CN106026080B - A kind of power generating capacity automatic control system and method - Google Patents
A kind of power generating capacity automatic control system and method Download PDFInfo
- Publication number
- CN106026080B CN106026080B CN201610342923.4A CN201610342923A CN106026080B CN 106026080 B CN106026080 B CN 106026080B CN 201610342923 A CN201610342923 A CN 201610342923A CN 106026080 B CN106026080 B CN 106026080B
- Authority
- CN
- China
- Prior art keywords
- unit
- load
- full factory
- optimization device
- allocation strategy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 14
- 238000005457 optimization Methods 0.000 claims abstract description 55
- 238000009826 distribution Methods 0.000 claims abstract description 31
- 230000033228 biological regulation Effects 0.000 claims description 18
- 230000008859 change Effects 0.000 claims description 14
- 238000010606 normalization Methods 0.000 claims description 10
- 238000003860 storage Methods 0.000 claims description 10
- 238000011217 control strategy Methods 0.000 claims description 6
- 230000005611 electricity Effects 0.000 claims description 4
- 238000005304 joining Methods 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 4
- 239000002699 waste material Substances 0.000 description 3
- 240000002853 Nelumbo nucifera Species 0.000 description 2
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 2
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000006477 desulfuration reaction Methods 0.000 description 2
- 238000010348 incorporation Methods 0.000 description 2
- 230000008520 organization Effects 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 230000004044 response Effects 0.000 description 2
- 244000131316 Panax pseudoginseng Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000023556 desulfurization Effects 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- H02J3/005—
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention relates to a kind of power generating capacity automatic control system and methods, the system comprises full factory's Automatic Generation Control optimization device and at least one set optimization device, set optimization device optimizes device with full factory's Automatic Generation Control respectively and external corresponding generator set controller connects;Full factory's Automatic Generation Control optimization device is also connect with external all generator set controllers;Set optimization device, for acquiring operating parameter, and the operational efficiency according to the corresponding unit of operating parameter calculating from corresponding generator set controller;Full factory's Automatic Generation Control optimizes device, the load value that each unit is calculated with the operational efficiency of received each unit is always instructed for full factory's load based on the received from grid side, and the sharing of load instruction for forming each unit is sent to corresponding generator set controller, so that generator set controller instructs control unit generation according to sharing of load.The present invention can be each unit reasonable distribution load according to the operation conditions of each unit, avoid the loss of power plant load.
Description
Technical field
The present invention relates to electric power network technical fields, and in particular to a kind of power generating capacity automatic control system and method.
Background technique
Currently, grid company mostly uses greatly AGC directly to adjust mode the scheduling of power plant units, i.e., load instruction is issued often
Platform unit directly dispatches every unit load.This scheduling mode according to the coa consumption rate of each unit, desulfurization due to that cannot imitate
The performance parameters such as rate, the speed of response, adjustable range, rate for incorporation into the power network, operating condition automatically, reasonably carry out the excellent of full brand-name computer group
Change combination and sharing of load, energy waste and unit durability is caused to reduce;Simultaneously when equipment faults such as power plant's single unit machine, furnaces
When dropping power output operation, institute's load down cannot be transferred to another unit, cause the loss of power plant load.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of power generating capacity automatic control system and method, Neng Gougen
It is each unit reasonable distribution load according to the operation conditions of each unit, avoids the loss of power plant load.
The technical scheme to solve the above technical problems is that a kind of power generating capacity automatic control system, including
Full factory's AGC Automatic Generation Control optimization device and at least one set optimization device, the set optimization device and the full factory
Automatic Generation Control optimizes device connection, and the set optimization device is also connected with external corresponding generator set controller;It is described complete
Factory's Automatic Generation Control optimization device is also connect with external all generator set controllers;
The set optimization device is used to acquire operating parameter from corresponding generator set controller, and according to the operation
Parameter calculates the operational efficiency of corresponding unit;
Full factory's Automatic Generation Control optimizes device, always instructs for full factory's load based on the received from grid side
The load value of each unit is calculated with the operational efficiency of received each unit, and forms the sharing of load instruction hair of each unit
Corresponding generator set controller is given, so that generator set controller controls corresponding unit generation according to sharing of load instruction.
