CN105862901B - Docking formula bedrock survey mark and its construction method - Google Patents

Docking formula bedrock survey mark and its construction method Download PDF

Info

Publication number
CN105862901B
CN105862901B CN201610380955.3A CN201610380955A CN105862901B CN 105862901 B CN105862901 B CN 105862901B CN 201610380955 A CN201610380955 A CN 201610380955A CN 105862901 B CN105862901 B CN 105862901B
Authority
CN
China
Prior art keywords
mark
measurement
bedrock
hidden
basement rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610380955.3A
Other languages
Chinese (zh)
Other versions
CN105862901A (en
Inventor
朱祥山
于松松
邵成立
刘建英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO INSTITUTE OF SURVEYING AND MAPPING SURVEY
Original Assignee
QINGDAO INSTITUTE OF SURVEYING AND MAPPING SURVEY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO INSTITUTE OF SURVEYING AND MAPPING SURVEY filed Critical QINGDAO INSTITUTE OF SURVEYING AND MAPPING SURVEY
Priority to CN201610380955.3A priority Critical patent/CN105862901B/en
Publication of CN105862901A publication Critical patent/CN105862901A/en
Application granted granted Critical
Publication of CN105862901B publication Critical patent/CN105862901B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • G01C15/02Means for marking measuring points
    • G01C15/06Surveyors' staffs; Movable markers
    • G01C15/08Plumbing or registering staffs or markers over ground marks

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Force Measurement Appropriate To Specific Purposes (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to measurement to indicate, especially dock formula bedrock survey mark and its construction method.Docking formula bedrock survey mark, is mainly made of basement rock stake, measurement mark, land protection device three parts;The measurement mark is divided into two parts up and down, is respectively visual observation mark and hidden observation monument, both are connected by connecting screw, and on same plumb line;The lower end of hidden observation monument is connected by nut with basement rock stake;Land protection device is arranged on the outside of visual observation mark.The docking formula bedrock survey mark of the present invention, basement rock stake can guarantee that mark stability, will not be settled with ground;Measurement indicates and is divided into the visual measurement mark and the hidden measurement mark of lower part on top, and remain stringent geometrical relationship between upper and lower mark can guarantee that the fast quick-recovery after a position destruction.And construction method is simple.

Description

Docking formula bedrock survey mark and its construction method
Technical field
The present invention relates to measurement to indicate, especially dock formula bedrock survey mark and its construction method.
Background technology
Current measurement control point is broadly divided into several classes, the first is grade control point, is coagulation more using survey monument The hard building stones such as soil or granite, green stone are made.Second is non-hierarchical control point, generally uses steel nail or the iron with copper core Nail, directly nail is on road surface.Survey monument is generally divided into markstone and lower markstone, and upper and lower markstone center is strictly in same plumb line On,(Also some survey monuments are concrete structure, in concrete top installation stainless steel measurement mark), such markstone is usually Face occupation of land scope is larger, is adapted to be laid in more open area(Such as mountain top, wasteland).Steel nail control point is generally laid in Road road surface, but it is easily destroyed, and the phenomenon with roadbed subsidence occurs, it is impossible to meet the purpose of long-time service.
The fast development of modern city, causes ground control point easily destroyed, and can not recover.And in coastal cities Xincheng District, easily there is sedimentation phenomenon, cause to lay on the ground more in beach area, newly-built road and greenbelt in establish Control point can not long-time service.
The content of the invention
A kind of it is adapted to be laid in road or greenbelt, it is necessary to develop to overcome problem above existing in the prior art Measurement mark, passes through the special designing of mark itself, and advanced construction method, it is ensured that control point is from surface subsidence shadow Ring, and after being destroyed on ground still can quick-recovery soon high-precision measurement mark, to reduce workload and cost of investment Measurement mark.
The present invention solves the technical solution that its technical problem uses:Docking formula bedrock survey mark, mainly by basement rock stake, Measurement mark, land protection device three parts composition;The measurement mark is divided into two parts up and down, is respectively visual observation mark Will and hidden observation monument, both are connected by connecting screw, and on same plumb line;The lower end of hidden observation monument It is connected by nut with basement rock stake;Land protection device is arranged on the outside of visual observation mark.
The basement rock stake is made of the screw-thread steel positioned at center and the exterior cement mortar poured, screw-thread steel it is upper End is welded with attaching nut.
The outside of the hidden observation monument is equipped with stainless steel pile casting.
The land protection device is to build well or cast iron sheath by laying bricks or stones.
The construction method of the docking formula bedrock survey mark of the present invention, comprises the following steps:1st, it is not small that the length of side is excavated first In 0.5 meter, the square hole of 0.9 meter of depth, drilling then is carried out using drilling machine, drilling depth is to reach below stable basement rock Subject to 2m;
2nd, attaching nut is welded on screw-thread steel, ensures that attaching nut and reinforcing bar are concentric;
3rd, reinforcing bar is vertically put into drilling using drilling machine, and keeps vertical;
4th, using drilling machine cement injection mortar from the bottom up, residual mud in extrusion drilling;
5th, after the cement mortar solidification irrigated, the unnecessary cement mortar in top is cleared up, measurement mark is installed on base In rock stake;
6th, after measurement mark installs, concrete, fine sand to basement rock stake and hidden measurement mark is filled successively in hole and is connected Meet place;Concrete, fine sand to hidden measurement mark indicate junction, concrete with visual measurement;Land protection dress is finally installed Put.
The docking formula bedrock survey mark of the present invention, basement rock stake can guarantee that mark stability, will not be settled with ground;Survey Amount mark is divided into the visual measurement mark on top and the hidden measurement mark of lower part again, remains between upper and lower mark stringent Geometrical relationship can guarantee that the fast quick-recovery after a position destruction.And construction method is simple.
Brief description of the drawings
Fig. 1 is the docking formula bedrock survey sign structure schematic diagram of embodiment 1;
Fig. 2 is the docking formula bedrock survey sign structure schematic diagram of embodiment 2.
Embodiment
The docking formula bedrock survey mark and its construction method of the present invention are done with reference to embodiment and attached drawing detailed Illustrate and illustrate.
The docking formula bedrock survey mark of 1 the present embodiment of embodiment, as shown in Figure 1, by basement rock stake 1, stainless steel pile casting 2, Hidden observation monument 3, visual observation mark 4, cast iron sheath 6 form, and hidden observation monument 3 and visual observation mark 4 pass through company Screw rod 5 is connect to connect, and on same plumb line;The lower end of hidden observation monument 3 is connected by nut with basement rock stake 1;Can Depending on the outside installation cast iron sheath 6 of observation monument 4.
The docking formula bedrock survey mark of 2 the present embodiment of embodiment, as shown in Fig. 2, by basement rock stake 1, stainless steel pile casting 2, Hidden observation monument 3, visual observation mark 4, build well 6 by laying bricks or stones and form, and hidden observation monument 3 and visual observation mark 4 pass through connection Screw rod 5 connects, and on same plumb line;The lower end of hidden observation monument 3 is connected by nut with basement rock stake 1;Visually Well 6 is built in the outside installation of observation monument 4 by laying bricks or stones.
Basement rock stake 1 is mainly by exterior 1:2 #425 cement mortar and internal φ 28mm screw-thread steels composition, basement rock stake are deep Degree is subject into middle 2 meters of decayed rock.The geological conditions basement rock stake depth of integration project location is between 3 meters to 25 meters. The a diameter of 180mm of basement rock stake, screw-thread steel applies antirust paint and plastic protective film for plastics outside, and fills a triangle centering every 2 meter amperes Stent, to ensure that screw-thread steel is in the center of whole basement rock stake.
Visual observation mark 4 is with ground at a distance of 20CM.The outside of hidden observation monument 3 is equipped with stainless steel pile casting 2, make its with Surrounding concrete separates.When visual observation mark is influenced by external force and when producing displacement, visual observation mark will be forced with The hidden observation monument in face disconnects at connecting screw, since the visual measurement landmark size on top is fixed, so when upper When portion's visual observation mark destroys, it can be repaired by reinstalling visual observation mark, also can be by opposite even if not repairing Position is continuing with the hidden observation monument in lower part.Hidden observation monument is connected by attaching nut with basement rock stake at the same time, hidden Observation monument is separated with outer concrete using stainless steel pile casting, therefore when external force is not very big, hidden base will not be corrupted to Rock point.When hidden observation monument part is also destroyed, can also be repaiied according to by reinstalling whole docking protection basement rock mark Multiple control point point position obtains the coordinate of the basement rock stake of lower part according to the fixed dimension of mark.
According to a position position, land protection device, which can be divided into, builds two kinds of well and cast iron sheath by laying bricks or stones.Greenbelt is open The land protection device in non-hard surface area is adapted to selection to build well by laying bricks or stones;The hardened grounds such as bituminous paving are adapted to protect using cast iron Set.
The construction method of the docking formula bedrock survey mark of the present invention of embodiment 3, comprises the following steps that:
1st, the length of side is excavated first and be not less than 0.5 meter, the square hole of 0.9 meter of depth, to have detected whether unknown object(Pipeline Or pre-buried cable etc.), drilling is carried out followed by drilling machine, drilling depth, which is subject to, reaches 2m below stable basement rock;Probing In pore forming process, using the advanced guide type drill bits of φ 180mm using drilling tool dead weight hole-enlarging hole-forming, and low solid phase premium mud is used Retaining wall, ensures drilling safety and prevents borehole collapse and undergauge;Following measures are taken in the control of basement rock hole perpendicularity:Ground should be put down Whole, compacting, it is ensured that boring tower, drilling machine vertical shaft center and aperture sight alignment;Drilling rod, drilling tool should keep glacing flatness, and curvature is small;Adopt Crept into lengthening drilling tool, going out the small drill bit of sword, light pressure, small pump amount;Using low solid phase premium mud guard aperture, borehole cleaning, ensure bottom hole Basement rock powder exclude in time it is clean, to prevent major structure into hole deviation.
2nd, attaching nut is welded on the screw-thread steel of φ 28mm, intercepts or be soldered to corresponding length according to drilling depth, To ensure that chain connected nut is strictly concentric with reinforcing bar in manufacturing process.2 meters of need of reinforcing bar bottommost are fixed in basement rock, thereon part profit Antirust treatment is done with epoxy resin and winds plastic film, while protects top connection bolt.Reinforcing bar puts one every 2 meter amperes Triangle centering fixing bracket, in the center entirely to drill during for determining that reinforcing bar enters hole.
3rd, reinforcing bar is vertically put into drilling using drilling machine, makes to fix after whole device is naturally vertical, so can ensure that It keeps vertical at the center entirely to drill.
4th, 1 is irrigated from the bottom up using drilling machine:2 #425 cement mortar, residual mud in extrusion drilling.
5th, after the cement mortar solidification irrigated, the unnecessary cement mortar in top is cleared up, passes through the connection spiral shell on reinforcing bar It is female to be connected with hidden measurement mark lower end, measurement mark is installed in basement rock stake.
6th, after mark installs, concrete, fine sand to basement rock stake and hidden measurement is filled successively in hole and indicates junction; Concrete, fine sand to hidden measurement mark indicate junction, concrete with visual measurement;Finally build protection well or installation cast iron by laying bricks or stones Sheath.

Claims (3)

1. a kind of construction method of docking formula bedrock survey mark, it is characterised in that the docking formula bedrock survey mark is main It is made of basement rock stake, measurement mark, land protection device three parts;The measurement mark is divided into two parts up and down, is respectively Visual observation mark and hidden observation monument, both are connected by connecting screw, and on same plumb line;Hidden observation The lower end of mark is connected by nut with basement rock stake;Land protection device is arranged on the outside of visual observation mark;The base Rock stake is mainly made of the screw-thread steel positioned at center and the exterior cement mortar poured, and the upper end of screw-thread steel is welded with connection Nut;Partly antirust treatment being done using epoxy resin on the screw-thread steel and winding plastic film, screw-thread steel puts one every 2 meter amperes A triangle centering fixing bracket;
Its construction method comprises the following steps:
(1), the length of side is excavated first and be not less than 0.5 meter, the square hole of 0.9 meter of depth, then carry out drilling using drilling machine, bore Hole depth, which is subject to, reaches 2m below stable basement rock;
(2), attaching nut is welded on screw-thread steel, ensures that attaching nut and reinforcing bar are concentric;
(3), reinforcing bar is vertically put into drilling using drilling machine, and keeps vertical;
(4), using drilling machine cement injection mortar from the bottom up, residual mud in extrusion drilling;
(5), after the cement mortar solidification irrigated, the unnecessary cement mortar in top is cleared up, measurement mark is installed on basement rock In stake;
(6), after measurement mark installs, concrete, fine sand to basement rock stake and hidden measurement mark connection are filled successively in hole Place;Concrete, fine sand to hidden measurement mark indicate junction, concrete with visual measurement;Land protection device is finally installed.
2. the construction method of docking formula bedrock survey mark according to claim 1, it is characterised in that:The hidden sight The outside of mark will is equipped with stainless steel pile casting.
3. the construction method of docking formula bedrock survey mark according to claim 1 or 2, it is characterised in that:The ground Face protective device is to build well or cast iron sheath by laying bricks or stones.
CN201610380955.3A 2016-06-01 2016-06-01 Docking formula bedrock survey mark and its construction method Active CN105862901B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610380955.3A CN105862901B (en) 2016-06-01 2016-06-01 Docking formula bedrock survey mark and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610380955.3A CN105862901B (en) 2016-06-01 2016-06-01 Docking formula bedrock survey mark and its construction method

Publications (2)

Publication Number Publication Date
CN105862901A CN105862901A (en) 2016-08-17
CN105862901B true CN105862901B (en) 2018-04-20

Family

ID=56675611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610380955.3A Active CN105862901B (en) 2016-06-01 2016-06-01 Docking formula bedrock survey mark and its construction method

Country Status (1)

Country Link
CN (1) CN105862901B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108955660B (en) * 2018-04-18 2020-12-15 深圳市路桥建设集团有限公司 Deviation detection method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101397800A (en) * 2008-09-17 2009-04-01 中冶集团武汉勘察研究院有限公司 Deep pile survey mark burying method
CN201233240Y (en) * 2008-07-31 2009-05-06 中冶集团武汉勘察研究院有限公司 Device for protecting survey mark
CN202485681U (en) * 2012-03-21 2012-10-10 中铁上海设计院集团有限公司 Survey marker for subway horizontal control point
CN104121895A (en) * 2013-04-28 2014-10-29 上海勘测设计研究院 Soft soil area plane height measurement control point and embedding method thereof
CN203964915U (en) * 2014-07-14 2014-11-26 深圳市勘察研究院有限公司 A kind of survey mark of the underground space
CN205776301U (en) * 2016-06-01 2016-12-07 青岛市勘察测绘研究院 Docking formula bedrock survey mark

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201233240Y (en) * 2008-07-31 2009-05-06 中冶集团武汉勘察研究院有限公司 Device for protecting survey mark
CN101397800A (en) * 2008-09-17 2009-04-01 中冶集团武汉勘察研究院有限公司 Deep pile survey mark burying method
CN202485681U (en) * 2012-03-21 2012-10-10 中铁上海设计院集团有限公司 Survey marker for subway horizontal control point
CN104121895A (en) * 2013-04-28 2014-10-29 上海勘测设计研究院 Soft soil area plane height measurement control point and embedding method thereof
CN203964915U (en) * 2014-07-14 2014-11-26 深圳市勘察研究院有限公司 A kind of survey mark of the underground space
CN205776301U (en) * 2016-06-01 2016-12-07 青岛市勘察测绘研究院 Docking formula bedrock survey mark

Also Published As

Publication number Publication date
CN105862901A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN103088814A (en) Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN108951612A (en) A kind of subway tunnel shield end reinforcement means
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN104631470A (en) Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN102943466A (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN112663600A (en) Construction method of cast-in-situ bored pile for water-rich sandy stratum
CN104121895B (en) The stake bar at plane measurement of higher degree control point, soft clay area and method for embedding thereof
CN102628266A (en) Construction method of long spiral cast-in-situ bored pile
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN106677168A (en) Construction method of cast-in-place superfluid concrete pile
CN106988305A (en) A kind of pile-column pier construction method of underground integrated molding
CN102494678A (en) Pavement settlement point arrangement apparatus in monitor measurement and burying method
CN102304915B (en) New method for controlling top quality of drilled pile
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN105862901B (en) Docking formula bedrock survey mark and its construction method
CN202925575U (en) Pre-buried structure for core-drilling detection of foundation pile
CN113338356A (en) Anti-floating anchor rod construction structure and construction method thereof
CN205776301U (en) Docking formula bedrock survey mark
CN203274729U (en) Soft soil area horizontal elevation measuring control point
CN103643674B (en) Erect column pile construction method under geologic condition of pebble bed sandstone
CN110714459A (en) Construction method of cast-in-situ bored pile
CN113174991B (en) Pile periphery stratum collapse grouting reinforcement method for ocean deepwater inclined piles
CN114687345A (en) Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant