CN109872030A - A kind of management management method suitable for construction project - Google Patents

A kind of management management method suitable for construction project Download PDF

Info

Publication number
CN109872030A
CN109872030A CN201811624418.4A CN201811624418A CN109872030A CN 109872030 A CN109872030 A CN 109872030A CN 201811624418 A CN201811624418 A CN 201811624418A CN 109872030 A CN109872030 A CN 109872030A
Authority
CN
China
Prior art keywords
construction
management
actual
data
construction project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811624418.4A
Other languages
Chinese (zh)
Inventor
方忠年
吴庆安
赵飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201811624418.4A priority Critical patent/CN109872030A/en
Publication of CN109872030A publication Critical patent/CN109872030A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of management management methods suitable for construction project, cross to each process and entire engineering carry out planning and it is actual comparison come to each process and entire engineering construction management, and the data of planning and actually detected data are recorded, are saved, to the purpose for improving information management standard, the work difficulty for reducing staff, the risk for reducing loss of data and raising Supervision Quality.

Description

A kind of management management method suitable for construction project
Technical field
The present invention relates to engineering construction field more particularly to a kind of management management methods suitable for construction project.
Background technique
Currently, the management of Project Supervision information, most of is all to fill in various tables manually, artificial progress information Transmitting and management.It using this way to manage, can not accomplish standardized management, can not accomplish the integration of information and share entirely, And the inefficiency, at high cost of management.
Summary of the invention
In order to solve the above technical problems, being mentioned the invention proposes the management management method for being suitable for construction project with reaching High information management standard, the work difficulty for reducing staff, the risk for reducing loss of data and the mesh for improving Supervision Quality 's.
In order to achieve the above objectives, technical scheme is as follows:
A kind of management management method suitable for construction project, comprising:
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements Parameter;Progress control includes the reference program before process starts and the actual progress table after the practical expansion of process;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result Amount, and the data are recorded and saved;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data It deposits.
The present invention is by carrying out planning and actual comparison to each process and entire engineering come to each process and whole A engineering construction management, and the data of planning and actually detected data are recorded, are saved, to improving information management standard Work difficulty, the purpose of the risk and raising Supervision Quality that reduce loss of data changed, reduce staff.
Preferably, it is described with reference to program include the process construction preplanning time interval and engineering to be reached The mass parameter arrived, there are also the signatures of practice of construction person and construction responsible person on the Gantt chart;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination Actual mass parameter.There are also actual operators and detection responsible person's signature on the actual progress table.
Preferably, the data in the step (3) can generate comparative bid parameter, and below standard parameter is marked Note.
The present invention has the advantage that
1. of the invention by carrying out planning and actual comparison to each process and entire engineering come to each process and entirely Engineering construction management, and the data of planning and actually detected data are recorded, are saved, to improving information management standard Work difficulty, the purpose of the risk and raising Supervision Quality that reduce loss of data changed, reduce staff.
Specific embodiment
The following is a clear and complete description of the technical scheme in the embodiments of the invention.
The present invention provides a kind of management management methods suitable for construction project, its working principle is that by each work Sequence and entire engineering are come to carry out planning and actual comparison to each process and entire engineering construction management, and by the number of planning According to being recorded, saved with actually detected data, to improve information management standard, the work difficulty for reducing staff, It reduces the risk of loss of data and improves the purpose of Supervision Quality.
Below with reference to embodiment and specific embodiment, the present invention is described in further detail.
A kind of management management method suitable for construction project, comprising:
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements Parameter;Progress control includes reference program before process starts and the actual progress table after the practical expansion of process, described With reference to program include the process construction preplanning time interval and engineering mass parameter to be achieved, it is described construct into Spend the also signature of practice of construction person and construction responsible person on table;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination Actual mass parameter.There are also actual operators and detection responsible person's signature on the actual progress table;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result Amount, and the data are recorded and saved, while data can be generated into comparative bid parameter, and mark to below standard parameter Note saves the time convenient for knowing which current link there is a problem for the remedial efforts of process;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data It deposits.
By above mode, the management management method provided by the present invention suitable for construction project, by each Process and entire engineering are come to carry out planning and actual comparison to each process and entire engineering construction management, and by planning Data and actually detected data are recorded, are saved, to the work hardly possible for improving information management standard, reducing staff Degree, the risk for reducing loss of data and the purpose for improving Supervision Quality.
Above-described is only the preferred implementation side of the management management method disclosed in this invention suitable for construction project Formula, it is noted that for those of ordinary skill in the art, without departing from the concept of the premise of the invention, may be used also To make several modifications and improvements, these are all within the scope of protection of the present invention.

