CN105913341A - Construction project supervision information management method and system - Google Patents

Construction project supervision information management method and system Download PDF

Info

Publication number
CN105913341A
CN105913341A CN201610222154.4A CN201610222154A CN105913341A CN 105913341 A CN105913341 A CN 105913341A CN 201610222154 A CN201610222154 A CN 201610222154A CN 105913341 A CN105913341 A CN 105913341A
Authority
CN
China
Prior art keywords
critical process
project
work
management
file
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610222154.4A
Other languages
Chinese (zh)
Inventor
余璇
黄家星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Construction Project Supervision Co Ltd
Original Assignee
Guangzhou Municipal Construction Project Supervision Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Construction Project Supervision Co Ltd filed Critical Guangzhou Municipal Construction Project Supervision Co Ltd
Priority to CN201610222154.4A priority Critical patent/CN105913341A/en
Publication of CN105913341A publication Critical patent/CN105913341A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a construction project supervision information management method which comprises the following steps: a construction project program is decomposed into different key procedures; when project commencing requirements for each key procedure are met, supervision work is done according to supervision work flows, acceptance specifications, and supervision work methods and measures that are preset in the key procedure, and documents that are needed in work of the key procedures are obtained and filed; when that work of all key procedures is completed is detected, supervision information management work of the construction project program is finished. Correspondingly, the invention also discloses a construction project supervision information management system. Via use of the construction project supervision information management method and system, management efficiency can be improved while management cost can be lowered.

