CN106088097A - The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope - Google Patents

The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope Download PDF

Info

Publication number
CN106088097A
CN106088097A CN201610529745.6A CN201610529745A CN106088097A CN 106088097 A CN106088097 A CN 106088097A CN 201610529745 A CN201610529745 A CN 201610529745A CN 106088097 A CN106088097 A CN 106088097A
Authority
CN
China
Prior art keywords
straight tube
pipe
elephant trunk
slope
hopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610529745.6A
Other languages
Chinese (zh)
Other versions
CN106088097B (en
Inventor
郑楚英
郑懿
冯宾
陈俊杰
骆德勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai Xinxian Construction Engineering Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610529745.6A priority Critical patent/CN106088097B/en
Publication of CN106088097A publication Critical patent/CN106088097A/en
Application granted granted Critical
Publication of CN106088097B publication Critical patent/CN106088097B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses construction method and the fog chute device of a kind of delivering concrete under gentle slope and abrupt slope, 3 60 6 meters of long straight tubes of joint become elephant trunk by Flange joint, axial flow blower is installed on the first segment straight tube of elephant trunk top, each joint straight tube is provided with fog generator;Flange joint bend pipe is passed through in first segment straight tube upper end, elephant trunk top, and hopper discharging opening slips straight tube under connecting, under slip straight tube and insert in bend pipe;Hopper frame is located on hopper base, and hopper base arranges water tank, draws water pipe from water tank, and water pipe is connected one by one with fog generator;Elephant trunk tail end final section straight tube is connected with tremie pipe one end by flange, a hanger it is welded with on tremie pipe outer layer pipe, cloth casing pipe sleeve on tremie pipe, present device small investment, operating cost are low, cost saving, durable, failure rate is low, the saving duration.

Description

The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope
Technical field
The invention belongs to the realm of building construction, relate to construction method and the fog of delivering concrete under gentle slope and abrupt slope Chute device.Particularly box culvert, channel, inverted-siphon, water-supply-pipe during the field work such as water conservancy, electric power, mine, agricultural irrigation The basis of concrete structures under the slopes such as road, underplate concrete, the pouring of short concrete structures.Equipment investment is few, operation Expense is low, cost saving, durable, failure rate is low, the saving duration.
Background technology
At present when the construction industries such as water conservancy, electric power, mine pour basis and structures concrete under heavy grade, because of The gradient excessive (needs of stability of slope), it is impossible to directly repair the roads (or expense is the biggest), to pouring location, water conservancy industry is generally adopted The method that or neighbouring method power industry lower with hole of repairing the roads then uses elephant trunk.When using the method repaired the roads, investment is significantly Improve, the most feasible.Elephant trunk method because inner-walls of duct need slip send before moistening, slip and send the rear mortar of time length to exist The solidification that the solidification of above inner-walls of duct and left and right or temperature cause time higher causes slipping send fault, simultaneously as concrete is from stirring It is longer to mix the time between sending of slipping, cause concrete slump loss exceeded specification regulation through time slump-loss value. Also have pump truck pumping, the method put in storage of material distributing machine cloth of using, but pumping method need to repair the roads, simultaneously need to concrete according to The gel material contents such as the specification of pumping carries out mix Design, cement must reach 300kg/m3Above, add Construction investment, simultaneous pumping concrete pumping must strengthen water-cement ratio smoothly, cause the loss that concrete strength is bigger, Er Qienai Property is poor for a long time.The investment of material distributing machine method is relatively big and the most inapplicable when remote.Now use the method directly put in storage of chute Feasible the most most economical, but elephant trunk is normally used at present is steel pipe, and easily abrasion, heaviness are not easy displacement, discharging opening is fixed not It is beneficial to cloth, and water-wet pipeline must be used before using, now easily be spread to pour on face by eaves gutter, if earth foundation is just Base surface can be caused defective.And steel pipe necessarily be in a kind of straight line angle, installation accuracy requires the highest, is not the most to produce Raw plugging produces isolation exactly.When producing concrete disintegration, the slump of concrete can only be adjusted, and from the linearity of steel pipe Adjust with in angle, bother very much.
Summary of the invention
Present invention aims to above technical deficiency, it is provided that a kind of delivering concrete under the gentle slope and abrupt slope Construction method and fog chute device.Equipment investment is few, operating cost is low, cost saving, durable, failure rate is low, saving Duration.
For achieving the above object, adopt the following technical scheme that
A kind of fog chute device of delivering concrete under gentle slope and abrupt slope, including hopper, under slip straight tube, bend pipe, straight tube, Tremie pipe, it is characterised in that: 3-60 JIEMI length (nominal diameter DN125mm-DN350mm) straight tube, become elephant trunk by Flange joint, It is fitted with leakproof rubber cushion between flange, elephant trunk top first segment straight tube is provided with axial flow blower, each joint straight tube is provided with Fog generator;
Flange joint bend pipe is passed through in first segment straight tube upper end, elephant trunk top, and bend pipe diameter is identical with straight tube, bent arc radius R300mm- R2000mm, arc length 400mm-3000mm;
Hopper discharging opening slips straight tube under connecting, under slip straight tube nominal diameter DN100mm-DN300mm, length 500mm-2000mm, Under slip straight tube horizontal sextant angle 60 degree-85 degree, under slip straight tube and insert in bend pipe;Hopper frame is located on hopper base, on hopper base Arranging water tank, draw water pipe from water tank, water pipe is connected one by one with fog generator;
