the positioning frame, the lower end is connected to the template group, and a transverse turnbuckle bolt is connected between the top ends of adjacent vertical turnbuckle bolts.
所述模板组的高度通过竖直花篮螺栓调节,而横向位置通过横向花篮螺栓调节。The height of the formwork set is adjusted by vertical turnbuckles, while the lateral position is adjusted by transverse turnbuckles.
在该实施例中,所述模板包括两侧的水沟侧模板7,两个所述水沟侧模板底部两端以铰接方式连接,同时在两端还设置有保持两个水沟侧模板相对位置的限位板4;In this embodiment, the template includes ditch side templates 7 on both sides, the two ends of the bottom of the two ditch side templates are connected in a hinged manner, and at both ends, limit plates 4 are provided to maintain the relative positions of the two ditch side templates;
所述线缆沟模板组件包括两侧的线缆沟侧模板3,在两个所述线缆沟侧模板的两端安装有保持两模板相对位置的限位板。The cable trench template assembly comprises cable trench side templates 3 on both sides, and limiting plates for maintaining the relative positions of the two templates are installed at both ends of the two cable trench side templates.
在该实施例中,所述吊梁与模具组的采用花篮螺栓或电动葫芦或手动葫芦连接。In this embodiment, the hanging beam is connected to the mold assembly by using a turnbuckle bolt or an electric hoist or a manual hoist.
在实施时,每部台车可配置数套长度12米的模具组,每个模具组由数块模板组和数个定位架组成,台车将模具组吊到指定位置后即可脱离该模具组,进行其他模具组的吊运工作。模具组依靠自身的调整机构将模板调整到准确位置,无需台车辅助。During implementation, each trolley can be equipped with several sets of 12-meter-long mold groups. Each mold group consists of several template groups and several positioning frames. After the trolley lifts the mold group to the specified position, it can detach from the mold group and carry out the lifting of other mold groups. The mold group relies on its own adjustment mechanism to adjust the template to the exact position without the assistance of the trolley.
本发明设计合理,结构简单,使用方便,能够实现多个模具组循环作业,用于隧道线缆沟和水沟的施工,克服了传统施工方法效率低,质量不稳定的问题,缩短水沟和线缆沟的施工周期,提高了作业效率。The invention has reasonable design, simple structure, and is easy to use. It can realize the cyclic operation of multiple mold groups and is used for the construction of tunnel cable trenches and water trenches. It overcomes the problems of low efficiency and unstable quality of traditional construction methods, shortens the construction period of water trenches and cable trenches, and improves operation efficiency.
一种采用隧道线缆沟和水沟的施工方法,其特征在于:包括如下步骤:A construction method using a tunnel cable trench and a water trench, characterized in that it comprises the following steps:
①准备多组模具组,将台车移动到隧道15内,使得台车在隧道基面16行走,通过带有行走机构的主桁架将一组模具组吊装到施工位置,并通过定位架安装好该模具组,在此过程中主桁架两侧是同时施工;① Prepare multiple sets of mold groups, move the trolley into the tunnel 15, make the trolley walk on the tunnel base 16, hoist one set of mold groups to the construction position through the main truss with a walking mechanism, and install the mold group through the positioning frame. During this process, both sides of the main truss are constructed simultaneously;
②一组工作人员向安装好的模具组中浇筑混凝土,在浇筑时,该组模具组是与主桁架脱离的,在浇筑的同时主桁架再吊装另一组模具组,并将新吊的模板组吊装到指定位置,并对其进行定位和拼接;② A group of workers pour concrete into the installed mold group. During the pouring, the mold group is separated from the main truss. While pouring, the main truss hoists another mold group, and hoists the newly hoisted template group to the designated position, and positions and splices it;
③向新安装的模具组进行混泥土浇筑,在浇筑时,可继续重复步骤②,实现循环浇筑,同时两侧同时施工;③ Pour concrete into the newly installed mold set. During the pouring, step ② can be repeated to achieve cyclic pouring and construction on both sides at the same time;
④拆卸前端混凝土凝固后的模具组,通过主桁架整体吊装,将其吊装到后端继续安装,并重复步骤②;④Dismantle the mold set after the concrete solidifies at the front end, hoist it as a whole through the main truss, hoist it to the rear end for further installation, and repeat step ②;
⑤重复步骤③和步骤④,直到整个隧道段浇筑完成。⑤ Repeat steps ③ and ④ until the entire tunnel section is cast.