The beneficial effects of the present invention are: operating parameter is acquired from corresponding generator set controller by set optimization device, with
And the operational efficiency of corresponding unit is calculated according to the operating parameter, and then Shi Quan factory Automatic Generation Control optimization device is according to connecing
The full factory's load from grid side received, which always instruct, calculates the load value of each unit with the operational efficiency of each unit, and by shape
At each unit sharing of load instruction be sent to corresponding generator set controller so that generator set controller refers to according to sharing of load
It enables and controls corresponding unit generation, to realize optimum organization and sharing of load automatic, that reasonably carry out full brand-name computer group, avoid
Energy waste and unit durability are reduced.
Based on the above technical solution, the present invention can also be improved as follows:
Further, full factory's Automatic Generation Control optimization device includes control strategy module;
The control strategy module, for always instructing and the fortune of each unit received full factory's load from grid side
Line efficiency calculates the load value of each unit according to load distribution strategy.
Further, the load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device receives full factory's load instruction of grid side, according to the electricity received
Full factory's load instruction calculated load changing value of full factory's load instruction of net side and the last grid side received, and work as load
When changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is that (operating unit number of units × single machine holds
Amount × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes the received load variations value < of device (operating unit number of units × 10) MW, then
Total rate of change be (operating unit number of units × single-machine capacity × 1.5% (and MW/min, when distribution need to meet single unit rate >=
(single-machine capacity × 1.5%) MW/min.
Further, the load distribution strategy is efficiency of generating unit allocation strategy, regulations speed allocation strategy, adjusts and hold
Measure any strategy in allocation strategy, normalization index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: always imitate the generating efficiency of each unit in all unit generations
Ratio in rate is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit all units the total rate of adjusting
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit all units adjusting total capacity
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The normalization index allocation strategy specifically: by the weight coefficient of preset each unit and full factory's load
Total instruction is multiplied, and obtains the load value of each unit;
The fixed point power allocation strategy specifically: by the fixed point power difference of each unit all units fixed point function
Accounting in rate difference is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is pre-
The difference of the fixed point power value and actually measured fixed point power value that first set.
Further, the system management module, for obtaining operating parameter and the classification of unit from set optimization device;
The database, for real-time and classification storage unit operating parameter;
The historical data base transfers corresponding operating parameter conduct for the record format according to setting from database
Historical record storage.
Further, full factory's Automatic Generation Control optimization device (1) further includes alarm module and Reports module;
The alarm module, for judging whether it is preset according to the data point operating parameter stored in historical data base
Normal operational parameters value if it is not, being then judged as failure, and is alarmed;Otherwise, it is not processed.
The Reports module, for by database in real time and classification storage unit operating parameter and/or historical data
Historical record in library exports in the Excel template pre-set.
Further, full factory's Automatic Generation Control optimization device further includes trend display module, for by database and/
Or the parameter forming curves figure in historical data base is shown.
The another technical solution that the present invention solves above-mentioned technical problem is as follows: a kind of power generating capacity automatic control side
Method, comprising the following steps:
Set optimization device acquires operating parameter from corresponding generator set controller, and according to operating parameter calculating pair
Answer the operational efficiency of unit;
Full factory's load from grid side is always instructed and is connect full factory's Automatic Generation Control optimization device based on the received
The operational efficiency for each unit received calculates the load value of each unit, and the sharing of load instruction for forming each unit is sent to
Corresponding generator set controller, so that generator set controller controls corresponding unit generation according to sharing of load instruction.
The beneficial effects of the present invention are: operating parameter is acquired from corresponding generator set controller by set optimization device, with
And the operational efficiency of corresponding unit is calculated according to the operating parameter, and then Shi Quan factory Automatic Generation Control optimization device is according to connecing
The full factory's load from grid side received, which always instruct, calculates the load value of each unit with the operational efficiency of each unit, and by shape
At each unit sharing of load instruction be sent to corresponding generator set controller so that generator set controller refers to according to sharing of load
It enables and controls corresponding unit generation, to realize optimum organization and sharing of load automatic, that reasonably carry out full brand-name computer group, avoid
Energy waste and unit durability are reduced.
