CN114687345A - Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall - Google Patents

Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall Download PDF

Info

Publication number
CN114687345A
CN114687345A CN202210459961.3A CN202210459961A CN114687345A CN 114687345 A CN114687345 A CN 114687345A CN 202210459961 A CN202210459961 A CN 202210459961A CN 114687345 A CN114687345 A CN 114687345A
Authority
CN
China
Prior art keywords
foundation pit
grouting
pipe
horizontal
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210459961.3A
Other languages
Chinese (zh)
Inventor
胡帅峰
成怡冲
吴才德
龚迪快
王洁栋
安然
曾婕
沈俊杰
叶维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN
Original Assignee
ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN filed Critical ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN
Priority to CN202210459961.3A priority Critical patent/CN114687345A/en
Publication of CN114687345A publication Critical patent/CN114687345A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种基坑围护墙外侧地表沉降或地下管变形的修复方法,包括以下施工步骤:在基坑围护墙外侧地表设多个监测点,采用监测设备适时获取基坑开挖时基坑围护墙外侧地表土体沉降值或地下管变形沉降值或地下管变形水平向移动值;根据监测值得到的需修复的高度位置、横向位置和水平向或斜向走向来确定基坑围护墙上施工孔的位置和走向;采用钻机钻出孔、置放注浆管、锚杆和沿轴向延伸的多个土工布袋、注浆使每个土工布袋注满水泥浆液并凝固后的注浆体构成一组浆囊袋以抬升基坑外侧地表下陷土体或复位变形地下管。该方法不在基坑外侧的地表上施工、注浆对地表的抬升恢复或地下管的复位针对性强且恢复或复位效果好。

Figure 202210459961

The invention discloses a method for repairing surface settlement or deformation of underground pipes on the outer side of a foundation pit enclosure wall. The settlement value of the surface soil outside the retaining wall of the foundation pit or the deformation settlement value of the underground pipe or the horizontal movement value of the deformation of the underground pipe; according to the height position, lateral position and horizontal or oblique direction to be repaired obtained from the monitoring value, the foundation is determined. The location and direction of the construction holes on the pit retaining wall; use a drilling rig to drill the holes, place grouting pipes, bolts and multiple geotextile bags extending along the axial direction, and grouting so that each geotextile bag is filled with cement slurry and solidified The latter grouting body constitutes a set of slurry pockets to lift the subsidence soil outside the foundation pit or reset the deformed underground pipe. The method does not carry out construction on the surface outside the foundation pit, and the grouting to restore the surface uplift or the reset of the underground pipe has strong pertinence and good recovery or reset effect.

Figure 202210459961

Description

基坑围护墙外侧地表沉降或地下管变形的修复方法Repair method for surface settlement or deformation of underground pipe on the outer side of retaining wall of foundation pit

技术领域technical field

本发明涉及地基加固技术领域,尤其涉及一种基坑围护墙外侧地表沉降或地下管变形的修复方法。The invention relates to the technical field of foundation reinforcement, in particular to a method for repairing surface settlement or deformation of underground pipes on the outer side of a retaining wall of a foundation pit.

背景技术Background technique

软土地区地下空间开发施工过程中,基坑内土体开挖过程一般会造成基坑围护墙或称基坑围护结构如地下连续墙或由外侧的止水帷幕加内侧的支护排桩构成的围护墙向基坑内侧位移,该位移会造成基坑外侧或称基坑围护墙外侧土体向基坑围护墙方向变形,造成地表沉降或市政工程的各种预埋的地下管变形。尤其是基坑开挖处理不当时会造成基坑围护墙变形过大,基坑围护墙向基坑内变形带动周围土体向基坑围护墙方向变形,造成地表沉降或地下管变形,甚至造成道路开裂和塌陷。During the development and construction of the underground space in the soft soil area, the soil excavation process in the foundation pit will generally cause the foundation pit retaining wall or the foundation pit retaining structure such as the underground diaphragm wall or the outer water-stop curtain and the inner supporting piles. The formed retaining wall is displaced to the inside of the foundation pit, and this displacement will cause the soil outside the foundation pit or the outer side of the foundation pit retaining wall to deform toward the foundation pit retaining wall, resulting in surface settlement or various pre-buried underground of municipal engineering. Tube deformation. In particular, improper excavation of the foundation pit will cause excessive deformation of the retaining wall of the foundation pit. Even cause road cracking and collapse.

传统处理方法是通过增加基坑围护墙的深度或增加基坑内支撑的刚度,或对基坑围护墙的底部加固,或在基坑开挖过程中采用分区分块开挖的措施对地表沉降或地下管线变形进行超前控制。但此种方式的加固与保护存在盲目性,往往投入大收益小,地表沉降或地下管变形、以致造成的道路开裂和塌陷的现象仍未能得到有效地控制,该技术问题未能得到很好地解决。The traditional treatment method is to increase the depth of the retaining wall of the foundation pit or increase the stiffness of the support in the foundation pit, or to reinforce the bottom of the retaining wall of the foundation pit, or to adopt the measures of zoning and block excavation during the excavation process of the foundation pit. Advance control of settlement or deformation of underground pipelines. However, the reinforcement and protection of this method are blind, and the investment is often large and the income is small. The cracking and collapse of the road caused by the surface settlement or the deformation of the underground pipe have not been effectively controlled, and the technical problem has not been well solved. resolved.

后有技术人员采用注浆的方法对地表沉降或地下管变形进行修复,如有的在基坑外侧的地面上采用竖向注浆或斜向注浆进行地表沉降修复,有的采用从地下管内凿孔后竖向注浆进行地下管沉降变形修复。以上现有技术基坑外地表沉降或地下管变形的注浆修复方法仍存在以下不足:由于从地表往下竖向注浆或斜向注浆,对地表的抬升恢复或地下管的变形的复位针对性不强,如对沉降或称塌陷的抬升效果不明显,需要抬升的位置可能未得到抬升,不需要抬升的位置可能又得到了抬升。又如在地下管内凿孔,给地下管产生了创口,且地下管变形的形态是复杂的,其变形不一定是在地下管的正下方。所以,该注浆方式修复即恢复或复位效果不明显,且未起到恢复或复位作用的水泥浆液占比较大,造成浆液的浪费较大,使修复成本过高。又由于该注浆是在基坑外的需修复的地表上操作,施工全程需进行交通管制,带来交通不便,且施工空间受到限制,既可能妨碍正常施工,又可能破坏地表原有路面和设施,且施工设备在需修复的地表或称地面震动,还有可能产生新的地表沉降或地下管变形。Later, some technicians used grouting to repair the surface settlement or the deformation of the underground pipe. For example, vertical grouting or oblique grouting was used to repair the surface settlement on the ground outside the foundation pit. After drilling, vertical grouting is used to repair the settlement and deformation of underground pipes. The above grouting repair methods for surface settlement or underground pipe deformation outside the foundation pit in the prior art still have the following shortcomings: due to vertical grouting or oblique grouting from the ground surface, the lifting of the surface is restored or the deformation of the underground pipe is reset. The pertinence is not strong, such as the lifting effect on settlement or collapse is not obvious, the position that needs to be lifted may not be lifted, and the position that does not need lifting may be lifted again. Another example is drilling a hole in an underground pipe, creating a wound for the underground pipe, and the deformation of the underground pipe is complicated, and the deformation is not necessarily directly below the underground pipe. Therefore, the restoration or restoration effect of this grouting method is not obvious, and the proportion of cement grout that does not play the role of restoration or restoration is relatively large, resulting in a large waste of grout and high restoration costs. In addition, since the grouting is operated on the surface to be repaired outside the foundation pit, traffic control is required throughout the construction process, which brings inconvenience to traffic, and the construction space is limited, which may not only hinder normal construction, but also damage the original road surface and surface. facilities, and the construction equipment vibrates on the surface to be repaired or ground, and new surface subsidence or underground pipe deformation may occur.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题是,提供一种不在基坑外侧的地表上施工、注浆对地表的抬升恢复或地下管的复位针对性强且恢复或复位效果好的基坑围护墙外侧地表沉降或地下管变形的修复方法。The technical problem to be solved by the present invention is to provide a surface outside the foundation pit enclosure wall that is not constructed on the ground outside the foundation pit, and that the grouting can lift the ground or restore the underground pipe with strong pertinence and good recovery or reset effect. Repair methods for settlement or deformation of underground pipes.

本发明的技术解决方案是,提供一种基坑围护墙外侧地表沉降或地下管变形的修复方法,包括以下施工步骤:The technical solution of the present invention is to provide a repair method for the surface settlement or the deformation of the underground pipe on the outer side of the retaining wall of the foundation pit, including the following construction steps:

(1)、根据预测和评估数据,在基坑围护墙中的地下连续墙上预埋一排或多排钢管,每排为多根,每根钢管呈水平状态或呈基坑内侧高基坑外侧低的斜向状态;(1) According to the prediction and evaluation data, one or more rows of steel pipes are pre-buried on the underground continuous wall in the retaining wall of the foundation pit, each row is multiple, and each steel pipe is in a horizontal state or a high foundation inside the foundation pit Low oblique state on the outside of the pit;

(2)、在基坑围护墙外侧地表沉降区域或地下管控制区域设多个监测点,监测点沿径向和纬向布置,采用监测设备适时获取基坑开挖时基坑围护墙外侧地表土体沉降值或地下管变形沉降值或地下管变形水平向移动值;(2) Set up multiple monitoring points in the surface subsidence area or the underground pipe control area outside the retaining wall of the foundation pit. The monitoring points are arranged in the radial and latitudinal directions. The monitoring equipment is used to timely obtain the retaining wall of the foundation pit when the foundation pit is excavated. The settlement value of the outer surface soil mass or the deformation settlement value of the underground pipe or the horizontal movement value of the underground pipe deformation;

(3)、根据监测值得到的需修复高度位置、横向位置和水平向或斜向走向来确定基坑围护墙上施工孔的位置和走向:地下连续墙上的第一施工孔在预埋的钢管中选,所述的第一施工孔为一排或多排,每排为多个;外侧的止水帷幕加内侧的支护排桩构成的围护墙的第二施工孔在支护排桩相邻支护桩缝隙的土体上选并标注,所述的第二施工孔为一排或多排,每排为多个,第二施工孔呈水平状态或呈基坑内侧高基坑外侧低的斜向状态;(3) Determine the position and direction of the construction hole on the retaining wall of the foundation pit according to the height position, lateral position and horizontal or oblique direction to be repaired obtained from the monitoring value: the first construction hole on the underground continuous wall is pre-buried The first construction holes are one or more rows, each row is multiple; the second construction holes of the enclosure wall formed by the outer water-stop curtain and the inner supporting row piles are in the supporting row. The soil of the gap between the supporting piles adjacent to the pile is selected and marked. The second construction holes are in one or more rows, and each row is multiple. The second construction holes are in a horizontal state or in a high foundation pit inside the foundation pit. Outer side low oblique state;

(4)、根据监测值得到的需钻孔的深度、需抬升土体的高度或需横移的距离来确定土工布袋的长度和套在土工布袋内的锚杆的长度和注浆管的长度及绑扎构成的多个土工布袋中的每个土工布袋的直径,其中注浆管留出连接注浆泵的长度,每个土工布袋对应一个或多个注浆孔;(4) Determine the length of the geotextile bag, the length of the anchor rod set in the geotextile bag and the length of the grouting pipe according to the depth of the hole to be drilled, the height of the soil to be lifted or the distance to be traversed according to the monitoring value. and the diameter of each geotextile bag in the multiple geotextile bags formed by binding, wherein the grouting pipe leaves a length for connecting the grouting pump, and each geotextile bag corresponds to one or more grouting holes;

(5)、采用钻机钻出水平向孔、置放水平向注浆管、水平向锚杆和沿轴向延伸的多个土工布袋、注浆使每个土工布袋注满水泥浆液并凝固后的注浆体构成一组水平向浆囊袋以抬升基坑外侧地表下陷土体或抬升变形地下管,所述的水平向浆囊袋为多排,每排为多组;或(5) Use a drilling rig to drill a horizontal hole, place a horizontal grouting pipe, a horizontal bolt and a plurality of geotextile bags extending along the axial direction, grouting so that each geotextile bag is filled with cement slurry and solidified. The grouting body forms a group of horizontal slurry pockets to lift the subsidence soil outside the foundation pit or lift the deformed underground pipe, and the horizontal slurry pockets are arranged in multiple rows, and each row has multiple groups; or

采用钻机钻出斜向孔、置放斜向注浆管、斜向锚杆和沿轴向延伸的多个土工布袋、注浆使每个土工布袋注满水泥浆液并凝固后的注浆体构成一组斜向浆囊袋以抬升基坑外侧变形地下管或横抵复位变形地下管,所述的斜向浆囊袋为多排,每排为多组;The grouting body is formed by drilling oblique holes with a drilling rig, placing oblique grouting pipes, oblique bolts and multiple geotextile bags extending along the axial direction, and grouting so that each geotextile bag is filled with cement slurry and solidified. A group of oblique pulp sac bags are used to lift the deformed underground pipe on the outside of the foundation pit or horizontally abut the deformed underground pipe, and the oblique pulp sac bags are in multiple rows, and each row is multiple groups;

(6)、注浆使钢管外侧端的第一施工孔封堵并凝固以利于止水,切割钢管内的注浆管;或:注浆将止水帷幕上和支护排桩相邻支护桩缝隙的土体上的第二施工孔封堵并凝固以利于止水,切割伸出第二施工孔基坑内侧的注浆管。(6), grouting makes the first construction hole at the outer end of the steel pipe block and solidifies to facilitate the water stop, and cut the grouting pipe in the steel pipe; The second construction hole on the soil body of the gap is blocked and solidified to facilitate water stop, and the grouting pipe extending out of the inner side of the foundation pit of the second construction hole is cut.

采用以上施工步骤后,本发明基坑围护墙外侧地表沉降或地下管变形的修复方法具有以下优点:After adopting the above construction steps, the method for repairing the surface settlement or the deformation of the underground pipe on the outer side of the retaining wall of the foundation pit of the present invention has the following advantages:

由于在基坑围护墙外侧地表沉降区域或地下管控制区域设多个监测点,监测点沿径向和纬向布置,采用监测设备适时获取基坑开挖时基坑围护墙外侧地表土体沉降值或地下管变形沉降值或地下管变形水平向移动值。又由于根据监测值得到的需修复的高度、横向位置和水平向或斜向走向来确定基坑围护墙上施工孔的位置和走向,如第一施工孔可选水平向或斜向,第二施工孔可钻水平向或斜向,和根据监测值得到的需钻孔的深度、需抬升土体的高度或需横移的距离来确定土工布袋的长度和套在土工布袋内的锚杆的长度和注浆管的长度及绑扎构成的多个土工布袋中的每个土工布袋的直径。且地表下陷处以下土体的水平向孔内或变形的地下管的以下土体水平向孔内、或地下管的侧部土体的斜向孔内或地下管的以下土体的斜向孔内的每根水平向注浆管或斜向注浆管上沿轴向绑扎有多个土工布袋,经注满水泥浆液并凝固后构成抬升土体恢复下陷地表或复位地下变形管的水平向浆囊袋或斜向浆囊袋。对地面沉降或开裂的抬升恢复或地下管的复位针对性很强,能准确确定哪里需抬升,哪里的地下管需横抵平移,而针对性地在沉降或称下陷土体下方或地下管的侧部和下方布置水平向锚杆、水平向注浆管和水平向浆囊袋或斜向锚杆、斜向注浆管和斜向浆囊袋,且变形地下管抬升和复位过程不会对地下管本身产生创口,并可对地下管进行竖向和水平向两个矢量方向的变形修复。地表沉降或称下陷土体的抬升恢复或地下管变形的抬升或横抵的复位效果均很明显。且由于采用浆囊袋定点抬升,土工布袋包裹住浆体,浆液不扩散,注浆质量有保障,且注浆量可根据现场每根注浆管上绑扎构成的多个土工布袋所能充盈的总的体积进行预估,既能得到较好的注浆充盈效果即抬升和复位效果,又使水泥浆液的消耗量相对小,使修复成本大幅度降低。Since there are multiple monitoring points in the surface settlement area or the underground pipe control area outside the foundation pit retaining wall, the monitoring points are arranged in the radial and latitudinal directions, and monitoring equipment is used to timely obtain the surface soil outside the foundation pit retaining wall during the excavation of the foundation pit. Volume settlement value or underground pipe deformation settlement value or underground pipe deformation horizontal movement value. In addition, the position and direction of the construction holes on the retaining wall of the foundation pit are determined according to the height to be repaired, the lateral position and the horizontal or oblique direction obtained according to the monitoring values. 2. The construction holes can be drilled horizontally or obliquely, and the length of the geotextile bag and the anchor rod set in the geotextile bag are determined according to the depth of the drilled hole, the height of the soil to be lifted, or the distance to be moved laterally according to the monitoring value. The length of the grouting pipe and the diameter of each geotextile bag in the plurality of geotextile bags formed by the binding. And the horizontal hole of the soil below the subsidence of the surface or the horizontal hole of the soil below the deformed underground pipe, or the oblique hole of the side soil of the underground pipe or the oblique hole of the soil below the underground pipe Each horizontal grouting pipe or oblique grouting pipe is bound with multiple geotextile bags along the axial direction. After filling with cement slurry and solidification, it constitutes the horizontal grouting of the uplifted soil to restore the subsidence surface or reset the underground deformed pipe. Capsular bag or oblique plasma sac. The lifting recovery of ground subsidence or cracking or the reset of underground pipes is highly targeted, and it can accurately determine where to lift and where the underground pipes need to be moved laterally, and targeted at the subsidence or subsidence soil or under the underground pipe. The horizontal bolt, the horizontal grouting pipe and the horizontal slurry bag or the oblique bolt, the oblique grouting pipe and the oblique slurry bag are arranged at the side and below, and the lifting and reset process of the deformed underground pipe will not affect the deformation of the underground pipe. The underground pipe itself produces wounds, and the underground pipe can be deformed and repaired in two vector directions, vertical and horizontal. The effect of surface subsidence or the uplift and recovery of subsidence soil or the uplift of underground pipe deformation or the reset effect of transverse contact are obvious. And because the slurry bag is lifted at a fixed point, the geotextile bag wraps the slurry, the slurry does not spread, and the grouting quality is guaranteed. By estimating the total volume, not only a good filling effect of grouting can be obtained, that is, lifting and reset effects, but also the consumption of cement slurry is relatively small, which greatly reduces the repair cost.

由于利用施工孔在已开挖好的基坑内侧操作施工,以对基坑外的下沉地表的以下土体或变形地下管以下土体或变形地下管侧部土体进行钻孔、置放锚杆、注浆管和土工布袋、注浆等操作,不需在基坑外需修复的地表上操作,施工全程不需进行交通管制,施工期间基坑外侧地面交通可保持正常不变,施工空间不受限制,能保证修复施工正常顺利进行,更不会破坏基坑外侧地表原有路面和设施,且由于施工设备在基坑内施工,对基坑外侧土体震动相对小,不会由于修复施工而产生新的地表沉降或地下管变形。Due to the use of construction holes to operate on the inside of the excavated foundation pit, drilling and placement of the soil below the subsidence surface outside the foundation pit or the soil below the deformed underground pipe or the soil on the side of the deformed underground pipe Anchor rods, grouting pipes, geotextile bags, grouting and other operations do not need to be operated on the surface to be repaired outside the foundation pit, and no traffic control is required during the construction process. During the construction period, the ground traffic outside the foundation pit can remain normal and unchanged. Unrestricted, it can ensure the normal and smooth progress of the repair construction, and will not damage the original road surface and facilities outside the foundation pit, and because the construction equipment is constructed in the foundation pit, the vibration of the soil outside the foundation pit is relatively small, and it will not be damaged by the repair construction. And new surface subsidence or underground pipe deformation occurs.

进一步地,在步骤(1)中,每根钢管的基坑内侧端内凸于地下连续墙的内表面,预埋前和注浆施工完成后在钢管的基坑内侧端旋紧密封盖;预埋前每根钢管的基坑外侧端内用临时封堵材料封堵。采用以上施工步骤后,可根据施工经验或预先所做的对地下连续墙外侧的土体及市政工程的预埋的地下管的监测和评估结果,对可能需要抬升和复位的位置预埋作为第一施工孔用的钢管,预埋时钢管两端封堵避免地下连续墙混凝土浇筑施工时混凝土堵塞和污染钢管内孔。该施工步骤能保证地下连续墙上预埋的第一施工孔施工操作方便,保证修复效果,且自身结构牢固可靠,打开第一施工孔或封堵第一施工孔均方便。施工完成后可密封以止水和保证本施工方法施工出的修复结构的完好性和耐久性。Further, in step (1), the inner end of the foundation pit of each steel pipe protrudes from the inner surface of the underground diaphragm wall, and the sealing cover is tightened on the inner end of the foundation pit of the steel pipe before pre-embedding and after the grouting construction is completed; Before burying, the outer end of the foundation pit of each steel pipe shall be sealed with temporary sealing material. After the above construction steps are adopted, according to the construction experience or the results of the monitoring and evaluation of the soil outside the diaphragm wall and the pre-buried underground pipes of the municipal engineering, the pre-buried positions that may need to be lifted and reset can be pre-buried as the first step. 1. Steel pipes for construction holes, both ends of the steel pipes are blocked during pre-embedding to avoid concrete blockage and contamination of the inner holes of the steel pipes during the concrete pouring construction of the underground continuous wall. The construction step can ensure that the first construction hole pre-buried in the underground continuous wall is easy to construct and operate, guarantees the repair effect, and has a firm and reliable structure, and it is convenient to open the first construction hole or block the first construction hole. After the construction is completed, it can be sealed to stop water and ensure the integrity and durability of the repaired structure constructed by this construction method.

进一步地,在步骤(1)的多排钢管中,相邻的上下两排钢管错开布置:相邻的上下两排钢管不在同一铅垂线上。采用以上施工步骤后,既能保证好的修复效果,又能将在地下连续墙上开孔而可能产生的对地下连续墙刚度的削弱作用降至最低。Further, in the multiple rows of steel pipes in step (1), the adjacent upper and lower rows of steel pipes are staggered: the adjacent upper and lower rows of steel pipes are not on the same vertical line. After the above construction steps are adopted, not only a good repair effect can be ensured, but also the weakening effect on the rigidity of the underground diaphragm wall which may be caused by opening holes in the underground diaphragm wall can be minimized.

进一步地,在步骤(3)中,每排施工孔布置在两排支撑围梁上下之间的基坑围护墙上。采用以上施工步骤后,有助于下述的基坑外侧地表沉降土体的修复或变形地下管的复位或称修复与基坑内开挖工程施工有效地契合。Further, in step (3), each row of construction holes is arranged on the surrounding wall of the foundation pit between the upper and lower sides of the two rows of supporting surrounding beams. After the above construction steps are adopted, it is helpful for the following repair of the surface settlement soil outside the foundation pit or the reset or repair of the deformed underground pipe to effectively fit the excavation engineering construction in the foundation pit.

进一步地,在步骤(5)中,基坑外侧地表沉降土体的修复或变形地下管的复位与基坑内开挖工程配合:基坑内挖土作业进行到一排施工孔以下的基坑围梁偏下的基坑开挖面后,需要进行基坑钢筋混凝土内支撑的浇筑工作,此时基坑内挖土作业暂停,等基坑钢筋混凝土内支撑达到预定强度后再继续向下挖土,在这个位置和这个时间点进行步骤(5)的施工。采用以上施工步骤后,基坑外地表沉降土体的修复或变形地下管的复位与基坑内开挖工程施工能有效契合或称很好配合,基坑内挖土作业进行到一排施工孔的基坑围梁偏下的基坑开挖面后,需要进行基坑钢筋混凝土内支撑的浇筑工作,此时基坑内挖土作业暂停,等基坑钢筋混凝土内支撑达到预定强度后再继续向下挖土,在这个位置和这个时间点进行基坑外地表沉降土体的修复或变形地下管的复位的修复施工,既不影响基坑开挖的工期,又使注浆修复施工空间更大,施工条件更理想,施工操作更方便,施工更顺利。Further, in step (5), the repair of the surface settlement soil outside the foundation pit or the reset of the deformed underground pipe is coordinated with the excavation project in the foundation pit: the excavation operation in the foundation pit is carried out to the foundation pit surrounding beam below a row of construction holes. After the excavation face of the lower foundation pit, it is necessary to carry out the pouring work of the inner support of the reinforced concrete of the foundation pit. At this time, the excavation operation in the foundation pit is suspended. After the inner support of the reinforced concrete of the foundation pit reaches the predetermined strength, the soil will continue to be excavated downward. The construction of step (5) is carried out at this position and at this time point. After the above construction steps are adopted, the repair of the subsidence soil outside the foundation pit or the reset of the deformed underground pipe can be effectively or very well matched with the excavation work in the foundation pit. After the excavation surface of the foundation pit on the lower part of the pit surrounding beam, it is necessary to carry out the pouring work of the reinforced concrete inner support of the foundation pit. At this time, the excavation operation in the foundation pit is suspended, and the reinforced concrete inner support of the foundation pit reaches the predetermined strength before continuing to dig downward. Soil, at this position and at this time, the repair of the surface settlement soil outside the foundation pit or the restoration of the deformed underground pipe will not affect the construction period of the foundation pit excavation, but also make the grouting repair construction space larger, and the construction The conditions are more ideal, the construction operation is more convenient, and the construction is smoother.