在该方法中,所述步骤②和步骤④吊装过程如下:平移油缸11的伸缩运动带动平移滑套10在悬梁9移动,平移滑套再通过吊梁8带动模具组在横向方向移动;所述悬梁9在竖直方向移动时,通过升降油缸带动滑套14在滑柱上移动,从而通过悬梁带动模具组竖直方向移动。In this method, the lifting process of step ② and step ④ is as follows: the telescopic movement of the translation cylinder 11 drives the translation sleeve 10 to move on the suspension beam 9, and the translation sleeve then drives the mold group to move in the horizontal direction through the suspension beam 8; when the suspension beam 9 moves in the vertical direction, the lifting cylinder drives the sleeve 14 to move on the sliding column, thereby driving the mold group to move in the vertical direction through the suspension beam.
在该方法中,吊装模具组时,线缆沟侧模板3和水沟侧模板7通过限位板保持形状,保持形状的模板再通过模板位置调整机构安装于定位架5,模具组通过吊梁与平移滑套连接;In this method, when the mold set is hoisted, the cable trench side template 3 and the water trench side template 7 are kept in shape by the limit plate, and the templates with the maintained shape are then installed on the positioning frame 5 by the template position adjustment mechanism, and the mold set is connected to the translation sliding sleeve by the hanging beam;
在安装组装好的模板时,通过位置调整机构调节其高度。所述模板组的高度通过竖直花篮螺栓调节,而横向位置通过横向花篮螺栓调节。When installing the assembled formwork, its height is adjusted by the position adjustment mechanism. The height of the formwork group is adjusted by the vertical turnbuckle bolts, while the lateral position is adjusted by the lateral turnbuckle bolts.
本发明在施工时能够缩短水沟和线缆沟的施工周期,降低成本,克服传统效率低,质量不稳定的问题,合理的设计台车,能够实现施工循环作业,提高效率。The present invention can shorten the construction period of the water ditch and the cable ditch during construction, reduce costs, overcome the traditional problems of low efficiency and unstable quality, and reasonably design the trolley to realize construction cycle operations and improve efficiency.
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911357509.0A CN111042835B (en) | 2019-12-25 | 2019-12-25 | A tunnel cable trench and water trench construction trolley and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911357509.0A CN111042835B (en) | 2019-12-25 | 2019-12-25 | A tunnel cable trench and water trench construction trolley and construction method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111042835A CN111042835A (en) | 2020-04-21 |
| CN111042835B true CN111042835B (en) | 2024-06-18 |
Family
ID=70239718
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201911357509.0A Active CN111042835B (en) | 2019-12-25 | 2019-12-25 | A tunnel cable trench and water trench construction trolley and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111042835B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113062753B (en) * | 2021-04-08 | 2023-09-19 | 贵州路桥集团有限公司 | Groove lining forming device for highway tunnel integral lining trolley |
| CN115162406B (en) * | 2022-08-04 | 2023-11-28 | 广东省水利水电第三工程局有限公司 | Integral template portal suitable for box culvert structure |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN211737150U (en) * | 2019-12-25 | 2020-10-23 | 都江堰现代机械制造有限责任公司 | A tunnel cable trench and water trench construction trolley |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN205349355U (en) * | 2015-12-14 | 2016-06-29 | 黄高飞 | Tunnel ditch cable groove support car |
| CN205370594U (en) * | 2016-02-26 | 2016-07-06 | 福建宏贯路桥防腐科技股份有限公司 | Tunnel cable groove forming device |
| CN105736016B (en) * | 2016-04-27 | 2018-01-19 | 中铁四局集团第一工程有限公司 | Tunnel double-lining framework of steel reinforcement construction equipment and its application |
| CN206617177U (en) * | 2017-03-31 | 2017-11-07 | 成都职业技术学院 | A kind of tunnel ditch cable trough monoblock type formwork jumbo |
| CN207363676U (en) * | 2017-06-30 | 2018-05-15 | 中铁十一局集团汉江重工有限公司 | A kind of self-propelled ditch cable trench trolley |
| KR101867595B1 (en) * | 2017-10-17 | 2018-06-14 | 남용학 | Utility-Pipe Conduit Construction Equipment of Tunnel |
| CN207673352U (en) * | 2017-12-04 | 2018-07-31 | 中铁十二局集团第三工程有限公司 | Cable trough lining trolley |
| CN208236439U (en) * | 2018-05-29 | 2018-12-14 | 湖南五新模板有限公司 | A kind of monoblock type ditch cable trench template automatic job vehicle |
-
2019
- 2019-12-25 CN CN201911357509.0A patent/CN111042835B/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN211737150U (en) * | 2019-12-25 | 2020-10-23 | 都江堰现代机械制造有限责任公司 | A tunnel cable trench and water trench construction trolley |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111042835A (en) | 2020-04-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103015325B (en) | Construction method of cast-in-place concrete crash barrier with eaves | |
| CN104594918B (en) | Split integrated underground passage steel mold plate trolley and construction method thereof | |
| CN106120563A (en) | Cast-in-situ box girder Combined movable mould bases and construction method thereof | |
| CN107165191A (en) | City comprehensive pipe gallery die and using method thereof | |
| CN104533460B (en) | Support replacement formula formwork jumbo and the construction method of underpass concreting | |
| CN106593469A (en) | Trolley for construction of inverted arch | |
| CN208533370U (en) | A kind of Bridge Erector of large span steel reinforced concrete combination beam erection construction | |
| CN110145341A (en) | A combined formwork system for concrete pouring in circular tunnels | |
| CN111042835B (en) | A tunnel cable trench and water trench construction trolley and construction method thereof | |
| CN212294398U (en) | An integral mobile box culvert formwork | |
| CN219865036U (en) | Automatic adjusting system for secondary lining trolley template of pipe gallery | |
| CN205277439U (en) | Rectangle tunnel lining platform truck | |
| CN216515141U (en) | Novel cantilever construction creeping formwork device | |
| CN211737150U (en) | A tunnel cable trench and water trench construction trolley | |
| CN213682135U (en) | A laterally retractable foundation pit support frame based on U-shaped shield machine | |
| CN204419203U (en) | All-hydraulic gantry type ditch, cable trench mould bases chassis | |
| CN112746857A (en) | Full-hydraulic highway tunnel cable trench lining construction device and construction method | |
| CN208168895U (en) | A kind of hydraulic elevation type tunnel cable groove overall movement template system | |
| CN203223230U (en) | Tunnel inverted arch forming template installment device | |
| CN206053965U (en) | A kind of tunnel ditch cable trough construction trolley | |
| CN106939793B (en) | Tunnel Center Ditch Trolley for Efficient Construction | |
| CN206035501U (en) | Tunnel water ditch die carrier device | |
| CN113464166B (en) | Tunnel two-lining continuous construction process based on multi-template type two-lining trolley | |
| CN214464241U (en) | Full-hydraulic lining construction device for cable trench of highway tunnel | |
| CN213653212U (en) | Self-propelled cast-in-place box girder integrated bridge construction machine |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20250310 Address after: No. 96, Xinjian Street, Dujiangyan Irrigation Project Economic Development Zone, Dujiangyan Irrigation Project, Chengdu, Sichuan 611830 Patentee after: Dujiangyan Irrigation Project Tunnel Construction Intelligent Decoration Technology Co.,Ltd. Country or region after: China Address before: 611830 No.7, Jintang Road, Dujiangyan Economic Development Zone, Chengdu, Sichuan Patentee before: DUJIANGYAN MODERN MACHINERY MANUFACTURING CO.,LTD. Country or region before: China |
|
| TR01 | Transfer of patent right |