Description

A kind of Project Supervision approaches to IM and system
Technical field
The present invention relates to engineering construction field, particularly relate to a kind of Project Supervision approaches to IM and be System.
Background technology
At present, the management of Project Supervision information, great majority are all manually to fill in various form, manually enter The transmission of row information and management.Use this way to manage, it is impossible to accomplish standardized management, it is impossible to accomplish The integration of information is shared with complete, and the inefficiency of management, and cost is high.
Summary of the invention
The embodiment of the present invention proposes a kind of Project Supervision approaches to IM and system, it is possible to increase management Efficiency, reduces management cost.
The embodiment of the present invention provides a kind of Project Supervision approaches to IM, including:
Construction project is decomposed into different critical processes;
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process Management is carried out in journey, acceptance specification, working approaches of surveillance and measure, and obtains the work of described critical process File needed in is filed;
At the end of the work all critical processes being detected, complete the management letter of described construction project Breath management work.
Further, described is different crucial works by the supervisory information management work breakdown of construction project Sequence, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
Further, described after the requirements for starting construction reaching each critical process, pre-according to described critical process If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and obtain institute State required file in critical process work to file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion Check and accept in information bank.
Further, the file corresponding to lists of documents that the described critical process of described acquisition is preset, specifically wraps Include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described at the end of the work all critical processes being detected, complete described construction work Journey item purpose supervisory information management works, and specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre- If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction The supervisory information management work of engineering project.
Further, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect Deposit the progress performance of described critical process.
Correspondingly, the embodiment of the present invention also provides for a kind of Project Supervision information management system, including:
Decomposing module, for being decomposed into different critical processes by construction project;
File acquisition module, for after the requirements for starting construction reaching each critical process, according to described crucial work Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains Take required file in the work of described critical process to file;And,
Worked module, at the end of the work all critical processes being detected, complete described in build If the supervisory information management work of engineering project.
Further, described decomposing module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication Operation.
Further, described file acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected During color, complete the supervisory information management work of described construction project.
Implement the embodiment of the present invention, have the advantages that
The Project Supervision approaches to IM of embodiment of the present invention offer and system, it is possible to by construction project Project is standardized decomposing, and refine to the work of each critical process, and each critical process is formed Documentation is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management, And reduce management cost;The time service time of each critical process is contrasted with projected operating times, Obtain the ratio that this critical process completes, thus entirety grasps the progress situation of whole project;Each crucial work Sequence arranges the director of correspondence, after each critical process is started working, is sent to by corresponding job task Director, in order to remind director in time.
Accompanying drawing explanation
Fig. 1 is the flow process signal of an embodiment of the Project Supervision approaches to IM that the present invention provides Figure;
Fig. 2 is the structural representation of an embodiment of the Project Supervision information management system that the present invention provides Figure.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clearly Chu, be fully described by, it is clear that described embodiment be only a part of embodiment of the present invention rather than Whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not making creation The every other embodiment obtained under property work premise, broadly falls into the scope of protection of the invention.
Seeing Fig. 1, the flow process of an embodiment of the Project Supervision approaches to IM that the present invention provides is shown It is intended to, including:
S1, construction project is decomposed into different critical processes;
S2, after the requirements for starting construction reaching each critical process, according to described critical process preset management work Make flow process, acceptance specification, working approaches of surveillance and measure and carry out management, and obtain described critical process File required in work is filed;
S3, at the end of the work all critical processes being detected, complete the prison of described construction project Reason information management work.
It should be noted that set out with the feature of supervising business, by the overall process of supervising business according to project pipe Reason target is decomposed, and the various data needed for supervision process are carried out in a organized way, orderlyly conclude, united Meter, classification, and realize the data base that can inquire about, download, print, share.In conjunction with science, the item of specialty Mesh management system, combing also realizes the standardization of business administration, standardization, sequencing and supervising business management Specialization.
During management, first construction project being carried out WBS and decompose step by step, formation with critical process is The task bag of minimum unit.Each task bag design " loose-leaf ", after each project generates, can call in advance The template of corresponding this project specialty in the WBS template base designed, further according to practical situation, the skill of this project Art feature, owner's requirement etc. carry out " personalized " transformation, template can be optimized, update, delete, The operations such as increase, thus form " loose-leaf " of each key procedure.Improved template is run up to template base, It is easy to calling of same type project in the future.
In " loose-leaf " of each critical process, the condition of having gone into operation can be set, and the condition that gone into operation is fixed Justice logical relation between operation and operation, only completes the condition of having gone into operation and just can carry out the construction of operation, Thus ensure that the task of each critical process is monitored, it is to avoid artificial " skipping " occurs or loses Leakage.It addition, in each critical process, corresponding key control point, management flow process, management can be arranged Job content, working approaches of surveillance and measure etc. illustrate, thus form complete Project Surveillance overall process " intelligence Can job instruction ", with to field personnel to instruct.For needing the corresponding crucial work guiding file Sequence, can add corresponding guide file in " loose-leaf ", with to field personnel to instruct, wherein, The operation of job specfication this operation corresponding guiding file association construction industry of operation or acceptance requirement, can To monitor, the supervision process of whole operation is legal, reasonable, close rule.