进一步地,在步骤(5)中,连接在一根水平向注浆管上的多个水平向浆囊袋位于基坑外侧地表下陷处以下土体的水平向孔内或基坑外侧变形地下管以下土体的水平向孔内;连接在一根斜向注浆管上的多个斜向浆囊袋位于基坑外侧变形地下管侧部土体的斜向孔内或基坑外侧变形地下管以下土体的斜向孔内。采用以上施工步骤后,位于地表土体下沉处的水平向浆囊袋和位于变形地下管的土体下沉处的水平向浆囊袋对沉降土体或变形地下管的抬升修复效果更好,针对性更强,做到抬升修复和节约水泥浆用料的和谐统一。位于变形地下管的土体下沉处或变形地下管侧部土体的斜向浆囊袋对变形沉降部分的抬升修复或横抵平移复位效果更好,针对性更强,做到抬升修复、横抵平移修复和节约水泥浆用料的和谐统一。Further, in step (5), a plurality of horizontal grout pockets connected to a horizontal grouting pipe are located in the horizontal hole of the soil below the subsidence of the ground outside the foundation pit or the underground pipe deformed outside the foundation pit. In the horizontal hole of the following soil mass; multiple oblique slurry pockets connected to an oblique grouting pipe are located in the oblique hole of the soil body on the side of the deformed underground pipe outside the foundation pit or the deformed underground pipe outside the foundation pit In the oblique hole of the following soil. After the above construction steps are adopted, the horizontal slurry pockets located at the subsidence of the surface soil mass and the horizontal slurry pockets located at the subsidence of the soil body of the deformed underground pipe have a better effect on the lifting and repair of the settled soil mass or the deformed underground pipe. , more targeted, to achieve the harmony and unity of lifting repair and saving cement slurry materials. The oblique pulp pockets located at the subsidence of the soil body of the deformed underground pipe or the soil on the side of the deformed underground pipe have a better effect on the lifting and repairing of the deformation and settlement part or the transversal translation reset, and are more targeted, so that the lifting and repairing, Harmony and unity of horizontal and translational repair and saving cement slurry materials.

进一步地,在步骤(5)中,水平向孔内的水平向锚杆远离基坑围护墙的一端固定在相邻的地下连续墙的沉孔内,水平向注浆管也延伸至沉孔内以向沉孔内注浆以固定。采用以上施工步骤后,可使设有水平向浆囊袋的水平向注浆管经水平向锚杆的两端固定,以构成担架结构而使水平向浆囊袋保持水平状态,从而更好实现抬升和加固土体的作用。Further, in step (5), the end of the horizontal bolt in the horizontal hole away from the retaining wall of the foundation pit is fixed in the countersunk hole of the adjacent underground continuous wall, and the horizontal grouting pipe also extends to the countersunk hole. The inside can be grouted into the counterbore to fix it. After the above construction steps are adopted, the horizontal grouting pipe with the horizontal slurry bag can be fixed by the two ends of the horizontal bolt to form a stretcher structure and the horizontal slurry bag can be kept in a horizontal state, so as to better realize the The role of lifting and strengthening soil.

附图说明Description of drawings

图1是本发明修复方法施工出的修复结构呈水平向布置时的竖向剖视结构示意图(可理解为水平向注浆管与水平向锚杆平行且水平向锚杆被遮挡)。1 is a vertical cross-sectional structural schematic diagram of the repair structure constructed by the repair method of the present invention when it is arranged horizontally (it can be understood that the horizontal grouting pipe is parallel to the horizontal anchor rod and the horizontal anchor rod is blocked).

图2是从基坑内侧看本发明修复方法施工出的修复结构中一种实施例的预埋钢管构成的第一施工孔在地下连续墙上的竖向布置示意图。2 is a schematic view of the vertical arrangement of the first construction hole formed by the pre-embedded steel pipe in an embodiment of the repair structure constructed by the repair method of the present invention on the underground continuous wall viewed from the inside of the foundation pit.

图3是本发明修复方法施工出的修复结构中一种实施例的预埋钢管和内端的密封盖及外端的密封材料的竖向剖视结构示意图(可理解为水平向注浆管与水平向锚杆平行且水平向锚杆被遮挡)。3 is a vertical cross-sectional structural schematic diagram of an embodiment of the pre-embedded steel pipe, the sealing cover at the inner end and the sealing material at the outer end in the repair structure constructed by the repair method of the present invention (it can be understood as the horizontal grouting pipe and the horizontal The anchors are parallel and the horizontal anchors are blocked).

图4是本发明修复方法施工出的修复结构呈水平向和斜向交叉布置时的竖向剖视结构示意图(可理解为水平向注浆管与水平向锚杆平行且水平向锚杆被遮挡;斜向注浆管与斜向锚杆平行且斜向锚杆被遮挡)。4 is a vertical cross-sectional structural schematic diagram of the repair structure constructed by the repair method of the present invention in a horizontal and oblique cross-arrangement (it can be understood that the horizontal grouting pipe is parallel to the horizontal bolt and the horizontal bolt is blocked. ; the oblique grouting pipe is parallel to the oblique bolt and the oblique bolt is blocked).

图5是本发明修复方法施工出的修复结构呈水平向布置且为两排时与相邻地下连续墙连接时的竖向剖视结构示意图(可理解为水平向注浆管与水平向锚杆平行且水平向锚杆被遮挡;沉孔中可有注浆体)。5 is a vertical cross-sectional structural schematic diagram of the repair structure constructed by the repair method of the present invention when it is horizontally arranged and connected to the adjacent underground diaphragm wall in two rows (it can be understood as the horizontal grouting pipe and the horizontal bolt Parallel and horizontal bolts are blocked; there may be grouting in the counterbore).

图6是本发明修复方法施工出的修复结构中一根呈水平向布置时锚杆与相邻地下连续墙连接的结构示意图(可理解为水平向注浆管与水平向锚杆平行且水平向注浆管被遮挡)。Fig. 6 is a structural schematic diagram of the connection between the anchor rod and the adjacent underground diaphragm wall when one of the repair structures constructed by the repair method of the present invention is arranged horizontally (it can be understood that the horizontal grouting pipe is parallel to the horizontal anchor rod and the horizontal direction Grouting pipe is blocked).

