CN105913341A - Construction project supervision information management method and system - Google Patents
Construction project supervision information management method and system Download PDFInfo
- Publication number
- CN105913341A CN105913341A CN201610222154.4A CN201610222154A CN105913341A CN 105913341 A CN105913341 A CN 105913341A CN 201610222154 A CN201610222154 A CN 201610222154A CN 105913341 A CN105913341 A CN 105913341A
- Authority
- CN
- China
- Prior art keywords
- critical process
- project
- work
- management
- file
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Abstract
The invention discloses a construction project supervision information management method which comprises the following steps: a construction project program is decomposed into different key procedures; when project commencing requirements for each key procedure are met, supervision work is done according to supervision work flows, acceptance specifications, and supervision work methods and measures that are preset in the key procedure, and documents that are needed in work of the key procedures are obtained and filed; when that work of all key procedures is completed is detected, supervision information management work of the construction project program is finished. Correspondingly, the invention also discloses a construction project supervision information management system. Via use of the construction project supervision information management method and system, management efficiency can be improved while management cost can be lowered.
Description
Technical field
The present invention relates to engineering construction field, particularly relate to a kind of Project Supervision approaches to IM and be
System.
Background technology
At present, the management of Project Supervision information, great majority are all manually to fill in various form, manually enter
The transmission of row information and management.Use this way to manage, it is impossible to accomplish standardized management, it is impossible to accomplish
The integration of information is shared with complete, and the inefficiency of management, and cost is high.
Summary of the invention
The embodiment of the present invention proposes a kind of Project Supervision approaches to IM and system, it is possible to increase management
Efficiency, reduces management cost.
The embodiment of the present invention provides a kind of Project Supervision approaches to IM, including:
Construction project is decomposed into different critical processes;
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process
Management is carried out in journey, acceptance specification, working approaches of surveillance and measure, and obtains the work of described critical process
File needed in is filed;
At the end of the work all critical processes being detected, complete the management letter of described construction project
Breath management work.
Further, described is different crucial works by the supervisory information management work breakdown of construction project
Sequence, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
Further, described after the requirements for starting construction reaching each critical process, pre-according to described critical process
If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and obtain institute
State required file in critical process work to file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process
Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure
Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion
Check and accept in information bank.
Further, the file corresponding to lists of documents that the described critical process of described acquisition is preset, specifically wraps
Include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province
The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described at the end of the work all critical processes being detected, complete described construction work
Journey item purpose supervisory information management works, and specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre-
If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction
The supervisory information management work of engineering project.
Further, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect
Deposit the progress performance of described critical process.
Correspondingly, the embodiment of the present invention also provides for a kind of Project Supervision information management system, including:
Decomposing module, for being decomposed into different critical processes by construction project;
File acquisition module, for after the requirements for starting construction reaching each critical process, according to described crucial work
Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains
Take required file in the work of described critical process to file;And,
Worked module, at the end of the work all critical processes being detected, complete described in build
If the supervisory information management work of engineering project.
Further, described decomposing module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event
Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication
Operation.
Further, described file acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process
If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described
The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With
And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction
Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset
Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents
File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process
Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected
During color, complete the supervisory information management work of described construction project.
Implement the embodiment of the present invention, have the advantages that
The Project Supervision approaches to IM of embodiment of the present invention offer and system, it is possible to by construction project
Project is standardized decomposing, and refine to the work of each critical process, and each critical process is formed
Documentation is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management,
And reduce management cost;The time service time of each critical process is contrasted with projected operating times,
Obtain the ratio that this critical process completes, thus entirety grasps the progress situation of whole project;Each crucial work
Sequence arranges the director of correspondence, after each critical process is started working, is sent to by corresponding job task
Director, in order to remind director in time.
Accompanying drawing explanation
Fig. 1 is the flow process signal of an embodiment of the Project Supervision approaches to IM that the present invention provides
Figure;
Fig. 2 is the structural representation of an embodiment of the Project Supervision information management system that the present invention provides
Figure.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clearly
Chu, be fully described by, it is clear that described embodiment be only a part of embodiment of the present invention rather than
Whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not making creation
The every other embodiment obtained under property work premise, broadly falls into the scope of protection of the invention.