Based on the above technical solution, the present invention can also be improved as follows:
Further, the load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device receives full factory's load instruction of grid side, according to the electricity received
Full factory's load instruction calculated load changing value of full factory's load instruction of net side and the last grid side received, and work as load
When changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is that (operating unit number of units × single machine holds
Amount × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes the received load variations value < of device (operating unit number of units × 10) MW, then
Total rate of change be (operating unit number of units × single-machine capacity × 1.5% (and MW/min, when distribution need to meet single unit rate >=
(single-machine capacity × 1.5%) MW/min.
Further, the load distribution strategy is efficiency of generating unit allocation strategy, regulations speed allocation strategy, adjusts and hold
Measure any strategy in allocation strategy, normalization index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: the generating efficiency of each unit is total in the power generation of all units
Ratio in efficiency is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit all units the total rate of adjusting
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit all units adjusting total capacity
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The normalization index allocation strategy specifically: by the weight coefficient of preset each unit and full factory's load
Total instruction is multiplied, and obtains the load value of each unit;
The fixed point power allocation strategy specifically: by the fixed point power difference of each unit all units fixed point function
Accounting in rate difference is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is pre-
The difference of the fixed point power value and actually measured fixed point power value that first set.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of power generating capacity automatic control system of the present invention;
Fig. 2 is a kind of flow diagram of power generating capacity autocontrol method of the present invention.
Specific embodiment
The principle and features of the present invention will be described below with reference to the accompanying drawings, and the given examples are served only to explain the present invention, and
It is non-to be used to limit the scope of the invention.
Fig. 1 is a kind of structural schematic diagram of power generating capacity automatic control system of the present invention.
As shown in Figure 1, a kind of power generating capacity automatic control system, including full factory AGC Automatic Generation Control optimize device 1
With at least one set optimization device 2, the set optimization device 2 is connect with full factory's Automatic Generation Control optimization device 1,
The set optimization device 2 is also connected with external corresponding generator set controller;Full factory's Automatic Generation Control optimization device 1 is also
It is connect with external all generator set controllers;
The set optimization device 2 is used to acquire operating parameter from corresponding generator set controller, and according to the operation
Parameter calculates the operational efficiency of corresponding unit;
Full factory's Automatic Generation Control optimizes device 1, always refers to for full factory's load based on the received from grid side
It enables and the operational efficiency of received each unit calculates the load value of each unit, and form the sharing of load instruction of each unit
It is sent to corresponding generator set controller, so that generator set controller controls corresponding unit generation according to sharing of load instruction.
Wherein, full factory's Automatic Generation Control optimization device includes system management module, database, control strategy module, figure
As interface module, historical data base and trend display module;
The system management module, for collecting from generator set controller the operating parameter of unit when set optimization device
Afterwards, it obtains the operating parameter of unit in real time from the set optimization device, and the operating parameter of each unit is divided
Class;The operating parameter of unit includes the property such as coa consumption rate, desulfuration efficiency, the speed of response, adjustable range, rate for incorporation into the power network, operating condition
It can parameter;
The database, for real-time and classification storage unit operating parameter;
Described image interface module, for providing drawing function, drawing user includes the various types of of suitable power plant's requirement
Type operation screen, and saved in the form of pel into picture library, wherein database includes picture library;
Graphical interfaces module provides tool box for user, and user only needs to choose corresponding tool, using mouse
Monitored picture is made in their own needs.
Graphical interfaces module is with the following functions:
1) document interface is provided;
2) a variety of basic drawing tools are provided, including straight line, rectangle, round rectangle, ellipse, sector, polygon, broken line,
Text and bitmap;
3) dynamic data point fastening means is provided, as analog quantity point, switching value point, rod figure, pointer, real-time curve, XY are bent
Line and alarm etc.;
4) each element figure can be changed after there is dynamic characteristic abundant to connect with dynamic data by defined condition
Become the operations such as color, flashing, hiding and movement;
5) provide editting function, such as copy, paste, in groups, division, redo, undo, overturning, left and right consistency from top to bottom, with height
With width with size and equidistant editting function.Working efficiency can be greatly improved in this way;
6) picture library function is provided.The complex figure that user makes can be stored in picture library in the form of pel, including suitable
Close various types operation screen (such as electrically operated gate, solenoid valve, motor, electric switch, program-controlled, help screen that power plant requires
Deng), it need to only be recalled from picture library when reusing, simplicity is answered in picture connection, greatly reduces repeated labor.
7) solid figure can be made.
8) feature-rich button and hot spot tool can easily realize base map switching, transmitting order to lower levels, ejection operation
The functions such as window.
9) flexible pop-up window function, can configuration picture, order etc. in pop-up window, and with simulation numeral key
Disk.
The historical data base transfers corresponding operating parameter conduct for the record format according to setting from database
Historical record storage;
Historical data base is to choose the operation ginseng for needing the data point recorded from database according to the record format of setting
Number, the record format of setting include: common acquisition moment record, hour record, day entry, recollect record, SOE record
(Sequence Of Event, sequence of events recording).Mode there are two types of the storages and processing of historical record in historical data base,
One is using the form for writing fixed disk file, another kind is the form using private database.Common acquisition moment record, refers to
Acquisition data point is gone according to the acquisition moment of the data point of default;
Historical data base consists of the following components:
Periodic recording: all points into database enter historical data base, record the variation of point per second.
Recollect record: recording some event and front and back (amount of logic variation), the data variation in specified time, a thing occurs
Part can be made of the inclusive-OR operation relationship that most 8 amount of logic change, and each event at most can recorde 128 data points,
The record period of each point is the second, and the minimum period is 1 second, and each point at most records event front and back totally 20 minute data.One text
Part records one day data, and the file named with the date on the same day is written.
Isolated cases record: the alarm logging that need to be deposited, every month one are indicated in alarm logging, record system database
Record file.
Trend display module, for showing the data forming curves figure in database and/or historical data base.
Full factory's Automatic Generation Control optimization device further includes alarm module, for according to the operation stored in historical data base
Parameter judges whether it is preset normal operational parameters, if it is not, being then judged as failure, and reports in a voice form to user
It is alert;Otherwise, it is not processed.
So that operations staff is found the problem in time by alarm module, quickly properly processes problem, and can reliably remember
Record alarm procedure.
Wherein, alarm module can also show warning message, warning message include the title of alarm point, type of alarm,
Current value, state, alarm date, time, place process station number, alarm group number, fastener number.
Full factory's Automatic Generation Control optimization device 1 further includes Reports module, is used for real-time and classification storage in database
Unit operating parameter and/or historical data base in historical record export in the Excel template pre-set.
Reports module is that records various in database and/or historical data base are exported to use based on Excel application program
Family is according in the good Excel template of actual field Demand Design.Excel template is by user according to requiring the various templates of tissue,
And it formats.
The control strategy module, for always instructing and the fortune of each unit received full factory's load from grid side
Line efficiency calculates the load value of each unit according to load distribution strategy;
The load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device 1 receives full factory's load instruction of grid side, according to what is received
Full factory's load instruction calculated load changing value of full factory's load instruction of grid side and the last grid side received, and when negative
When lotus changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is (operating unit number of units × single machine
Capacity × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes 1 received load variations value < (operating unit number of units × 10) MW of device,
Then total rate of change is that ((MW/min, when distribution need to meet single unit rate to operating unit number of units × single-machine capacity × 1.5%
>=(single-machine capacity × 1.5%) MW/min.
The load distribution strategy is efficiency of generating unit allocation strategy, regulations speed allocation strategy, pondage distribution
Any strategy in strategy, normalization index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: always imitate the generating efficiency of each unit in all unit generations
Ratio in rate is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit all units the total rate of adjusting
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit all units adjusting total capacity
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The normalization index allocation strategy specifically: by the weight coefficient of preset each unit and full factory's load
Total instruction is multiplied, and obtains the load value of each unit;
The fixed point power allocation strategy specifically: by the fixed point power difference of each unit all units fixed point function
Accounting in rate difference is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is pre-
The difference of the unit load value and actually measured unit load value that first set.
Fig. 2 is a kind of flow diagram of power generating capacity autocontrol method of the present invention.
As shown in Fig. 2, a kind of power generating capacity autocontrol method, comprising the following steps:
Set optimization device 2 acquires operating parameter from corresponding generator set controller, and is calculated according to the operating parameter
The operational efficiency of corresponding unit;
Full factory's load from grid side is always instructed and is connect full factory's Automatic Generation Control optimization device 1 based on the received
The operational efficiency for each unit received calculates the load value of each unit, and the sharing of load instruction for forming each unit is sent to
Corresponding generator set controller, so that generator set controller controls corresponding unit generation according to sharing of load instruction.
