CN106088097B - Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope - Google Patents

Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope Download PDF

Info

Publication number
CN106088097B
CN106088097B CN201610529745.6A CN201610529745A CN106088097B CN 106088097 B CN106088097 B CN 106088097B CN 201610529745 A CN201610529745 A CN 201610529745A CN 106088097 B CN106088097 B CN 106088097B
Authority
CN
China
Prior art keywords
pipe
straight tube
elephant trunk
slope
hopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610529745.6A
Other languages
Chinese (zh)
Other versions
CN106088097A (en
Inventor
郑楚英
郑懿
冯宾
陈俊杰
骆德勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai Xinxian Construction Engineering Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610529745.6A priority Critical patent/CN106088097B/en
Publication of CN106088097A publication Critical patent/CN106088097A/en
Application granted granted Critical
Publication of CN106088097B publication Critical patent/CN106088097B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of construction method and fog chute device for delivering concrete under gentle slope and abrupt slope, 3 60 6 meters of long straight tubes of section connect into elephant trunk by flange, axial flow blower is installed on the first segment straight tube of elephant trunk top, fog generator is installed on each section straight tube;Elephant trunk top first segment straight tube upper end slips straight tube by flange bridge piece under the connection of hopper discharging opening, under slip in straight tube insertion bend pipe;Hopper is erected on hopper base, and water tank is set on hopper base, draws water pipe from water tank, water pipe is connected one by one with fog generator;Elephant trunk tail end final section straight tube is connected by flange with tremie pipe one end, a hanger is welded with tremie pipe outer layer pipe, cloth sleeve pipe is enclosed on tremie pipe, present device small investment, operating cost are low, cost saving, durable, fault rate is low, save the duration.

Description

Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope
Technical field
The invention belongs to the realm of building construction, is related to the construction method and fog for delivering concrete under gentle slope and abrupt slope Chute device.Particularly box culvert, channel, inverted-siphon, water-supply-pipe during the field work such as water conservancy, electric power, mine, agricultural irrigation The basis of concrete structures under the slopes such as road, underplate concrete, short concrete structures pour.Equipment investment is few, operation Expense is low, cost saving, durable, fault rate is low, save the duration.
Background technology
At present at basis under the construction such as water conservancy, electric power, mine industry pours heavy grade and structures concrete, because The gradient is excessive(The needs of stability of slope), can not directly repair the roads(Or expense is very big)To pouring location, water conservancy industry is generally adopted With the method repaired the roads under cheating or neighbouring method power industry then uses elephant trunk.During using the method repaired the roads, investment is significantly Improve, it is sometimes even infeasible.Elephant trunk method because inner-walls of duct need slip send before soak, slip and send the time to grow rear mortar to exist Solidification caused by when the solidification of above inner-walls of duct and left and right or higher temperature, which causes to slip, send failure, simultaneously as concrete is from stirring It is longer to mix the time slipped between sending, cause concrete slump loss exceeded as defined in specification through when slump-loss value. Also have pumped using pump truck, the method that material distributing machine cloth puts in storage, but pumping method need repair the roads, while need to concrete according to The specification of pumping, which carries out the gel material content such as mix Design, cement, must reach 300kg/m3More than, add Construction investment, simultaneous pumping concrete pumping must smoothly increase water-cement ratio, cause the loss that concrete strength is larger, Er Qienai Long property is poor.The investment of material distributing machine method is larger, and apart from it is remote when just do not apply to.Now use the method that chute is directly put in storage most It is feasible also most economical, but at present elephant trunk it is usually used be steel pipe, easily abrasion, heaviness be not easy displacement, discharging opening fix not Beneficial to cloth, and pipeline must be soaked with water before use, now easily be spread to pour on face by eaves gutter, if earth foundation is just Base surface can be caused unqualified.And steel pipe necessarily be in a kind of straight line angle, installation accuracy requires very high, is not otherwise production Raw plugging is exactly to produce isolation.When producing concrete disintegration, the slump of concrete can only be adjusted, and from the linearity of steel pipe It is then very troublesome with being adjusted in angle.
The content of the invention
It is an object of the invention to for above technical deficiency, there is provided a kind of for delivering concrete under gentle slope and abrupt slope Construction method and fog chute device.Equipment investment is few, operating cost is low, cost saving, durable, fault rate is low, save Duration.
To achieve the above object, adopt the following technical scheme that:
A kind of fog chute device for delivering concrete under gentle slope and abrupt slope, including hopper, under slip straight tube, bend pipe, Straight tube, tremie pipe, it is characterised in that:3-60 section rice is long(Nominal diameter DN125mm-DN350mm)Straight tube, connected into by flange Elephant trunk, leakproof rubber cushion is fitted between flange, axial flow blower is installed on the first segment straight tube of elephant trunk top, pacified on each section straight tube Equipped with fog generator;
Elephant trunk top first segment straight tube upper end is by flange bridge piece, and bend pipe diameter is identical with straight tube, bent arc radius R300mm-R2000mm, arc length 400mm-3000mm;
Hopper discharging opening connection under slip straight tube, under slip straight tube nominal diameter DN100mm-DN300mm, length 500mm- 2000mm, under slip 60 degree -85 of straight tube horizontal sextant angle degree, under slip in straight tube insertion bend pipe;Hopper is erected on hopper base, hopper Water tank is set on support, draws water pipe from water tank, water pipe is connected one by one with fog generator;
Elephant trunk tail end final section straight tube is connected by flange with tremie pipe one end, and tremie pipe is plastic-steel products compound tube, Internal layer is PE or PP plastics, and outer layer is steel, and tremie pipe inner layer plastic tube nominal diameter is identical with straight tube, and outer layer pipe rolls chi It is very little to be interference fitted with inner layer plastic tube external diameter, a hanger is welded with tremie pipe outer layer pipe, cloth sleeve pipe is enclosed on tremie pipe, Cloth sleeve pipe is steel pipe, nominal diameter DN150mm-DN400mm, length 3-9 rice, and cloth sleeve pipe is provided with width 15mm- vertically 30mm grooves, length 2.8-8.8 rice.
A kind of construction method for delivering concrete under gentle slope and abrupt slope, its step are:
A, elephant trunk is made:By the plastic tube purchased or the good flange of steel pipe melting welding, pipe inside weld is polished;Wherein it is used for elephant trunk The branch pipe being welded on the first segment straight tube on top for connection of axial flow fan, each save are welded on straight tube for connecting fog The branch pipe of device;
B, earth anchor is squeezed into:Angle steel is squeezed on road on the transversal line slope of arrangement elephant trunk, is used as earth anchor;
Hawser is installed C,:The flexible steel wire on the upper flange bottom set for need first segment elephant trunk straight tube to be mounted, by cable Rope is fixed on earth anchor.
D, elephant trunk is installed:According to the slope excavating gradient(1:0.5;1:1;1:1.5;1:2 or the reality between above-mentioned slope ratio Border slope ratio), prolong domatic arrangement installation plastic tube or steel pipe on the transversal line for need casting concrete(Either plastic tube and steel Pipe mixes, that is, is needing the place for adjusting conduit slope to arrange plastic tube), connected using flange between pipeline, matched somebody with somebody between flange Fill leakproof rubber cushion;
Supporting trolley is installed E,:It is longer in side slope, when being disposed with packway in the middle part of slope, the good and sound supporting trolley on packway;
F, hopper mounting platform is excavated:On elephant trunk top, the top elevation of first segment straight tube digs 1.25m*1.25m platform, Hopper base is set on platform;
Bend pipe is installed G,:Bend pipe is installed in the first segment straight tube upper end on elephant trunk top;
H, install hopper and under slip straight tube:Hopper be arranged on hopper base on, hopper discharging opening connection under slip straight tube, under slip 75 degree -85 of straight tube horizontal sextant angle degree, under slip in straight tube insertion bend pipe, and adjust the height of hopper in 1.5m-3m;
Water tank is installed I,:Water tank is installed on hopper base;
Tremie pipe and cloth sleeve pipe are installed J,:Elephant trunk tail end final section straight tube is connected by flange with tremie pipe one end, Cloth sleeve pipe is enclosed on tremie pipe, and the hanger on tremie pipe is connected by suspension hook with the electric block on walking door frame, passes through row Movable and electric block the lifting moving tremie pipe of door frame is walked, and the extension and contraction control cloth for passing through cloth sleeve pipe is remote Closely;
Fog generator is installed K,:Fog generator is installed on the branch pipe welded in advance on straight tube, water is drawn from water tank Pipe, water pipe are connected one by one with fog generator;
Axial flow blower is installed L,:Axial flow blower is installed on the branch pipe that first segment straight tube welds in advance on elephant trunk top;
Cable is installed M,:Cable is loaded onto on fog generator and axial flow blower;
N, examination is slipped:Examination is slipped and the rubber cement that the mix Design parameter sent is prepared is slipped using plan(It is during without admixture Mortar), before examination are slipped, fog generator and axial flow blower are opened, allows fog to be full of pipeline, and keep moisture state;It is wet in pipeline After profit, the rubber cement prepared is subjected to examination and slipped(Examination can close axial flow blower when slipping);
O, adjust:The gradient is too slow when slipping motionless or plugging, first adjusts the linearity of pipeline, pipeline is kept straight line, then adjust The vertical angle of straight tube is slipped under whole, while adjusts the height of hopper and bend pipe top, or the first segment upper end by elephant trunk straight tube Portion raises, and improves material initial velocity, is slipped under being easy to;When material produces isolation, middle part, the middle and lower part of padded elephant trunk, or in the gradient When too steep, pipeline can be put into S molded line, or it is 30 degree of -60 degree of horizontal sextant angle that the vertical angle of straight tube 2 is slipped under adjustment.
It is 1 that the construction method, which is applied to the gradient,:2-1:0.5(21.800-63.430).
The construction method is applied to length of grade 50m-350m.
Beneficial effects of the present invention are as follows compared with prior art:
1, the long-term wet channels inwall of fog is used in elephant trunk, is reduced the frictional resistance slipped under material, has been reached low In 300 The effect of delivering concrete under slope, at the same overcome can not directly plus water compensation slump-loss the drawbacks of;
2, elephant trunk uses plastic tube(PE, PP pipe etc.)Slight S can be arranged to or plastic tube is combined with steel pipe, during abrupt slope Type pipe, solves the problems, such as aggregate segregation during abrupt slope, while lower end can be lifted and be swung, and both solve reduction discharging section The problem of material speed, voluntarily cloth is also achieved, solve the problems, such as that elephant trunk is unable to cloth;
3, construct the intermittent phase, be not required to wash pipe in 10h, water profit pipe need not be used during beginning, labor intensity is both alleviated, also solve Base surface can not have the problem of water;
4, trucd mixer can directly under expect hopper, hopper and the height of bend pipe upper port can voluntarily be adjusted, avoided The problem of Uneven road causes aggregate bin to be higher than trucd mixer discharging opening;
5, a chain-wales, hopper and water tank are excavated out in place during gentle slope directly in side slope upper shed with digging machine, letter Folk prescription just, is not necessary to fill or make discharging platform at gentle slope, solves the problems, such as to improve initial velocity during gentle slope;
6, by the adjustment in step, cover 1:2-1:0.5(21.800-63.430)Side slope in the case of elephant trunk mix Solidifying soil conveying scope, have also been enlarged the use range of elephant trunk technology;
7, during using plastic tube, overall weight is light, and slope upper tube road manually can be adjusted and moved, the water consumption of fog device Also very little, will not be limited by field condition.
8, supporting trolley track is made of channel-section steel, is easy to artificial movement.
9, abrupt slope slips straight tube and tilts 70 at present0-850, fallen immediately close to tube wall when material falls, and it is smooth along bend pipe Flow forward, avoid the segregation phenomenon that rebounded caused by falling behind excessive velocities under straight line.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention
Wherein:1- hoppers, slip straight tube under 2-, 3- bend pipes, 4- flanges, 5- axial flow blowers, 6- straight tubes, 7- fog generators, 8- joint steel pipes, 9- water tanks, 10- water pipes, 11- supporting trolleys, 12- hangers, 13- tremie pipes, 14- cloth sleeve pipes, the electronic calabashes of 15- Reed, 16- mobile holders.
Embodiment
A kind of fog chute device for delivering concrete under gentle slope and abrupt slope, including hopper 1, under slip straight tube 2, bend pipe 3rd, straight tube 6, tremie pipe 13, it is characterised in that:3-60 sections are 6 meters long(Nominal diameter DN125mm-DN350mm)Straight tube 6, passes through method Orchid connects into elephant trunk, and leakproof rubber cushion is fitted between flange, and axial flow blower 5 is provided with elephant trunk top first segment straight tube 6, each Fog generator 7 is installed on section straight tube 6;
The upper end of elephant trunk top first segment straight tube 6 is by flange bridge piece 3, and the diameter of bend pipe 3 is identical with straight tube 6, curved arc half Footpath R300mm-R2000mm, arc length 400mm-3000mm;
The discharging opening of hopper 1 connection under slip straight tube 2, under slip straight tube 2 nominal diameter DN100mm-DN300mm, length 500mm- 2000mm, under slip 60 degree -85 of 2 horizontal sextant angle of straight tube degree, under slip straight tube 2 and insert in bend pipe 3;Hopper 1 is erected on hopper base, Water tank 9 is set on hopper base, draws water pipe 10 from water tank 9, water pipe 10 is connected one by one with fog generator 7;
Elephant trunk tail end final section straight tube 6 is connected by flange with the one end of tremie pipe 13, and tremie pipe 13 is plastic-steel products group Pipe is closed, internal layer is PE or PP plastics, and outer layer is steel, and the inner layer plastic tube nominal diameter of tremie pipe 13 is identical with straight tube 6, outer layer steel Pipe rolls size and is interference fitted with inner layer plastic tube external diameter, and a hanger 12, cloth sleeve pipe are welded with the outer layer pipe of tremie pipe 13 14 are enclosed on tremie pipe 13, and cloth sleeve pipe 14 is steel pipe, nominal diameter DN150mm-DN400mm, length 3-9 rice, cloth sleeve pipe 14 are provided with width 15mm-30mm grooves, length 2.8-8.8 rice vertically.
A kind of construction method for delivering concrete under gentle slope and abrupt slope, its step are:
A, elephant trunk is made:By the plastic tube purchased or the good flange of steel pipe melting welding, pipe inside weld is polished;Wherein it is used for elephant trunk The branch pipe being welded on the first segment straight tube 6 on top for connection of axial flow fan 5, each save are welded on straight tube 6 for connecting fog The branch pipe of generator;
B, earth anchor is squeezed into:Angle steel is squeezed on road on the transversal line slope of arrangement elephant trunk, is used as earth anchor;
Hawser is installed C,:The flexible steel wire on the upper flange bottom set for need first segment elephant trunk straight tube to be mounted, by cable Rope is fixed on earth anchor.
D, elephant trunk is installed:According to the slope excavating gradient(1:0.5;1:1;1:1.5;1:2 or the reality between above-mentioned slope ratio Border slope ratio), prolong domatic arrangement installation plastic tube or steel pipe on the transversal line for need casting concrete(Either plastic tube and steel Pipe mixes, that is, is needing the place for adjusting conduit slope to arrange plastic tube), connected using flange between pipeline, matched somebody with somebody between flange Fill leakproof rubber cushion;
Supporting trolley 11 is installed E,:It is longer in side slope, when being disposed with packway in the middle part of slope, the good and sound supporting trolley on packway 11;
F, hopper mounting platform is excavated:On elephant trunk top, the top elevation of first segment straight tube 6 digs the flat of 1.25m*1.25m Platform, hopper base is set on platform;
Bend pipe 3 is installed G,:Bend pipe is installed in the upper end of first segment straight tube 6 on elephant trunk top;
H, install hopper 1 and under slip straight tube 2:Hopper 1 is arranged on hopper base, and straight tube is slipped under the connection of the discharging opening of hopper 1 2, under slip 75 degree -85 of 2 horizontal sextant angle of straight tube degree, under slip straight tube 2 and insert in bend pipe 3, and adjust the height of hopper 1 in 1.5m- 3m;
Water tank 10 is installed I,:Water tank 10 is installed on hopper base;
Tremie pipe 13 and cloth sleeve pipe 14 are installed J,:Elephant trunk tail end final section straight tube 6 passes through flange and tremie pipe 13 1 End connection, cloth sleeve pipe 14 are enclosed on tremie pipe 13, and the hanger 12 on tremie pipe 13 passes through suspension hook and the electricity on walking door frame 16 Dynamic cucurbit 15 connects, and by movable and electric block 15 the lifting moving tremie pipe 13 for door frame 16 of walking, and passes through cloth Expect the distance of the extension and contraction control cloth of sleeve pipe 14;
Fog generator 7 is installed K,:Fog generator 7 is installed on the branch pipe welded in advance on straight tube 6, drawn from water tank 9 Outlet pipe 10, water pipe 10 are connected one by one with fog generator 7;
Axial flow blower 5 is installed L,:Axial flow blower is installed on the branch pipe that elephant trunk top first segment straight tube 6 welds in advance;
Cable is installed M,:Cable is loaded onto on fog generator 7 and axial flow blower 5;
N, examination is slipped:Examination is slipped and the rubber cement that the mix Design parameter sent is prepared is slipped using plan(It is during without admixture Mortar), before examination are slipped, fog generator and axial flow blower are opened, allows fog to be full of pipeline, and keep moisture state;It is wet in pipeline After profit, the rubber cement prepared is subjected to examination and slipped(Examination can close axial flow blower when slipping);
O, adjust:The gradient is too slow when slipping motionless or plugging, first adjusts the linearity of pipeline, pipeline is kept straight line, then adjust The vertical angle of straight tube 2 is slipped under whole, while adjusts the height of hopper 1 and the top of bend pipe 3, or the first segment by elephant trunk straight tube 6 Upper end is raised, and is improved material initial velocity, is slipped under being easy to;When material produces isolation, middle part, the middle and lower part of padded elephant trunk, or When the gradient is too steep, pipeline can be put into S molded line, or the vertical angle of straight tube 2 is slipped under adjustment as 30 degree -60 of horizontal sextant angle Degree.
It is 1 that the construction method, which is applied to the gradient,:2-1:0.5(21.800-63.430).
The construction method is applied to length of grade 50m-350m.

Claims (4)

1. a kind of fog chute device for delivering concrete under gentle slope and abrupt slope, including hopper(1), under slip straight tube(2), it is curved Pipe(3), straight tube(6), tremie pipe(13), it is characterised in that:3-60 saves 6 meters long, nominal diameter DN125mm-DN350mm straight tube (6)Elephant trunk is connected into by flange, leakproof rubber cushion, elephant trunk top first segment straight tube are fitted between flange(6)On axle is installed Flow fan(5), each section straight tube(6)On fog generator is installed(7);
Elephant trunk top first segment straight tube(6)Upper end passes through flange bridge piece(3), bend pipe(3)Diameter and straight tube(6)It is identical, it is curved Arc radius R300mm-R2000mm, arc length 400mm-3000mm;
Hopper(1)Straight tube is slipped under discharging opening connection(2), under slip straight tube(2)Nominal diameter DN100mm-DN300mm, length 500mm-2000mm, under slip straight tube(2)60 degree -85 of horizontal sextant angle degree, under slip straight tube(2)Insert bend pipe(3)It is interior;Hopper(1)Frame It is located on hopper base, water tank is set on hopper base(9), from water tank(9)Draw water pipe(10), water pipe(10)Occur with fog Device(7)Connect one by one;
Elephant trunk tail end final section straight tube(6)Pass through flange and tremie pipe(13)One end connects, tremie pipe(13)For plastic-steel products Compound tube, internal layer are PE or PP plastics, and outer layer is steel, tremie pipe(13)Inner layer plastic tube nominal diameter and straight tube(6)It is identical, Outer layer pipe rolls size and is interference fitted with inner layer plastic tube external diameter, tremie pipe(13)A hanger is welded with outer layer pipe (12), cloth sleeve pipe(14)It is enclosed on tremie pipe(13)On, cloth sleeve pipe(14)For steel pipe, nominal diameter DN150mm-DN400mm, Length 3-9 rice, cloth sleeve pipe(14)Width 15mm-30mm grooves, length 2.8-8.8 rice are provided with vertically.
2. a kind of construction method for delivering concrete under gentle slope and abrupt slope, its step are:
A, elephant trunk is made:By the plastic tube purchased or the good flange of steel pipe melting welding, pipe inside weld is polished;Wherein it is used for elephant trunk top First segment straight tube(6)On be welded for connection of axial flow fan(5)Branch pipe, each section straight tube(6)On be welded for connecting mist The branch pipe of gas generator;
B, earth anchor is squeezed into:Angle steel is squeezed on road on the transversal line slope of arrangement elephant trunk, is used as earth anchor;
Hawser is installed C,:The flexible steel wire on the upper flange bottom set for need first segment elephant trunk straight tube to be mounted, hawser is consolidated It is scheduled on earth anchor;
D, elephant trunk is installed:According to the slope excavating gradient, the gradient is 1:0.5 or 1:1 or 1:1.5 or 1:2 or between above-mentioned slope Actual slope ratio than between, the either modeling of plastic tube or steel pipe is installed along domatic arrangement on the transversal line for need casting concrete Expects pipe mixes with steel pipe, that is, is needing the place for adjusting conduit slope to arrange plastic tube, connected between pipeline using flange, flange Between be equipped with leakproof rubber cushion;
Supporting trolley is installed E,(11):It is longer in side slope, when being disposed with packway in the middle part of slope, the good and sound supporting trolley on packway (11);
F, hopper mounting platform is excavated:In elephant trunk top first segment straight tube(6)Top elevation dig 1.25m*1.25m platform, Hopper base is set on platform;
Bend pipe is installed G,(3):First segment straight tube on elephant trunk top(6)Upper end installs bend pipe;
Hopper is installed H,(1)Straight tube is slipped with(2):Hopper(1)On hopper base, hopper(1)Slipped under discharging opening connection Straight tube(2), under slip straight tube(2)75 degree -85 of horizontal sextant angle degree, under slip straight tube(2)Insert bend pipe(3)It is interior, and adjust hopper(1) Height in 1.5m-3m;
Water tank is installed I,(9):Water tank is installed on hopper base(9);
Tremie pipe is installed J,(13)With cloth sleeve pipe(14):Elephant trunk tail end final section straight tube(6)Pass through flange and tremie pipe (13)One end connects, cloth sleeve pipe(14)It is enclosed on tremie pipe(13)On, tremie pipe(13)On hanger(12)Pass through suspension hook and row Walk door frame(16)On electric block(15)Connection, passes through door frame of walking(16)Movable and electric block(15)Lifting Mobile tremie pipe(13), and pass through cloth sleeve pipe(14)Extension and contraction control cloth distance;
Fog generator is installed K,(7):In straight tube(6)On fog generator is installed on the branch pipe that welds in advance(7), from water tank (9)Draw water pipe(10), water pipe(10)With fog generator(7)Connect one by one;
Axial flow blower is installed L,(5):In elephant trunk top first segment straight tube(6)Axial flow blower is installed on the branch pipe welded in advance;
Cable is installed M,:In fog generator(7)And axial flow blower(5)On load onto cable;
N, examination is slipped:Examination slips the rubber cement that use plan to slip the mix Design parameter preparation sent or during without admixture for sand Slurry, before examination is slipped, fog generator and axial flow blower are opened, allows fog to be full of pipeline, and keep moisture state;It is moistened in pipeline Afterwards, the rubber cement prepared is carried out into examination to slip, examination can close axial flow blower when slipping;
O, adjust:The gradient is too slow when slipping motionless or plugging, first adjusts the linearity of pipeline, pipeline is kept straight line, then adjust down Slip straight tube(2)Vertical angle, while adjust hopper(1)With bend pipe(3)The height on top, or by elephant trunk straight tube(6) One section upper end is raised, and is improved material initial velocity, is slipped under being easy to;When material produces isolation, middle part, the middle and lower part of padded elephant trunk, Or when the gradient is too steep, pipeline is put under S molded line, or adjustment and slips straight tube(2)Vertical angle be 30 degree -60 of horizontal sextant angle Degree.
A kind of 3. construction method for delivering concrete under gentle slope and abrupt slope as claimed in claim 2, it is characterised in that:Institute It is 1 that construction method, which is stated, suitable for the gradient:2-1:0.5 i.e. 21.800-63.430
A kind of 4. construction method for delivering concrete under gentle slope and abrupt slope as claimed in claim 2, it is characterised in that:Institute State construction method and be applied to length of grade 50m-350m.
CN201610529745.6A 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope Active CN106088097B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610529745.6A CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610529745.6A CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Publications (2)

Publication Number Publication Date
CN106088097A CN106088097A (en) 2016-11-09
CN106088097B true CN106088097B (en) 2018-01-16

Family

ID=57212434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610529745.6A Active CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Country Status (1)

Country Link
CN (1) CN106088097B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984577B (en) * 2019-12-21 2021-07-20 河南昊锦建设集团有限公司 Concrete pouring system
CN111396676B (en) * 2020-04-27 2024-04-12 南京晨光东螺波纹管有限公司 Displacement compensation device of arc-shaped heat pipe and installation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1827920A (en) * 2005-03-02 2006-09-06 李勇 Method for reducing steel pipe concrete pumping resistance
CN101338860A (en) * 2007-07-03 2009-01-07 中国水利水电闽江工程局 Roller compacted concrete full package chute vertical conveying technology
CN101812845A (en) * 2009-02-25 2010-08-25 中国葛洲坝集团股份有限公司 Vertical concrete conveying system of small and medium hydropower station at high steep slopes
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103953193A (en) * 2014-04-16 2014-07-30 中国十九冶集团有限公司 Construction method for long-distance gentle-slope concrete conveying
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6278318A (en) * 1985-09-30 1987-04-10 Okumura Constr Co Ltd Vertical chute for concreting work

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1827920A (en) * 2005-03-02 2006-09-06 李勇 Method for reducing steel pipe concrete pumping resistance
CN101338860A (en) * 2007-07-03 2009-01-07 中国水利水电闽江工程局 Roller compacted concrete full package chute vertical conveying technology
CN101812845A (en) * 2009-02-25 2010-08-25 中国葛洲坝集团股份有限公司 Vertical concrete conveying system of small and medium hydropower station at high steep slopes
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103953193A (en) * 2014-04-16 2014-07-30 中国十九冶集团有限公司 Construction method for long-distance gentle-slope concrete conveying
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
上海世茂深坑酒店混凝土向下超深三级接力输送技术;葛乃剑等;《施工技术》;20151031;第44卷(第19期);1-3 *
上海世茂深坑酒店混凝土超深一溜到底施工技术;钱海波等;《施工技术》;20151031;第44卷(第19期);8-11 *

Also Published As

Publication number Publication date
CN106088097A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN101338562B (en) Concrete conveying process for high steep and big drop height landform
CN105201012B (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN106192907A (en) Set up the construction method of 150m~the 300m level high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN104989873B (en) Penstock oblique-pulling inversion assembling method
CN205917701U (en) A sleeve pipe distributing device for elephant trunk transport concrete
CN106088097B (en) Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope
CN107956246A (en) A kind of large-scale inspection shaft segmentation prefabricating construction method of installation
CN106836445A (en) A kind of trapezoidal gutter based on adjustable groove mould pours forming method
CN108360504A (en) The device and its construction method of manual digging pile construction
CN107130631A (en) A kind of basement Retaining wall method based on concreting moulding wall
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN106868958B (en) Self-compacting concrete construction system and construction method thereof
CN208309573U (en) The device of manual digging pile construction
CN207847102U (en) Appts. for transferring ready-mixed concrete
CN105780736B (en) A kind of chute cast-in-place construction device
CN205935686U (en) A fog elephant trunk device that is used for carrying concrete under gentle slope and abrupt slope
CN112324990A (en) Method and structure for reinforcing underground straight buried pipe
CN207974149U (en) Pre-buried skeleton strength core masonry cable duct
CN211566328U (en) Automatic maintenance device for highway engineering concrete member
CN207660620U (en) One kind two serves as a contrast concrete construction part flow arrangement
CN105604129A (en) Water pump mounting construction method
CN205975530U (en) Dual formula slip form construction device of bend loss and straight section concrete
CN206971725U (en) Hang the erecting device of mould
CN206903234U (en) A kind of rotary concrete pump of cone bucket construction send device
CN207047829U (en) Modified vibrosinking pile construction equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190801

Address after: 430072 Room 19, Room 21, Building 4, Mingshi 1, Shucheng Road, Hongshan District, Wuhan City, Hubei Province

Co-patentee after: Zheng Chuying

Patentee after: HUBEI 209 ENGINEERING Co.,Ltd.

Address before: 430071 2 Units 1002, 2 Blocks, Xingyuan, Anshun, 115 North Road, Wuchang District, Wuhan City, Hubei Province

Patentee before: Zheng Chuying

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230403

Address after: 433200 maojiang Avenue, Xindi, Honghu City, Jingzhou City, Hubei Province

Patentee after: Hubei Jugong Construction Engineering Co.,Ltd.

Address before: 430072 room 19, floor 21, building 4, No. 1 Mingshi, Shucheng Road, Hongshan District, Wuhan City, Hubei Province

Patentee before: HUBEI 209 ENGINEERING Co.,Ltd.

Patentee before: Zheng Chuying

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240812

Address after: No. 143, Liulintan Village, Qinglin Township, Datong Hui and Tu Autonomous County, Xining City, Qinghai Province 810100

Patentee after: Ha Guishan

Country or region after: China

Patentee after: Du Wenju

Address before: 433200 maojiang Avenue, Xindi, Honghu City, Jingzhou City, Hubei Province

Patentee before: Hubei Jugong Construction Engineering Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240829

Address after: Room 12301, Unit 1, Building 1, No. 25 Shengli Road, Chengxi District, Xining City, Qinghai Province 810000

Patentee after: Qinghai Xinxian Construction Engineering Co.,Ltd.

Country or region after: China

Address before: No. 143, Liulintan Village, Qinglin Township, Datong Hui and Tu Autonomous County, Xining City, Qinghai Province 810100

Patentee before: Ha Guishan

Country or region before: China

Patentee before: Du Wenju