Seeing Fig. 1, the flow process of an embodiment of the Project Supervision approaches to IM that the present invention provides is shown
It is intended to, including:
S1, construction project is decomposed into different critical processes;
S2, after the requirements for starting construction reaching each critical process, according to described critical process preset management work
Make flow process, acceptance specification, working approaches of surveillance and measure and carry out management, and obtain described critical process
File required in work is filed;
S3, at the end of the work all critical processes being detected, complete the prison of described construction project
Reason information management work.
It should be noted that set out with the feature of supervising business, by the overall process of supervising business according to project pipe
Reason target is decomposed, and the various data needed for supervision process are carried out in a organized way, orderlyly conclude, united
Meter, classification, and realize the data base that can inquire about, download, print, share.In conjunction with science, the item of specialty
Mesh management system, combing also realizes the standardization of business administration, standardization, sequencing and supervising business management
Specialization.
During management, first construction project being carried out WBS and decompose step by step, formation with critical process is
The task bag of minimum unit.Each task bag design " loose-leaf ", after each project generates, can call in advance
The template of corresponding this project specialty in the WBS template base designed, further according to practical situation, the skill of this project
Art feature, owner's requirement etc. carry out " personalized " transformation, template can be optimized, update, delete,
The operations such as increase, thus form " loose-leaf " of each key procedure.Improved template is run up to template base,
It is easy to calling of same type project in the future.
In " loose-leaf " of each critical process, the condition of having gone into operation can be set, and the condition that gone into operation is fixed
Justice logical relation between operation and operation, only completes the condition of having gone into operation and just can carry out the construction of operation,
Thus ensure that the task of each critical process is monitored, it is to avoid artificial " skipping " occurs or loses
Leakage.It addition, in each critical process, corresponding key control point, management flow process, management can be arranged
Job content, working approaches of surveillance and measure etc. illustrate, thus form complete Project Surveillance overall process " intelligence
Can job instruction ", with to field personnel to instruct.For needing the corresponding crucial work guiding file
Sequence, can add corresponding guide file in " loose-leaf ", with to field personnel to instruct, wherein,
The operation of job specfication this operation corresponding guiding file association construction industry of operation or acceptance requirement, can
To monitor, the supervision process of whole operation is legal, reasonable, close rule.
After the requirements for starting construction reaching each critical process, according to the management flow process arranged in " loose-leaf ",
Management is carried out in acceptance specification, working approaches of surveillance and measure, collects the documentation that this operation is checked and accepted,
And complete signature, formality of affixing one's seal carry out preserve filing.After the work of all critical processes all terminates, explanation
The management management work of construction project is fully completed, it is achieved the real-time monitoring to project, improves management effect
Rate, and reduce management cost.
Further, described is different crucial works by the supervisory information management work breakdown of construction project
Sequence, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
It should be noted that by engineering project according to unit individual works, part-to-item project, working procedure
Decompose layer by layer, form multiple task bag with critical process as minimum unit, each task bag can completely,
Describe operation to start to the overall process checked and accepted comprehensively.
Further, described after the requirements for starting construction reaching each critical process, pre-according to described critical process
If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and obtain institute
State required file in critical process work to file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process
Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure
Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion
Check and accept in information bank.
Further, the file corresponding to lists of documents that the described critical process of described acquisition is preset, specifically wraps
Include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province
The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
It should be noted that after the requirements for starting construction reaching each critical process, this critical process is started working,
At work, and document control directory associates, to obtain the procedure file corresponding to lists of documents and achievement literary composition
Part.Wherein, can call the province's system table needed for this critical process, standardizing to fill in online for user obtains literary composition
Part, it is possible to use family is directly obtained by transmitting file on adnexa.Procedure file and Outcome Document can be shared,
Outcome Document can associate with final acceptance of construction document data base again and share, can be to the literary composition obtained in work progress
Part detects, it is judged that whether it belongs to handing over document, and handing over document is summed up in the point that completion automatically
In examination data, and the catalogue requirement in corresponding governmental archives shop.In the course of the work, every executing can also be called
Work acceptance specification, supports, assists whether the inspect for acceptance work of unit in charge of construction of management closes rule.It addition, it is each
Critical process is previously provided with corresponding person liable, when having arrived the timing node of each critical process, automatically pushes away
Send the corresponding job task person liable to presetting, play prompting and directive function.
Further, described at the end of the work all critical processes being detected, complete described construction work
Journey item purpose supervisory information management works, and specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre-
If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction
The supervisory information management work of engineering project.
It should be noted that the supervision process of whole project organically combines with project process gunter drawing, Mei Geguan
The color filling degree of key operation represents the progress of this operation.The operation completed is shown as in progress gunter drawing
The color preset, such as green, and be not fully complete shown in red, shown by automatically indicating of color
The overall progress situation of whole project, it is simple to management level are from more macroscopic aspect management and control project.
Further, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect
Deposit the progress performance of described critical process.
It should be noted that the projected operating times of pre-set each critical process, by each crucial work
Running time and the projected operating times of sequence contrast, it is achieved progress " in advance " or " delayed "
Differentiate, provide foundation for progress claim in the future.When each critical process soon reaches projected operating times,
It is automatically reminded to the person liable corresponding to this operation.
The Project Supervision approaches to IM that the embodiment of the present invention provides, it is possible to construction project is entered
Column criterionization is decomposed, and refine to the work of each critical process, and the file money forming each critical process
Material is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management, and reduces
Management cost;Being contrasted with projected operating times the time service time of each critical process, obtaining should
The ratio that critical process completes, thus the overall progress situation grasping whole project;Each critical process is arranged
Corresponding director, after each critical process is started working, is sent to director by corresponding job task,
To remind director in time.
Accordingly, the present invention also provides for a kind of Project Supervision information management system, it is possible to realize above-mentioned reality
Execute all flow processs of Project Supervision approaches to IM in example.
See Fig. 2, be the structure of an embodiment of the Project Supervision information management system that the present invention provides
Schematic diagram, including:
Decomposing module 1, for being decomposed into different critical processes by construction project;
File acquisition module 2, for after the requirements for starting construction reaching each critical process, according to described crucial work
Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains
Take required file in the work of described critical process to file;And,
Worked module 3, at the end of the work all critical processes being detected, complete described in build
If the supervisory information management work of engineering project.
Further, described decomposing module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event
Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication
Operation.
Further, described file acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process
If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described
The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With
And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction
Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset
Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents
File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
Further, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process
Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected
During color, complete the supervisory information management work of described construction project.
The Project Supervision information management system that the embodiment of the present invention provides, it is possible to construction project is entered
Column criterionization is decomposed, and refine to the work of each critical process, and the file money forming each critical process
Material is filed and orderly management in time, it is achieved the real-time monitoring to project, improves the efficiency of management, and reduces
Management cost;Being contrasted with projected operating times the time service time of each critical process, obtaining should
The ratio that critical process completes, thus the overall progress situation grasping whole project;Each critical process is arranged
Corresponding director, after each critical process is started working, is sent to director by corresponding job task,
To remind director in time.
The above is the preferred embodiment of the present invention, it is noted that for the common skill of the art
For art personnel, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, this
A little improvements and modifications are also considered as protection scope of the present invention.
Claims (10)
1. a Project Supervision approaches to IM, it is characterised in that including:
Construction project is decomposed into different critical processes;
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process
Management is carried out in journey, acceptance specification, working approaches of surveillance and measure, and obtains the work of described critical process
File needed in is filed;
At the end of the work all critical processes being detected, complete the management letter of described construction project
Breath management work.
2. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described general
The supervisory information management work breakdown of construction project is different critical process, specifically includes:
Build according to room, construction project is decomposed into unit individual works by municipal administration specialty;
Described unit individual works are decomposed into part-to-item project;
Described part-to-item project is decomposed into working procedure;
From described working procedure, all of critical process is chosen according to job specfication.
3. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described
After reaching the requirements for starting construction of each critical process, according to described critical process preset management flow process, test
Receive specification, working approaches of surveillance and measure and carry out management, and obtain in the work of described critical process required
File file, specifically include:
After the requirements for starting construction reaching each critical process, the management stream preset according to described critical process
Management, and being correlated with described critical process are carried out in journey, acceptance specification, working approaches of surveillance and measure
Information is sent to corresponding person liable;
Obtain the file corresponding to lists of documents that described critical process is preset;
When detecting that the file of acquisition is handing over document, described handing over document is filed completion
Check and accept in information bank.
4. Project Supervision approaches to IM as claimed in claim 3, it is characterised in that described in obtain
Take the file corresponding to lists of documents that described critical process is preset, specifically include:
Call the province's system table corresponding to lists of documents that described critical process is preset, and obtain user in described province
The information filled on system table, it is thus achieved that the file corresponding to described lists of documents;
Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
5. Project Supervision approaches to IM as claimed in claim 1, it is characterised in that described
At the end of the work all of all critical processes being detected, complete the supervisory information management of described construction project
Work, specifically includes:
When the end-of-job of each critical process, the color of the gunter drawing of described critical process is shown as pre-
If color;
When detecting that the color of gunter drawing of all critical processes is default color, complete described construction
The supervisory information management work of engineering project.
6. the Project Supervision approaches to IM as described in any one of claim 1 to 5, its feature exists
In, described Project Supervision approaches to IM also includes:
The projected operating times of each critical process is set;
The running time of described critical process is contrasted with described projected operating times, obtains and protect
Deposit the progress performance of described critical process.
7. a Project Supervision information management system, it is characterised in that including:
Decomposing module, for being decomposed into different critical processes by construction project;
File acquisition module, for after the requirements for starting construction reaching each critical process, according to described crucial work
Management is carried out in management flow process, acceptance specification, working approaches of surveillance and measure that sequence is preset, and obtains
Take required file in the work of described critical process to file;And,
Worked module, at the end of the work all critical processes being detected, complete described in build
If the supervisory information management work of engineering project.
8. Project Supervision information management system as claimed in claim 7, it is characterised in that described point
Solution module specifically includes:
First resolving cell, for building according to room, municipal administration specialty construction project is decomposed into unit individual event
Engineering;
Second resolving cell, for being decomposed into part-to-item project by described unit individual works;
3rd resolving cell, for being decomposed into working procedure by described part-to-item project;And,
Critical process chooses unit, for choosing all of key from described working procedure according to job specfication
Operation.
9. Project Supervision information management system as claimed in claim 7, it is characterised in that described literary composition
Part acquisition module specifically includes:
Working cell, for after the requirements for starting construction reaching each critical process, pre-according to described critical process
If management flow process, acceptance specification, working approaches of surveillance and measure carry out management, and by described
The relevant information of critical process is sent to corresponding person liable;
File obtaining unit, for obtaining the file corresponding to lists of documents that described critical process is preset;With
And,
Profiling unit, for when detecting that the file of acquisition is handing over document, by described final acceptance of construction
Archive is in final acceptance of construction information bank;
Wherein, file obtaining unit is specifically for calling corresponding to the lists of documents that described critical process is preset
Save system table, and obtain the information that user fills on described province system table, it is thus achieved that corresponding to described lists of documents
File;Or, the file corresponding to lists of documents that the described critical process that reception user uploads is preset.