图7是本发明修复方法中采用钻机经预埋的钢管钻斜孔时的示意图。FIG. 7 is a schematic diagram of the use of a drilling rig to drill an oblique hole through a pre-buried steel pipe in the repair method of the present invention.

图8是本发明修复方法中基坑外侧地表沉降或地下管变形监测点布置俯视示意图(七条横向长方形可理解为水平向浆囊袋示意图或斜向浆囊袋示意图)。8 is a schematic top view of the layout of monitoring points for surface settlement or underground pipe deformation outside the foundation pit in the repair method of the present invention (seven horizontal rectangles can be understood as a schematic diagram of a horizontal pulp bag or a schematic diagram of an oblique pulp bag).

图中所示:1、外侧地表,2、地表沉降曲线,3、地下连续墙,4、支撑围梁,5、基坑钢筋混凝土内支撑,6、水平向钢管,7、水平向孔,8、土工布袋,9、水平向注浆管,10、绑扎带,11、注浆体,12、水平向浆囊袋,13、密封盖,14、地下室底板,15、防渗水密封材料,16、密封垫圈,17、变形地下管,18、地下管,19、斜向孔,20、斜向注浆管,21、斜向浆囊袋,22、斜向钢管,23、相邻的地下连续墙,24、固定端,25、沉孔,26、监测点,27、水平向锚杆,28、第一施工孔,29、钻杆,30、钻杆夹具,31、钻机,32、基坑开挖面。As shown in the picture: 1. Outer surface, 2. Surface settlement curve, 3. Diaphragm wall, 4. Supporting surrounding beam, 5. Inner support of reinforced concrete in foundation pit, 6. Horizontal steel pipe, 7. Horizontal hole, 8 , geotextile bag, 9, horizontal grouting pipe, 10, binding tape, 11, grouting body, 12, horizontal grouting bag, 13, sealing cover, 14, basement floor, 15, water-proof sealing material, 16 , sealing gasket, 17, deformed underground pipe, 18, underground pipe, 19, oblique hole, 20, oblique grouting pipe, 21, oblique slurry bag, 22, oblique steel pipe, 23, adjacent underground continuous wall, 24, fixed end, 25, countersunk hole, 26, monitoring point, 27, horizontal bolt, 28, first construction hole, 29, drill pipe, 30, drill pipe clamp, 31, drilling rig, 32, foundation pit excavation surface.

具体实施方式Detailed ways

下面结合附图对本发明的具体实施方式作进一步说明。在此需要声明的是,对于这些具体实施方式的说明用于帮助理解本发明,但并不构成对本发明的限定。此外,下面所描述的本发明的各个具体实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互组合。The specific embodiments of the present invention will be further described below with reference to the accompanying drawings. It should be stated here that the description of these specific embodiments is used to help the understanding of the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the specific embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

如图1、图2、图3、图4、图5、图6、图7和图8所示。As shown in FIG. 1 , FIG. 2 , FIG. 3 , FIG. 4 , FIG. 5 , FIG. 6 , FIG. 7 and FIG. 8 .

现有技术的基坑围护墙一般为两种结构,地下连续墙3和外侧的止水帷幕加内侧的支护排桩构成的围护墙(图中未示出)。Existing foundation pit enclosure walls generally have two structures, an enclosure wall (not shown in the figure) consisting of an underground continuous wall 3 and a water-stop curtain on the outside and supporting piles on the inside.

本发明基坑围护墙外侧地表沉降或地下管变形的修复方法,展开讲即为,基坑围护墙外侧地表沉降的修复方法或基坑围护墙外侧地下管变形的修复方法,也可称为修复基坑围护墙外侧地表沉降或地下管变形的方法,包括以下施工步骤:The method for repairing the surface settlement outside the foundation pit enclosure wall or the deformation of the underground pipe in the present invention can be described as the repair method for the surface settlement outside the foundation pit enclosure wall or the repair method for the deformation of the underground pipe outside the foundation pit enclosure wall. It is called the method of repairing the surface settlement or the deformation of the underground pipe on the outer side of the retaining wall of the foundation pit, including the following construction steps:

(1)、根据预测和评估数据,在基坑围护墙中的地下连续墙3上预埋一排或多排钢管,每排为多根,每根钢管呈水平状态即为水平向钢管6或呈基坑内侧高基坑外侧低的斜向状态即为斜向钢管22。(1) According to the prediction and evaluation data, one or more rows of steel pipes are pre-buried on the underground diaphragm wall 3 in the retaining wall of the foundation pit, each row is multiple, and each steel pipe is horizontal, that is, the horizontal steel pipe 6 Or the inclined state in which the inside of the foundation pit is high and the outside of the foundation pit is low is the inclined steel pipe 22 .

(2)、在基坑围护墙外侧地表1沉降区域或地下管18控制区域设多个监测点26,监测点26沿径向和纬向布置,采用监测设备适时获取基坑开挖时基坑围护墙外侧地表1土体沉降值或地下管18变形沉降值或地下管18变形水平向移动值。(2) Set up a plurality of monitoring points 26 in the settlement area of the surface 1 or the control area of the underground pipe 18 on the outer side of the retaining wall of the foundation pit. The monitoring points 26 are arranged in the radial and latitudinal directions, and the monitoring equipment is used to obtain the time base of the excavation of the foundation pit in a timely manner. The settlement value of the soil body on the surface 1 outside the retaining wall of the pit or the deformation settlement value of the underground pipe 18 or the horizontal displacement value of the underground pipe 18 deformation.

基坑围护墙外侧地表1也称基坑外侧地表1。基坑围护墙外侧地表1土体如基坑围护墙外侧地表1的地表沉降曲线2以下的土体。地下管18为市政工程各种预埋的地下管18。地下管18也可称地下管道。外侧地表1也称外侧地面。基坑围护墙也称基坑围护结构。The outer surface 1 of the retaining wall of the foundation pit is also called the outer surface 1 of the foundation pit. The soil mass on the outer surface 1 of the retaining wall of the foundation pit is the soil mass below the surface settlement curve 2 of the outer surface 1 of the retaining wall of the foundation pit. The underground pipes 18 are various pre-buried underground pipes 18 in municipal engineering. The underground pipes 18 may also be referred to as underground pipes. The outer surface 1 is also called the outer surface. The foundation pit retaining wall is also called the foundation pit retaining structure.