Elephant trunk tail end final section straight tube is connected with tremie pipe one end by flange, and tremie pipe is plastic-steel products compound tube, internal layer For PE or PP plastics, outer layer is steel, and tremie pipe inner layer plastic tube nominal diameter is identical with straight tube, outer layer pipe roll size with Inner layer plastic tube external diameter interference fit, tremie pipe outer layer pipe is welded with a hanger, cloth casing pipe sleeve on tremie pipe, cloth Sleeve pipe is steel pipe, nominal diameter DN150mm-DN400mm, length 3-9 rice, and cloth sleeve pipe has width 15mm-30mm vertically Groove, length 2.8-8.8 rice.
A kind of construction method of delivering concrete under gentle slope and abrupt slope, the steps include:
A, making elephant trunk: by good to the plastic tube purchased or steel pipe melting welding flange, polish pipe inside weld;Wherein for elephant trunk top First segment straight tube on be welded and be welded for connecting fog generator on the arm of connecting shaft flow fan, each joint straight tube Arm;
B, squeeze into earth anchor: on the transversal line slope arranging elephant trunk, squeeze into angle steel on road, use as earth anchor;
C, installation hawser: flexible steel wire on the upper flange bottom set need first segment elephant trunk straight tube to be mounted, hawser is solid It is scheduled on earth anchor.
D, install elephant trunk: according to the slope excavating gradient (1:0.5;1:1;1:1.5;1:2 or the reality between the ratio of above-mentioned slope Slope, border than), the transversal line need casting concrete prolongs domatic layout plastic tube or steel pipe (or plastic tube and steel is installed Pipe mixes, and is i.e. needing to adjust the local layout plastic tube of conduit slope), use Flange joint between pipeline, join between flange Dress leakproof rubber cushion;
E, installation supporting trolley: longer in side slope, when being disposed with packway in the middle part of slope, good and sound supporting trolley on packway;
F, excavation hopper mounting platform: the top elevation at elephant trunk top first segment straight tube digs the platform of 1.25m*1.25m, platform On hopper base is set;
G, installation bend pipe: install bend pipe in the first segment straight tube upper end on elephant trunk top;
H, install hopper and under slip straight tube: hopper is arranged on hopper base, and hopper discharging opening slips straight tube under connecting, under slip straight tube Horizontal sextant angle 75 degree-85 degree, under slip straight tube and insert in bend pipe, and adjust the height of hopper at 1.5m-3m;
I, installation water tank: water tank is installed on hopper base;
J, installation tremie pipe and cloth sleeve pipe: elephant trunk tail end final section straight tube is connected with tremie pipe one end by flange, cloth Casing pipe sleeve is on tremie pipe, and the hanger on tremie pipe is connected with the electric block on walking door frame by suspension hook, by walking door Mobile and the lifting moving tremie pipe of electric block before and after frame, and by the distance of the extension and contraction control cloth of cloth sleeve pipe;
K, installation fog generator: fog generator is installed on the arm welded in advance on straight tube, draws water pipe, water from water tank Pipe is connected one by one with fog generator;
L, installation axial flow blower: axial flow blower is installed on the arm that elephant trunk top first segment straight tube welds in advance;
M, installation cable: on fog generator and axial flow blower, load onto cable;
N, examination are slipped: examination is slipped employing plan and slipped the rubber cement of the mix Design parameter preparation sent (without being sand during admixture Slurry), before examination is slipped, open fog generator and axial flow blower, allow fog be full of pipeline, and keep moisture state;Moisten at pipeline Afterwards, the rubber cement prepared is carried out examination and slips (when examination is slipped can closing axle flow fan);
O, adjustment: the gradient is excessively slow slip motionless or plugging time, first adjust the linearity of pipeline, make pipeline keep straight line, then under adjusting Slip the vertical angle of straight tube, adjust the height of hopper and bend pipe top simultaneously, or the first segment upper end of elephant trunk straight tube is lifted Height, improve material initial velocity, it is simple under slip;When material produces isolation, the middle part of padded elephant trunk, middle and lower part, or the steepest in the gradient Time, pipeline can be put into S molded line, or to slip the vertical angle of straight tube 2 under adjusting be 30 degree of-60 degree of horizontal sextant angle.
