CN109872030A - A kind of management management method suitable for construction project - Google Patents
A kind of management management method suitable for construction project Download PDFInfo
- Publication number
- CN109872030A CN109872030A CN201811624418.4A CN201811624418A CN109872030A CN 109872030 A CN109872030 A CN 109872030A CN 201811624418 A CN201811624418 A CN 201811624418A CN 109872030 A CN109872030 A CN 109872030A
- Authority
- CN
- China
- Prior art keywords
- construction
- management
- actual
- data
- construction project
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 36
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 238000000034 method Methods 0.000 claims abstract description 32
- 230000000052 comparative effect Effects 0.000 claims description 3
- 238000001514 detection method Methods 0.000 claims description 3
- 238000011017 operating method Methods 0.000 claims description 3
- 238000009430 construction management Methods 0.000 abstract description 5
- 230000010354 integration Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000246 remedial effect Effects 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of management management methods suitable for construction project, cross to each process and entire engineering carry out planning and it is actual comparison come to each process and entire engineering construction management, and the data of planning and actually detected data are recorded, are saved, to the purpose for improving information management standard, the work difficulty for reducing staff, the risk for reducing loss of data and raising Supervision Quality.
Description
Technical field
The present invention relates to engineering construction field more particularly to a kind of management management methods suitable for construction project.
Background technique
Currently, the management of Project Supervision information, most of is all to fill in various tables manually, artificial progress information
Transmitting and management.It using this way to manage, can not accomplish standardized management, can not accomplish the integration of information and share entirely,
And the inefficiency, at high cost of management.
Summary of the invention
In order to solve the above technical problems, being mentioned the invention proposes the management management method for being suitable for construction project with reaching
High information management standard, the work difficulty for reducing staff, the risk for reducing loss of data and the mesh for improving Supervision Quality
's.
In order to achieve the above objectives, technical scheme is as follows:
A kind of management management method suitable for construction project, comprising:
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor
It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements
Parameter;Progress control includes the reference program before process starts and the actual progress table after the practical expansion of process;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result
Amount, and the data are recorded and saved;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data
It deposits.
The present invention is by carrying out planning and actual comparison to each process and entire engineering come to each process and whole
A engineering construction management, and the data of planning and actually detected data are recorded, are saved, to improving information management standard
Work difficulty, the purpose of the risk and raising Supervision Quality that reduce loss of data changed, reduce staff.
Preferably, it is described with reference to program include the process construction preplanning time interval and engineering to be reached
The mass parameter arrived, there are also the signatures of practice of construction person and construction responsible person on the Gantt chart;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination
Actual mass parameter.There are also actual operators and detection responsible person's signature on the actual progress table.
Preferably, the data in the step (3) can generate comparative bid parameter, and below standard parameter is marked
Note.
The present invention has the advantage that
1. of the invention by carrying out planning and actual comparison to each process and entire engineering come to each process and entirely
Engineering construction management, and the data of planning and actually detected data are recorded, are saved, to improving information management standard
Work difficulty, the purpose of the risk and raising Supervision Quality that reduce loss of data changed, reduce staff.
Specific embodiment
The following is a clear and complete description of the technical scheme in the embodiments of the invention.
The present invention provides a kind of management management methods suitable for construction project, its working principle is that by each work
Sequence and entire engineering are come to carry out planning and actual comparison to each process and entire engineering construction management, and by the number of planning
According to being recorded, saved with actually detected data, to improve information management standard, the work difficulty for reducing staff,
It reduces the risk of loss of data and improves the purpose of Supervision Quality.
Below with reference to embodiment and specific embodiment, the present invention is described in further detail.
A kind of management management method suitable for construction project, comprising:
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor
It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements
Parameter;Progress control includes reference program before process starts and the actual progress table after the practical expansion of process, described
With reference to program include the process construction preplanning time interval and engineering mass parameter to be achieved, it is described construct into
Spend the also signature of practice of construction person and construction responsible person on table;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination
Actual mass parameter.There are also actual operators and detection responsible person's signature on the actual progress table;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result
Amount, and the data are recorded and saved, while data can be generated into comparative bid parameter, and mark to below standard parameter
Note saves the time convenient for knowing which current link there is a problem for the remedial efforts of process;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data
It deposits.
By above mode, the management management method provided by the present invention suitable for construction project, by each
Process and entire engineering are come to carry out planning and actual comparison to each process and entire engineering construction management, and by planning
Data and actually detected data are recorded, are saved, to the work hardly possible for improving information management standard, reducing staff
Degree, the risk for reducing loss of data and the purpose for improving Supervision Quality.