After the requirements for starting construction reaching each critical process, according to the management flow process arranged in " loose-leaf ", Management is carried out in acceptance specification, working approaches of surveillance and measure, collects the documentation that this operation is checked and accepted, And complete signature, formality of affixing one's seal carry out preserve filing.After the work of all critical processes all terminates, explanation The management management work of construction project is fully completed, it is achieved the real-time monitoring to project, improves management effect Rate, and reduce management cost.
Further, described is different crucial works by the supervisory information management work breakdown of construction project Sequence, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
It should be noted that by engineering project according to unit individual works, part-to-item project, working procedure Decompose layer by layer, form multiple task bag with critical process as minimum unit, each task bag can completely, Describe operation to start to the overall process checked and accepted comprehensively.
Further, described after the requirements for starting construction reaching each critical process, pre-according to described critical process If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and obtain institute State required file in critical process work to file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion Check and accept in information bank.
Further, the file corresponding to lists of documents that the described critical process of described acquisition is preset, specifically wraps Include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
It should be noted that after the requirements for starting construction reaching each critical process, this critical process is started working, At work, and document control directory associates, to obtain the procedure file corresponding to lists of documents and achievement literary composition Part.Wherein, can call the province's system table needed for this critical process, standardizing to fill in online for user obtains literary composition Part, it is possible to use family is directly obtained by transmitting file on adnexa.Procedure file and Outcome Document can be shared, Outcome Document can associate with final acceptance of construction document data base again and share, can be to the literary composition obtained in work progress Part detects, it is judged that whether it belongs to handing over document, and handing over document is summed up in the point that completion automatically In examination data, and the catalogue requirement in corresponding governmental archives shop.In the course of the work, every executing can also be called Work acceptance specification, supports, assists whether the inspect for acceptance work of unit in charge of construction of management closes rule.It addition, it is each Critical process is previously provided with corresponding person liable, when having arrived the timing node of each critical process, automatically pushes away Send the corresponding job task person liable to presetting, play prompting and directive function.
Further, described at the end of the work all critical processes being detected, complete described construction work Journey item purpose supervisory information management works, and specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre- If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction The supervisory information management work of engineering project.
It should be noted that the supervision process of whole project organically combines with project process gunter drawing, Mei Geguan The color filling degree of key operation represents the progress of this operation.The operation completed is shown as in progress gunter drawing The color preset, such as green, and be not fully complete shown in red, shown by automatically indicating of color The overall progress situation of whole project, it is simple to management level are from more macroscopic aspect management and control project.
Further, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect Deposit the progress performance of described critical process.
It should be noted that the projected operating times of pre-set each critical process, by each crucial work Running time and the projected operating times of sequence contrast, it is achieved progress " in advance " or " delayed " Differentiate, provide foundation for progress claim in the future.When each critical process soon reaches projected operating times, It is automatically reminded to the person liable corresponding to this operation.
The Project Supervision approaches to IM that the embodiment of the present invention provides, it is possible to construction project is entered Column criterionization is decomposed, and refine to the work of each critical process, and the file money forming each critical process Material is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management, and reduces Management cost;Being contrasted with projected operating times the time service time of each critical process, obtaining should The ratio that critical process completes, thus the overall progress situation grasping whole project;Each critical process is arranged Corresponding director, after each critical process is started working, is sent to director by corresponding job task, To remind director in time.
Accordingly, the present invention also provides for a kind of Project Supervision information management system, it is possible to realize above-mentioned reality Execute all flow processs of Project Supervision approaches to IM in example.
See Fig. 2, be the structure of an embodiment of the Project Supervision information management system that the present invention provides Schematic diagram, including:
Decomposing module 1, for being decomposed into different critical processes by construction project;
File acquisition module 2, for after the requirements for starting construction reaching each critical process, according to described crucial work Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains Take required file in the work of described critical process to file;And,
Worked module 3, at the end of the work all critical processes being detected, complete described in build If the supervisory information management work of engineering project.
Further, described decomposing module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication Operation.
Further, described file acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected During color, complete the supervisory information management work of described construction project.
The Project Supervision information management system that the embodiment of the present invention provides, it is possible to construction project is entered Column criterionization is decomposed, and refine to the work of each critical process, and the file money forming each critical process Material is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management, and reduces Management cost;Being contrasted with projected operating times the time service time of each critical process, obtaining should The ratio that critical process completes, thus the overall progress situation grasping whole project;Each critical process is arranged Corresponding director, after each critical process is started working, is sent to director by corresponding job task, To remind director in time.
The above is the preferred embodiment of the present invention, it is noted that for the common skill of the art For art personnel, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, this A little improvements and modifications are also considered as protection scope of the present invention.

Claims (10)

1. a Project Supervision approaches to IM, it is characterised in that including:
Construction project is decomposed into different critical processes;
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process Management is carried out in journey, acceptance specification, working approaches of surveillance and measure, and obtains the work of described critical process File needed in is filed;
At the end of the work all critical processes being detected, complete the management letter of described construction project Breath management work.
2. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described general The supervisory information management work breakdown of construction project is different critical process, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
3. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described After reaching the requirements for starting construction of each critical process, according to described critical process preset management flow process, test Receive specification, working approaches of surveillance and measure and carry out management, and obtain in the work of described critical process required File file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion Check and accept in information bank.
4. Project Supervision approaches to IM as claimed in claim 3, it is characterised in that described in obtain Take the file corresponding to lists of documents that described critical process is preset, specifically include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
5. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described At the end of the work all of all critical processes being detected, complete the supervisory information management of described construction project Work, specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre- If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction The supervisory information management work of engineering project.
6. the Project Supervision approaches to IM as described in any one of claim 1 to 5, its feature exists In, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect Deposit the progress performance of described critical process.
7. a Project Supervision information management system, it is characterised in that including:
Decomposing module, for being decomposed into different critical processes by construction project;
File acquisition module, for after the requirements for starting construction reaching each critical process, according to described crucial work Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains Take required file in the work of described critical process to file;And,
Worked module, at the end of the work all critical processes being detected, complete described in build If the supervisory information management work of engineering project.
8. Project Supervision information management system as claimed in claim 7, it is characterised in that described point Solution module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication Operation.
9. Project Supervision information management system as claimed in claim 7, it is characterised in that described literary composition Part acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
10. the Project Supervision information management system as described in any one of claim 7 to 9, its feature Being, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected During color, complete the supervisory information management work of described construction project.
CN201610222154.4A 2016-04-11 2016-04-11 Construction project supervision information management method and system Pending CN105913341A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610222154.4A CN105913341A (en) 2016-04-11 2016-04-11 Construction project supervision information management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610222154.4A CN105913341A (en) 2016-04-11 2016-04-11 Construction project supervision information management method and system

Publications (1)

Publication Number Publication Date
CN105913341A true CN105913341A (en) 2016-08-31

Family

ID=56745805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610222154.4A Pending CN105913341A (en) 2016-04-11 2016-04-11 Construction project supervision information management method and system

Country Status (1)

Country Link
CN (1) CN105913341A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107067225A (en) * 2017-03-16 2017-08-18 苏州天狮建设监理有限公司 A kind of approaches to IM and system
CN107480171A (en) * 2017-06-29 2017-12-15 中国建筑局(集团)有限公司 The database and preparation method that working procedure is combined with engineering data
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN107908810A (en) * 2017-09-28 2018-04-13 中建局集团第二建筑有限公司 Execution management method therefor based on BIM models and mobile positioning technique
CN108122089A (en) * 2016-11-30 2018-06-05 中国航空工业集团公司成都飞机设计研究所 A kind of task feedback based on delivery object
CN108319431A (en) * 2018-01-17 2018-07-24 四川同兴达建设咨询有限公司 A kind of Construction Cost Data management system
CN108376311A (en) * 2018-02-06 2018-08-07 江苏普信工程项目管理有限公司 The step that leaves a question open in project supervision checks amending method and system
CN108460526A (en) * 2018-02-24 2018-08-28 浙江华诚工程管理有限公司 A kind of construction quality supervision method and system in project supervision
CN109299851A (en) * 2018-08-21 2019-02-01 内蒙古康远工程建设监理有限责任公司 A kind of intelligence progress kinetic-control system
CN109583842A (en) * 2018-12-04 2019-04-05 北京诺士诚国际工程项目管理有限公司 A kind of management monthly magazine generation method, device, electronic equipment and computer storage medium
CN109767103A (en) * 2018-12-29 2019-05-17 福建华闽通达信息技术有限公司 A kind of method and system carrying out highway engineering task management based on WBS
CN109872034A (en) * 2018-12-30 2019-06-11 广州骏升建设管理有限公司 The project process method and system of project supervision
CN109872030A (en) * 2018-12-28 2019-06-11 徐州中国矿业大学建筑设计咨询研究院有限公司 A kind of management management method suitable for construction project
CN110648116A (en) * 2019-09-23 2020-01-03 北京地厚云图科技有限公司 Management method for digital paperless real-time dynamic filing of whole process of building engineering
CN110928838A (en) * 2019-12-16 2020-03-27 郑卫华 Engineering file management system architecture method and device
CN111210196A (en) * 2019-12-27 2020-05-29 宁波国际投资咨询有限公司 Intelligent engineering supervision information supervision method

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108122089A (en) * 2016-11-30 2018-06-05 中国航空工业集团公司成都飞机设计研究所 A kind of task feedback based on delivery object
CN107067225A (en) * 2017-03-16 2017-08-18 苏州天狮建设监理有限公司 A kind of approaches to IM and system
CN107480171A (en) * 2017-06-29 2017-12-15 中国建筑局(集团)有限公司 The database and preparation method that working procedure is combined with engineering data
CN107908810A (en) * 2017-09-28 2018-04-13 中建局集团第二建筑有限公司 Execution management method therefor based on BIM models and mobile positioning technique
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN108319431A (en) * 2018-01-17 2018-07-24 四川同兴达建设咨询有限公司 A kind of Construction Cost Data management system
CN108376311A (en) * 2018-02-06 2018-08-07 江苏普信工程项目管理有限公司 The step that leaves a question open in project supervision checks amending method and system
CN108460526A (en) * 2018-02-24 2018-08-28 浙江华诚工程管理有限公司 A kind of construction quality supervision method and system in project supervision
CN109299851A (en) * 2018-08-21 2019-02-01 内蒙古康远工程建设监理有限责任公司 A kind of intelligence progress kinetic-control system
CN109583842A (en) * 2018-12-04 2019-04-05 北京诺士诚国际工程项目管理有限公司 A kind of management monthly magazine generation method, device, electronic equipment and computer storage medium
CN109872030A (en) * 2018-12-28 2019-06-11 徐州中国矿业大学建筑设计咨询研究院有限公司 A kind of management management method suitable for construction project
CN109767103A (en) * 2018-12-29 2019-05-17 福建华闽通达信息技术有限公司 A kind of method and system carrying out highway engineering task management based on WBS
CN109872034A (en) * 2018-12-30 2019-06-11 广州骏升建设管理有限公司 The project process method and system of project supervision
CN110648116A (en) * 2019-09-23 2020-01-03 北京地厚云图科技有限公司 Management method for digital paperless real-time dynamic filing of whole process of building engineering
CN110648116B (en) * 2019-09-23 2022-09-16 北京地厚云图科技有限公司 Management method for digital paperless real-time dynamic filing of whole process of building engineering
CN110928838A (en) * 2019-12-16 2020-03-27 郑卫华 Engineering file management system architecture method and device
CN111210196A (en) * 2019-12-27 2020-05-29 宁波国际投资咨询有限公司 Intelligent engineering supervision information supervision method

Similar Documents

Publication Publication Date Title
CN105913341A (en) Construction project supervision information management method and system
CN107730077A (en) Node tasks data display method, device, storage medium and computer equipment
CN103605459A (en) Fast application launching method and fast application launching terminal
CN104917551B (en) Method and equipment for pairing blue-tooth devices
CN105913225A (en) Construction project agent-construction information management method and system
CN105426307B (en) A kind of Local Area Network products' test resource sharing method and system
CN103886255B (en) The privacy authority management method and device of application program
CN103093517A (en) Human face recognition visitor management method
CN105041025A (en) System and method for unlocking carport ground lock
Hoła Methodology of hazards identification in construction work course
CN103761598A (en) Enterprise information centralized collection processing method and system
CN106095561A (en) Freeze the management method of application, the managing device freezing application and terminal
CN107464055A (en) Schedule estimation method and device
CN106372189A (en) Realization method of cloud diagnosis of transportation means and related device
CN104925595B (en) The method of controlling operation thereof of elevator and device
CN105743850B (en) Method and device for obtaining user authentication information when delivering articles by using express box
CN107067225A (en) A kind of approaches to IM and system
US20060195350A1 (en) Design review, progress check information transmission method and apparatus
KR101482380B1 (en) System for construction information creation and method for construction information creation using the same
CN110019947A (en) A kind of data extraction method and device
CN105141946B (en) The test system and method for a kind of monitoring camera
CN108696718B (en) Monitoring system and information terminal device in monitoring system
CN107230163B (en) System for on-site quality supervision and inspection of power engineering
CN109993421A (en) Apply the site safety risk recognition system and operating method in electricity power enterprise
CN109377183A (en) Coalmine Safety Supervision intelligence enforcement system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160831