A kind of method of Fast Installation log cabin
Technical field
The invention belongs to build integrated assembled type modular construction field, and in particular to a kind of side of Fast Installation log cabin
Method.
Background technology
What the country generally used is all the house of reinforced concrete structure at present, and this house construction period is long, when construction
A large amount of building waste is generated, especially when business building is developed in urban road both sides, the period is longer to bring long-term traffic
Gather around wall.Certainly, at part building site and workshop, also there is the utilization in integrated house, the house built using materials such as color steel tiles,
Neither antidetonation, also not sound-insulating and heat-insulating, may be only available for requiring on lower building site and workshop, cannot promote and answer in house
With.
Log cabin is global leisure, household main product.Its design-build has evolved to a high level.Wood
Room is beautiful using lines, and the soft pine of color and luster is built, and feature is cool in summer and warm in winter, and moisturizing is heat-insulated.Light-duty wooden is because of its wood knot
On the plank base of structure outer, it is abundant outer vertical that different ornament materials can be used in the characteristics of structure, internal structure flexible arrangement
Face;For the indoor design of log cabin with natural health, comfortable use is principle;Various family is considered in Rational function division, carefulness
Structure is suitble to different age people to live, can meet the individual needs of developer's a variety of design styles and consumer.
Currently, the construction of log cabin is primarily limited to the problem of dismounting.The structure of domestic and international log cabin mostly uses greatly round log or rule
Then log cabin collar tie beam, column are bound connect one by one by lattice material as collar tie beam, column and skeleton by steel nail, screw, rivet etc.
Wooden house framework is formed, process of binding needs artificial position one by one to carry out, this often takes considerable time and manpower.The wood bound
Room is high to the positioning requirements of flitch or round log, once careless manipulation easily generate positioning it is crooked so that the log cabin knot after binding
Structure is unstable, and discontinuity easily has security risk.This, to the more demanding of operator, to need Expenses Cost culture
Professional, cost are higher.Furthermore the log cabin bound can only be carried integrally or be removed after thoroughly dismantling log cabin when needing mobile
It transports to appointed place and binds flitch one by one again again, but in order to make log cabin structure more securely often in nail when log cabin is bound
Upper setting hangnail or smearing fastening agent make nail be firmly fixed in flitch, this to generally require to destroy flitch in dismounting
Connecting portion could complete so that disassembly process needs to expend a large amount of manpowers and time, and time cost is high, very not side
Just.
But the installation that above-mentioned log cabin structure can be now solved there is presently no preferable mounting structure and installation method is difficult
Topic.
Invention content
The purpose of the present invention is to provide a kind of methods of Fast Installation log cabin can be fast using modularization assemble mode
Speed Pinyin fills to form whole frame stressing structure, simple to operate.
In order to achieve the above objectives, the technical scheme is that:A kind of method of Fast Installation log cabin, including following installation
Step:
The first step buries multiple Pseudobulbus Bletillae (Rhizoma Bletillae)s at infield, Pseudobulbus Bletillae (Rhizoma Bletillae) is adjusted horizontal;
Second step installs ground beam on Pseudobulbus Bletillae (Rhizoma Bletillae) so that ground beam is in horizontality, the ground beam by connector and
Intubation grafting forms;
Third walks, and column is installed in ground beam, crossbeam is installed on column so that ground beam, column and crossbeam are formed
Integral frame structure;
4th step, mounting base and wallboard in integral frame structure;
5th step, installs roof in integral frame structure.
When using above-mentioned technical proposal, entire log cabin uses modular mounting means, is carried out in the factory to module pre-
System processing, transports to infield later, builds log cabin in such a way that multiple modules are assembled, greatly improves the construction of log cabin
Efficiency.Specifically, connector and intubation are assembled into ground beam on Pseudobulbus Bletillae (Rhizoma Bletillae), recycle vertical reserved at ground beam top connection
Column is plugged on the connector of ground beam by connector, then crossbeam is also secured on column by other connector so that geosphere
The frame structure of beam, column and the integral stress of crossbeam shape.Due to being installed by the way of connector and intubation grafting, make
Obtain quick and easy for installation, the accurate positioning when forming frame structure, the connector that need not substantially assist.Along with connector and
Intubation is all hollow-core construction, and weight is smaller, carries and installs convenient for artificial, the requirement to muscle power is smaller.Furthermore by bottom plate and wall
Prefabricated modular structure is also made in plate, directly scene integral installation, and modular bottom plate and wallboard are directly installed on whole frame
In frame structure, using modes such as clampings, bottom plate and wallboard can also be fixed in integral frame structure by connection assist,
So that forming a complete room body.Finally, roof is installed on it, roof is also to use frame and prefabricated roofing template knot
Structure, the frame and integral frame structure on roof are connected, and roofing template also uses similar bottom plate and wall with the frame on roof
The mode that plate is connect with integral frame structure.When mounted, due to being assembled using single function module, wood is being built
Each function module need to only be carried out to simple positioning assembly when room can build up log cabin.It is individually fixed to be carried out to flitch
It position and binds, saves a large amount of time, construction efficiency is high.Even if assembled between a small number of function modules generate Form and position error
It will be substantially less that the Form and position error that generation is bound by flitch so that the structure of whole log cabin is more stablized.In addition, dismounting is also simpler
Single, the time needed for disassembly process also will substantially shorten, and can realize the fast mounting-dismounting of log cabin, the module after dismounting is also convenient for removing
Fortune.During the installation process, used material is reusable, to primitive environment no pollution.The material and facility depth of installation
Integrated, zero finishing is moved in.Installation period is extremely short, and handling are simple, installation effectiveness multiplication.It is produced using unified modular design, just
It is replaced in handling and individual event.It is more convenient, time saving and energy saving to disassemble and install log cabin, can realize being rapidly assembled and disassembled for log cabin.
It is further improved scheme, the connector in the second step includes three-way connection, the three-way connection point T-shaped three
Pass joint and right angle trigonometry connector.By three-way connection point T-shaped three-way connection and right angle trigonometry connector, different location can adapt to
Installation requirements, such as T shape three-way connections be used for stage casing position, and right angle trigonometry connector be used for corner installation site
On.
It is further improved scheme, in the 5th step, tile is fixed with by way of nailing or stickup on roof.It can be with
Tile is produced by the way of integral prefabricated, tile is integrally attached on roof, solves overlap joint tile institute one by one
The longer set-up time brought.
Be further improved scheme, in the 4th step, be integrated in the wallboard waterproof layer, insulating layer, thermal insulation layer and every
Sound-absorbing layer.Waterproof layer, insulating layer, thermal insulation layer and puigging are integrated in wallboard, there is no need to individually be installed again when mounted
It is convenient and efficient with processing.
It is further improved scheme, circuit and connection card are integrated in the intubation.Be integrated in intubation circuit and
Connection card avoids the step of cabling after mounting and wiring, can settle at one go, simplifies installation procedure, and have
Better safety and aesthetics.
Same improvement project, in the 4th step, wallboard includes shingle nail, window panel and door face board, the window face
It is integrated with window on plate, door, the shingle nail, window panel and door face board modulus having the same are integrated on the door face board.
The setting makes shingle nail, window panel and door face board that can have interchangeability, can arbitrarily arrange in pairs or groups, can also pacify when mounted
Do not have to the sequence and the position that deliberately pay attention to installation in dress, avoids the problem that because needing to dismount again after installation site mistake proofing.
It is further improved scheme, in the 4th step, is mounted between two columns from inside to outside when wallboard is installed, it is described
Strip is installed between two adjacent metopes.Installation between wallboard and column can be improved using mounting means from inside to outside
Bonding strength, and active force can be acted on column after mounting, it is kept away when leaning on wallboard or from interior collision wallboard
That has exempted from wallboard is stressed directly damage.
Same improvement project is integrated with wind power generation plant on the roof;Electric heating wire, institute are equipped in the wallboard
Electric heating wire is stated to electrically connect with wind power generation plant.By integrating wind power generation plant on roof, it can utilize and scrape roof
Wind-force, rotation wind power generation plant generate electricity, in addition, power generation is supplied to electric heating wire, make its power generation.Specifically,
Violent storm day, wallboard inevitably get wet, and in order to avoid wallboard makes moist, using wind-power electricity generation, are heated to wallboard, it is made to keep dry
It is dry.
It is further improved scheme, is equipped with water collection chamber in the wallboard, the roof is equipped with ponding mouth, on the roof
Ponding mouth is connected with the water collection chamber in wallboard, and the wallboard is equipped with the drain valve being connected to water collection chamber.Pass through ponding mouth, energy
It enough will be in the rainwater-collecting to water collection chamber on rainy day so that there is one layer of aquifer in wallboard.Guarantor can be played by aquifer
Warm, heat-insulated and sound insulation effect, that is, be utilized natural rainwater, while also having reached preferable technique effect.Furthermore pass through row
Rainwater therein can be discharged in water valve as needed, and rainwater is avoided to overstock too long.
It is further improved scheme, air bag is equipped in the wallboard, the wallboard is equipped with the inflating port being connected to air bag.If
Set gas
Capsule can make it play heat preservation, heat-insulated and sound insulation by airbag aeration, using the gas filled-in panel of high pressure
Effect.Furthermore more spaces in wallboard can be occupied after air bag expansion, while also having preferable support effect to wallboard, such as
There is ponding in fruit wallboard, can be squeezed out ponding therein by air bag.
Specific implementation mode
Embodiment 1
A kind of method of Fast Installation log cabin, including following installation steps:
The first step buries multiple Pseudobulbus Bletillae (Rhizoma Bletillae)s at infield, Pseudobulbus Bletillae (Rhizoma Bletillae) is adjusted horizontal;
Second step installs ground beam on Pseudobulbus Bletillae (Rhizoma Bletillae) so that ground beam is in horizontality, and ground beam is by connector and intubation
Grafting forms;Its center tap is largely three-way connection, and three-way connection is largely divided into T shapes three-way connection and right angle trigonometry connector.T
Shape three-way connection can be used on the position in stage casing, and right angle trigonometry connector is used for the installation site of corner.
Third walks, and column is installed in ground beam, crossbeam is installed on column so that ground beam, column and crossbeam are formed
Integral frame structure;
4th step, mounting base and wallboard in integral frame structure;Two are mounted on from inside to outside when wallboard is installed to stand
Between column, strip is installed between two adjacent metopes.Wallboard and column can be improved using mounting means from inside to outside
Between installation bonding strength, and active force can be acted on column after mounting, lean on wallboard or touched from interior
Wallboard is avoided when hitting wallboard is stressed directly damage.
5th step, installs roof in integral frame structure.It is fixed with tile by way of nailing or stickup on roof,
Can also on roof integrated installation solar panels.
In addition, wall module includes exterior trim panel and inner veneer, it is integrated with waterproof layer between exterior trim panel and interior facing, protects
Warm layer, thermal insulation layer and puigging.Waterproof layer, insulating layer, thermal insulation layer and puigging are integrated in wallboard, when mounted there is no need to
Individually is installed and handled again, it is convenient and efficient.In addition, being also integrated with circuit and connection card in wallboard.In wallboard
In be integrated with circuit and the step of connection card avoids cabling after mounting and wiring, can settle at one go, simplify peace
Program is filled, and there is better safety and aesthetics.
Furthermore wallboard includes shingle nail, window panel and door face board, it is integrated with window on window panel, is integrated on door face board
There are door, shingle nail, window panel and door face board modulus having the same.The setting makes shingle nail, and window panel and door face board can
It with interchangeability, can arbitrarily arrange in pairs or groups when mounted, the sequence and the position that deliberately pay attention to installation can also not had in an installation, kept away
Exempt from because of the problem of needing to dismount again after installation site mistake proofing.
By the way that Pseudobulbus Bletillae (Rhizoma Bletillae) is arranged, certain height of foundation is formed between bottom plate and ground, plays the work of insect prevention and waterproof
With.For hollow tubing as column etc., inner cavity can be as the pipe space that pipeline passes through.
Wind power generation plant is integrated on roof;Electric heating wire, electric heating wire and wind power generation plant electricity are equipped in wallboard
Connection.By integrating wind power generation plant on roof, the wind-force for scraping roof, rotation wind power generation plant can be utilized to carry out
Power generation, in addition, power generation is supplied to electric heating wire, makes its power generation.Specifically, in violent storm day, wallboard inevitably gets wet, in order to
It avoids wallboard from making moist, using wind-power electricity generation, wallboard is heated, it is made to keep drying.
Embodiment 2
A kind of method of Fast Installation log cabin, including following installation steps:
The first step buries multiple Pseudobulbus Bletillae (Rhizoma Bletillae)s at infield, Pseudobulbus Bletillae (Rhizoma Bletillae) is adjusted horizontal;
Second step installs ground beam on Pseudobulbus Bletillae (Rhizoma Bletillae) so that ground beam is in horizontality, and ground beam is by connector and intubation
Grafting forms;Its center tap is largely three-way connection, and three-way connection is largely divided into T shapes three-way connection and right angle trigonometry connector.T
Shape three-way connection can be used on the position in stage casing, and right angle trigonometry connector is used for the installation site of corner.
Third walks, and column is installed in ground beam, crossbeam is installed on column so that ground beam, column and crossbeam are formed
Integral frame structure;
4th step, mounting base and wallboard in integral frame structure;Two are mounted on from inside to outside when wallboard is installed to stand
Between column, strip is installed between two adjacent metopes.Wallboard and column can be improved using mounting means from inside to outside
Between installation bonding strength, and active force can be acted on column after mounting, lean on wallboard or touched from interior
Wallboard is avoided when hitting wallboard is stressed directly damage.
5th step, installs roof in integral frame structure.It is fixed with tile by way of nailing or stickup on roof,
Can also on roof integrated installation solar panels.
In addition, wall module includes exterior trim panel and inner veneer, it is integrated with waterproof layer between exterior trim panel and interior facing, protects
Warm layer, thermal insulation layer and puigging.Waterproof layer, insulating layer, thermal insulation layer and puigging are integrated in wallboard, when mounted there is no need to
Individually is installed and handled again, it is convenient and efficient.In addition, being also integrated with circuit and connection card in wallboard.In wallboard
In be integrated with circuit and the step of connection card avoids cabling after mounting and wiring, can settle at one go, simplify peace
Program is filled, and there is better safety and aesthetics.
Furthermore wallboard includes shingle nail, window panel and door face board, it is integrated with window on window panel, is integrated on door face board
There are door, shingle nail, window panel and door face board modulus having the same.The setting makes shingle nail, and window panel and door face board can
It with interchangeability, can arbitrarily arrange in pairs or groups when mounted, the sequence and the position that deliberately pay attention to installation can also not had in an installation, kept away
Exempt from because of the problem of needing to dismount again after installation site mistake proofing.
By the way that Pseudobulbus Bletillae (Rhizoma Bletillae) is arranged, certain height of foundation is formed between bottom plate and ground, plays the work of insect prevention and waterproof
With.For hollow tubing as column etc., inner cavity can be as the pipe space that pipeline passes through.
Water collection chamber is equipped in wallboard, roof is equipped with ponding mouth, and the ponding mouth on roof is connected with the water collection chamber in wallboard
Logical, wallboard is equipped with the drain valve being connected to water collection chamber.It, can be by the rainwater-collecting on rainy day to water collection chamber by ponding mouth
In so that there is one layer of aquifer in wallboard.It can play the role of heat preservation, heat-insulated and sound insulation by aquifer, that is, be utilized
Natural rainwater, while also having reached preferable technique effect.Furthermore rain therein can be discharged by drain valve as needed
Water avoids rainwater from overstocking too long.
Embodiment 3
A kind of method of Fast Installation log cabin, including following installation steps:
The first step buries multiple Pseudobulbus Bletillae (Rhizoma Bletillae)s at infield, Pseudobulbus Bletillae (Rhizoma Bletillae) is adjusted horizontal;
Second step installs ground beam on Pseudobulbus Bletillae (Rhizoma Bletillae) so that ground beam is in horizontality, and ground beam is by connector and intubation
Grafting forms;Its center tap is largely three-way connection, and three-way connection is largely divided into T shapes three-way connection and right angle trigonometry connector.T
Shape three-way connection can be used on the position in stage casing, and right angle trigonometry connector is used for the installation site of corner.
Third walks, and column is installed in ground beam, crossbeam is installed on column so that ground beam, column and crossbeam are formed
Integral frame structure;
4th step, mounting base and wallboard in integral frame structure;Two are mounted on from inside to outside when wallboard is installed to stand
Between column, strip is installed between two adjacent metopes.Wallboard and column can be improved using mounting means from inside to outside
Between installation bonding strength, and active force can be acted on column after mounting, lean on wallboard or touched from interior
Wallboard is avoided when hitting wallboard is stressed directly damage.
5th step, installs roof in integral frame structure.It is fixed with tile by way of nailing or stickup on roof,
Can also on roof integrated installation solar panels.
In addition, wall module includes exterior trim panel and inner veneer, it is integrated with waterproof layer between exterior trim panel and interior facing, protects
Warm layer, thermal insulation layer and puigging.Waterproof layer, insulating layer, thermal insulation layer and puigging are integrated in wallboard, when mounted there is no need to
Individually is installed and handled again, it is convenient and efficient.In addition, being also integrated with circuit and connection card in wallboard.In wallboard
In be integrated with circuit and the step of connection card avoids cabling after mounting and wiring, can settle at one go, simplify peace
Program is filled, and there is better safety and aesthetics.
Furthermore wallboard includes shingle nail, window panel and door face board, it is integrated with window on window panel, is integrated on door face board
There are door, shingle nail, window panel and door face board modulus having the same.The setting makes shingle nail, and window panel and door face board can
It with interchangeability, can arbitrarily arrange in pairs or groups when mounted, the sequence and the position that deliberately pay attention to installation can also not had in an installation, kept away
Exempt from because of the problem of needing to dismount again after installation site mistake proofing.
By the way that Pseudobulbus Bletillae (Rhizoma Bletillae) is arranged, certain height of foundation is formed between bottom plate and ground, plays the work of insect prevention and waterproof
With.For hollow tubing as column etc., inner cavity can be as the pipe space that pipeline passes through.
Water collection chamber is equipped in wallboard, roof is equipped with ponding mouth, and the ponding mouth on roof is connected with the water collection chamber in wallboard
Logical, wallboard is equipped with the drain valve being connected to water collection chamber.It, can be by the rainwater-collecting on rainy day to water collection chamber by ponding mouth
In so that there is one layer of aquifer in wallboard.In addition, being equipped with air bag in the water collection chamber of wallboard, wallboard is equipped with to be connected with air bag
Logical inflating port.Air bag is set, it can be made to play heat preservation, heat-insulated by airbag aeration, using the gas filled-in panel of high pressure
With the effect of sound insulation.Furthermore more spaces in wallboard can be occupied after air bag expansion, while also having preferable support to wallboard
Effect can be squeezed out ponding therein by air bag if there is ponding in wallboard.
What has been described above is only a preferred embodiment of the present invention, it is noted that for those skilled in the art,
Without departing from the inventive concept of the premise, several modifications and improvements can also be made, these should also be considered as the guarantor of the present invention
Range is protected, these all do not interfere with the effect and patent practicability that the present invention is implemented.The present invention omits the technology of description, shape
Shape, construction part are known technology.