CN106099768A - Outdoor complicated piping lane cable laying of bridge frame method - Google Patents
Outdoor complicated piping lane cable laying of bridge frame method Download PDFInfo
- Publication number
- CN106099768A CN106099768A CN201610672506.6A CN201610672506A CN106099768A CN 106099768 A CN106099768 A CN 106099768A CN 201610672506 A CN201610672506 A CN 201610672506A CN 106099768 A CN106099768 A CN 106099768A
- Authority
- CN
- China
- Prior art keywords
- cable
- grinding machine
- traction
- laying
- strand grinding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
Abstract
The present invention provides a kind of outdoor complicated piping lane cable laying of bridge frame method, it by arrange pulling equipment, intend release cable carriage, end bondage equipment by cable from cable hank traction to strand grinding machine top crane span structure at, and cable is placed in the crane span structure of regulation, at each keypoint part, responsible person is set;Present invention substantially reduces personnel labor intensity, improve work efficiency, decrease cable laying difficulty, by arranging carriage at cable laying circuit, greatly reduce the scraping of cable, rub etc. and to damage, make the present invention have equipment investment is few, project benefit efficiency high, the safety of personnel and cable is high advantage.
Description
Technical field
The present invention relates to cable laying technical field, be specifically related to a kind of outdoor complicated piping lane cable laying of bridge frame method.
Background technology
Along with Tong Ye company 2 × 104Nm3/h oxygen generating station and the construction of converter system, whole Tong Ye company on-site piping lane
Crane span structure begins to take shape.Complete from the outlet of 110KV transformer station to each 6KV electric substation YJV-6/6KV, 3 × 240mm2 high tension cable
Count 32 (without 1# oxygen generating station altitude chamber to 4, former smelting 4# electric substations) totally 32.7 kilometers, move towards path extremely complex: 1,
In 110KV transformer station, from high-voltage board outlet to vertical shaft.Vertical shaft has two passages, to 110 side high-voltage boards after entrance vertical shaft, interval
Under narrow and small and side walls and altitude chamber, cable trailing arm is triangle ironware, and various equipment cannot be put to good use.2, vertical shaft is to electrolysis plant
South, room enclosure wall, this section is the most straight, about 180 meters.3, in cell room, this section with front two sections the same, be all this and apply from now on
If the common sections of cable, and it is bilateral Multilayer bridge frame.Predominantly it is intended for a people side in a descending grade section, a uphill slope section and Factory Building
Two little curved segment compositions that body passes through.4, shaft part in north, including going the systems such as oxygen generating station, 350 fan stations and Improving Project electrolysis
The cable laying in direction, this time mainly lays 1# oxygen generating station and new power center (PC) Liang Ge electric substation cable.Share gantry part bag
Include three sections of flat segments, one section of descending branch and one period of abrupt slope ascent stage, one section two 90 degree turn round.The crane span structure of remainder is monolateral
Setting up, the crane span structure to new power center (PC) is two 90 degree and turns round and one section of straightway forms, and the crane span structure removing 1# oxygen generating station is then
Three sections of flat segments, falls one liter and three 90 degree are turned round, this segment length about 320 meters.5, electrolysis west section, including removing earth of positive pole comprehensive utilization
With workshop electric substation with electrolysis second phase electric substation cable, this section is straight, only one 90 degree turn round with one at descending grade, but both sides
Unshielded.6, east line crane span structure, this section is the longest, will transform new sulfate system cable, newly lay silver stove power center (PC) cable and pre-
Having stayed the position of Flash Smelting Furnace power center (PC) cable, seemed straight, but turned round at most, periphery protection is not in place, also has part height
Pressure, control, communication, monitor, crane span structure layer used with by the cable such as illumination.
In the face of path is moved towards in above-mentioned and complicated cable laying, use traditional cable laying method can not meet,
And the many employings of cable laying of bridge frame at present are manually laid, for complicated piping lane cable laying of bridge frame, owing to height laid by crane span structure
Height, turns round many, rises descending grade amplitude big, and institute's cabling is long, brings great difficulty to laying, takes traditional cable
Laying method, construction is hard, and personnel labor intensity is big, easily there is potential safety hazard when work high above the ground;Simultaneously cable sheath and
Cable itself also can be the most impaired.
Summary of the invention
It is an object of the invention to provide a kind of outdoor complicated piping lane cable laying of bridge frame method, to solve electricity in prior art
Cable lays the problem that difficulty is big, cable is the most impaired.
To this end, the present invention adopts the following technical scheme that a kind of outdoor complicated piping lane cable laying of bridge frame method, including as follows
Step:
A, equipment are installed: one end being arranged on cabling circuit of pulling equipment arranges a strand grinding machine, and cable reel stent sets
Cable hank pernetti is placed on cable overall length by the cable that putting needs to do medial head according to cabling length more than or equal to 500m
The center of degree;The terminal being then placed on cable laying circuit less than 500m, it is simple to the steel wire rope folding and unfolding of folding and unfolding steel wire rope
Frame be arranged on strand grinding machine side, by strand grinding machine tractive after by wirerope-winding on steel wire rope retractable frame;
Intend release cable carriage installation, intend release cable carriage include movable pulley, guide fixed pulley, support wheel,
Lower pressure wheel, deflecting roller, described movable pulley is arranged on cable testing bridge walkway board, and described guiding fixed pulley is arranged on the upper of strand grinding machine
Side and lower section, described support wheel is arranged on the position that cable testing bridge declines, and described lower pressure wheel is arranged on the position that cable testing bridge rises
Putting, described deflecting roller is arranged on the position that cable testing bridge turns to;
End bondage equipment includes end traction casing, middle traction casing, wire rope connector, traction cone, is bored by traction
Cable is connected with pull rope;
After the installation of B: equipment is in place, steel wire rope is sequentially passed through guiding fixed pulley, movable pulley, lower pressure wheel, support from strand grinding machine end
Wheel and deflecting roller, cable hank above support take turns to cable reel stent end;Pull rope is started reverse with artificial from strand grinding machine side
Move at cable reel stent, traction cone is loaded in traction casing, further rise and strain traction casing gently after being entangled by cable, pass through steel
Cable is connected by cord adapter with pull rope;
C, startup strand grinding machine, drawn cable to the crane span structure on strand grinding machine top from cable hank by pull rope, and cable to enter
During switchgear house, remove end traction casing, and be replaced with middle traction casing, according to cable testing bridge to switchgear house power distribution cabinet away from
From, to measure cable length, herein, centre traction casing is connected with cable, be again started up twisting grinding machine, trailing cable, by artificial controlled
Cable louding processed, slowly by cable pulling to power distribution cabinet position, completes cable pulling;
D, after cable tractive puts in place, start to be placed in the crane span structure of regulation cable from cable hank end, until cable laying line
Road terminal;
E, at strand grinding machine, cable hank point of release, it is respectively configured a staff is responsible for twisting the start and stop communication of grinding machine and electricity
Cable traction and cable hank cable release work, be respectively configured a staff at each flex point, the turning of cable laying circuit
Be responsible for the pull rope of both sides at flex point, deflecting roller, cable by work;Rising, drop point at cable laying circuit crane span structure
It is respectively configured a staff and is responsible for each support wheel, the work of lower pressure wheel.
Further, twisting grinding machine and be bolted on platform in described step A, described platform passes through channel-section steel, angle steel
It is welded.
Further, described step D reserves 1m-2m cable at the turning point, flex point of cable laying circuit.
Further, the described angular movable pulley of place arrangement being more than 15 ° in cable testing bridge trend.
Further, described step D by cable laying circuit tilts, vertical, the cable BV electric wire of climb and fall section enters
Row colligation.
The invention has the beneficial effects as follows: greatly reduce personnel labor intensity, improve work efficiency, decrease cable and apply
If difficulty, by arranging carriage at cable laying circuit, greatly reduce the scraping of cable, rub etc. and to damage, make the present invention have
Have that equipment investment is few, project benefit efficiency high, advantage that the safety of personnel and cable is high.
Accompanying drawing explanation
Fig. 1 is cable laying line construction schematic diagram of the present invention.
In figure: 1, steel wire rope retractable frame;2, strand grinding machine;3, steel wire rope;4, wheel is supported;5, movable pulley;6, lower pressure wheel;7, turn
To wheel;8, wire rope connector;9, end traction casing;10, cable reel stent;11 cable hanks.