Wherein, load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device 1 receives full factory's load instruction of grid side, according to what is received
Full factory's load instruction calculated load changing value of full factory's load instruction of grid side and the last grid side received, and when negative
When lotus changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is (operating unit number of units × single machine
Capacity × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes 1 received load variations value < (operating unit number of units × 10) MW of device,
Then total rate of change is that ((MW/min, when distribution need to meet single unit rate to operating unit number of units × single-machine capacity × 1.5%
>=(single-machine capacity × 1.5%) MW/min.
Wherein, load distribution strategy is efficiency of generating unit allocation strategy, regulations speed allocation strategy, pondage distribution
Any strategy in strategy, normalization index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: always imitate the generating efficiency of each unit in all unit generations
Ratio in rate is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit all units the total rate of adjusting
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit all units adjusting total capacity
In ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The normalization index allocation strategy specifically: by the weight coefficient of preset each unit and full factory's load
Total instruction is multiplied, and obtains the load value of each unit;
The fixed point power allocation strategy specifically: by the fixed point power difference of each unit all units fixed point function
Accounting in rate difference is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is pre-
The difference of the unit load value and actually measured unit load value that first set.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (5)
1. a kind of power generating capacity automatic control system, which is characterized in that including full factory's Automatic Generation Control optimization device (1) and
At least one set optimization device (2), the set optimization device (2) and full factory's Automatic Generation Control optimization device (1)
Connection, the set optimization device (2) also connect with external corresponding generator set controller;Full factory's Automatic Generation Control optimization
Device (1) is also connect with external all generator set controllers;
The set optimization device (2), for joining from corresponding generator set controller acquisition operating parameter, and according to the operation
Number calculates the operational efficiency of corresponding unit;
Full factory's Automatic Generation Control optimization device (1), always instructs for full factory's load based on the received from grid side
The load value of each unit is calculated with the operational efficiency of received each unit, and forms the sharing of load instruction hair of each unit
Corresponding generator set controller is given, so that generator set controller controls corresponding unit generation according to sharing of load instruction;
Full factory's Automatic Generation Control optimization device includes control strategy module;
The control strategy module is imitated for always instructing received full factory's load from grid side with the operation of each unit
Rate calculates the load value of each unit according to load distribution strategy;
The load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device (1) receives full factory's load instruction of grid side, according to the electricity received
Full factory's load instruction calculated load changing value of full factory's load instruction of net side and the last grid side received, and work as load
When changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is that (operating unit number of units × single machine holds
Amount × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes device (1) received load variations value < (operating unit number of units × 10) MW, then
Total rate of change is (operating unit number of units × single-machine capacity × 1.5%) MW/min, when distribution need to meet single unit rate >=
(single-machine capacity × 1.5%) MW/min;
The load distribution strategy be efficiency of generating unit allocation strategy, regulations speed allocation strategy, pondage allocation strategy,
Normalize any strategy in index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: by the generating efficiency of each unit in all unit generation gross efficiencys
Ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit in the total rate of adjusting of all units
Ratio is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit in the adjusting total capacity of all units
Ratio is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The normalization index allocation strategy specifically: always refer to the weight coefficient of preset each unit and full factory's load
It enables and being multiplied, obtain the load value of each unit;
The fixed point power allocation strategy specifically: the fixed point power difference of each unit is poor in the fixed point power of all units
Accounting in value is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is to set in advance
The difference of fixed unit load value and actually measured unit load value.
2. a kind of power generating capacity automatic control system according to claim 1, which is characterized in that full factory's automatic generation
Control optimization device (1) further includes system management module, database and historical data base;
The system management module, for obtaining operating parameter and the classification of unit from set optimization device;
The database, for real-time and classification storage unit operating parameter;
The historical data base transfers corresponding operating parameter as history for the record format according to setting from database
Record storage.
3. a kind of power generating capacity automatic control system according to claim 1, which is characterized in that full factory's automatic generation
Control optimization device (1) further includes alarm module and Reports module;
The alarm module is joined for judging whether it is preset normal operation according to the operating parameter stored in historical data base
Number, if it is not, being then judged as failure, and alarms;Otherwise, it is not processed;
The Reports module, for by database in real time and the unit operating parameter and/or historical data base of classification storage in
Historical record export in the Excel template pre-set.
4. a kind of power generating capacity automatic control system according to claim 1, which is characterized in that full factory's automatic generation
Control optimization device (1) further includes trend display module, for by the data forming curves in database and/or historical data base
Scheme and shows.
5. a kind of power generating capacity autocontrol method, which is characterized in that use such as of any of claims 1-4 one
Kind power generating capacity automatic control system carries out power generating capacity automatic control, comprising the following steps:
Set optimization device (2) acquires operating parameter from corresponding generator set controller, and according to operating parameter calculating pair
Answer the operational efficiency of unit;
Full factory's Automatic Generation Control optimization device (1) based on the received full factory's load from grid side always instruct and it is received respectively
The operational efficiency of a unit calculates the load value of each unit, and the sharing of load instruction for forming each unit is sent to accordingly
Generator set controller, so that generator set controller controls corresponding unit generation according to sharing of load instruction;
The load distribution strategy specifically:
After full factory's Automatic Generation Control optimization device (1) receives full factory's load instruction of grid side, according to the electricity received
Full factory's load instruction calculated load changing value of full factory's load instruction of net side and the last grid side received, and work as load
When changing value >=(operating unit number of units × 10) MW, then total rate of change of all units is that (operating unit number of units × single machine holds
Amount × 1%) MW/min, when distribution need to meet single unit rate >=(single-machine capacity × 1.5%) MW/min;
When full factory's Automatic Generation Control optimizes device (1) received load variations value < (operating unit number of units × 10) MW, then
Total rate of change is (operating unit number of units × single-machine capacity × 1.5%) MW/min, when distribution need to meet single unit rate >=
(single-machine capacity × 1.5%) MW/min;
The load distribution strategy be efficiency of generating unit allocation strategy, regulations speed allocation strategy, pondage allocation strategy,
Normalize any strategy in index allocation strategy and fixed point power allocation strategy;
The efficiency of generating unit allocation strategy specifically: by the generating efficiency of each unit in all unit generation gross efficiencys
Ratio always instruct and be multiplied with full factory's load, obtain the load value of each unit;
The regulations speed allocation strategy specifically: by the regulations speed of each unit in the total rate of adjusting of all units
Ratio is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The pondage allocation strategy specifically: by the pondage of each unit in the adjusting total capacity of all units
Ratio is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;
The normalization index allocation strategy specifically: always refer to the weight coefficient of preset each unit and full factory's load
It enables and being multiplied, obtain the load value of each unit;
The fixed point power allocation strategy specifically: the fixed point power difference of each unit is poor in the fixed point power of all units
Accounting in value is always instructed with full factory's load to be multiplied, and obtains the load value of each unit;The fixed point power difference is to set in advance
The difference of fixed unit load value and actually measured unit load value.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610342923.4A CN106026080B (en) | 2016-05-23 | 2016-05-23 | A kind of power generating capacity automatic control system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610342923.4A CN106026080B (en) | 2016-05-23 | 2016-05-23 | A kind of power generating capacity automatic control system and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106026080A CN106026080A (en) | 2016-10-12 |
CN106026080B true CN106026080B (en) | 2019-10-22 |
Family
ID=57096576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610342923.4A Active CN106026080B (en) | 2016-05-23 | 2016-05-23 | A kind of power generating capacity automatic control system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106026080B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107612045A (en) * | 2017-10-09 | 2018-01-19 | 国网安徽省电力公司 | A kind of Power Plant generated energy intelligent dispensing system and method |
CN113554251B (en) * | 2020-04-23 | 2024-06-28 | 中国南方电网有限责任公司 | Power generation load deviation distribution method, device, system and computer equipment |
CN113011724A (en) * | 2021-03-04 | 2021-06-22 | 国家能源集团国源电力有限公司 | Unit load distribution method and device and electronic equipment |
CN113300410A (en) * | 2021-04-14 | 2021-08-24 | 华能国际电力股份有限公司大连电厂 | Whole-plant load optimization control system and method for cogeneration unit |
CN113266868B (en) * | 2021-04-15 | 2022-11-29 | 国电汉川发电有限公司 | Multi-unit cooperative heat supply heat load intelligent distribution control system and method |
CN113346498B (en) * | 2021-07-07 | 2022-11-29 | 中国电建集团山东电力建设有限公司 | IGCC generator set power load distribution method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101453188A (en) * | 2008-12-30 | 2009-06-10 | 上海市电力公司 | Indication computing system with dynamic electricity generation side controlling performance standard |
CN101840215A (en) * | 2009-12-22 | 2010-09-22 | 中国南方电网有限责任公司调峰调频发电公司天生桥水力发电总厂 | Hydropower station machine unit automatic generation control realization method based on PLC (Programmable Logic Controller) device |
CN102593860A (en) * | 2012-01-18 | 2012-07-18 | 北京四方继保自动化股份有限公司 | Automatic generation control and automatic voltage control integrated substation system of power plant |
CN203967766U (en) * | 2014-02-19 | 2014-11-26 | 广东电网公司电力科学研究院 | Cogeneration power plant's level of factory load based on level of factory information monitoring system is optimized distributor |
-
2016
- 2016-05-23 CN CN201610342923.4A patent/CN106026080B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101453188A (en) * | 2008-12-30 | 2009-06-10 | 上海市电力公司 | Indication computing system with dynamic electricity generation side controlling performance standard |
CN101840215A (en) * | 2009-12-22 | 2010-09-22 | 中国南方电网有限责任公司调峰调频发电公司天生桥水力发电总厂 | Hydropower station machine unit automatic generation control realization method based on PLC (Programmable Logic Controller) device |
CN102593860A (en) * | 2012-01-18 | 2012-07-18 | 北京四方继保自动化股份有限公司 | Automatic generation control and automatic voltage control integrated substation system of power plant |
CN203967766U (en) * | 2014-02-19 | 2014-11-26 | 广东电网公司电力科学研究院 | Cogeneration power plant's level of factory load based on level of factory information monitoring system is optimized distributor |
Non-Patent Citations (1)
Title |
---|
基于分层控制的AGC与AVC自动优化协调控制策略;胡伟 等;《电力系统自动化》;20110810;第35卷(第15期);全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN106026080A (en) | 2016-10-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106026080B (en) | A kind of power generating capacity automatic control system and method | |
CN108873842B (en) | One-stop unattended pump station automatic control system | |
CN105529793B (en) | Control method for electromobile group-charging microgrid simultaneously serving as emergency power supply | |
CN103944265B (en) | A kind of interactive intelligent adapted electric energy monitoring device and method | |
CN102957205B (en) | A kind of method and system setting up electricity distribution network model | |
CN106451761B (en) | Large-area power failure automatic monitoring and analyzing system based on dynamic data driving | |
CN108767851A (en) | Intelligent operation command method and system for operation and maintenance of transformer substation | |
CN106786558B (en) | Flexible load regulation and control simulation system and method based on dispatching automation master station system | |
CN111614160A (en) | Low-voltage user load regulation service bearing platform | |
CN107492040A (en) | A kind of multidimensional analysis display systems and method based on power grid regulation operation monitoring | |
CN103440531A (en) | Wind power plant short-term wind power prediction system in view of operating state of wind power plant draught fan | |
CN105573243A (en) | Pump station monitoring system based on PLC | |
CN109613448A (en) | Intelligent power dynamic environment test method and system | |
CN116599160B (en) | Active sensing method and system for new energy station cluster and new energy station | |
Yan et al. | Development of a tool for urban microgrid optimal energy planning and management | |
CN105955116A (en) | Photovoltaic air conditioner frequency converter electric energy controller and control system | |
CN107390624A (en) | A kind of electric real training intelligence system and its management method based on cloud platform | |
CN109017406A (en) | A kind of charging station station control management equipment and charging station | |
CN107086670A (en) | A kind of multiple-energy-source micro-capacitance sensor charging station experiment porch monitoring system and control method | |
CN104504519B (en) | A kind of grid maintenance working strength graphical representation method based on GIS technology | |
CN101976845A (en) | Wind-power reactive power automatic control method for monitor system of wind power station | |
CN106647419B (en) | The matrix form mapping method of protective relaying device hardware corridor | |
CN105421298A (en) | Sluice gate control method based on multiple-screen display | |
DE102020212574A1 (en) | Method and arrangement for optimizing the energy consumption of buildings | |
CN104504199B (en) | Multiple Time Scales active distribution network Interactive Simulation Methods of Scenic based on workflow engine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |