CN109872034A - The project process method and system of project supervision - Google Patents
The project process method and system of project supervision Download PDFInfo
- Publication number
- CN109872034A CN109872034A CN201811647207.2A CN201811647207A CN109872034A CN 109872034 A CN109872034 A CN 109872034A CN 201811647207 A CN201811647207 A CN 201811647207A CN 109872034 A CN109872034 A CN 109872034A
- Authority
- CN
- China
- Prior art keywords
- project
- supervision
- block chain
- content
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 184
- 238000005516 engineering process Methods 0.000 claims description 16
- 238000012544 monitoring process Methods 0.000 claims description 14
- 230000000694 effects Effects 0.000 abstract description 3
- 238000007726 management method Methods 0.000 description 45
- 238000010276 construction Methods 0.000 description 9
- 230000002427 irreversible effect Effects 0.000 description 4
- 230000003466 anti-cipated effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to the technical fields of project supervision, and more particularly, to a kind of project process method and system of project supervision, the project process method of project supervision includes: to establish project supervision project according to engineering project content and project supervision standard;Management program is obtained according to the project supervision project;Each flow nodes in the management program are obtained, this constructs management block chain according to the flow nodes;If getting project process content, the management block chain is written into the project process content, and be monitored to the project process content.The present invention has the effect of improving the efficiency of the project process of project supervision.
Description
Technical field
The present invention relates to the technical fields of project supervision, a kind of project process method more particularly, to project supervision and are
System.
Background technique
Currently, project supervision refers to work of the supervisor with related qualification by the commission of Party A, according to state approval
Journey project construction file, the law in relation to engineering construction, regulation and engineering supervision contract and other construction contracts, generation
A kind of proficient service activity of the table Party A to the engineering construction implementing monitoring of Party B.
It is cumbersome due to project work during existing project supervision, it needs to the staff's of responsible project
Work exercises supervision, and can only be exercised supervision at present by related personnel to the work of load terms purpose staff, does not meet
Now to the requirement of office automatic, while extra work personnel are needed, causes the waste of human resources.
Summary of the invention
The object of the present invention is to provide it is a kind of improve project supervision project process efficiency project supervision project into
Spend method and system.
Foregoing invention purpose one of the invention has the technical scheme that
A kind of project process method of project supervision, the project process method of the project supervision include:
According to engineering project content and project supervision standard, project supervision project is established;
Management program is obtained according to the project supervision project;
Each flow nodes in the management program are obtained, this constructs management block chain according to the flow nodes;
If getting project process content, the management block chain is written into the project process content, and to the project
Progress content is monitored.
By using above-mentioned technical proposal, according to engineering project content and project supervision standard, the project supervision item of management
Mesh enables to the project supervision project under the premise of complying with standard, is more in line with the content of concrete engineering project;Meanwhile
Management block chain is established to each management step by block chain technology, since each process is all one straight sequentially in time
Exhibition, the time being utilized in block chain well is irreversible, the characteristic that can not be distorted, and ensure that the safety of each process, meanwhile,
The decentralization of block chain technology also improves the efficiency in monitoring.
The present invention is further arranged to: described to obtain management program according to the project supervision project, comprising:
According to the engineering project curriculum offering project supervision project process;
Obtain each process step of project supervision project process, and to each process step setting it is corresponding at the beginning of
Between and the deadline after, obtain the management program.
By using above-mentioned technical proposal, by being planned for project supervision project, the process of project supervision is carried out
Refinement and arrange, obtain corresponding process step and it is corresponding at the beginning of and the deadline so that the progress of project supervision
It is more reasonable, while time started and deadline are set, it is also beneficial to be compared when being monitored.
The present invention is further arranged to: each flow nodes of the acquisition in the management program, this is according to institute
State flow nodes building management block chain, comprising:
Using each process step as the corresponding flow nodes, and it is corresponding described to obtain each process step
Deadline;
Each flow nodes are handled by block chain technology, obtain corresponding progress block, and according to described complete
The progress block is constructed into the management block chain at the time.