(3)、根据监测值得到的需修复的高度、横向位置和水平向或斜向走向确定基坑围护墙上施工孔的位置和走向:地下连续墙3上的第一施工孔28在预埋的钢管中选,可选水平向的,也可选斜向的。所述的第一施工孔28为一排或多排,每排为多个。外侧的止水帷幕加内侧的支护排桩构成的围护墙的第二施工孔在支护排桩相邻支护桩缝隙的土体上选并标注,所述的第二施工孔为一排或多排,每排为多个,第二施工孔呈水平状态即为水平向孔或呈基坑内侧高基坑外侧低的斜向状态即为斜向孔(止水帷幕、支护排桩、支护桩的缝隙的土体及缝隙土体上的第二施工孔等图中均未示出)。水平向或斜向走向可称为水平向走向或斜向走向。基坑围护墙上的施工孔一般位于基坑挖好后的地下室底板14水平位置以上的基坑围护墙上。所述的施工孔如第一施工孔28或第二施工孔可为一排,也可为多排,如两排、三排或四排等。每排均为多个如几个、十几个、几十个或几十几个等。(3) Determine the position and direction of the construction hole on the retaining wall of the foundation pit according to the height to be repaired, the lateral position and the horizontal or oblique direction obtained from the monitoring value: the first construction hole 28 on the underground diaphragm wall 3 is in the The buried steel pipe can be selected horizontally or obliquely. The first construction holes 28 are in one or more rows, and each row is plural. The second construction hole of the enclosure wall formed by the water-stop curtain on the outside and the support piles on the inside is selected and marked on the soil body in the gap between the support piles adjacent to the support piles, and the second construction hole is a Row or rows, each row is multiple, the second construction hole is horizontal, which is horizontal hole, or the oblique state where the inner side of the foundation pit is high and the outer side of the foundation pit is low is the oblique hole (waterproof curtain, support row The soil body of the gap of the pile, the supporting pile and the second construction hole on the gap soil body are not shown in the drawings). A horizontal or oblique trend may be referred to as a horizontal or oblique trend. The construction holes on the retaining wall of the foundation pit are generally located on the retaining wall of the foundation pit above the horizontal position of the basement floor 14 after the foundation pit has been dug. The construction holes, such as the first construction holes 28 or the second construction holes, may be in one row, or may be in multiple rows, such as two rows, three rows, or four rows. Each row is multiple, such as several, dozens, dozens or dozens and so on.

(4)、根据监测值得到的需钻孔的深度、需抬升土体的高度或需横移的距离来确定土工布袋8的长度和套在土工布袋8内的锚杆的长度和注浆管的长度及绑扎构成的多个土工布袋8中的每个土工布袋8的直径,其中注浆管留出连接注浆泵(注浆泵图中未示出)的长度,每个土工布袋8对应注浆管上的一个或多个注浆孔(注浆孔图中未示出)。锚杆包括水平向锚杆27和斜向锚杆(图中未示出)。注浆管包括水平向注浆管9和斜向注浆管20。(4) Determine the length of the geotextile bag 8 and the length of the anchor rod set in the geotextile bag 8 and the grouting pipe according to the depth of the required drilling hole, the height of the soil body to be lifted or the distance to be traversed according to the monitoring value. The length and the diameter of each geotextile bag 8 in the multiple geotextile bags 8 formed by binding, wherein the grouting pipe is reserved for the length of the grouting pump (not shown in the figure of the grouting pump), and each geotextile bag 8 corresponds to One or more grouting holes on the grouting pipe (not shown in the grouting hole diagram). The anchor rod includes a horizontal anchor rod 27 and an oblique anchor rod (not shown in the figure). The grouting pipe includes a horizontal grouting pipe 9 and an oblique grouting pipe 20 .

(5)、采用钻机31钻出水平向孔7、在水平向孔7内置放水平向注浆管9、水平向锚杆27和沿轴向延伸的多个土工布袋8、注浆使每个土工布袋8注满水泥浆液并凝固后的注浆体11构成一组水平向浆囊袋12以抬升基坑外侧地表1沉降土体或称下陷土体或抬升变形地下管17,所述的水平向浆囊袋12为多排,每排为多组。或(5), use the drilling rig 31 to drill the horizontal hole 7, put the horizontal grouting pipe 9, the horizontal bolt 27 and the multiple geotextile bags 8 extending in the axial direction in the horizontal hole 7, and grouting makes each The geotextile bag 8 is filled with cement slurry and the grouting body 11 after solidification constitutes a set of horizontal slurry pockets 12 to lift the subsidence soil body or the subsidence soil body or the lifting deformation underground pipe 17 on the outside of the foundation pit. The pulp pockets 12 are arranged in multiple rows, and each row is arranged in multiple groups. or

采用钻机31钻出斜向孔19、置放斜向注浆管20、斜向锚杆和沿轴向延伸的多个土工布袋8、注浆使每个土工布袋8注满水泥浆液并凝固后的注浆体11构成一组斜向浆囊袋21以抬升基坑外侧变形地下管17或横抵复位变形地下管17,所述的斜向浆囊袋21为多排,每排为多组。The oblique hole 19 is drilled by the drilling machine 31, the oblique grouting pipe 20, the oblique bolt and the multiple geotextile bags 8 extending in the axial direction are placed, and each geotextile bag 8 is filled with cement slurry and solidified after grouting. The grouting body 11 constitutes a set of oblique slurry sacks 21 to lift the deformed underground pipe 17 outside the foundation pit or cross the reset and deformed underground pipe 17. The oblique slurry sacks 21 are arranged in multiple rows, and each row has multiple groups. .

所述的抬升可称隆起。所述的水平向孔7或斜向孔19可为一排,也可为多排,如两排、三排或四排等。每排可为多个如几个、十几个、几十个或几十几个等。The lift can be called a bulge. The horizontal holes 7 or the oblique holes 19 may be in one row, or may be in multiple rows, such as two rows, three rows, or four rows. Each row may be multiple, such as several, dozens, dozens or dozens, etc.

所述的水平向孔7内由水平向锚杆27、水平向注浆管9和轴向布置的多个土工布袋8注满水泥浆液并凝固后的注浆体11构成的一组水平向浆囊袋12可为一排,也可为多排,如两排、三排或四排等,每排可为多组如几组、十几组、几十组或几十几组等。The horizontal hole 7 consists of a horizontal bolt 27, a horizontal grouting pipe 9 and a plurality of axially arranged geotextile bags 8 filled with cement slurry and solidified. The pouches 12 can be in one row or in multiple rows, such as two rows, three rows or four rows, and each row can be in multiple groups, such as several groups, dozens of groups, dozens of groups, or dozens of groups.

