CN107908810A - Execution management method therefor based on BIM models and mobile positioning technique - Google Patents
Execution management method therefor based on BIM models and mobile positioning technique Download PDFInfo
- Publication number
- CN107908810A CN107908810A CN201710899355.2A CN201710899355A CN107908810A CN 107908810 A CN107908810 A CN 107908810A CN 201710899355 A CN201710899355 A CN 201710899355A CN 107908810 A CN107908810 A CN 107908810A
- Authority
- CN
- China
- Prior art keywords
- bim models
- construction
- bim
- mobile
- rover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 41
- 238000007726 management method Methods 0.000 title claims abstract description 23
- 238000010276 construction Methods 0.000 claims abstract description 62
- 241001061260 Emmelichthys struhsakeri Species 0.000 claims abstract description 27
- 230000008859 change Effects 0.000 claims abstract description 8
- 230000002950 deficient Effects 0.000 claims abstract description 7
- 230000000694 effects Effects 0.000 claims abstract description 7
- 238000009430 construction management Methods 0.000 claims description 11
- 230000008569 process Effects 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 description 5
- 230000008901 benefit Effects 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- Business, Economics & Management (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Health & Medical Sciences (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Computational Mathematics (AREA)
- Economics (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses the execution management method therefor based on BIM models and mobile positioning technique, specific steps include:BIM models, including building element and Mechatronic Systems are established, light-weight technologg BIM models simultaneously load on the mobile apparatus;Construction site and the common origin of BIM models, the rover of setting are set, and rover roams with the change in location of mobile equipment in BIM models;Carry with mobile equipment and enter construction site, by contrasting the scene of discovery and the difference of BIM models;In the BIM model current view points shown by mobile equipment, defective in quality component is selected to carry out problem registration, and submit;Submitted quality problems are proved;Unit in charge of construction responsible person concerned describes according to quality problems, with reference to BIM models and running fix, construction responsible person concerned is directed into problem scene, is rectified and improved;Correlation technique director proves rectification effect, if demonstration is not by continuing to rectify and improve, until demonstration passes through.
Description
Technical field
The present invention relates to construction management technical field, more particularly to the construction pipe based on BIM models and mobile positioning technique
Reason method.
Background technology
BIM technology is gradually ripe in the application of building trade construction field, is mainly reflected in virtual construction and construction
In management, certain error can be produced with BIM models when constructing due to entity, cause model and live actual not fully phase
Symbol, it is also possible to have other quality problems.
Traditional construction quality problem needs to position on two bitmap paper, and this positioning is not directly perceived, and needs substantial amounts of paper
Face records and management, construction management are inefficient.
With the progressively popularization of BIM technology, increasingly drawn using BIM progress construction quality management in construction industry
Play everybody attention.The characteristics of due to BIM virtual constructions, be loaded into mobile equipment so that base by the BIM models of light-weight technologg
It is possibly realized in the navigation of BIM, the position of quality problems occurs with reference to construction site, can not only be accurately positioned, but also can confront
Amount problem carries out description in real time and submits.
Mobile positioning technique is mainly used for determining the position of equipment holder, can be by mobile positioning technique and BIM models
With reference to the quality problems of convenient mark and processing construction site, improve the efficiency of management of construction.
The content of the invention
The purpose of the present invention is for above-mentioned technical problem, there is provided the construction based on BIM models and mobile positioning technique
Management method, its step is reasonable, and BIM dummy models are combined with mobile positioning technique, is accurately positioned, quickly navigated, structure
Part quality problems mark, and improve construction management efficiency.
Technical scheme
In order to solve the above technical problems, the execution management method therefor provided by the invention based on BIM models and mobile positioning technique, bag
Include following steps:
S1, establishes BIM models, including building element and Mechatronic Systems, and light-weight technologg BIM models are simultaneously loaded in mobile equipment
On, BIM models are shown on the mobile apparatus, preview, positioning, navigation;
S2, sets construction site and the common origin of BIM models, sets rover, rover is with mobile equipment
Change in location roamed in BIM models;
S3, carries with mobile equipment and enters construction site, passes through the positioning of mobile equipment, rover's real time roaming to shifting
The position of the BIM models of construction site position correspondence residing for dynamic equipment, by contrasting the scene of discovery and the difference of BIM models;
BIM model current view points shown by mobile equipment, select defective in quality component to carry out problem registration, and submit;
S4, construction unit, designing unit, supervisor, unit in charge of construction correlation technique director are to submitted quality problems
Proved;
S5, unit in charge of construction responsible person concerned describe according to quality problems, with reference to BIM models and running fix, by the related duty of construction
Let people and direct into problem scene, rectified and improved;
S6, designing unit, supervisor, unit in charge of construction correlation technique director prove rectification effect, if demonstration is obstructed
Cross, continue to rectify and improve, until demonstration passes through.
Further, in step S2, the rover is virtual construction manager.
Further, in step S3, contrast finds that the device that the difference of scene and BIM models uses is 3D scanners.
Meanwhile present invention also provides a kind of construction management system based on BIM models and mobile positioning technique, its feature
It is, including mobile equipment, 3D scanners and rover, it performs following management process:
BIM models, including building element and Mechatronic Systems are established, light-weight technologg BIM models simultaneously load on the mobile apparatus,
BIM models are shown on the mobile apparatus, preview, positioning, navigation;
Construction site and the common origin of BIM models are set, rover is set, and rover is with the position of mobile equipment
Change is put to roam in BIM models;
Carry with mobile equipment and enter construction site, pass through the positioning of mobile equipment, rover's real time roaming to movement
The position of the BIM models of construction site position correspondence residing for equipment, by contrasting the scene of discovery and the difference of BIM models;Moving
BIM model current view points shown by dynamic equipment, select defective in quality component to carry out problem registration, and submit;
Construction unit, designing unit, supervisor, unit in charge of construction correlation technique director carry out submitted quality problems
Demonstration;
Unit in charge of construction responsible person concerned describes according to quality problems, with reference to BIM models and running fix, by the responsible person concerned that constructs
Problem scene is directed into, is rectified and improved;
Designing unit, supervisor, unit in charge of construction correlation technique director to rectification effect prove, if demonstration not by,
Continue to rectify and improve, until demonstration passes through.
Beneficial effect of the present invention:
Compared with the prior art, the execution management method therefor provided by the invention based on BIM models and mobile positioning technique, step are closed
Reason, has the advantages that:
(1)BIM technology and running fix are combined, BIM technology can embody the space occupy-place feelings of construction site from three-dimensional perspective
Condition, mobile positioning technique guiding construction management, can intuitively, be accurately positioned, quick navigation, visualization mark component quality is asked
Topic;
(2)Once there is provided scene and the common reference origin of model, mobile equipment will combine the automatic fast positioning of BIM models,
It need not train and can be used, reduce using threshold;
(3)Compared with traditional execution management method therefor, the application can accurately have found quality problems position, without paper pipe
Reason data, effectively increases construction management efficiency, reduces management cost.
Brief description of the drawings
By the detailed description made in conjunction with the following drawings, above-mentioned advantage of the invention will be apparent and be easier reason
Solution, these attached drawings are simply schematical, are not intended to limit the present invention, wherein:
Fig. 1 is the flow chart of the execution management method therefor of the present invention based on BIM models and mobile positioning technique.
Embodiment
With reference to specific embodiments and the drawings, to construction management of the present invention based on BIM models and mobile positioning technique
Method is described in detail.
The embodiment recorded herein is specific embodiment of the invention, for illustrating the design of the present invention,
It is explanatory and exemplary, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein
Outside embodiment, those skilled in the art can also be based on the application claims and specification disclosure of that using aobvious and
The other technical solutions being clear to, these technical solutions include any obvious using making for the embodiment to recording herein
The technical solution of substitutions and modifications.
Execution management method therefor provided by the invention based on BIM models and mobile positioning technique, comprises the following steps:
S1, establishes BIM models, including building element and Mechatronic Systems, and light-weight technologg BIM models are simultaneously loaded in mobile equipment
On, BIM models are shown on the mobile apparatus, preview, positioning, navigation;
S2, sets construction site and the common origin of BIM models, sets rover, rover is with mobile equipment
Change in location roamed in BIM models;
In this step, the rover is virtual construction manager, and rover is with the position of mobile equipment
Change is put to roam in BIM models.
S3, carries with mobile equipment and enters construction site, passes through the positioning of mobile equipment, rover's real time roaming
To the position of the BIM models of construction site position correspondence residing for mobile equipment, by contrasting the scene of discovery and the difference of BIM models
It is different;In the BIM model current view points shown by mobile equipment, defective in quality component is selected to carry out problem registration, and submit;
In this step, contrast finds that the device that the difference of scene and BIM models uses is 3D scanners.3D scanners, which have, to be swept
The advantages of precision is high is retouched, using 3D scanner scannings construction site, is carried out further according to the point cloud model after scanning and BIM models
Compare, the accurate difference for finding both.
S4, construction unit, designing unit, supervisor, unit in charge of construction correlation technique director are to submitted quality
Problem is proved;
S5, unit in charge of construction responsible person concerned describe according to quality problems, with reference to BIM models and running fix, by the related duty of construction
Let people and direct into problem scene, rectified and improved;
S6, designing unit, supervisor, unit in charge of construction correlation technique director prove rectification effect, if demonstration is obstructed
Cross, continue to rectify and improve, until demonstration passes through.
Meanwhile present invention also provides a kind of construction management system based on BIM models and mobile positioning technique, its feature
It is, including mobile equipment, 3D scanners and rover, it performs following management process:
BIM models, including building element and Mechatronic Systems are established, light-weight technologg BIM models simultaneously load on the mobile apparatus,
BIM models are shown on the mobile apparatus, preview, positioning, navigation;
Construction site and the common origin of BIM models are set, rover is set, and rover is with the position of mobile equipment
Change is put to roam in BIM models;
Carry with mobile equipment and enter construction site, pass through the positioning of mobile equipment, rover's real time roaming to movement
The position of the BIM models of construction site position correspondence residing for equipment, by contrasting the scene of discovery and the difference of BIM models;Moving
BIM model current view points shown by dynamic equipment, select defective in quality component to carry out problem registration, and submit;
Construction unit, designing unit, supervisor, unit in charge of construction correlation technique director carry out submitted quality problems
Demonstration;
Unit in charge of construction responsible person concerned describes according to quality problems, with reference to BIM models and running fix, by the responsible person concerned that constructs
Problem scene is directed into, is rectified and improved;
Designing unit, supervisor, unit in charge of construction correlation technique director to rectification effect prove, if demonstration not by,
Continue to rectify and improve, until demonstration passes through.
Execution management method therefor described herein based on BIM models and mobile positioning technique is suitable for antidetonation suspension and support
The management of construction quality, can also be applied to the construction management of other building elements.
Compared with the prior art the shortcomings that and deficiency, applying based on BIM models and mobile positioning technique provided by the invention
Work management method, its step is reasonable, and BIM dummy models are combined with mobile positioning technique, be accurately positioned, quickly navigated,
Component quality problem marks, and improves construction management efficiency.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention
Enclose and be defined, on the premise of design spirit of the present invention is not departed from, technical side of the those of ordinary skill in the art to the present invention
The various modifications and improvement that case is made, should all fall into the protection domain that claims of the present invention determines.
Claims (4)
1. the execution management method therefor based on BIM models and mobile positioning technique, it is characterised in that comprise the following steps:
S1, establishes BIM models, including building element and Mechatronic Systems, and light-weight technologg BIM models are simultaneously loaded in mobile equipment
On, BIM models are shown on the mobile apparatus, preview, positioning, navigation;
S2, sets construction site and the common origin of BIM models, sets rover, rover is with mobile equipment
Change in location roamed in BIM models;
S3, carries with mobile equipment and enters construction site, passes through the positioning of mobile equipment, rover's real time roaming to shifting
The position of the BIM models of construction site position correspondence residing for dynamic equipment, by contrasting the scene of discovery and the difference of BIM models;
BIM model current view points shown by mobile equipment, select defective in quality component to carry out problem registration, and submit;
S4, construction unit, designing unit, supervisor, unit in charge of construction correlation technique director are to submitted quality problems
Proved;
S5, unit in charge of construction responsible person concerned describe according to quality problems, with reference to BIM models and running fix, by the related duty of construction
Let people and direct into problem scene, rectified and improved;
S6, designing unit, supervisor, unit in charge of construction correlation technique director prove rectification effect, if demonstration is obstructed
Cross, continue to rectify and improve, until demonstration passes through.
2. the execution management method therefor based on BIM models and mobile positioning technique according to claim 1, it is characterised in that step
In rapid S2, the rover is virtual construction manager.
3. the execution management method therefor based on BIM models and mobile positioning technique according to claim 1, it is characterised in that step
In rapid S3, contrast finds that the device that the difference of scene and BIM models uses is 3D scanners.
4. a kind of construction management system based on BIM models and mobile positioning technique, it is characterised in that including mobile equipment, 3D
Scanner and rover, it performs following management process:
BIM models, including building element and Mechatronic Systems are established, light-weight technologg BIM models simultaneously load on the mobile apparatus,
BIM models are shown on the mobile apparatus, preview, positioning, navigation;
Construction site and the common origin of BIM models are set, rover is set, and rover is with the position of mobile equipment
Change is put to roam in BIM models;
Carry with mobile equipment and enter construction site, pass through the positioning of mobile equipment, rover's real time roaming to movement
The position of the BIM models of construction site position correspondence residing for equipment, by contrasting the scene of discovery and the difference of BIM models;Moving
BIM model current view points shown by dynamic equipment, select defective in quality component to carry out problem registration, and submit;
Construction unit, designing unit, supervisor, unit in charge of construction correlation technique director carry out submitted quality problems
Demonstration;
Unit in charge of construction responsible person concerned describes according to quality problems, with reference to BIM models and running fix, by the responsible person concerned that constructs
Problem scene is directed into, is rectified and improved;
Designing unit, supervisor, unit in charge of construction correlation technique director to rectification effect prove, if demonstration not by,
Continue to rectify and improve, until demonstration passes through.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710899355.2A CN107908810B (en) | 2017-09-28 | 2017-09-28 | Construction management method based on BIM model and mobile positioning technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710899355.2A CN107908810B (en) | 2017-09-28 | 2017-09-28 | Construction management method based on BIM model and mobile positioning technology |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107908810A true CN107908810A (en) | 2018-04-13 |
CN107908810B CN107908810B (en) | 2022-02-08 |
Family
ID=61840338
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710899355.2A Active CN107908810B (en) | 2017-09-28 | 2017-09-28 | Construction management method based on BIM model and mobile positioning technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107908810B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN109559007A (en) * | 2018-09-19 | 2019-04-02 | 中建科技有限公司深圳分公司 | A kind of construction quality management method and device |
CN110782134A (en) * | 2019-10-08 | 2020-02-11 | 上海建工五建集团有限公司 | Engineering quality monitoring method and system |
CN113252015A (en) * | 2021-05-10 | 2021-08-13 | 中建三局集团华南有限公司 | Actual measurement real-size robot device based on point cloud and AI processing |
WO2022083108A1 (en) * | 2020-10-21 | 2022-04-28 | 中建科技集团有限公司 | Construction quality test method and apparatus, and terminal and storage medium |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
US20170109981A1 (en) * | 2015-10-16 | 2017-04-20 | Honeywell International Inc. | System and method of using a fire spread forecast and bim to guide occupants using smart signs |
CN106776963A (en) * | 2016-12-05 | 2017-05-31 | 同济大学 | The light-weighted online method for visualizing of BIM big datas and system |
CN106909749A (en) * | 2017-03-08 | 2017-06-30 | 朱海涛 | Mobile terminal is based on the Intelligent Recognition localization method of BIM |
KR101764849B1 (en) * | 2016-03-17 | 2017-08-04 | 윤승휘 | System for monitoring cultural structure |
-
2017
- 2017-09-28 CN CN201710899355.2A patent/CN107908810B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20170109981A1 (en) * | 2015-10-16 | 2017-04-20 | Honeywell International Inc. | System and method of using a fire spread forecast and bim to guide occupants using smart signs |
KR101764849B1 (en) * | 2016-03-17 | 2017-08-04 | 윤승휘 | System for monitoring cultural structure |
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
CN106776963A (en) * | 2016-12-05 | 2017-05-31 | 同济大学 | The light-weighted online method for visualizing of BIM big datas and system |
CN106909749A (en) * | 2017-03-08 | 2017-06-30 | 朱海涛 | Mobile terminal is based on the Intelligent Recognition localization method of BIM |
Non-Patent Citations (2)
Title |
---|
互联立方BIM咨询: ""看全球顶尖的BIM玩法:在增强现实(AR)领域的BIM应用"", 《HTTPS://WWW.SOHU.COM/A/191563900_769918》 * |
孙昱晨等: ""Fuzor 仿真技术在建筑项目中的运用"", 《技术与应用》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109559007A (en) * | 2018-09-19 | 2019-04-02 | 中建科技有限公司深圳分公司 | A kind of construction quality management method and device |
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN109360123B (en) * | 2018-10-22 | 2021-07-27 | 上海建工四建集团有限公司 | Multi-professional construction management method and system based on room |
CN110782134A (en) * | 2019-10-08 | 2020-02-11 | 上海建工五建集团有限公司 | Engineering quality monitoring method and system |
WO2022083108A1 (en) * | 2020-10-21 | 2022-04-28 | 中建科技集团有限公司 | Construction quality test method and apparatus, and terminal and storage medium |
CN113252015A (en) * | 2021-05-10 | 2021-08-13 | 中建三局集团华南有限公司 | Actual measurement real-size robot device based on point cloud and AI processing |
Also Published As
Publication number | Publication date |
---|---|
CN107908810B (en) | 2022-02-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107908810A (en) | Execution management method therefor based on BIM models and mobile positioning technique | |
CN106338245B (en) | A kind of non-contact traverse measurement method of workpiece | |
CN103455480B (en) | A kind of position search method based on electronic chart and device | |
CN108873908B (en) | Robot city navigation system based on combination of visual SLAM and network map | |
CN105806345B (en) | A kind of initialization positioning method for Intelligent Mobile Robot laser navigation | |
CN102368810A (en) | Semi-automatic aligning video fusion system and method thereof | |
CN106441087B (en) | A kind of more size Multi-parameter Measurement Methods of workpiece based on image procossing | |
CN108801142A (en) | A kind of super workpiece double-movement measurement robot system and method | |
CN103596263B (en) | Method and device for position acquisition in indoor positioning | |
CN103747207A (en) | Positioning and tracking method based on video monitor network | |
CN104807467A (en) | Display method and system of navigation map | |
CN105025290A (en) | Method for automatically adjusting inclination between image photographing module group sensor and lens | |
US9554253B2 (en) | Locating method, drive test terminal and hand-held terminal | |
CN105448184A (en) | Map road drawing method and map road drawing device | |
CN109903382B (en) | Point cloud data fusion method and device | |
CN106355647A (en) | Augmented reality system and method | |
CN104897160A (en) | Method and device for manufacturing indoor map and positioning | |
CN110502839B (en) | GIS (geographic information System) coordinate and CAD (computer aided design) coordinate conversion method based on BIM (building information modeling) platform | |
CN109141402B (en) | Positioning method based on laser grids and robot autonomous charging method | |
WO2019119954A1 (en) | Indoor network signal collection method and device and navigation robot | |
CN109031373A (en) | A kind of Intelligent Mobile Robot navigation system and method | |
CN106931978B (en) | Indoor map generation method for automatically constructing road network | |
CN104075712A (en) | Interactive type navigation system and method | |
CN102542555B (en) | Method and system for generating edge seam path and edge seam topological structure of raster image | |
CN108789412A (en) | A kind of robot motion's Trajectory Planning System, method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |