CN201332231Y - Power line casting and reeling device for overhead line - Google Patents

Power line casting and reeling device for overhead line Download PDF

Info

Publication number
CN201332231Y
CN201332231Y CNU2008201237565U CN200820123756U CN201332231Y CN 201332231 Y CN201332231 Y CN 201332231Y CN U2008201237565 U CNU2008201237565 U CN U2008201237565U CN 200820123756 U CN200820123756 U CN 200820123756U CN 201332231 Y CN201332231 Y CN 201332231Y
Authority
CN
China
Prior art keywords
transmission line
line power
main shaft
overhead transmission
retractable cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008201237565U
Other languages
Chinese (zh)
Inventor
田成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Electric Power Corp
State Grid Corp of China SGCC
Original Assignee
Beijing Electric Power Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Electric Power Corp filed Critical Beijing Electric Power Corp
Priority to CNU2008201237565U priority Critical patent/CN201332231Y/en
Application granted granted Critical
Publication of CN201332231Y publication Critical patent/CN201332231Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本实用新型提供了一种架空线路动力收放线设备,特别地,该设备包括:支架;主轴,可转动地支撑在支架中;卷线盘,可拆卸地套设于主轴上;传动装置,设置在支架上并连接于主轴;电动机,设置在支架上并连接于传动装置;以及调速控制装置,设置在支架上并电连接于电动机。本实用新型的架空线路动力收放线设备采用动力操作,可以大量节省人力,收放线速度比人工拽线提高几倍,放线速度均匀、可控,同时旧导线又自动盘成捆,省去人工最后再盘旧导线的环节,另外,利用根据本实用新型的架空线路动力收放线设备进行紧线,可以减少在架线时的导线余量。

The utility model provides a power take-up and pay-off equipment for overhead lines, in particular, the equipment includes: a bracket; a main shaft, rotatably supported in the bracket; a reel, detachably sleeved on the main shaft; a transmission device, It is arranged on the bracket and connected to the main shaft; the motor is arranged on the bracket and connected to the transmission device; and the speed regulation control device is arranged on the bracket and electrically connected to the motor. The power take-up and pay-off equipment for overhead lines of the utility model adopts power operation, which can save a lot of manpower. Eliminate the link of rewinding the old wires manually at the end. In addition, using the power take-up and release equipment for overhead lines according to the utility model to tighten the wires can reduce the wire margin when erecting the wires.

Description

架空线路动力收放线设备 Power take-up and pay-off equipment for overhead lines

技术领域 technical field

本实用新型涉及电力领域,并且具体地涉及架空线路动力收放线设备。The utility model relates to the field of electric power, and in particular to power take-up and release equipment for overhead lines.

背景技术 Background technique

在电力工程中,线路的铺设任务繁重,经常需要将不符合标准的旧的架空线路改造成新的架空线路,并经常需要新建架空线路。在以前的架空线路改造过程中,收放线时均采用人工操作,工作人员在线路的两端奔走,既浪费时间又影响工作效率,同时,由于人员的增加,相应地增加了管理难度,造成了安全隐患。In electric power engineering, the task of laying lines is arduous. It is often necessary to transform old overhead lines that do not meet the standards into new overhead lines, and often to build new overhead lines. In the previous reconstruction process of overhead lines, manual operation was used when receiving and releasing the lines, and the staff ran around at both ends of the lines, which not only wasted time but also affected work efficiency. safety hazard.

例如,针对10kv架空线路传统的放紧线工作而言,采用人工或车辆拽线,受到施工环境、地形、天气等诸多因素的限制。工作人员既要上杆过线又要到线路的一端紧线,忙碌奔波非常劳累,并且还需要十几个工人拽线,最后还需要人工回收旧导线,工作效率低。因此,需要一种动力收放线设备来完成上述的收放线及紧线任务。For example, for the traditional line tensioning work of 10kv overhead lines, the use of manual or vehicle pulling lines is limited by many factors such as the construction environment, terrain, and weather. The staff have to go up the pole to cross the line and go to one end of the line to tighten the line. Busy running is very tiring, and more than a dozen workers are required to pull the line, and finally need to manually recycle the old wire, which is low in work efficiency. Therefore, a kind of power take-up and pay-off equipment is needed to complete the above-mentioned take-up and pay-off and tightening tasks.

实用新型内容 Utility model content

本实用新型正是致力于克服现有技术的上述缺陷而作出的。本实用新型的目的在于提供一种动力架空线路收放线设备,以便减少收放线过程中所需的大量人力劳动,并提高收放线工作效率和安全性,简化收放线的操作过程。The utility model is devoted to overcoming the above-mentioned defective of prior art just and makes. The purpose of the utility model is to provide a power overhead line retracting and releasing equipment, so as to reduce a large amount of human labor required in the process of retracting and releasing the cables, improve the work efficiency and safety of the retracting and releasing cables, and simplify the operation process of the retracting and releasing cables.

为解决上述技术问题,本实用新型提供了一种架空线路动力收放线设备,特别地,该设备包括:支架;主轴,可枢转地支撑在支架中;卷线盘,可拆卸地套设于主轴上;传动装置,设置在支架上并连接于主轴;电动机,设置在支架上并连接于传动装置;以及调速控制装置,设置在支架上并电连接于电动机。In order to solve the above technical problems, the utility model provides a power take-up and pay-off equipment for overhead lines, in particular, the equipment includes: a bracket; a main shaft, which is pivotally supported in the bracket; on the main shaft; the transmission device is arranged on the bracket and connected to the main shaft; the motor is arranged on the bracket and connected to the transmission device; and the speed control device is arranged on the bracket and electrically connected to the motor.

优选地,根据本实用新型的架空线路动力收放线设备,其中,支架两侧均设置有高度可调的主轴支承部件,该主轴支承部件中设置有至少一对滚动轴承,主轴支撑在至少一对滚动轴承之间。Preferably, according to the power take-up and pay-off equipment for overhead lines of the present utility model, height-adjustable main shaft supporting parts are arranged on both sides of the bracket, at least one pair of rolling bearings are arranged in the main shaft supporting part, and the main shaft is supported on at least one pair of between rolling bearings.

优选地,根据本实用新型的架空线路动力收放线设备,其中,主轴支承部件具有提拉部,支架两侧的顶部处各自安装有被钢索绕过的定滑轮,钢索的一端可连接于提拉部。Preferably, according to the power take-up and pay-off equipment for overhead lines of the present utility model, the main shaft supporting part has a lifting part, fixed pulleys bypassed by steel cables are respectively installed at the tops of both sides of the support, and one end of the steel cables can be connected to Yu Tila Department.

优选地,根据本实用新型的架空线路动力收放线设备,其中,传动装置包括:涡轮蜗杆减速机,设置在支架上并邻近电动机;两个第一皮带轮,分别安装在电动机上和涡轮蜗杆减速机上,并且两个第一皮带轮处于同一水平高度;第一皮带,环绕两个第一皮带轮;第二皮带轮,安装于涡轮蜗杆减速机的侧部;第三皮带轮,安装于卷线盘的侧部,第二皮带轮与第三皮带轮位于同一垂直平面中;以及第二皮带,环绕第二皮带轮与第三皮带轮。Preferably, according to the power take-up and pay-off equipment for overhead lines of the present utility model, the transmission device includes: a worm gear reducer, arranged on the support and adjacent to the motor; two first pulleys, respectively installed on the motor and the worm reducer On the machine, and the two first pulleys are at the same level; the first belt, around the two first pulleys; the second pulley, installed on the side of the worm gear reducer; the third pulley, installed on the side of the reel , the second pulley and the third pulley are in the same vertical plane; and a second belt wraps around the second pulley and the third pulley.

优选地,根据本实用新型的架空线路动力收放线设备,其中,卷线盘包括至少一个用于卷绕缆线的卷轴部。Preferably, in the power take-up and take-off equipment for overhead lines according to the present invention, the wire reel includes at least one reel portion for winding the cable.

优选地,根据本实用新型的架空线路动力收放线设备还包括:车轮,安装在支架的两侧并支撑支架;以及牵引架,固定至支架的前端。Preferably, the power take-up and pay-off equipment for overhead lines according to the present invention further includes: wheels installed on both sides of the support and supporting the support; and a traction frame fixed to the front end of the support.

优选地,根据本实用新型的架空线路动力收放线设备,其中,牵引架包括两个侧梁以及连接在侧梁之间的横梁,牵引架的前端具有牵引环。Preferably, according to the power take-up and pay-off equipment for overhead lines of the present invention, the traction frame includes two side beams and a beam connected between the side beams, and the front end of the traction frame has a traction ring.

优选地,根据本实用新型的架空线路动力收放线设备,还包括设置在电杆柱顶上的转角放线滑轮,转角放线滑轮由楔形支承件支撑。Preferably, the overhead line power take-up and pay-off equipment according to the utility model further includes a corner pay-off pulley arranged on the pole top, and the corner pay-off pulley is supported by a wedge-shaped support.

优选地,根据本实用新型的架空线路动力收放线设备,发电机,该发电机电连接至电动机。Preferably, the power take-up and take-off equipment for overhead lines according to the present utility model is a generator, and the generator is electrically connected to the motor.

优选地,根据本实用新型的架空线路动力收放线设备,其中,卷线盘包括3个用于卷绕缆线的卷轴部。Preferably, according to the power take-up and take-off equipment for overhead lines of the present invention, the wire reel includes three reel parts for winding cables.

本实用新型具有以下技术效果:The utility model has the following technical effects:

首先,根据本实用新型的架空线路动力收放线设备实现了机械化的收放线操作,可以显著减少收放线过程中的人力消耗;First of all, the power take-up and take-off equipment for overhead lines according to the utility model realizes the mechanized take-up and take-off operation, which can significantly reduce the manpower consumption in the take-up and take-off process;

其次,根据本实用新型的架空线路动力收放线设备采用电动机驱动卷线盘进行收放线操作,从收放线速度比人工拽线提高3倍,且通过调速控制装置确保放线速度均匀、可控,同时,可以在收旧线的同时布置新线,且旧线可自动卷绕在卷线盘上,省去人工盘旧导线的环节,总体上比传统工作效率提高3-4倍。Secondly, the power take-up and pay-off equipment for overhead lines according to the utility model adopts the electric motor to drive the reel to carry out the take-up and take-off operation, and the take-up and take-off speed is 3 times higher than that of manual pulling, and the speed control device ensures that the take-off speed is uniform , controllable, and at the same time, new wires can be arranged while collecting old wires, and the old wires can be automatically wound on the reel, eliminating the need to manually reel the old wires, and the overall efficiency is 3-4 times higher than the traditional work .

此外,根据本实用新型的架空线路动力收放线设备采用无级变速电动机进行驱动,放线平稳,放线速度0-50米/分钟无级调速,紧线拉力可控,当拽线拉力超过所设定值电动机会自动停止,从而安全性能比车辆拽线方法明显提高。In addition, the power take-up and pay-off equipment for overhead lines according to the utility model is driven by a stepless variable speed motor, the pay-off is stable, the pay-off speed is 0-50 m/min stepless speed regulation, and the tension of the wire is controllable. The electric motor will stop automatically if the set value is exceeded, so the safety performance is obviously improved compared with the vehicle pulling wire method.

总之,采用根据本实用新型的架空线路动力收放线设备可以提高现场工作人员安全性能、降低工作人员的劳动强度,节约人工、节省新导线、旧导线充分回收利用,为企业增加经济效益。In a word, the use of the overhead line power take-up and release equipment according to the utility model can improve the safety performance of on-site workers, reduce the labor intensity of the workers, save labor, save new wires, fully recycle old wires, and increase economic benefits for enterprises.

应该理解,以上的一般性描述和以下的详细描述都是列举和说明性质的,目的是为了对要求保护的本实用新型提供进一步的说明。It should be understood that both the above general description and the following detailed description are enumerative and explanatory, and the purpose is to provide further explanation of the claimed utility model.

附图说明 Description of drawings

附图组成本说明书的一部分,用来帮助进一步理解本实用新型。附图中:The accompanying drawings constitute a part of this specification and are used to help further understand the utility model. In the attached picture:

图1是示出了根据本实用新型的一个优选实施例的架空线路动力收放线设备的俯视示意图;Fig. 1 is a schematic top view showing a power take-up and pay-off equipment for overhead lines according to a preferred embodiment of the present invention;

图2是示出了根据本实用新型的一个优选实施例的架空线路动力收放线设备的侧视示意图;Fig. 2 is a schematic side view showing a power take-up and take-off equipment for overhead lines according to a preferred embodiment of the present invention;

图3是示出了根据本实用新型的另一优选实施例的架空线路动力收放线设备的俯视示意图;Fig. 3 is a schematic top view showing a power take-up and take-off equipment for overhead lines according to another preferred embodiment of the present invention;

图4是示出了根据本实用新型的又一优选实施例的架空线路动力收放线设备的主轴支撑部件的侧视示意图;Fig. 4 is a schematic side view showing the main shaft supporting part of the overhead line power take-up and take-off equipment according to another preferred embodiment of the present invention;

图5是示出了根据本实用新型的转角放线滑轮的示意图;以及Fig. 5 is a schematic diagram showing a corner pay-off pulley according to the utility model; and

图6是示出了根据本实用新型的转角放线滑轮的使用状态的示意图。Fig. 6 is a schematic view showing the use state of the corner pay-off pulley according to the present invention.

具体实施方式 Detailed ways

下面将结合附图详细说明本实用新型的具体实施方式。应注意,下文仅对本实用新型与现有技术不同的特征进行说明,对于在现有技术中可以发现的技术特征,这里就不赘述了。The specific embodiment of the utility model will be described in detail below in conjunction with the accompanying drawings. It should be noted that the following only describes the features of the utility model that are different from the prior art, and the technical features that can be found in the prior art will not be repeated here.

首先参照图1,其示出了根据本实用新型的一个优选实施例的架空线路动力收放线设备的俯视示意图。从图中1可以看出,根据本实用新型的该实施例的架空线路动力收放线设备包括:支架9;主轴10,可枢转地设置在支架9中;可拆卸的卷线盘8,套设于主轴10上;传动装置,其包括设置在支架上并邻近电动机1的涡轮蜗杆减速机2、分别安装在电动机1上和涡轮蜗杆减速机2上并处于同一水平高度的两个第一皮带轮3、环绕两个第一皮带轮3的第一皮带6、安装于涡轮蜗杆减速机2侧部的第二皮带轮4、安装在卷线盘8侧部并与第二皮带轮4位于同一垂直平面中的第三皮带轮5、及环绕第二皮带轮4和第三皮带轮5的第二皮带7;电动机1,通过传动装置驱动主轴10转动;调速控制装置,具体为过电流自动停机无级变速控制器14,该控制器14控制电动机1的转速;以及车辆,其具有安装在支架两侧并支撑该支架的车轮12以及固定至支架前端的牵引架11,具体地,该牵引架为等腰三角形,其包括两个侧梁11a、11b以及连接这两个侧梁的横梁11c,在两个侧梁的相交处具有牵引环11d;以及三相汽油发电机(未示出),作为电动机11的电源。可以理解的是,车辆的设置是用于将架空线路动力收放线设备运输至合适的位置,以减轻搬运该设备所造成的人力消耗。Referring first to FIG. 1 , it shows a schematic top view of a power take-up and take-off equipment for overhead lines according to a preferred embodiment of the present invention. As can be seen from Figure 1, the power take-up and pay-off equipment for overhead lines according to this embodiment of the utility model includes: a bracket 9; a main shaft 10, which is pivotally arranged in the bracket 9; a detachable reel 8, Sleeved on the main shaft 10; the transmission device includes a worm gear reducer 2 arranged on the bracket and adjacent to the motor 1, two first gears installed on the motor 1 and the worm gear reducer 2 respectively and at the same level The pulley 3, the first belt 6 surrounding the two first pulleys 3, the second pulley 4 installed on the side of the worm reducer 2, installed on the side of the reel 8 and located in the same vertical plane as the second pulley 4 The third pulley 5 and the second belt 7 surrounding the second pulley 4 and the third pulley 5; the motor 1 drives the main shaft 10 to rotate through the transmission device; the speed control device is specifically an over-current automatic stop stepless speed change controller 14, the controller 14 controls the rotating speed of the motor 1; and the vehicle, which has wheels 12 installed on both sides of the support and supports the support and a traction frame 11 fixed to the front end of the support, specifically, the traction frame is an isosceles triangle, It consists of two side beams 11a, 11b and a cross beam 11c connecting them, with a traction ring 11d at the intersection of the two side beams; . It can be understood that the setting of the vehicle is used to transport the overhead line power take-up and pay-off equipment to a suitable location, so as to reduce the manpower consumption caused by carrying the equipment.

图2是示出了根据本实用新型的一个优选实施例的架空线路动力收放线设备的侧视示意图。同时参照图1和图2可以更加清楚地说明根据本实用新型的该优选实施例的架空线路动力收放线设备的工作原理及具体实施方法。其中,通过三相汽油发电机(未示出)(功率为5.5千瓦)驱动无级电动机1(功率为3千瓦),该电动机1输出动力通过第一皮带轮3和第一皮带6输送至涡轮蜗杆变速器2,而后经过第二皮带轮4、第三皮带轮5及第二皮带7输送至主轴10带动该主轴10旋转从而带动卷线盘8旋转,即可完成收放线以及紧线工作。Fig. 2 is a schematic side view showing the power take-up and take-off equipment for overhead lines according to a preferred embodiment of the present invention. Referring to Fig. 1 and Fig. 2 at the same time, the working principle and specific implementation method of the power take-up and pay-off equipment for overhead lines according to this preferred embodiment of the present utility model can be more clearly explained. Wherein, a stepless motor 1 (power of 3 kilowatts) is driven by a three-phase gasoline generator (not shown) (power of 5.5 kilowatts), and the output power of the motor 1 is delivered to the worm gear through the first pulley 3 and the first belt 6. The speed changer 2 is then delivered to the main shaft 10 through the second pulley 4, the third pulley 5 and the second belt 7 to drive the main shaft 10 to rotate so as to drive the reel 8 to rotate, and then the winding and unwinding and tightening work can be completed.

采用根据本实用新型的架空线路动力收放线设备进行新旧线更换的基本过程如下。在操作时,在线路的放线端将新导线与旧导线牢固连接,在线路的收线端将旧导线与该动力收放线设备连接(即,将旧导线缠绕在卷线盘8上),启动设备后,回收旧导线的同时就可将新导线敷设在线路上。根据实际工作情况(诸如,导线垂度、线路挡距)计算出紧线的导线余量,接着在放线端用紧线器将导线卡牢,收线端开始收线,当收线到达规定程度时,随之在收线端用紧线器将导线卡牢,进而调整导线弧垂,则换线工作完毕。另外,由控制器14监测拽线的拉力,当拽线拉力超过电线杆抗压拉力的60%时,该收放线设备停止工作。The basic process of replacing old and new lines by adopting the power take-up and pay-off equipment for overhead lines according to the utility model is as follows. During operation, firmly connect the new lead with the old lead at the pay-off end of the line, and connect the old lead with the power take-up and pay-off device at the take-up end of the line (that is, wind the old lead on the reel 8) , after starting the equipment, the new wire can be laid on the line while the old wire is recycled. According to the actual working conditions (such as the sag of the wire, the distance of the line), calculate the wire allowance for the tightened wire, and then use the wire tightener to clamp the wire firmly at the pay-off end, and start to take up the wire at the take-up end. When the take-up end reaches the specified When the level is reached, then use a wire tensioner to clamp the wire firmly at the wire take-up end, and then adjust the wire sag, and then the wire changing work is completed. In addition, the tension of the wire is monitored by the controller 14, and when the tension of the wire exceeds 60% of the compressive tension of the utility pole, the wire take-up and pay-off device stops working.

下面参照图3,其示出了根据本实用新型的另一优选实施例的架空线路动力收放线设备的俯视示意图。图3中所示实施例与图1中所示实施例的组成部件大体上相同,它们的不同之处在于:卷线盘8包括3个用于卷绕缆线的卷轴部8a、8b、8c,此外采用12千瓦发电机代替5.5千瓦的发电机提供电源,并采用7.5千瓦电动机代替3千瓦的电动机提供动力,增加了拽线拉力,可以同时拽3条导线。在线路放线端将3条新导线分别与旧导线连接牢固,在线路的收线端将旧导线与该收放线设备相连接,转动卷线盘,回收旧导线的同时新导线就可敷设在线路上。当然可以理解的是,该卷线盘8可以被构造成具有可容纳若干盘线缆的空间,并选用合适功率的发电机及电动机即可同时拽若干条导线。Referring to Fig. 3 below, it shows a schematic top view of a power take-up and take-off equipment for overhead lines according to another preferred embodiment of the present invention. The embodiment shown in Fig. 3 is substantially the same as the constituent parts of the embodiment shown in Fig. 1, and their difference is that: the reel 8 includes 3 reel parts 8a, 8b, 8c for winding cables , In addition, a 12 kW generator is used instead of a 5.5 kW generator to provide power, and a 7.5 kW motor is used instead of a 3 kW motor to provide power, which increases the pulling force of the wire and can pull 3 wires at the same time. Connect the 3 new wires to the old wires firmly at the pay-off end of the line, connect the old wires to the take-up and pay-off equipment at the take-up end of the line, turn the reel, recover the old wires and lay the new wires at the same time on the line. Of course, it can be understood that the cable reel 8 can be configured to have space for accommodating several coils of cables, and several wires can be drawn simultaneously by selecting a suitable power generator and motor.

根据本实用新型的架空线路动力收放线设备还可应用于新建线路施工,例如在农村低压线路3线(电话线、路灯线、有线电视光纤线路)的架线过程中,其操作过程如下所述。首先同时展放该动力收放线设备上的3根φ6mm钢丝绳至线路的放线端,并将钢丝绳放在直线杆上相对应的滑轮中;然后在线路的放线端分别将3根钢丝绳与要展放导线连接牢固;最后启动该动力收放线设备回收3条钢丝绳,则3条钢丝绳就能将导线展放在预定的电杆上。紧线方法和旧导线换新导线方法相同。这种架设新线的方法不仅可以节省人力,提高工作效率,而且可避免3线发生搭挂现象(采用传统的人工架线的方法时3线搭挂现象非常严重)。此外,同时收放3条导线使得跨越障碍的次数减少,即,当整个线路中存在5处障碍时,同时放3根φ6mm钢丝绳跨越障碍的次数是5次,而传统施工方法跨越障碍的次数是15次,这明显节省工作时间。The power take-up and release equipment for overhead lines according to the utility model can also be applied to the construction of new lines, for example, in the process of erecting lines of low-voltage lines in rural areas (telephone lines, street lamp lines, cable TV optical fiber lines), the operation process is as follows stated. Firstly, lay three φ6mm steel wire ropes on the power take-up and pay-off equipment to the pay-off end of the line at the same time, and put the steel wire ropes in the corresponding pulleys on the straight rod; It is necessary to extend and release the wires to be firmly connected; finally start the power retracting and releasing equipment to reclaim 3 steel wire ropes, then the 3 wire ropes can lay the wires on the predetermined electric pole. The tightening method is the same as the method of replacing old wires with new wires. This method of erecting new wires can not only save manpower, improve work efficiency, but also avoid the phenomenon of 3 wires being hung up (the phenomenon of 3 wires being hung up is very serious when adopting the traditional manual method of setting up wires). In addition, retracting and deploying 3 conductors at the same time reduces the number of times of crossing obstacles, that is, when there are 5 obstacles in the whole line, the number of times of crossing obstacles by placing 3 φ6mm steel wire ropes at the same time is 5 times, while the number of times of crossing obstacles with traditional construction methods is 15 times, which significantly saves work time.

下面参照图4,是示出了根据本实用新型的又一优选实施例的架空线路动力收放线设备的主轴支撑部件的侧视示意图。在该实施例中,支架9两侧均具有高度可调的主轴支承部件13,每侧的主轴支承部件13中设置有两对平行并列布置的滚动轴承16(图4中仅示出一对),主轴10支撑在两对滚动轴承16之间,每对轴承16均定位于夹板20中,支架9每一侧的两根垂直立柱23、24上具有多对平行的定位孔21。当需要调整主轴10的高度时,就提升主轴支承部件13同时在定位孔21中插入定位销(未示出),随之将主轴支承部件13放置在定位销上,从而限定了主轴10的水平高度。具体地,该主轴支承部件13具有提拉部13a,支架9两侧的顶部处各自安装有被钢索17绕过的定滑轮15,钢索17的一端可连接于提拉部13a,因此可以拉动钢索17的另一端从而调整主轴支承部件13的高度。当施工场地不平整时,主轴10会向高度较低的一侧移动,从而造成主轴10上的卷线盘与支架9刮蹭,此时就必须调节支架9两侧的主轴支撑部件13的高度以便解决该问题。Referring now to FIG. 4 , it is a schematic side view showing the main shaft supporting part of the overhead line power take-up and take-off equipment according to another preferred embodiment of the present invention. In this embodiment, both sides of the bracket 9 are provided with height-adjustable main shaft supporting parts 13, and two pairs of rolling bearings 16 (only one pair is shown in Fig. 4 ) arranged in parallel are arranged in the main shaft supporting parts 13 on each side, The main shaft 10 is supported between two pairs of rolling bearings 16, and each pair of bearings 16 is positioned in a splint 20. Two vertical columns 23, 24 on each side of the bracket 9 have multiple pairs of parallel positioning holes 21. When the height of the main shaft 10 needs to be adjusted, the main shaft supporting part 13 is lifted and a positioning pin (not shown) is inserted in the positioning hole 21 at the same time, and the main shaft supporting part 13 is placed on the positioning pin, thereby limiting the level of the main shaft 10. high. Specifically, the main shaft supporting part 13 has a lifting part 13a, fixed pulleys 15 bypassed by steel cables 17 are respectively installed at the tops on both sides of the bracket 9, and one end of the steel cables 17 can be connected to the lifting part 13a, so that The other end of the cable 17 is pulled to adjust the height of the spindle supporting member 13 . When the construction site is uneven, the main shaft 10 will move to the side with a lower height, thereby causing the reel on the main shaft 10 to scrape against the support 9. At this time, the height of the main shaft supporting parts 13 on both sides of the support 9 must be adjusted. in order to resolve this issue.

参照图5和图6,示出了根据本实用新型的转角放线滑轮的结构及应用的示意图。参见图5,与通常的滑轮相比,该转角放线滑轮18的下部设置有使滑轮倾斜的楔形支承件19。下面详细介绍该转角放线滑轮18的具体应用情况及其所解决的技术问题。Referring to Fig. 5 and Fig. 6, it shows a schematic view of the structure and application of the corner pay-off pulley according to the present invention. Referring to Fig. 5, compared with the usual pulley, the lower part of the corner pay-off pulley 18 is provided with a wedge support 19 which makes the pulley tilt. The specific application of the corner pay-off pulley 18 and the technical problems it solves will be introduced in detail below.

架空线路是由多个耐张段组成,每个耐张段又是由10-20基电杆组成。由于受地形、建筑物限制,电线线路并不是一条直线,每个耐张段可能出现1-2个角度不大于45度的转角,这种不大于45度的转角杆在工程上称为抱立杆。在架空线路放线施工过程中,特别是采用旧线带动新线的情况下,导线要放在滑轮中移动,当遇到抱立杆型的电杆时,导线经常会由于转角的存在而卡在滑轮上,而且导线移动时会与滑轮的侧面立柱摩擦,从而导致放线阻力增加进而减缓放线速度,且容易损伤导线。采用根据本实用新型的转角放线滑轮18的目的在于使滑轮与水平方向之间形成大约30度的转角(参见图6,通过楔形支承件19实现),这样导线在滑轮中移动时就不会与滑轮的侧面立柱接触,使导线容易通过滑轮。The overhead line is composed of multiple tension sections, and each tension section is composed of 10-20 base poles. Due to the constraints of terrain and buildings, the wire line is not a straight line, and each tension section may have 1-2 corners with an angle not greater than 45 degrees. This kind of corner pole not greater than 45 degrees is called a hug stand in engineering pole. During the construction of overhead lines, especially when old lines are used to drive new lines, the wires must be moved on pulleys. When encountering a pole-type pole, the wires are often stuck due to the corner On the pulley, and when the wire moves, it will rub against the side column of the pulley, which will increase the wire resistance and slow down the wire speed, and easily damage the wire. The purpose of adopting the corner pay-off pulley 18 according to the utility model is to form an approximately 30-degree angle of rotation between the pulley and the horizontal direction (referring to Fig. The side posts of the pulley are in contact, making it easy for the wire to pass through the pulley.

以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the utility model, and are not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model shall be included in the protection scope of the present utility model.

Claims (10)

1. an overhead transmission line power retractable cable equipment is characterized in that, comprising:
Support (9);
Main shaft (10) is supported in the described support pivotly;
Winding roll (8) removably is sheathed on the described main shaft;
Transmission device is arranged on the described support and is connected in described main shaft;
Motor (1) is arranged on the described support and is connected in described transmission device; And
Speed-regulating control device (14) is arranged on the described support and is electrically connected on described motor.
2. overhead transmission line power retractable cable equipment according to claim 1, it is characterized in that, described support both sides are provided with adjustable for height main shaft supporting parts (13), be provided with at least one pair of rolling bearing (16) in the described main shaft supporting parts, described main shaft support is between described at least one pair of rolling bearing.
3. overhead transmission line power retractable cable equipment according to claim 2, it is characterized in that, described main shaft supporting parts have pulling part (13a), and the place, top of described support both sides is equipped with the fixed pulley of being walked around by cable wire (17) (15) separately, and an end of described cable wire is connected in described pulling part.
4. overhead transmission line power retractable cable equipment according to claim 1 is characterized in that described transmission device comprises:
Turbine and worm reductor (2) is arranged on the described support and contiguous described motor;
Two first belt pulleys (3), be installed in respectively on the described motor and described turbine and worm reductor on, and described two first belt pulleys are in same level height;
First belt (6) is around described two first belt pulleys;
Second belt pulley (4) is installed on the sidepiece of described turbine and worm reductor;
The 3rd belt pulley (5) is installed on the sidepiece of described winding roll, and described second belt pulley and described the 3rd belt pulley are arranged in same vertical plane; And
Second belt (7) is around described second belt pulley and described the 3rd belt pulley.
5. overhead transmission line power retractable cable equipment according to claim 1 is characterized in that, described winding roll comprises the spool portion (8a) of at least one cable that is used to reel.
6. overhead transmission line power retractable cable equipment according to claim 1 is characterized in that, described overhead transmission line power retractable cable equipment also comprises:
Wheel (12) is installed in the both sides of described support and supports described support; And
Hitch frame (11) is fixed to the front end of described support.
7. overhead transmission line power retractable cable equipment according to claim 6, it is characterized in that, described hitch frame comprises two curb girders (11a, 11b) and is connected crossbeam (11c) between the described curb girder that wherein, the front end of described hitch frame has bail (11d).
8. overhead transmission line power retractable cable equipment according to claim 1, it is characterized in that, described overhead transmission line power retractable cable equipment also comprises the corner pulley block (18) that is arranged on the electric pole capital, and described corner pulley block is supported by wedge shape strutting piece (19).
9. overhead transmission line power retractable cable equipment according to claim 1 is characterized in that, described overhead transmission line power retractable cable equipment also comprises generator, and described generator is electrically connected to described motor.
10. overhead transmission line power retractable cable equipment according to claim 5 is characterized in that, described winding roll comprises the spool portion of 3 cables that are used to reel.
CNU2008201237565U 2008-11-19 2008-11-19 Power line casting and reeling device for overhead line Expired - Lifetime CN201332231Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201237565U CN201332231Y (en) 2008-11-19 2008-11-19 Power line casting and reeling device for overhead line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201237565U CN201332231Y (en) 2008-11-19 2008-11-19 Power line casting and reeling device for overhead line

Publications (1)

Publication Number Publication Date
CN201332231Y true CN201332231Y (en) 2009-10-21

Family

ID=41225614

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201237565U Expired - Lifetime CN201332231Y (en) 2008-11-19 2008-11-19 Power line casting and reeling device for overhead line

Country Status (1)

Country Link
CN (1) CN201332231Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009875A (en) * 2010-11-12 2011-04-13 唐夫洲 Conducting wire taking-up and paying-off device of power supply circuit and taking-up and paying-off method
CN102437543A (en) * 2011-12-12 2012-05-02 河南省电力公司洛阳供电公司 Electro-hydraulic cable pay-off
CN103474916A (en) * 2012-06-06 2013-12-25 南京工程学院 Spool drawing machine
CN103683112A (en) * 2013-11-30 2014-03-26 国网河南省电力公司南阳供电公司 Twisting and grinding type power transmission line cable tightening device and using method thereof
CN104037711A (en) * 2014-06-19 2014-09-10 国网四川省电力公司成都市新都供电分公司 Cable reel with tightness conveniently adjustable
CN113896033A (en) * 2021-09-17 2022-01-07 国网河南省电力公司许昌市建安供电公司 Power cable replacing method
CN115709926A (en) * 2022-11-21 2023-02-24 国网山西省电力公司运城供电公司 Line construction wire take-up reel

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009875A (en) * 2010-11-12 2011-04-13 唐夫洲 Conducting wire taking-up and paying-off device of power supply circuit and taking-up and paying-off method
CN102437543A (en) * 2011-12-12 2012-05-02 河南省电力公司洛阳供电公司 Electro-hydraulic cable pay-off
CN103474916A (en) * 2012-06-06 2013-12-25 南京工程学院 Spool drawing machine
CN103683112A (en) * 2013-11-30 2014-03-26 国网河南省电力公司南阳供电公司 Twisting and grinding type power transmission line cable tightening device and using method thereof
CN104037711A (en) * 2014-06-19 2014-09-10 国网四川省电力公司成都市新都供电分公司 Cable reel with tightness conveniently adjustable
CN104037711B (en) * 2014-06-19 2016-06-15 国网四川省电力公司成都市新都供电分公司 It is easy to the cable hank of adjusting elasticity
CN113896033A (en) * 2021-09-17 2022-01-07 国网河南省电力公司许昌市建安供电公司 Power cable replacing method
CN115709926A (en) * 2022-11-21 2023-02-24 国网山西省电力公司运城供电公司 Line construction wire take-up reel

Similar Documents

Publication Publication Date Title
CN201332231Y (en) Power line casting and reeling device for overhead line
KR101579660B1 (en) Method for horizontally winding and unwinding a parallel wire strand
CN109687349B (en) Bypass cable wiring method and special equipment thereof
CN208345451U (en) Hydraulic lifting type just adjusts pay off rack
CN103441451A (en) An overhead line spanning wiring device
CN213171204U (en) Construction equipment hoisting device
CN214618151U (en) Municipal works pipe-line installation device
CN207782294U (en) Cable dragging device
CN220976128U (en) An electric power construction device
CN217577707U (en) New and old belt curls and changes device
KR200163244Y1 (en) A wiring apparatus of an electric wire
CN102709849A (en) Manual multifunctional wire tightening device and wire tightening method
CN105293216A (en) Wire take-up and tensioning method for electric power construction
CN203491607U (en) Overhead line cross wiring device
CN211110301U (en) A pay-off device for power transmission
CN218809510U (en) Cable pay-off device
CN206735510U (en) A kind of electric power cable coiling apparatus
CN216736899U (en) Automatic conveyor for bypass cables
CN105293167A (en) Paying-off machine
CN215885862U (en) Cable winder
CN210326718U (en) Highway unwrapping wire structure is striden to distribution network
CN221552680U (en) Pulley for cable support
CN221970895U (en) Power transmission and transformation engineering is with transmission line pay-off of being convenient for change
CN222574259U (en) A kind of air duct installation lifting device
KR100320278B1 (en) A Wiring Apparatus of an Electric Wire

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING ELECTRIC POWER CORP.

Effective date: 20130528

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: BEIJING ELECTRIC POWER CORP.

Effective date: 20130528

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100031 XICHENG, BEIJING TO: 100031 DONGCHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20130528

Address after: 100031 West Chang'an Avenue, Beijing, No. 86

Patentee after: State Grid Corporation of China

Patentee after: Beijing Electric Power Corp.

Address before: 100031 Beijing Qianmen West Street, Xicheng District, No. 41

Patentee before: Beijing Electric Power Corp.

CX01 Expiry of patent term

Granted publication date: 20091021

CX01 Expiry of patent term