By using above-mentioned technical proposal, each flow nodes are constructed by the management block chain by block chain technology, are mentioned
More structurally sound data framework is supplied, while when building block chain, it will be between each management block by the time of each block
The flow nodes of each progress can be obtained from the management block chain to obtain the management block chain by forming chain structure
Specific beginning and deadline, it is convenient for subsequent monitoring.
The present invention is further arranged to: if described get project process content, the project process content being written
The management block chain, comprising:
If getting the project process content, corresponding actual finish time is obtained;
Corresponding position in the management block chain is written into the project process content and the actual finish time.
Further, the project process content is monitored, comprising:
According to the project process content, when obtaining the corresponding processing time and the completion from the management program
Between;
The project process content further includes the actual treatment time, obtains the actual treatment time of the project process content
With the actual finish time, and respectively by the actual treatment time and the actual finish time and the corresponding processing
Time and the deadline are compared;
If the result compared be that the actual treatment time is more late than the processing time and/or the actual finish time ratio described in
Evening deadline then generates and sends progress unexpected message.
By using above-mentioned technical proposal, by by management program processing time and deadline and time project
The processing time of progress is compared with actual finish time, can obtain unexpected message in time, convenient for management.
Foregoing invention purpose two of the invention has the technical scheme that
A kind of project process system of project supervision, the project process system of the project supervision include:
Project establishes module, for establishing project supervision project according to engineering project content and project supervision standard;
Program obtains module, for obtaining management program according to the project supervision project;
Block chain building module, for obtaining each flow nodes in the management program, this is according to the process section
Point building management block chain;
Monitoring module, if the management block chain is written in the project process content for getting project process content,
And the project process content is monitored.
By using above-mentioned technical proposal, according to engineering project content and project supervision standard, the project supervision item of management
Mesh enables to the project supervision project under the premise of complying with standard, is more in line with the content of concrete engineering project;Meanwhile
Management block chain is established to each management step by block chain technology, since each process is all one straight sequentially in time
Exhibition, the time being utilized in block chain well is irreversible, the characteristic that can not be distorted, and ensure that the safety of each process, meanwhile,
The decentralization of block chain technology also improves the efficiency in monitoring.
In conclusion advantageous effects of the invention are as follows:
1. according to engineering project content and project supervision standard, the project supervision project of management enables to the project supervision item
Mesh is more in line with the content of concrete engineering project under the premise of complying with standard;
2. management block chain is established to each management step by block chain technology, since each process is all sequentially in time
It is in progress always, the time being utilized in block chain well is irreversible, and the characteristic that can not be distorted ensure that the peace of each process
Entirely, meanwhile, the decentralization of block chain technology also improves the efficiency in monitoring.
Detailed description of the invention
Fig. 1 is a flow chart of the project process method of project supervision in one embodiment of the invention.
Fig. 2 is in the project process method of project supervision in one embodiment of the invention to the implementation flow chart of step S20.
Fig. 3 is in the project process method of project supervision in one embodiment of the invention to the implementation flow chart of step S30.
Fig. 4 is in the project process method of project supervision in one embodiment of the invention to the implementation flow chart of step S40.
Fig. 5 is another implementation process in the project process method of project supervision in one embodiment of the invention to step S40
Figure.
Fig. 6 is a functional block diagram of the project process system of project supervision in one embodiment of the invention.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment one:
In one embodiment, it as shown in Figure 1, being a kind of project process method of project supervision disclosed by the invention, specifically includes
Following steps:
S10: according to engineering project content and project supervision standard, project supervision project is established.
In the present embodiment, engineering project content refers to by examining on the spot and being planned to obtain according to surveys
Specific engineering construction in content.Project supervision standard refers to basis when carrying out project supervision according to the work of state approval
Journey project construction file, the law in relation to engineering construction, regulation and engineering supervision contract and other construction contracts from
And the standard formulated.Project supervision project, which refers to, is monitored and manages corresponding item in actually construction to the engineering project
Mesh.
Specifically, when establishing the project supervision project, according to project supervision standard and referring to actual engineering project
The case where content and demand are adaptively adjusted, and the project supervision project is established, so that the project supervision project established
More meet actual engineering project.
S20: management program is obtained according to project supervision project.
In the present embodiment, management program refers to the tables of data that project supervision project is planned and arranged
Lattice.
Specifically, according to the actual content in project supervision project, preparatory planning is carried out, it will be to engineering project reality
The step of management setting estimated time carried out and complete, to obtain the management program.
S30: obtaining each flow nodes in management program, this constructs management block chain according to flow nodes.
In one embodiment, flow nodes refer to each step in management program.Block chain is distributed data
The new application mode of the computer technologies such as storage, point-to-point transmission, common recognition mechanism, Encryption Algorithm.So-called common recognition mechanism is exactly
How to reach common understanding between all accounting nodes, goes the validity for assert a record, this is both the means of identification, and prevents
The means distorted.Management block chain refers to the block chain for being stored with project supervision process step particular content.
Specifically, by the technology of block chain, chain structure will be formed between each flow nodes in management program,
To obtain the management block chain.
S40: if getting project process content, management block chain is written into project process content, and to project process
Content is monitored.
In the present embodiment, project process content, which refers to, obtains the specific progresses in real time of the engineering project by project supervision
Corresponding data.
Specifically, after getting the project process content, by the project process content and working as the content is got
Corresponding position in the management block chain is written in the preceding time.And according to the time planned in the current time and step S20
It is compared, realization is monitored project process content.
In the present embodiment, according to engineering project content and project supervision standard, the project supervision project of management can make
The project supervision project is obtained under the premise of complying with standard, is more in line with the content of concrete engineering project;Meanwhile passing through block chain
Technology establishes management block chain to each management step, since each process is all to be in progress always sequentially in time, well
The time being utilized in block chain is irreversible, the characteristic that can not be distorted, and ensure that the safety of each process, meanwhile, block chain skill
The decentralization of art also improves the efficiency in monitoring.
In one embodiment, as shown in Fig. 2, in step S20, i.e., management program is obtained according to project supervision project,
Specifically comprise the following steps:
S21: according to engineering project curriculum offering project supervision project process.
In the present embodiment, project supervision project process, which refers to, carries out the specific process step of management to the engineering project content
Suddenly.
Specifically, according to engineering project content, the i.e. actual demand of the engineering project, each process of the engineering project is formulated
The time that step is carried out and completed, so that the project supervision project process is arranged, so that the progress to the engineering project carries out
Management.
S22: obtaining each process step of project supervision project process, and to the setting of each process step it is corresponding at the beginning of
Between and the deadline after, obtain management program.
Specifically, each process step of the project supervision project process respectively with the process step in engineering project content
It is corresponding, according to the process step, be arranged it is corresponding it is estimated at the beginning of and the deadline, obtain this and establish program.
In one embodiment, as shown in figure 3, in step s 30, that is, obtaining each process section in management program
Point, this constructs management block chain according to flow nodes, specifically comprises the following steps:
S31: using each process step as corresponding flow nodes, and each process step corresponding deadline is obtained.
Specifically, each process step corresponding deadline in obtaining step S22.
S32: each flow nodes are handled by block chain technology, obtain corresponding progress block, and according to complete
Progress block is constructed into management block chain at the time.
Specifically, the sequence according to the time from front to back, by the deadline most previous flow nodes, i.e. the process walks
After the progress block of the rapid first step is as the wound generation block of the management block chain, by each flow nodes and corresponding completion
Time is handled by block chain technology, obtains corresponding progress block.
Further, when obtaining the progress block, from the sequence according to the time from front to back, from second process section
The corresponding progress block of point starts, and the deadline of upper progress block is added, so that all progress blocks be constructed to obtain
The management block chain.
In one embodiment, as shown in figure 4, in step s 40, even getting project process content, then by project into
It spends content and management block chain is written, specifically comprise the following steps:
S41: if getting project process content, corresponding actual finish time is obtained.
Specifically, it during the engineering project carries out, according to management program one process step of every completion, obtains
The corresponding engineering project progress content of the process step and current time, as actually accomplishing for the project process content
Time.
S42: by corresponding position in project process content and actual finish time write-in management block chain.
Specifically, in step S41, the project process content is corresponding with the process step in management program, obtains
The process step establishes the specific location of block chain at this, and the position of the management block chain is written as the project process content.
Further, by corresponding position in project process content and actual finish time write-in management block chain.
In one embodiment, specific to wrap as shown in figure 5, in step s 40, i.e., and to project process content being monitored
Include following steps:
S43: according to project process content, corresponding processing time and deadline are obtained from management program.
Specifically, according to project process content, from the processing time obtained in management program in corresponding process step and
Deadline.
S44: project process content further includes the actual treatment time, obtains actual treatment time and the reality of project process content
The border deadline, and respectively compare actual treatment time and actual finish time with corresponding processing time and deadline
It is right.
When specifically, by the processing that will be acquired in the actual treatment time of the project process content and step S43
Between be compared, and by the deadline acquired in the actual finish time of the project process content and step S43 into
Row compares.
S45: if the result compared is that the actual treatment time is more late than the processing time and/or actual finish time compares the deadline
Evening then generates and sends progress unexpected message.
Specifically, when the actual treatment time is more late than the processing time and actual finish time any one more late than the deadline
Or when all occurring, illustrate the project process content without it is anticipated that carry out, then generate and send progress unexpected message, lead to
Know that related personnel handles and analyzes.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each process
Execution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limit
It is fixed.
Embodiment two:
In one embodiment, a kind of project process system of project supervision is provided, the project process system of the project supervision with it is upper
The project process method for stating project supervision in embodiment corresponds.As shown in fig. 6, the project process system packet of the project supervision
The project of including establishes module 10, program obtains module 20, block chain building module 30 and monitoring module 40.Each functional module is detailed
It is described as follows:
Project establishes module 10, for establishing project supervision project according to engineering project content and project supervision standard;
Program obtains module 20, for obtaining management program according to project supervision project;
Block chain building module 30, for obtaining each flow nodes in management program, this is constructed according to flow nodes
Management block chain;
Monitoring module 40, if management block chain is written in project process content, and to item for getting project process content
Mesh progress content is monitored.
Preferably, program obtains module 20, comprising:
Flow setting module 21, for according to engineering project curriculum offering project supervision project process;
Program acquisition submodule 22, for obtaining each process step of project supervision project process, and to each process step
At the beginning of setting is corresponding and after the deadline, management program is obtained.
Preferably, block chain building module 30, comprising:
Deadline acquisition submodule 31 is used for using each process step as corresponding flow nodes, and obtains each process
The step corresponding deadline;
Block chain building submodule 32, for each flow nodes to be handled by block chain technology, obtain it is corresponding into
Block is spent, and progress block is constructed by management block chain according to the deadline.
Preferably, monitoring module 40, comprising:
Actual finish time acquisition submodule 41, if for getting project process content, when obtaining corresponding actually accomplish
Between;
Reading and writing data submodule 42, for corresponding position in management block chain to be written in project process content and actual finish time
It sets.
Preferably, monitoring module 40, further includes:
Time acquisition submodule 43, for according to project process content, obtained from management program the corresponding processing time with
Deadline;
Submodule 44 is compared, further includes the actual treatment time for project process content, obtains the practical place of project process content
Time and actual finish time are managed, and respectively by actual treatment time and actual finish time and corresponding processing time and completion
Time is compared;
Message sending submodule 45, if the result for comparison is that the actual treatment time is more late and/or actually accomplish than the processing time
Time is more late than the deadline, then generates and sends progress unexpected message.
The specific of project process system about project supervision limits the project that may refer to above for project supervision
The restriction of progress method, details are not described herein.Modules in the project process system of above-mentioned project supervision can whole or portion
Divide and is realized by software, hardware and combinations thereof.Above-mentioned each module can be embedded in the form of hardware or independently of computer equipment
In processor in, can also be stored in a software form in the memory in computer equipment, in order to processor calling hold
The corresponding operation of the above modules of row.
Claims (10)
1. a kind of project process method of project supervision, which is characterized in that the project process method of the project supervision includes:
According to engineering project content and project supervision standard, project supervision project is established;
Management program is obtained according to the project supervision project;
Each flow nodes in the management program are obtained, this constructs management block chain according to the flow nodes;
If getting project process content, the management block chain is written into the project process content, and to the project
Progress content is monitored.
2. the project process method of project supervision as described in claim 1, which is characterized in that described according to the project supervision
Project obtains management program, comprising:
According to the engineering project curriculum offering project supervision project process;
Obtain each process step of project supervision project process, and to each process step setting it is corresponding at the beginning of
Between and the deadline after, obtain the management program.
3. the project process method of project supervision as described in claim 1, which is characterized in that it is described obtain the management into
Each flow nodes in table are spent, this constructs management block chain according to the flow nodes, comprising:
Using each process step as the corresponding flow nodes, and it is corresponding described to obtain each process step
Deadline;
Each flow nodes are handled by block chain technology, obtain corresponding progress block, and according to described complete
The progress block is constructed into the management block chain at the time.
4. the project process method of project supervision as described in claim 1, which is characterized in that if described get project process
Then the management block chain is written in the project process content by content, comprising:
If getting the project process content, corresponding actual finish time is obtained;
Corresponding position in the management block chain is written into the project process content and the actual finish time.
5. the project process method of project supervision as described in claim 1 or 4, which is characterized in that in the project process
Appearance is monitored, comprising:
According to the project process content, when obtaining the corresponding processing time and the completion from the management program
Between;
The project process content further includes the actual treatment time, obtains the actual treatment time of the project process content
With the actual finish time, and respectively by the actual treatment time and the actual finish time and the corresponding processing
Time and the deadline are compared;
If the result compared be that the actual treatment time is more late than the processing time and/or the actual finish time ratio described in
Evening deadline then generates and sends progress unexpected message.
6. a kind of project process system of project supervision, which is characterized in that the project process system of the project supervision includes:
Project establishes module, for establishing project supervision project according to engineering project content and project supervision standard;
Program obtains module, for obtaining management program according to the project supervision project;
Block chain building module, for obtaining each flow nodes in the management program, this is according to the process section
Point building management block chain;
Monitoring module, if the management block chain is written in the project process content for getting project process content,
And the project process content is monitored.
7. the project process system of project supervision as claimed in claim 6, which is characterized in that the program obtains module,
Include:
Flow setting module, for according to the engineering project curriculum offering project supervision project process;
Program acquisition submodule, for obtaining each process step of project supervision project process, and to each stream
At the beginning of the setting of journey step is corresponding and after the deadline, the management program is obtained.
8. the project process system of project supervision as claimed in claim 6, which is characterized in that the block chain building module,
Include:
Deadline acquisition submodule is used for using each process step as the corresponding flow nodes, and is obtained every
The one process step corresponding deadline;
Block chain building submodule obtains corresponding for being handled each flow nodes by block chain technology
Progress block, and the progress block is constructed by the management block chain according to the deadline.
9. the project process system of project supervision as claimed in claim 6, which is characterized in that the monitoring module, comprising:
Actual finish time acquisition submodule, if obtaining corresponding actually accomplish for getting the project process content
Time;
Reading and writing data submodule, for the management block chain to be written in the project process content and the actual finish time
In corresponding position.
10. the project process system of the project supervision as described in claim 6 or 9, which is characterized in that the monitoring module, also
Include:
Time acquisition submodule, for being obtained from the management program corresponding described according to the project process content
Handle time and the deadline;
Submodule is compared, further includes the actual treatment time for the project process content, obtains the project process content
The actual treatment time and the actual finish time, and respectively by the actual treatment time and the actual finish time
It is compared with the corresponding processing time and the deadline;
Message sending submodule, if the result for comparison is the actual treatment time is more late than the processing time and/or institute
It is more late than the deadline to state actual finish time, then generates and sends progress unexpected message.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811647207.2A CN109872034A (en) | 2018-12-30 | 2018-12-30 | The project process method and system of project supervision |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811647207.2A CN109872034A (en) | 2018-12-30 | 2018-12-30 | The project process method and system of project supervision |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109872034A true CN109872034A (en) | 2019-06-11 |
Family
ID=66917367
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811647207.2A Pending CN109872034A (en) | 2018-12-30 | 2018-12-30 | The project process method and system of project supervision |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109872034A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116644943A (en) * | 2023-07-26 | 2023-08-25 | 湖南湘江城市运营管理有限公司 | Engineering supervision data management system based on Internet of things |
CN117933919A (en) * | 2023-12-29 | 2024-04-26 | 上海翎熠工程监理有限公司 | Engineering supervision system based on information terminal |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
CN108197909A (en) * | 2018-03-24 | 2018-06-22 | 浙江鼎力工程项目管理有限公司 | A kind of project process supervision control system |
CN108898289A (en) * | 2018-06-13 | 2018-11-27 | 鹰投(上海)海洋科技发展有限公司 | Project completion management system and its implementation based on block chain |
-
2018
- 2018-12-30 CN CN201811647207.2A patent/CN109872034A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
CN108197909A (en) * | 2018-03-24 | 2018-06-22 | 浙江鼎力工程项目管理有限公司 | A kind of project process supervision control system |
CN108898289A (en) * | 2018-06-13 | 2018-11-27 | 鹰投(上海)海洋科技发展有限公司 | Project completion management system and its implementation based on block chain |
Non-Patent Citations (1)
Title |
---|
何宗耀: "《新型智慧城市建设现状、技术与研究》", 北京邮电大学出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116644943A (en) * | 2023-07-26 | 2023-08-25 | 湖南湘江城市运营管理有限公司 | Engineering supervision data management system based on Internet of things |
CN116644943B (en) * | 2023-07-26 | 2023-09-29 | 湖南湘江城市运营管理有限公司 | Engineering supervision data management system based on Internet of things |
CN117933919A (en) * | 2023-12-29 | 2024-04-26 | 上海翎熠工程监理有限公司 | Engineering supervision system based on information terminal |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Ozcan et al. | Examination timetabling using late acceptance hyper-heuristics | |
CN104794057B (en) | A kind of crossing event automated testing method and device | |
US20150012902A1 (en) | Automatic mapping method for a distribution network based on logical layout | |
CN109872034A (en) | The project process method and system of project supervision | |
CN108234127A (en) | A kind of Internet of Things method and device based on block chain | |
CN106448779B (en) | Master-control room of nuclear power plant screen inter-linked controlling method and device | |
CN203118041U (en) | Project cost progress management system | |
CN109242732A (en) | Campus activities organization system and method for organizing | |
CN109857565A (en) | Data processing method, device, computer equipment and storage medium | |
CN110705808A (en) | Power transmission network planning scheme generation system and method considering maintenance under new energy access | |
CN104199820A (en) | Cloud platform MapReduce workflow scheduling optimizing method | |
CN110310090A (en) | Dynamic electron approval process generation method, device, equipment and medium based on modularization | |
Jaengchuea et al. | A hybrid genetic algorithm with local search and tabu search approaches for solving the post enrolment based course timetabling problem: Outperforming guided search genetic algorithm | |
CN110046638A (en) | Fusion method, device and the equipment of multi-platform data | |
CN107229628A (en) | The method and device of distributed data base pretreatment | |
CN109150981A (en) | Block chain network network-building method, device, equipment and computer readable storage medium | |
Pita et al. | ARMOR Security for Los Angeles International Airport. | |
CN115688495B (en) | Distributed LVC simulation system collaborative planning method, server and storage medium | |
Wang | P-value based task allocation in a scrum team: a multi-agent simulation | |
CN108804307A (en) | process automation test method and device | |
CN105468455A (en) | Dynamic task distribution method and apparatus for multiple devices | |
CN109272292A (en) | The processing method and system of meeting summary based on block chain | |
CN108510188A (en) | Data processing method, device based on alliance's operation and equipment | |
CN104020938B (en) | A kind of information processing method and electronic equipment | |
Walker et al. | Effects Of An Early Prototyping Experience: Can Design Fixation Be Avoided? |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190611 |