Above-described is only the preferred implementation side of the management management method disclosed in this invention suitable for construction project
Formula, it is noted that for those of ordinary skill in the art, without departing from the concept of the premise of the invention, may be used also
To make several modifications and improvements, these are all within the scope of protection of the present invention.
Claims (3)
1. a kind of management management method suitable for construction project characterized by comprising
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor
It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements
Parameter;Progress control includes the reference program before process starts and the actual progress table after the practical expansion of process;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result
Amount, and the data are recorded and saved;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data
It deposits.
2. a kind of management management method suitable for construction project as described in claim 1, which is characterized in that it is described with reference into
Degree table includes the time interval and engineering mass parameter to be achieved of process construction preplanning, on the Gantt chart
There are also the signatures of practice of construction person and construction responsible person;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination
Actual mass parameter;There are also actual operators and detection responsible person's signature on the actual progress table.
3. a kind of management management method suitable for construction project according to claim 1, which is characterized in that the step
(3) data in can generate comparative bid parameter, and below standard parameter is marked.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811624418.4A CN109872030A (en) | 2018-12-28 | 2018-12-28 | A kind of management management method suitable for construction project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811624418.4A CN109872030A (en) | 2018-12-28 | 2018-12-28 | A kind of management management method suitable for construction project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109872030A true CN109872030A (en) | 2019-06-11 |
Family
ID=66917361
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811624418.4A Pending CN109872030A (en) | 2018-12-28 | 2018-12-28 | A kind of management management method suitable for construction project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109872030A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
CN108460526A (en) * | 2018-02-24 | 2018-08-28 | 浙江华诚工程管理有限公司 | A kind of construction quality supervision method and system in project supervision |
-
2018
- 2018-12-28 CN CN201811624418.4A patent/CN109872030A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105913341A (en) * | 2016-04-11 | 2016-08-31 | 广州市城市建设工程监理公司 | Construction project supervision information management method and system |
CN108460526A (en) * | 2018-02-24 | 2018-08-28 | 浙江华诚工程管理有限公司 | A kind of construction quality supervision method and system in project supervision |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108536770B (en) | Distribution network ring net automatic generation method based on distribution GIS model | |
CN107292590A (en) | A kind of method and device based on cloud management platform construction business approval flow | |
CN107682220A (en) | Method for inspecting for power equipment | |
DE60318470D1 (en) | METHOD FOR GRANTING ACCESS TO A DEVICE THROUGH A LINKING OF A FIRST CHARACTERISTIC OF A FIRST DEVICE AND A SECOND CHARACTERISTIC OF A SECOND DEVICE | |
ATE301483T1 (en) | DEVICE FOR PLANNING AN INFUSION | |
CN106803165A (en) | Using the method for task tree schema synergetic office work | |
CN102938109B (en) | Grid power blackout method of combination and device | |
CN105023117A (en) | Electrified detection standardized operation management system based on mobile and cloud computing technologies | |
CN106373351A (en) | Elevator maintenance system | |
CN106991140A (en) | monitoring information table checking method and system | |
CN111861180A (en) | Management system for real-time early warning of digital energy production and manufacturing | |
WO2014040488A1 (en) | Method and device for guaranteeing consistency of planning data | |
CA2389274A1 (en) | Apparatus and method for performance and fault data analysis | |
CN109872030A (en) | A kind of management management method suitable for construction project | |
CN109102245A (en) | A kind of processing method of approval process, system and device | |
CN107885850A (en) | A kind of localization method and device of banking class problem | |
CN107844369A (en) | A kind of method that big data transformation task cutting is realized in task based access control scheduling | |
CN109272249A (en) | A kind of platform area line loss defect elimination method based on platform area identifier | |
CN110288247A (en) | Product quality analysis system and method | |
CN109144551A (en) | Equipment firmware update and system under a kind of multi-layer networking mode | |
CN111640493B (en) | Automatic scheduling method for operation notice based on bubbling algorithm | |
CN106204786A (en) | Operating condition of transformer station equipment one key inspection method | |
CN100547624C (en) | The method of a kind of remote monitoring working-yard operation | |
CN103607715B (en) | A kind of method and device of frequency configuration | |
CN109528195A (en) | In a kind of MRI/CT image bone boundary and method for distinguishing is known with reference to bone mark object |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190611 |