It is 1:2-1:0.5(21.80 that described construction method is applicable to the gradient0-63.430).
Described construction method is applicable to length of grade 50m-350m.
Compared with prior art beneficial effects of the present invention is as follows:
1, elephant trunk uses fog long-term wet channels inwall, reduces the frictional resistance slipped under material, reached less than 300 The effect of delivering concrete under slope, overcoming directly to add water simultaneously compensates the drawback of slump-loss;
2, elephant trunk uses plastic tube (PE, PP pipe etc.) or plastic tube to be combined with steel pipe, can be arranged to slight S type during abrupt slope Pipe, the problem of aggregate segregation when solving abrupt slope, lower end can promote and swing simultaneously, has both solved reduction discharging section thing The problem of material speed, also achieves cloth voluntarily, and solving elephant trunk can not the problem of cloth;
3, construct the intermission, in 10h, be not required to wash pipe, need not both alleviate labor intensity with water profit pipe, also solved base during beginning The problem that can not there be water in plinth face;
4, trucd mixer can directly under expect hopper, the height of hopper and bend pipe upper port can be from Row sum-equal matrix, it is to avoid road surface Injustice causes the problem that aggregate bin is higher than trucd mixer discharging opening;
5, during gentle slope, directly place digging machine in side slope upper shed excavates out a chain-wales, hopper and water tank, the most just Just, it is not necessary to when gentle slope fill or make discharging platform, the problem improving initial velocity when solving gentle slope;
6, by the adjustment in step, cover 1:2-1:0.5(21.800-63.430) side slope in the case of elephant trunk concrete Conveying scope, have also been enlarged the range of elephant trunk technology;
7, when using plastic tube, overall weight is light, and pipeline manually i.e. adjustable and movement on slope, the water consumption of fog device is the most very Little, will not be limited by field condition.
8, supporting trolley track uses channel-section steel to make, it is simple to manually move.
9, abrupt slope slip at present straight tube tilt 700-850, material againsts tube wall when falling immediately, and smooths along bend pipe Flow forward, it is to avoid fall behind the bounce-back segregation phenomenon that excessive velocities causes under straight line.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram
Wherein: under 1-hopper, 2-, slip straight tube, 3-bend pipe, 4-flange, 5-axial flow blower, 6-straight tube, 7-fog generator, 8-is even Connect steel pipe, 9-water tank, 10-water pipe, 11-supporting trolley, 12-hanger, 13-tremie pipe, 14-cloth sleeve pipe, 15-electric block, 16-mobile roof support.
Detailed description of the invention
A kind of fog chute device of delivering concrete under gentle slope and abrupt slope, including hopper 1, under slip straight tube 2, bend pipe 3, straight tube 6, tremie pipe 13, it is characterised in that: 3-60 saves 6 meters long (nominal diameter DN125mm-DN350mm) straight tubes 6, passes through method Orchid connects into elephant trunk, is fitted with leakproof rubber cushion between flange, and elephant trunk top first segment straight tube 6 is provided with axial flow blower 5, each On joint straight tube 6, fog generator 7 is installed;
Flange joint bend pipe 3 is passed through in first segment straight tube 6 upper end, elephant trunk top, and bend pipe 3 diameter is identical with straight tube 6, bent arc radius R300mm-R2000mm, arc length 400mm-3000mm;
Hopper 1 discharging opening slips straight tube 2 under connecting, under slip straight tube 2 nominal diameter DN100mm-DN300mm, length 500mm- 2000mm, under slip straight tube 2 horizontal sextant angle 60 degree-85 degree, under slip straight tube 2 and insert in bend pipe 3;Hopper 1 is erected on hopper base, Arranging water tank 9 on hopper base, draw water pipe 10 from water tank 9, water pipe 10 is connected one by one with fog generator 7;
Elephant trunk tail end final section straight tube 6 is connected with tremie pipe 13 one end by flange, and tremie pipe 13 is plastic-steel products compound tube, Internal layer is PE or PP plastics, and outer layer is steel, and tremie pipe 13 inner layer plastic tube nominal diameter is identical with straight tube 6, and outer layer pipe is rolled up Size processed and inner layer plastic tube external diameter interference fit, tremie pipe 13 outer layer pipe is welded with a hanger 12, and cloth sleeve pipe 14 overlaps On tremie pipe 13, cloth sleeve pipe 14 is steel pipe, nominal diameter DN150mm-DN400mm, length 3-9 rice, cloth sleeve pipe 14 edge Axially have width 15mm-30mm groove, length 2.8-8.8 rice.