Detailed description of the invention
Below the present invention is described in further details.
Select the strand grinding machine of 5 tons of pull strengths, model JJM5-C, input power 4.4Kw, rated load weight 5T at a slow speed, quickly
2.5T, at a slow speed 4.5m/min, quick 8.5m/min;∮ 13 anti-twisting steel wire rope.Tractive auxiliary equipment mainly has end traction casing
∮ 80, middle traction casing ∮ 80, wire rope connector, traction cone.
A kind of outdoor complicated piping lane cable laying of bridge frame method, comprises the steps:
A, equipment are installed: one end being arranged on cabling circuit of pulling equipment arranges a strand grinding machine 2, cable reel stent 10
Arranging needs to do the cable of medial head according to cabling length more than or equal to 500m that cable reel stent 10 is placed on cable is total
The center of length;The terminal being then placed on cable laying circuit less than 500m, it is simple to the steel wire rope of folding and unfolding steel wire rope is received
Put frame 1 and be arranged on strand grinding machine 2 side, after the tractive by strand grinding machine 2, steel wire rope 3 is wrapped on steel wire rope retractable frame 1;
Intend the installation of release cable carriage, intend release cable carriage and include movable pulley 5, guiding fixed pulley, support wheel
4, lower pressure wheel 6, deflecting roller 7, movable pulley 5 is arranged on cable testing bridge walkway board with 2m uniformly for spacing, guides fixed pulley and sets
Putting above and below strand grinding machine 2, support wheel 4 and be arranged on the position that cable testing bridge declines, lower pressure wheel 6 is arranged on cable testing bridge
The position risen, deflecting roller 7 is arranged on the position that cable testing bridge turns to;
End bondage equipment includes end traction casing 9, middle traction casing, wire rope connector 8, traction cone, by traction
Cable is connected by cone with pull rope;
B: equipment install in place after, by steel wire rope 3 from strand grinding machine 2 end sequentially pass through guiding fixed pulley, movable pulley 5, lower pressure wheel 6,
Support the support above wheel 4 and deflecting roller 7, cable hank 11 and take turns to cable reel stent 10 end;By pull rope from the beginning of strand grinding machine 2 side
Reverse with manually moving at cable reel stent 10, traction cone is loaded in traction casing, further rises and strain gently after cable is entangled
Traction casing, is connected cable with pull rope by wire rope connector 8;
C, startup strand grinding machine 2, drawn cable to the crane span structure on strand grinding machine 2 top from cable hank 11 by pull rope, and cable is wanted
When entering switchgear house, remove end traction casing 9, and be replaced with middle traction casing, according to cable testing bridge to switchgear house power distribution cabinet
Distance, measure cable length, herein, centre traction casing is connected with cable, be again started up strand grinding machine 2, trailing cable, by
Artificial Control cable louding, slowly by cable pulling to power distribution cabinet position, completes cable pulling;
D, after cable tractive puts in place, start to be placed in the crane span structure of regulation cable from cable hank 11 end, until cable laying
Circuit terminal;
E, strand grinding machine 2, cable hank 11 point of release at be respectively configured a staff be responsible for twist grinding machine 2 start and stop communication
And cable pulling and cable hank 11 cable release work, it is respectively configured a work at each flex point, the turning of cable laying circuit
As personnel be responsible for the pull rope of both sides at flex point, deflecting roller, cable by work;Cable laying circuit crane span structure rising,
Drop point is respectively configured a staff and is responsible for each support wheel 4, the work of lower pressure wheel 6.
Strand grinding machine 2 is bolted on platform, and platform is welded by channel-section steel, angle steel;It is strictly on guard against tractive cable
Pulling force promotes strand mill, prevents the shake of strand mill from the power of letting out occur, makes cable laying circuit crane span structure to damage.
Step D reserves 1m-2m cable at the turning point, flex point of cable laying circuit;Convenient by turning point, flex point
Cable unloads from pulley.
Dispose angular movable pulley in the cable testing bridge trend place more than 15 °, reduce pull rope, cable on piping lane frame
Frictional force, prevents from scratching cable, reduces cable bad.
Step D by cable laying circuit tilts, vertical, the cable BV electric wire of climb and fall section carry out colligation;Make each curved
Good sag, camber is kept, it is to avoid cable is because expanding with heat and contract with cold phenomenon and unbalance stress causes damage at angle.
The cable manually dragged is the most also on sliding apparatus, facility, and the most both safety did not hinder cable joint-box, the most laborsaving;Also
There is the speed manually dragging cable basically identical with the speed of the strand main traction of mill, prevent cable accumulation, hair fastener from damaging cable.
Claims (5)
1. an outdoor complicated piping lane cable laying of bridge frame method, it is characterised in that comprise the steps:
A, equipment are installed: one end being arranged on cabling circuit of pulling equipment arranges a strand grinding machine, and cable reel stent sets
Cable hank pernetti is placed on cable overall length by the cable that putting needs to do medial head according to cabling length more than or equal to 500m
The center of degree;The terminal being then placed on cable laying circuit less than 500m, it is simple to the steel wire rope folding and unfolding of folding and unfolding steel wire rope
Frame be arranged on strand grinding machine side, by strand grinding machine tractive after by wirerope-winding on steel wire rope retractable frame;
Intend release cable carriage installation, intend release cable carriage include movable pulley, guide fixed pulley, support wheel,
Lower pressure wheel, deflecting roller, described movable pulley is arranged on cable testing bridge walkway board, and described guiding fixed pulley is arranged on the upper of strand grinding machine
Side and lower section, described support wheel is arranged on the position that cable testing bridge declines, and described lower pressure wheel is arranged on the position that cable testing bridge rises
Putting, described deflecting roller is arranged on the position that cable testing bridge turns to;
End bondage equipment includes end traction casing, middle traction casing, wire rope connector, traction cone, is bored by traction
Cable is connected with pull rope;
After the installation of B: equipment is in place, steel wire rope is sequentially passed through guiding fixed pulley, movable pulley, lower pressure wheel, support from strand grinding machine end
Wheel and deflecting roller, cable hank above support take turns to cable reel stent end;Pull rope is started reverse with artificial from strand grinding machine side
Move at cable reel stent, traction cone is loaded in traction casing, further rise and strain traction casing gently after being entangled by cable, pass through steel
Cable is connected by cord adapter with pull rope;
C, startup strand grinding machine, drawn cable to the crane span structure on strand grinding machine top from cable hank by pull rope, and cable to enter
During switchgear house, remove end traction casing, and be replaced with middle traction casing, according to cable testing bridge to switchgear house power distribution cabinet away from
From, to measure cable length, herein, centre traction casing is connected with cable, be again started up twisting grinding machine, trailing cable, by artificial controlled
Cable louding processed, slowly by cable pulling to power distribution cabinet position, completes cable pulling;
D, after cable tractive puts in place, start to be placed in the crane span structure of regulation cable from cable hank end, until cable laying line
Road terminal;
E, at strand grinding machine, cable hank point of release, it is respectively configured a staff is responsible for twisting the start and stop communication of grinding machine and electricity
Cable traction and cable hank cable release work, be respectively configured a staff at each flex point, the turning of cable laying circuit
Be responsible for the pull rope of both sides at flex point, deflecting roller, cable by work;Rising, drop point at cable laying circuit crane span structure
It is respectively configured a staff and is responsible for each support wheel, the work of lower pressure wheel.
Outdoor complicated piping lane cable laying of bridge frame method the most according to claim 1, it is characterised in that: in described step A
Strand grinding machine is bolted on platform, and described platform is welded by channel-section steel, angle steel.
Outdoor complicated piping lane cable laying of bridge frame method the most according to claim 1, it is characterised in that: in described step D
1m-2m cable is reserved at the turning point, flex point of cable laying circuit.
Outdoor complicated piping lane cable laying of bridge frame method the most according to claim 1, it is characterised in that: described deposited at cable
If line alignment disposes angular movable pulley more than the place of 15 ° of angles.
Outdoor complicated piping lane cable laying of bridge frame method the most according to claim 1, it is characterised in that: described step D will
Tilt in cable laying circuit, vertical, the cable BV electric wire of climb and fall section carries out colligation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610672506.6A CN106099768B (en) | 2016-08-16 | 2016-08-16 | Outdoor complicated piping lane cable laying of bridge frame method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610672506.6A CN106099768B (en) | 2016-08-16 | 2016-08-16 | Outdoor complicated piping lane cable laying of bridge frame method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106099768A true CN106099768A (en) | 2016-11-09 |
CN106099768B CN106099768B (en) | 2018-04-10 |
Family
ID=58071071
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610672506.6A Active CN106099768B (en) | 2016-08-16 | 2016-08-16 | Outdoor complicated piping lane cable laying of bridge frame method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106099768B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106505484A (en) * | 2016-12-27 | 2017-03-15 | 二十二冶集团天津建设有限公司 | Piping lane cable laying method |
CN106786193A (en) * | 2016-12-26 | 2017-05-31 | 浙江舟山启明电力集团公司海缆工程公司 | Long range intertidal zone submarine cable logs in cable laying operation operational method and system |
CN107302195A (en) * | 2017-08-23 | 2017-10-27 | 中国十九冶集团有限公司 | A kind of cable laying method |
CN107359550A (en) * | 2017-08-25 | 2017-11-17 | 中国十七冶集团有限公司 | A kind of big cable of converter oxygen gun main motor colligation laying method on the way |
CN110474259A (en) * | 2019-08-30 | 2019-11-19 | 北京海瑞兴能源科技有限责任公司 | Log in section cable laying system and a laying method |
CN114927988A (en) * | 2022-05-19 | 2022-08-19 | 中铁武汉电气化局集团有限公司城市建设分公司 | Basement power cable laying system |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10224932A (en) * | 1997-02-13 | 1998-08-21 | Nishi Nippon Plant Kogyo Kk | Cable lead guide device |
CN2932778Y (en) * | 2006-08-16 | 2007-08-08 | 江南造船(集团)有限责任公司 | Cable laying device |
CN101478124A (en) * | 2009-02-18 | 2009-07-08 | 中建八局第一建设有限公司 | Automatic laying method for electric cable and apparatus thereof |
KR20120083753A (en) * | 2011-01-18 | 2012-07-26 | 삼성중공업 주식회사 | Cable guiding device |
CN202534990U (en) * | 2012-03-05 | 2012-11-14 | 上海市电力公司 | Equipment used for laying cables in underground tunnel |
CN203456805U (en) * | 2013-09-25 | 2014-02-26 | 中国化学工程第六建设有限公司 | Large cross-section cable mechanization laying device |
CN104377603A (en) * | 2014-12-04 | 2015-02-25 | 中石化胜利建设工程有限公司 | Device for laying cables in horizontal cable trays and application method of device |
CN104426092A (en) * | 2013-08-21 | 2015-03-18 | 大宇造船海洋株式会社 | Transport device for laying power lines |
CN105226574A (en) * | 2015-11-05 | 2016-01-06 | 山西省工业设备安装有限公司 | Cable laying method and lay part |
CN205265154U (en) * | 2015-12-23 | 2016-05-25 | 中国核工业第五建设有限公司 | Pulley type cable laying device |
-
2016
- 2016-08-16 CN CN201610672506.6A patent/CN106099768B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10224932A (en) * | 1997-02-13 | 1998-08-21 | Nishi Nippon Plant Kogyo Kk | Cable lead guide device |
CN2932778Y (en) * | 2006-08-16 | 2007-08-08 | 江南造船(集团)有限责任公司 | Cable laying device |
CN101478124A (en) * | 2009-02-18 | 2009-07-08 | 中建八局第一建设有限公司 | Automatic laying method for electric cable and apparatus thereof |
KR20120083753A (en) * | 2011-01-18 | 2012-07-26 | 삼성중공업 주식회사 | Cable guiding device |
CN202534990U (en) * | 2012-03-05 | 2012-11-14 | 上海市电力公司 | Equipment used for laying cables in underground tunnel |
CN104426092A (en) * | 2013-08-21 | 2015-03-18 | 大宇造船海洋株式会社 | Transport device for laying power lines |
CN203456805U (en) * | 2013-09-25 | 2014-02-26 | 中国化学工程第六建设有限公司 | Large cross-section cable mechanization laying device |
CN104377603A (en) * | 2014-12-04 | 2015-02-25 | 中石化胜利建设工程有限公司 | Device for laying cables in horizontal cable trays and application method of device |
CN105226574A (en) * | 2015-11-05 | 2016-01-06 | 山西省工业设备安装有限公司 | Cable laying method and lay part |