Claims (3)

1. a kind of management management method suitable for construction project characterized by comprising
(1) construction project is decomposed into different critical processes by;
(2) sets respective workflow, acceptance criteria and progress control to each critical process, and by above-mentioned record, guarantor It deposits;
Wherein, workflow is the operating procedure of each critical process of specification;Acceptance criteria should be reached according to building requirements Parameter;Progress control includes the reference program before process starts and the actual progress table after the practical expansion of process;
(3) in progress control reference program and actual progress table be compared, which is judged according to comparison result Amount, and the data are recorded and saved;
(4) after the completion of whole process, integrated engineering requirement is referred again to, to judge whether to close rule, and record guarantor is carried out to the data It deposits.
2. a kind of management management method suitable for construction project as described in claim 1, which is characterized in that it is described with reference into Degree table includes the time interval and engineering mass parameter to be achieved of process construction preplanning, on the Gantt chart There are also the signatures of practice of construction person and construction responsible person;
Acquisition when the actual progress table includes the time that practice of construction starts and the time that practice of construction terminates and examination Actual mass parameter;There are also actual operators and detection responsible person's signature on the actual progress table.
3. a kind of management management method suitable for construction project according to claim 1, which is characterized in that the step (3) data in can generate comparative bid parameter, and below standard parameter is marked.
CN201811624418.4A 2018-12-28 2018-12-28 A kind of management management method suitable for construction project Pending CN109872030A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811624418.4A CN109872030A (en) 2018-12-28 2018-12-28 A kind of management management method suitable for construction project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811624418.4A CN109872030A (en) 2018-12-28 2018-12-28 A kind of management management method suitable for construction project

Publications (1)

Publication Number Publication Date
CN109872030A true CN109872030A (en) 2019-06-11

Family

ID=66917361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811624418.4A Pending CN109872030A (en) 2018-12-28 2018-12-28 A kind of management management method suitable for construction project

Country Status (1)

Country Link
CN (1) CN109872030A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105913341A (en) * 2016-04-11 2016-08-31 广州市城市建设工程监理公司 Construction project supervision information management method and system
CN108460526A (en) * 2018-02-24 2018-08-28 浙江华诚工程管理有限公司 A kind of construction quality supervision method and system in project supervision

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105913341A (en) * 2016-04-11 2016-08-31 广州市城市建设工程监理公司 Construction project supervision information management method and system
CN108460526A (en) * 2018-02-24 2018-08-28 浙江华诚工程管理有限公司 A kind of construction quality supervision method and system in project supervision

Similar Documents

Publication Publication Date Title
CN108536770B (en) Distribution network ring net automatic generation method based on distribution GIS model
CN107292590A (en) A kind of method and device based on cloud management platform construction business approval flow
CN107682220A (en) Method for inspecting for power equipment
DE60318470D1 (en) METHOD FOR GRANTING ACCESS TO A DEVICE THROUGH A LINKING OF A FIRST CHARACTERISTIC OF A FIRST DEVICE AND A SECOND CHARACTERISTIC OF A SECOND DEVICE
ATE301483T1 (en) DEVICE FOR PLANNING AN INFUSION
CN106803165A (en) Using the method for task tree schema synergetic office work
CN102938109B (en) Grid power blackout method of combination and device
CN105023117A (en) Electrified detection standardized operation management system based on mobile and cloud computing technologies
CN106373351A (en) Elevator maintenance system
CN106991140A (en) monitoring information table checking method and system
CN111861180A (en) Management system for real-time early warning of digital energy production and manufacturing
WO2014040488A1 (en) Method and device for guaranteeing consistency of planning data
CA2389274A1 (en) Apparatus and method for performance and fault data analysis
CN109872030A (en) A kind of management management method suitable for construction project
CN109102245A (en) A kind of processing method of approval process, system and device
CN107885850A (en) A kind of localization method and device of banking class problem
CN107844369A (en) A kind of method that big data transformation task cutting is realized in task based access control scheduling
CN109272249A (en) A kind of platform area line loss defect elimination method based on platform area identifier
CN110288247A (en) Product quality analysis system and method
CN109144551A (en) Equipment firmware update and system under a kind of multi-layer networking mode
CN111640493B (en) Automatic scheduling method for operation notice based on bubbling algorithm
CN106204786A (en) Operating condition of transformer station equipment one key inspection method
CN100547624C (en) The method of a kind of remote monitoring working-yard operation
CN103607715B (en) A kind of method and device of frequency configuration
CN109528195A (en) In a kind of MRI/CT image bone boundary and method for distinguishing is known with reference to bone mark object

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190611