CN105978152A - Automatic closed loop joint debugging method for telecontrol equipment and regulation and control main station of intelligent substation - Google Patents
Automatic closed loop joint debugging method for telecontrol equipment and regulation and control main station of intelligent substation Download PDFInfo
- Publication number
- CN105978152A CN105978152A CN201610448002.6A CN201610448002A CN105978152A CN 105978152 A CN105978152 A CN 105978152A CN 201610448002 A CN201610448002 A CN 201610448002A CN 105978152 A CN105978152 A CN 105978152A
- Authority
- CN
- China
- Prior art keywords
- joint debugging
- regulation
- main website
- control main
- loop joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 39
- 238000004088 simulation Methods 0.000 claims abstract description 19
- 238000012544 monitoring process Methods 0.000 claims abstract description 8
- 230000011664 signaling Effects 0.000 claims description 53
- 238000012795 verification Methods 0.000 claims description 9
- 230000008859 change Effects 0.000 claims description 8
- 230000008569 process Effects 0.000 claims description 8
- 230000001276 controlling effect Effects 0.000 claims description 6
- 238000005259 measurement Methods 0.000 claims description 6
- 230000001105 regulatory effect Effects 0.000 claims description 6
- 230000008676 import Effects 0.000 claims description 5
- 230000001960 triggered effect Effects 0.000 claims description 4
- 230000000007 visual effect Effects 0.000 claims description 4
- 238000012550 audit Methods 0.000 claims description 3
- 238000012360 testing method Methods 0.000 description 8
- 238000004891 communication Methods 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 4
- 238000012216 screening Methods 0.000 description 2
- 238000013479 data entry Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 230000036541 health Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000001131 transforming effect Effects 0.000 description 1
Classifications
-
- H02J13/0013—
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/16—Electric power substations
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610448002.6A CN105978152B (en) | 2016-06-21 | 2016-06-21 | A kind of intelligent substation telemechanical apparatus and the method for regulating and controlling main website automated closed-loop joint debugging |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610448002.6A CN105978152B (en) | 2016-06-21 | 2016-06-21 | A kind of intelligent substation telemechanical apparatus and the method for regulating and controlling main website automated closed-loop joint debugging |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105978152A true CN105978152A (en) | 2016-09-28 |
CN105978152B CN105978152B (en) | 2018-05-04 |
Family
ID=57021474
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610448002.6A Active CN105978152B (en) | 2016-06-21 | 2016-06-21 | A kind of intelligent substation telemechanical apparatus and the method for regulating and controlling main website automated closed-loop joint debugging |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105978152B (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106941281A (en) * | 2017-04-12 | 2017-07-11 | 国网福建省电力有限公司 | A kind of telemechanical apparatus based on supervisory control of substation backstage and the method for regulating and controlling main website remote measurement automated closed-loop joint debugging |
CN106953407A (en) * | 2017-04-11 | 2017-07-14 | 国网福建省电力有限公司 | A kind of telemechanical apparatus based on supervisory control of substation backstage real-time database and the method for regulating and controlling the Remote Control Automatic closed loop joint debugging of main website |
CN107069961A (en) * | 2017-04-12 | 2017-08-18 | 国网福建省电力有限公司 | A kind of transformer station's telemechanical apparatus and the method for regulating and controlling main website remote signalling automated closed-loop joint debugging |
CN107133275A (en) * | 2017-04-11 | 2017-09-05 | 国网福建省电力有限公司 | The method that a kind of regulation and control main website telemechanical point table is audited automatically |
CN109150636A (en) * | 2018-10-31 | 2019-01-04 | 国网四川省电力公司电力科学研究院 | A kind of intelligent substation of full link information stream is assisted to experimental tests method and system |
CN109167432A (en) * | 2018-08-20 | 2019-01-08 | 国网福建省电力有限公司 | A kind of substation's regulation remote control object online recognition method |
CN109361563A (en) * | 2018-10-31 | 2019-02-19 | 广东电网有限责任公司 | A kind of substation DNP specification adjustment method |
CN109508945A (en) * | 2018-06-22 | 2019-03-22 | 广东电网有限责任公司 | A kind of method of dispatching automation information point automatic checking |
CN110021995A (en) * | 2019-01-30 | 2019-07-16 | 国网浙江宁波市鄞州区供电有限公司 | A kind of distribution network automated information joint debugging emulation test system |
CN110445685A (en) * | 2019-08-09 | 2019-11-12 | 云南电网有限责任公司电力科学研究院 | Remote motion signal all-round property testing method and system |
CN111030301A (en) * | 2019-12-18 | 2020-04-17 | 广东电网有限责任公司 | Method for checking correlation of scheduling automation information points |
CN111668938A (en) * | 2020-06-17 | 2020-09-15 | 南京太司德智能电气有限公司 | Method for realizing simulation remote control of electric power measurement and control device |
CN112134351A (en) * | 2020-08-21 | 2020-12-25 | 国网山东省电力公司 | Remote telemetry acceptance system and method based on transformer substation distribution network |
CN112165444A (en) * | 2020-08-10 | 2021-01-01 | 国网安徽省电力有限公司 | Automatic comparison and verification system and method for remote signaling and remote measuring quantity of telecontrol machine of intelligent substation |
CN113131620A (en) * | 2021-05-25 | 2021-07-16 | 国网河南省电力公司平顶山供电公司 | Telecontrol information joint debugging method for transformer substation |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104184215A (en) * | 2014-09-12 | 2014-12-03 | 国网浙江宁波市鄞州区供电公司 | Substation dispatching automation joint debugging method and device and system using same |
CN104578407A (en) * | 2014-12-15 | 2015-04-29 | 国电南瑞科技股份有限公司 | Method for exporting full-substation virtual terminal connection of intelligent substation by devices without repetition |
CN105511294A (en) * | 2015-11-24 | 2016-04-20 | 积成电子股份有限公司 | Simulated-IED-device-based simulated telecontrol virtual debugging method |
CN105549418A (en) * | 2015-12-07 | 2016-05-04 | 国网安徽省电力公司蚌埠供电公司 | SCD communication debugging system for intelligent substation |
-
2016
- 2016-06-21 CN CN201610448002.6A patent/CN105978152B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104184215A (en) * | 2014-09-12 | 2014-12-03 | 国网浙江宁波市鄞州区供电公司 | Substation dispatching automation joint debugging method and device and system using same |
CN104578407A (en) * | 2014-12-15 | 2015-04-29 | 国电南瑞科技股份有限公司 | Method for exporting full-substation virtual terminal connection of intelligent substation by devices without repetition |
CN105511294A (en) * | 2015-11-24 | 2016-04-20 | 积成电子股份有限公司 | Simulated-IED-device-based simulated telecontrol virtual debugging method |
CN105549418A (en) * | 2015-12-07 | 2016-05-04 | 国网安徽省电力公司蚌埠供电公司 | SCD communication debugging system for intelligent substation |
Non-Patent Citations (2)
Title |
---|
宋康等: "数字化智能变电站远动双测控实现方法", 《电力自动化设备》 * |
彭志强等: "电力远动装置闭环测试方法实现及应用", 《电气应用》 * |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106953407A (en) * | 2017-04-11 | 2017-07-14 | 国网福建省电力有限公司 | A kind of telemechanical apparatus based on supervisory control of substation backstage real-time database and the method for regulating and controlling the Remote Control Automatic closed loop joint debugging of main website |
CN107133275A (en) * | 2017-04-11 | 2017-09-05 | 国网福建省电力有限公司 | The method that a kind of regulation and control main website telemechanical point table is audited automatically |
CN107069961A (en) * | 2017-04-12 | 2017-08-18 | 国网福建省电力有限公司 | A kind of transformer station's telemechanical apparatus and the method for regulating and controlling main website remote signalling automated closed-loop joint debugging |
CN107069961B (en) * | 2017-04-12 | 2019-04-26 | 国网福建省电力有限公司 | A kind of method of substation's telemechanical apparatus and regulation main website remote signalling automated closed-loop joint debugging |
CN106941281B (en) * | 2017-04-12 | 2019-04-26 | 国网福建省电力有限公司 | A method of telemechanical apparatus and regulation main website telemetering automated closed-loop joint debugging based on supervisory control of substation backstage |
CN106941281A (en) * | 2017-04-12 | 2017-07-11 | 国网福建省电力有限公司 | A kind of telemechanical apparatus based on supervisory control of substation backstage and the method for regulating and controlling main website remote measurement automated closed-loop joint debugging |
CN109508945A (en) * | 2018-06-22 | 2019-03-22 | 广东电网有限责任公司 | A kind of method of dispatching automation information point automatic checking |
CN109167432B (en) * | 2018-08-20 | 2021-10-29 | 国网福建省电力有限公司 | Online identification method for remote control object regulated and controlled by transformer substation |
CN109167432A (en) * | 2018-08-20 | 2019-01-08 | 国网福建省电力有限公司 | A kind of substation's regulation remote control object online recognition method |
CN109150636A (en) * | 2018-10-31 | 2019-01-04 | 国网四川省电力公司电力科学研究院 | A kind of intelligent substation of full link information stream is assisted to experimental tests method and system |
CN109361563A (en) * | 2018-10-31 | 2019-02-19 | 广东电网有限责任公司 | A kind of substation DNP specification adjustment method |
CN109150636B (en) * | 2018-10-31 | 2023-08-22 | 国网四川省电力公司电力科学研究院 | Intelligent substation auxiliary point-to-point test method and system for full-link information flow |
CN110021995A (en) * | 2019-01-30 | 2019-07-16 | 国网浙江宁波市鄞州区供电有限公司 | A kind of distribution network automated information joint debugging emulation test system |
CN110445685A (en) * | 2019-08-09 | 2019-11-12 | 云南电网有限责任公司电力科学研究院 | Remote motion signal all-round property testing method and system |
CN111030301B (en) * | 2019-12-18 | 2020-09-25 | 广东电网有限责任公司 | Method for checking correlation of scheduling automation information points |
CN111030301A (en) * | 2019-12-18 | 2020-04-17 | 广东电网有限责任公司 | Method for checking correlation of scheduling automation information points |