10. the Project Supervision information management system as described in any one of claim 7 to 9, its feature
Being, described work completes module and specifically includes:
Display unit, for when the end-of-job of each critical process, by the gunter drawing of described critical process
Color be shown as default color;And,
Worked unit, is default face for the color at the gunter drawing all critical processes being detected
During color, complete the supervisory information management work of described construction project.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610222154.4A CN105913341A (en) | 2016-04-11 | 2016-04-11 | Construction project supervision information management method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610222154.4A CN105913341A (en) | 2016-04-11 | 2016-04-11 | Construction project supervision information management method and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105913341A true CN105913341A (en) | 2016-08-31 |
Family
ID=56745805
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610222154.4A Pending CN105913341A (en) | 2016-04-11 | 2016-04-11 | Construction project supervision information management method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105913341A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107067225A (en) * | 2017-03-16 | 2017-08-18 | 苏州天狮建设监理有限公司 | A kind of approaches to IM and system |
CN107480171A (en) * | 2017-06-29 | 2017-12-15 | 中国建筑局(集团)有限公司 | The database and preparation method that working procedure is combined with engineering data |
CN107705020A (en) * | 2017-10-12 | 2018-02-16 | 山东联诚工程建设监理有限公司 | A kind of overall process intelligence engineering supervisory information managing and control system |
CN107908810A (en) * | 2017-09-28 | 2018-04-13 | 中建局集团第二建筑有限公司 | Execution management method therefor based on BIM models and mobile positioning technique |
CN108122089A (en) * | 2016-11-30 | 2018-06-05 | 中国航空工业集团公司成都飞机设计研究所 | A kind of task feedback based on delivery object |
CN108319431A (en) * | 2018-01-17 | 2018-07-24 | 四川同兴达建设咨询有限公司 | A kind of Construction Cost Data management system |
CN108376311A (en) * | 2018-02-06 | 2018-08-07 | 江苏普信工程项目管理有限公司 | The step that leaves a question open in project supervision checks amending method and system |
CN108460526A (en) * | 2018-02-24 | 2018-08-28 | 浙江华诚工程管理有限公司 | A kind of construction quality supervision method and system in project supervision |
CN109299851A (en) * | 2018-08-21 | 2019-02-01 | 内蒙古康远工程建设监理有限责任公司 | A kind of intelligence progress kinetic-control system |
CN109583842A (en) * | 2018-12-04 | 2019-04-05 | 北京诺士诚国际工程项目管理有限公司 | A kind of management monthly magazine generation method, device, electronic equipment and computer storage medium |
CN109767103A (en) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | A kind of method and system carrying out highway engineering task management based on WBS |
CN109872034A (en) * | 2018-12-30 | 2019-06-11 | 广州骏升建设管理有限公司 | The project process method and system of project supervision |
CN109872030A (en) * | 2018-12-28 | 2019-06-11 | 徐州中国矿业大学建筑设计咨询研究院有限公司 | A kind of management management method suitable for construction project |
CN110648116A (en) * | 2019-09-23 | 2020-01-03 | 北京地厚云图科技有限公司 | Management method for digital paperless real-time dynamic filing of whole process of building engineering |
CN110928838A (en) * | 2019-12-16 | 2020-03-27 | 郑卫华 | Engineering file management system architecture method and device |
CN111210196A (en) * | 2019-12-27 | 2020-05-29 | 宁波国际投资咨询有限公司 | Intelligent engineering supervision information supervision method |
-
2016
- 2016-04-11 CN CN201610222154.4A patent/CN105913341A/en active Pending
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108122089A (en) * | 2016-11-30 | 2018-06-05 | 中国航空工业集团公司成都飞机设计研究所 | A kind of task feedback based on delivery object |
CN107067225A (en) * | 2017-03-16 | 2017-08-18 | 苏州天狮建设监理有限公司 | A kind of approaches to IM and system |
CN107480171A (en) * | 2017-06-29 | 2017-12-15 | 中国建筑局(集团)有限公司 | The database and preparation method that working procedure is combined with engineering data |
CN107908810A (en) * | 2017-09-28 | 2018-04-13 | 中建局集团第二建筑有限公司 | Execution management method therefor based on BIM models and mobile positioning technique |