CN205265154U (en) * | 2015-12-23 | 2016-05-25 | 中国核工业第五建设有限公司 | Pulley type cable laying device |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106786193A (en) * | 2016-12-26 | 2017-05-31 | 浙江舟山启明电力集团公司海缆工程公司 | Long range intertidal zone submarine cable logs in cable laying operation operational method and system |
CN106786193B (en) * | 2016-12-26 | 2018-08-21 | 浙江舟山启明电力集团公司海缆工程公司 | Long range intertidal zone submarine cable logs in cable laying operation operational method and system |
CN106505484A (en) * | 2016-12-27 | 2017-03-15 | 二十二冶集团天津建设有限公司 | Piping lane cable laying method |
CN107302195A (en) * | 2017-08-23 | 2017-10-27 | 中国十九冶集团有限公司 | A kind of cable laying method |
CN107359550A (en) * | 2017-08-25 | 2017-11-17 | 中国十七冶集团有限公司 | A kind of big cable of converter oxygen gun main motor colligation laying method on the way |
CN110474259A (en) * | 2019-08-30 | 2019-11-19 | 北京海瑞兴能源科技有限责任公司 | Log in section cable laying system and a laying method |
CN114927988A (en) * | 2022-05-19 | 2022-08-19 | 中铁武汉电气化局集团有限公司城市建设分公司 | Basement power cable laying system |
Also Published As
Publication number | Publication date |
---|---|
CN106099768B (en) | 2018-04-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106099768A (en) | Outdoor complicated piping lane cable laying of bridge frame method | |
RU2461935C1 (en) | High-voltage overhead power transmission line and method of erection of high-voltage overhead power transmission line | |
CN108736377B (en) | Live crossing system for paying-off construction crossing power line and application method thereof | |
CN102290742A (en) | Tension stringing construction technology | |
CN102664358B (en) | Live replacement method for static contact of 220 kV flexible busbar | |
RU2461937C1 (en) | Distribution system and method of distribution system maintenance | |
CN201332231Y (en) | Power line casting and reeling device for overhead line | |
CN105932601B (en) | Disconnected strand of overhead grounding wire method for repairing and mending | |
CN102593759B (en) | One-pulling-two expansion and construction process of large-section lead | |
CN204190260U (en) | A kind of high pressure power transmission and distribution cable sets up facility across road | |
CN101707335A (en) | Large cable laying device | |
RU2461939C1 (en) | High-voltage overhead line and repair method for high-voltage overhead line | |
CN204361586U (en) | High-tension cable lays uses device | |
CN207010098U (en) | A kind of electric wire payout stand | |
CN205450398U (en) | Optical cable unwrapping wire coaster for transmission line of intelligent control | |
CN114256774A (en) | Construction method for erecting power supply line of contact network based on unmanned aerial vehicle technology | |
CN208904543U (en) | A kind of pulley block | |
CN201663387U (en) | Large cable laying device | |
RU2594208C1 (en) | Method of erecting high-voltage overhead transmission line and high-voltage overhead power transmission line, built using said method | |
RU2594207C1 (en) | Method of erecting high-voltage overhead transmission line and high-voltage overhead power transmission line, built using said method | |
RU2585627C1 (en) | Method of erecting high-voltage overhead transmission line and high-voltage overhead power transmission line, built using said method | |
CN211063216U (en) | Power supply cable laying device for coal mine power supply | |
RU2594219C1 (en) | Method of erecting high-voltage overhead transmission line and high-voltage overhead power transmission line, built using said method | |
CN215101087U (en) | Optical cable paying-off electric device with remote control lifting platform | |
CN208272540U (en) | A kind of stockyard mobile power supply equipment cable support device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200610 Address after: 730900 No.31 Yinshan Road, Baiyin District, Baiyin City, Gansu Province Co-patentee after: BAIYIN NONFERROUS METALS GROUP Co.,Ltd. Patentee after: BAIYIN NONFERROUS POWER Co.,Ltd. Address before: 730900 Friendship Road 96, Baiyin District, Gansu, Baiyin Patentee before: BAIYIN NONFERROUS METALS GROUP Co.,Ltd. |