CN111668938A (en) * | 2020-06-17 | 2020-09-15 | 南京太司德智能电气有限公司 | Method for realizing simulation remote control of electric power measurement and control device |
CN111668938B (en) * | 2020-06-17 | 2023-08-04 | 南京太司德智能电气有限公司 | Method for realizing analog remote control of electric power measurement and control device |
CN112165444A (en) * | 2020-08-10 | 2021-01-01 | 国网安徽省电力有限公司 | Automatic comparison and verification system and method for remote signaling and remote measuring quantity of telecontrol machine of intelligent substation |
CN112134351A (en) * | 2020-08-21 | 2020-12-25 | 国网山东省电力公司 | Remote telemetry acceptance system and method based on transformer substation distribution network |
CN113131620A (en) * | 2021-05-25 | 2021-07-16 | 国网河南省电力公司平顶山供电公司 | Telecontrol information joint debugging method for transformer substation |
Also Published As
Publication number | Publication date |
---|---|
CN105978152B (en) | 2018-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105978152A (en) | Automatic closed loop joint debugging method for telecontrol equipment and regulation and control main station of intelligent substation | |
CN107069961B (en) | A kind of method of substation's telemechanical apparatus and regulation main website remote signalling automated closed-loop joint debugging | |
CN105302121A (en) | Sequential control operation order automatic anti-error check method based on simulation IED device | |
CN103051065B (en) | The distributed FA interlock method of testing of a kind of power distribution automation and system | |
CN104460346B (en) | Feeder automation action logic test method based on power distribution terminal service verification | |
CN104090194B (en) | Intelligent substation relay protection non-intrusion type test system and method | |
CN105511294B (en) | Simulation telemechanical Virtual Debugging method based on emulation IED devices | |
CN106329730A (en) | Substation monitoring information automatic acceptance system based on intelligent power grid scheduling system | |
CN106941281B (en) | A method of telemechanical apparatus and regulation main website telemetering automated closed-loop joint debugging based on supervisory control of substation backstage | |
CN105978159B (en) | A kind of substation's remote control test is online to exempt to execute checking method | |
CN105262220B (en) | Substation's intelligence shutdown telecontrol information check method and system | |
CN104820635A (en) | Method of testing robustness of closed loop protocol based on semantic analysis of dynamic script | |
CN108983006A (en) | Type feeder automation switch terminal scene does not have a power failure full-automatic testing method on the spot | |
CN105548742B (en) | System is tested in a distant place for relay protection | |
CN204291050U (en) | A kind of dispatching and monitoring information check system | |
CN106329720A (en) | Detecting and debugging method for reconstruction and extension project secondary system for intelligent substation | |
CN109217472B (en) | Automatic closed-loop joint debugging method for monitoring information checking | |
CN102788915A (en) | Feeder automation online simulation method based on maintenance workstation | |
CN104076807B (en) | The adjustment method of the automated system of intelligent substation | |
CN104269090B (en) | The analogue system of a kind of power information acquisition terminal wheel secondary control switch and method thereof | |
CN105680441B (en) | Simulation based on stimulated replacement technology is to a device | |
CN104184215B (en) | Transformer station's dispatching automation joint debugging method and the Apparatus and system of application the method | |
CN205389138U (en) | Intelligent substation simulation main website integrated test system | |
CN103544104B (en) | Testing method for power distribution terminal remote control functional software module | |
CN102508052B (en) | Test method for field band channel operation of automatic bus transfer system of area network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 350003 No. 54 road 54 Fuzhou, Fujian Co-patentee after: STATE GRID CORPORATION OF CHINA Patentee after: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd. Co-patentee after: STATE GRID FUJIAN MAINTENANCE Co. Address before: 350003 No. 54 road 54 Fuzhou, Fujian Co-patentee before: State Grid Corporation of China Patentee before: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd. Co-patentee before: STATE GRID FUJIAN MAINTENANCE Co. |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20181206 Address after: 350003 No. 54 road 54 Fuzhou, Fujian Co-patentee after: STATE GRID CORPORATION OF CHINA Patentee after: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd. Co-patentee after: STATE GRID FUJIAN MAINTENANCE Co. Co-patentee after: STATE GRID FUJIAN ECONOMIC Research Institute Address before: 350003 No. 54 road 54 Fuzhou, Fujian Co-patentee before: STATE GRID CORPORATION OF CHINA Patentee before: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd. Co-patentee before: STATE GRID FUJIAN MAINTENANCE Co. |