CN107705020A (en) * | 2017-10-12 | 2018-02-16 | 山东联诚工程建设监理有限公司 | A kind of overall process intelligence engineering supervisory information managing and control system |
CN108319431A (en) * | 2018-01-17 | 2018-07-24 | 四川同兴达建设咨询有限公司 | A kind of Construction Cost Data management system |
CN108376311A (en) * | 2018-02-06 | 2018-08-07 | 江苏普信工程项目管理有限公司 | The step that leaves a question open in project supervision checks amending method and system |
CN108460526A (en) * | 2018-02-24 | 2018-08-28 | 浙江华诚工程管理有限公司 | A kind of construction quality supervision method and system in project supervision |
CN109299851A (en) * | 2018-08-21 | 2019-02-01 | 内蒙古康远工程建设监理有限责任公司 | A kind of intelligence progress kinetic-control system |
CN109583842A (en) * | 2018-12-04 | 2019-04-05 | 北京诺士诚国际工程项目管理有限公司 | A kind of management monthly magazine generation method, device, electronic equipment and computer storage medium |
CN109872030A (en) * | 2018-12-28 | 2019-06-11 | 徐州中国矿业大学建筑设计咨询研究院有限公司 | A kind of management management method suitable for construction project |
CN109767103A (en) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | A kind of method and system carrying out highway engineering task management based on WBS |
CN109872034A (en) * | 2018-12-30 | 2019-06-11 | 广州骏升建设管理有限公司 | The project process method and system of project supervision |
CN110648116A (en) * | 2019-09-23 | 2020-01-03 | 北京地厚云图科技有限公司 | Management method for digital paperless real-time dynamic filing of whole process of building engineering |
CN110648116B (en) * | 2019-09-23 | 2022-09-16 | 北京地厚云图科技有限公司 | Management method for digital paperless real-time dynamic filing of whole process of building engineering |
CN110928838A (en) * | 2019-12-16 | 2020-03-27 | 郑卫华 | Engineering file management system architecture method and device |
CN111210196A (en) * | 2019-12-27 | 2020-05-29 | 宁波国际投资咨询有限公司 | Intelligent engineering supervision information supervision method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105913341A (en) | Construction project supervision information management method and system | |
CN107730077A (en) | Node tasks data display method, device, storage medium and computer equipment | |
CN103605459A (en) | Fast application launching method and fast application launching terminal | |
CN104917551B (en) | Method and equipment for pairing blue-tooth devices | |
CN105913225A (en) | Construction project agent-construction information management method and system | |
CN105426307B (en) | A kind of Local Area Network products' test resource sharing method and system | |
CN103886255B (en) | The privacy authority management method and device of application program | |
CN103093517A (en) | Human face recognition visitor management method | |
CN105041025A (en) | System and method for unlocking carport ground lock | |
Hoła | Methodology of hazards identification in construction work course | |
CN103761598A (en) | Enterprise information centralized collection processing method and system | |
CN106095561A (en) | Freeze the management method of application, the managing device freezing application and terminal | |
CN107464055A (en) | Schedule estimation method and device | |
CN106372189A (en) | Realization method of cloud diagnosis of transportation means and related device | |
CN104925595B (en) | The method of controlling operation thereof of elevator and device | |
CN105743850B (en) | Method and device for obtaining user authentication information when delivering articles by using express box | |
CN107067225A (en) | A kind of approaches to IM and system | |
US20060195350A1 (en) | Design review, progress check information transmission method and apparatus | |
KR101482380B1 (en) | System for construction information creation and method for construction information creation using the same | |
CN110019947A (en) | A kind of data extraction method and device | |
CN105141946B (en) | The test system and method for a kind of monitoring camera | |
CN108696718B (en) | Monitoring system and information terminal device in monitoring system | |
CN107230163B (en) | System for on-site quality supervision and inspection of power engineering | |
CN109993421A (en) | Apply the site safety risk recognition system and operating method in electricity power enterprise | |
CN109377183A (en) | Coalmine Safety Supervision intelligence enforcement system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160831 |