A kind of construction method of delivering concrete under gentle slope and abrupt slope, the steps include:
A, making elephant trunk: by good to the plastic tube purchased or steel pipe melting welding flange, polish pipe inside weld;Wherein for elephant trunk top First segment straight tube 6 on be welded be welded on the arm of connecting shaft flow fan 5, each joint straight tube 6 for connect fog occur The arm of device;
B, squeeze into earth anchor: on the transversal line slope arranging elephant trunk, squeeze into angle steel on road, use as earth anchor;
C, installation hawser: flexible steel wire on the upper flange bottom set need first segment elephant trunk straight tube to be mounted, hawser is solid It is scheduled on earth anchor.
D, install elephant trunk: according to the slope excavating gradient (1:0.5;1:1;1:1.5;1:2 or the reality between the ratio of above-mentioned slope Slope, border than), the transversal line need casting concrete prolongs domatic layout plastic tube or steel pipe (or plastic tube and steel is installed Pipe mixes, and is i.e. needing to adjust the local layout plastic tube of conduit slope), use Flange joint between pipeline, join between flange Dress leakproof rubber cushion;
E, installation supporting trolley 11: longer in side slope, when being disposed with packway in the middle part of slope, good and sound supporting trolley 11 on packway;
F, excavation hopper mounting platform: the top elevation at elephant trunk top first segment straight tube 6 digs the platform of 1.25m*1.25m, flat Hopper base is set on platform;
G, installation bend pipe 3: install bend pipe in first segment straight tube 6 upper end on elephant trunk top;
H, install hopper 1 and under slip straight tube 2: hopper 1 is arranged on hopper base, and hopper 1 discharging opening slips straight tube 2 under connecting, under Slip straight tube 2 horizontal sextant angle 75 degree-85 degree, under slip straight tube 2 and insert in bend pipe 3, and adjust the height of hopper 1 at 1.5m-3m;
I, installation water tank 10: water tank 10 is installed on hopper base;
J, installation tremie pipe 13 and cloth sleeve pipe 14: elephant trunk tail end final section straight tube 6 is by flange with tremie pipe 13 one end even Connecing, cloth sleeve pipe 14 is enclosed within tremie pipe 13, and the hanger 12 on tremie pipe 13 is by suspension hook and the electronic calabash on walking door frame 16 Reed 15 connects, by the mobile and lifting moving tremie pipe 13 of electric block 15 before and after walking door frame 16, and by cloth set The distance of the extension and contraction control cloth of pipe 14;
K, installation fog generator 7: fog generator 7 is installed on the arm welded in advance on straight tube 6, draws water from water tank 9 Pipe 10, water pipe 10 is connected one by one with fog generator 7;
L, installation axial flow blower 5: axial flow blower is installed on the arm that elephant trunk top first segment straight tube 6 welds in advance;
M, installation cable: on fog generator 7 and axial flow blower 5, load onto cable;
N, examination are slipped: examination is slipped employing plan and slipped the rubber cement of the mix Design parameter preparation sent (without being sand during admixture Slurry), before examination is slipped, open fog generator and axial flow blower, allow fog be full of pipeline, and keep moisture state;Moisten at pipeline Afterwards, the rubber cement prepared is carried out examination and slips (when examination is slipped can closing axle flow fan);
O, adjustment: the gradient is excessively slow slip motionless or plugging time, first adjust the linearity of pipeline, make pipeline keep straight line, then under adjusting Slip the vertical angle of straight tube 2, adjust the height of hopper 1 and bend pipe 3 top simultaneously, or by the first segment upper end of elephant trunk straight tube 6 Portion raises, improve material initial velocity, it is simple under slip;When material produces isolation, the middle part of padded elephant trunk, middle and lower part, or in the gradient Time too steep, pipeline can be put into S molded line, or to slip the vertical angle of straight tube 2 under adjusting be 30 degree of-60 degree of horizontal sextant angle.
It is 1:2-1:0.5(21.80 that described construction method is applicable to the gradient0-63.430).
Described construction method is applicable to length of grade 50m-350m.

Claims (4)

1. a fog chute device for delivering concrete under gentle slope and abrupt slope, including hopper (1), under slip straight tube (2), curved Pipe (3), straight tube (6), tremie pipe (13), it is characterised in that: 3-60 saves 6 meters long, the straight tube of nominal diameter DN125mm-DN350mm (6) become elephant trunk by Flange joint, be fitted with leakproof rubber cushion between flange, elephant trunk top first segment straight tube (6) is provided with axle Flow fan (5), each joint straight tube (6) is provided with fog generator (7);
Flange joint bend pipe (3) is passed through in first segment straight tube (6) upper end, elephant trunk top, and bend pipe (3) diameter is identical with straight tube (6), curved Arc radius R300mm-R2000mm, arc length 400mm-3000mm;
Hopper (1) discharging opening slips straight tube (2) under connecting, under slip straight tube (2) nominal diameter DN100mm-DN300mm, length 500mm-2000mm, under slip straight tube (2) horizontal sextant angle 60 degree-85 degree, under slip straight tube (2) and insert in bend pipe (3);Hopper (1) frame Being located on hopper base, hopper base arranges water tank (9), draw water pipe (10) from water tank (9), water pipe (10) occurs with fog Device (7) connects one by one;
Elephant trunk tail end final section straight tube (6) is connected with tremie pipe (13) one end by flange, and tremie pipe (13) is plastic-steel products Compound tube, internal layer is PE or PP plastics, and outer layer is steel, and tremie pipe (13) inner layer plastic tube nominal diameter is identical with straight tube (6), Outer layer pipe rolls size and inner layer plastic tube external diameter interference fit, and tremie pipe (13) outer layer pipe is welded with a hanger (12), cloth sleeve pipe (14) is enclosed within tremie pipe (13), and cloth sleeve pipe (14) is steel pipe, nominal diameter DN150mm-DN400mm, Length 3-9 rice, cloth sleeve pipe (14) has width 15mm-30mm groove, length 2.8-8.8 rice vertically.
2. a construction method for delivering concrete under gentle slope and abrupt slope, the steps include:
A, making elephant trunk: by good to the plastic tube purchased or steel pipe melting welding flange, polish pipe inside weld;Wherein for elephant trunk top First segment straight tube (6) on be welded and be welded for connecting mist on the arm of connecting shaft flow fan (5), each joint straight tube (6) The arm of gas generator;
B, squeeze into earth anchor: on the transversal line slope arranging elephant trunk, squeeze into angle steel on road, use as earth anchor;
C, installation hawser: flexible steel wire on the upper flange bottom set need first segment elephant trunk straight tube to be mounted, hawser is solid It is scheduled on earth anchor;
D, install elephant trunk: according to the slope excavating gradient (1:0.5;1:1;1:1.5;1:2 or the actual slope between the ratio of above-mentioned slope Than), the transversal line need casting concrete prolongs domatic layout and plastic tube or steel pipe is installed (or plastic tube mixes with steel pipe Close, i.e. needing to adjust the local layout plastic tube of conduit slope), use Flange joint between pipeline, equipped anti-between flange Leakage rubber cushion;
E, installation supporting trolley (11): longer in side slope, when being disposed with packway in the middle part of slope, good and sound supporting trolley on packway (11);
F, excavation hopper mounting platform: the top elevation on elephant trunk top first segment straight tube (6) digs the platform of 1.25m*1.25m, Hopper base is set on platform;
G, installation bend pipe (3): install bend pipe in first segment straight tube (6) upper end on elephant trunk top;
H, install hopper (1) and under slip straight tube (2): hopper (1) is arranged on hopper base, slips under the connection of hopper (1) discharging opening Straight tube (2), under slip straight tube (2) horizontal sextant angle 75 degree-85 degree, under slip straight tube (2) and insert in bend pipe (3), and adjust hopper (1) Height at 1.5m-3m;
I, installation water tank (10): water tank (10) is installed on hopper base;
J, installation tremie pipe (13) and cloth sleeve pipe (14): elephant trunk tail end final section straight tube (6) passes through flange and tremie pipe (13) one end connects, and cloth sleeve pipe (14) is enclosed within tremie pipe (13), and the hanger (12) on tremie pipe (13) passes through suspension hook and row Walk the electric block (15) on door frame (16) to connect, by mobile before and after walking door frame (16) and the lifting of electric block (15) Mobile tremie pipe (13), and by the distance of the extension and contraction control cloth of cloth sleeve pipe (14);
K, installation fog generator (7): fog generator (7) is installed, from water tank on the arm welded in advance on straight tube (6) (9) drawing water pipe (10), water pipe (10) is connected one by one with fog generator (7);
L, installation axial flow blower (5): axial flow blower is installed on the arm that elephant trunk top first segment straight tube (6) is welded in advance;
M, installation cable: on fog generator (7) and axial flow blower (5), load onto cable;
N, examination are slipped: examination is slipped employing plan and slipped the rubber cement of the mix Design parameter preparation sent (without being sand during admixture Slurry), before examination is slipped, open fog generator and axial flow blower, allow fog be full of pipeline, and keep moisture state;Moisten at pipeline Afterwards, the rubber cement prepared is carried out examination and slips (when examination is slipped can closing axle flow fan);
O, adjustment: the gradient is excessively slow slip motionless or plugging time, first adjust the linearity of pipeline, make pipeline keep straight line, then under adjusting Slip the vertical angle of straight tube (2), adjust the height of hopper (1) and bend pipe (3) top simultaneously, or by the of elephant trunk straight tube (6) One joint upper end raises, improve material initial velocity, it is simple under slip;When material produces isolation, the middle part of padded elephant trunk, middle and lower part, Or when the gradient is too steep, pipeline can be put into S molded line, or to slip the vertical angle of straight tube (2) under adjusting be horizontal sextant angle 30 Degree-60 degree.
A kind of construction method of delivering concrete under gentle slope and abrupt slope, it is characterised in that: institute State construction method being applicable to the gradient is 1:2-1:0.5(21.800-63.430).
A kind of construction method of delivering concrete under gentle slope and abrupt slope, it is characterised in that: institute State construction method and be applicable to length of grade 50m-350m.
CN201610529745.6A 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope Active CN106088097B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610529745.6A CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610529745.6A CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Publications (2)

Publication Number Publication Date
CN106088097A true CN106088097A (en) 2016-11-09
CN106088097B CN106088097B (en) 2018-01-16

Family

ID=57212434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610529745.6A Active CN106088097B (en) 2016-07-07 2016-07-07 Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope

Country Status (1)

Country Link
CN (1) CN106088097B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984577A (en) * 2019-12-21 2020-04-10 河南昊锦建设集团有限公司 Concrete pouring system
CN111396676A (en) * 2020-04-27 2020-07-10 南京晨光东螺波纹管有限公司 Displacement compensation device of arc-shaped heat pipe and installation method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6278318A (en) * 1985-09-30 1987-04-10 Okumura Constr Co Ltd Vertical chute for concreting work
CN1827920A (en) * 2005-03-02 2006-09-06 李勇 Method for reducing steel pipe concrete pumping resistance
CN101338860A (en) * 2007-07-03 2009-01-07 中国水利水电闽江工程局 Roller compacted concrete full package chute vertical conveying technology
CN101812845A (en) * 2009-02-25 2010-08-25 中国葛洲坝集团股份有限公司 Vertical concrete conveying system of small and medium hydropower station at high steep slopes
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103953193A (en) * 2014-04-16 2014-07-30 中国十九冶集团有限公司 Construction method for long-distance gentle-slope concrete conveying
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6278318A (en) * 1985-09-30 1987-04-10 Okumura Constr Co Ltd Vertical chute for concreting work
CN1827920A (en) * 2005-03-02 2006-09-06 李勇 Method for reducing steel pipe concrete pumping resistance
CN101338860A (en) * 2007-07-03 2009-01-07 中国水利水电闽江工程局 Roller compacted concrete full package chute vertical conveying technology
CN101812845A (en) * 2009-02-25 2010-08-25 中国葛洲坝集团股份有限公司 Vertical concrete conveying system of small and medium hydropower station at high steep slopes
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103953193A (en) * 2014-04-16 2014-07-30 中国十九冶集团有限公司 Construction method for long-distance gentle-slope concrete conveying
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
葛乃剑等: "上海世茂深坑酒店混凝土向下超深三级接力输送技术", 《施工技术》 *
钱海波等: "上海世茂深坑酒店混凝土超深一溜到底施工技术", 《施工技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984577A (en) * 2019-12-21 2020-04-10 河南昊锦建设集团有限公司 Concrete pouring system
CN110984577B (en) * 2019-12-21 2021-07-20 河南昊锦建设集团有限公司 Concrete pouring system
CN111396676A (en) * 2020-04-27 2020-07-10 南京晨光东螺波纹管有限公司 Displacement compensation device of arc-shaped heat pipe and installation method thereof
CN111396676B (en) * 2020-04-27 2024-04-12 南京晨光东螺波纹管有限公司 Displacement compensation device of arc-shaped heat pipe and installation method thereof

Also Published As

Publication number Publication date
CN106088097B (en) 2018-01-16

Similar Documents

Publication Publication Date Title
CN104343455B (en) Long-distance curved jacking pipe and pipe roof construction technique
CN108952733A (en) Separate launching shield technique application construction method in municipal sewerage engineering
CN104989873B (en) Penstock oblique-pulling inversion assembling method
CN104533449B (en) A kind of tunnel excavation stand and apply the adit construction method of this stand
CN108625894A (en) The waste filling solid grouting construction method of the flat working face of shortwall lane water acquisition
CN106192907A (en) Set up the construction method of 150m~the 300m level high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN205917701U (en) A sleeve pipe distributing device for elephant trunk transport concrete
CN106088097A (en) The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope
CN106192898A (en) The joint construction method of Face Slab of Concrete-faced Rockfill anti-settling deformation
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN114876515A (en) Two lining platform trucks in tunnel are pour fast
CN207847102U (en) Appts. for transferring ready-mixed concrete
CN205935686U (en) A fog elephant trunk device that is used for carrying concrete under gentle slope and abrupt slope
CN205975530U (en) Dual formula slip form construction device of bend loss and straight section concrete
CN211566328U (en) Automatic maintenance device for highway engineering concrete member
CN105604129A (en) Water pump mounting construction method
CN109403636A (en) A kind of conveying based on skyscraper concrete construction pours device
CN212764100U (en) Batching and stirring integrated machine capable of being folded integrally
CN211340675U (en) Precast lining plate cement mortar caulking machine for water delivery channel
CN210434375U (en) Movable foaming agent production equipment
CN207144496U (en) Concrete filled steel tubular column concrete lift-up device for casting
CN209228060U (en) A kind of conveying based on skyscraper concrete construction pours device
CN206800148U (en) A kind of pitch-rood
CN206555620U (en) A kind of Large Diameter Pipeline bend pipe bearing
CN204663540U (en) A kind of Metro Deep Excavation lid excavation construction agent structure cast pump line distribution device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190801

Address after: 430072 Room 19, Room 21, Building 4, Mingshi 1, Shucheng Road, Hongshan District, Wuhan City, Hubei Province

Co-patentee after: Zheng Chuying

Patentee after: HUBEI 209 ENGINEERING Co.,Ltd.

Address before: 430071 2 Units 1002, 2 Blocks, Xingyuan, Anshun, 115 North Road, Wuchang District, Wuhan City, Hubei Province

Patentee before: Zheng Chuying

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230403

Address after: 433200 maojiang Avenue, Xindi, Honghu City, Jingzhou City, Hubei Province

Patentee after: Hubei Jugong Construction Engineering Co.,Ltd.

Address before: 430072 room 19, floor 21, building 4, No. 1 Mingshi, Shucheng Road, Hongshan District, Wuhan City, Hubei Province

Patentee before: HUBEI 209 ENGINEERING Co.,Ltd.

Patentee before: Zheng Chuying

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240812

Address after: No. 143, Liulintan Village, Qinglin Township, Datong Hui and Tu Autonomous County, Xining City, Qinghai Province 810100

Patentee after: Ha Guishan

Country or region after: China

Patentee after: Du Wenju

Address before: 433200 maojiang Avenue, Xindi, Honghu City, Jingzhou City, Hubei Province

Patentee before: Hubei Jugong Construction Engineering Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240829

Address after: Room 12301, Unit 1, Building 1, No. 25 Shengli Road, Chengxi District, Xining City, Qinghai Province 810000

Patentee after: Qinghai Xinxian Construction Engineering Co.,Ltd.

Country or region after: China

Address before: No. 143, Liulintan Village, Qinglin Township, Datong Hui and Tu Autonomous County, Xining City, Qinghai Province 810100

Patentee before: Ha Guishan

Country or region before: China

Patentee before: Du Wenju