所述的斜向孔19内由斜向锚杆、斜向注浆管20和轴向布置的多个土工布袋8注满水泥浆液并凝固后的注浆体11构成的一组斜向浆囊袋21可为一排,也可为多排,如两排、三排或四排等,每排可为多组如几组、十几组、几十组或几十几组等。The oblique hole 19 is a group of oblique slurry sacs composed of oblique bolts, oblique grouting pipes 20 and a plurality of axially arranged geotextile bags 8 filled with cement slurry and solidified grouting body 11. The bags 21 can be one row or multiple rows, such as two rows, three rows or four rows, and each row can be multiple groups, such as several groups, dozens of groups, dozens of groups or dozens of groups.

(6)、注浆使钢管如水平向钢管6或斜向钢管22外侧端的第一施工孔28封堵并凝固以利于止水,切割钢管内如水平向钢管6内或斜向钢管22内的注浆管。或:注浆将止水帷幕上和支护排桩相邻支护桩的缝隙土体上的第二施工孔封堵并凝固以利于止水,切割伸出第二施工孔基坑内侧的注浆管。(6), grouting makes the steel pipe such as the first construction hole 28 at the outer end of the horizontal steel pipe 6 or the oblique steel pipe 22 to be blocked and solidified to facilitate water stop, and cut the steel pipe such as the horizontal steel pipe 6 or the oblique steel pipe 22. Grouting pipe. Or: grouting seals and solidifies the second construction hole on the water-stop curtain and the gap between the supporting piles adjacent to the supporting piles to facilitate water-stopping, and cut the grouting projecting out of the second construction hole inside the foundation pit. Slurry tube.

在步骤(1)中,每根钢管如水平向钢管6或斜向钢管22的基坑内侧端内凸于地下连续墙3的内表面,预埋前和注浆施工完成后在钢管如水平向钢管6或斜向钢管22的基坑内侧端旋紧密封盖13。预埋前每根钢管如水平向钢管6或斜向钢管22的基坑外侧端内用临时封堵材料封堵。每根钢管的基坑内侧端上设有可拆式密封盖13,可拆式如螺纹连接,可在钢管基坑内侧端的内孔设内螺纹,在密封盖13的外圆周上设外螺纹,还可在密封盖13上套密封垫圈16,以密封钢管基坑内侧的端面与密封盖13的台阶面。In step (1), the inner end of the foundation pit of each steel pipe, such as the horizontal steel pipe 6 or the oblique steel pipe 22, protrudes from the inner surface of the underground diaphragm wall 3. Before pre-embedding and after the grouting construction is completed, the steel pipe such as horizontal Tighten the sealing cover 13 to the inner end of the foundation pit of the steel pipe 6 or the inclined steel pipe 22 . Before pre-embedding, the outer end of the foundation pit of each steel pipe, such as the horizontal steel pipe 6 or the oblique steel pipe 22, is sealed with a temporary sealing material. The inner end of the foundation pit of each steel pipe is provided with a detachable sealing cover 13. The detachable type, such as threaded connection, can be provided with an inner thread in the inner hole of the inner end of the foundation pit of the steel pipe, and an outer thread on the outer circumference of the sealing cover 13. A sealing gasket 16 can also be set on the sealing cover 13 to seal the end face inside the steel pipe foundation pit and the stepped surface of the sealing cover 13 .

所述的钢管预埋,可以在地下连续墙3的钢筋笼制作时,预先将水平向钢管6或斜向钢管22焊接在钢筋笼(钢筋笼图中未示出)的预定位置上,钢管的基坑内端用密封盖13预先旋紧密封,钢管的基坑外端可采用零时密封材料如丝绵或石棉等预先封堵,待地下连续墙3施工完成后,需注浆时,再将内端预埋钢管的密封盖13旋下而将外端的密封材料钻孔钻出。The steel pipe pre-embedding can be performed by welding the horizontal steel pipe 6 or the oblique steel pipe 22 to the predetermined position of the steel cage (the steel cage is not shown in the figure) in advance when the steel cage of the underground continuous wall 3 is made. The inner end of the foundation pit is pre-tightened and sealed with the sealing cover 13, and the outer end of the foundation pit of the steel pipe can be pre-sealed with zero-time sealing materials such as silk wool or asbestos. The sealing cover 13 of the pre-embedded steel pipe at the end is unscrewed and the sealing material at the outer end is drilled.

钻孔、置注浆管、锚杆、土工布袋8及注浆施工完成后的每根钢管即水平向钢管6或斜向钢管22的第一施工孔28内的基坑外侧端上有防渗水密封材料15如注浆溢至该处并凝固后的水泥浆液。然后将钢管的内螺纹处的水泥浆液清除干净以旋紧密封盖13并压紧密封垫圈16。防渗水密封材料15又称填充材料。每排钢管在这里可理解为全部为水平向钢管6,或全部为斜向钢管22,或同时具有水平向钢管6和斜向钢管22。钻孔、置注浆管、锚杆27、土工布袋8及注浆施工完成后这句话可这样理解:钻孔、置注浆管、置锚杆、置土工布袋8及注浆这五项施工完成后。Drilling holes, placing grouting pipes, bolts, geotextile bags 8 and each steel pipe after the grouting construction is completed, that is, the horizontal steel pipe 6 or the first construction hole 28 of the oblique steel pipe 22, there is an anti-seepage on the outer end of the foundation pit. The water sealing material 15 is, for example, the cement slurry after grouting overflows and solidifies. Then, remove the cement slurry at the inner thread of the steel pipe to tighten the sealing cover 13 and compress the sealing gasket 16 . The water-proof sealing material 15 is also called a filling material. Each row of steel pipes can be understood here as all horizontal steel pipes 6 , or all oblique steel pipes 22 , or both horizontal steel pipes 6 and oblique steel pipes 22 . After drilling, placing grouting pipe, anchor rod 27, geotextile bag 8 and grouting, the sentence can be understood as follows: drilling, placing grouting pipe, placing anchor rod, placing geotextile bag 8 and grouting. After construction is complete.

在步骤(1)的多排钢管中,相邻的上下两排钢管错开布置:相邻的上下两排钢管不在同一铅垂线上。展开讲,在步骤(1)的多排钢管如水平向钢管6中,相邻的上下两排钢管如水平向钢管6错开布置:相邻的上下两排的钢管如水平向钢管6不在同一铅垂线上。或,在步骤(1)的多排钢管如斜向钢管22中,相邻的上下两排钢管如斜向钢管22错开布置:相邻的上下两排的钢管如斜向钢管22不在同一铅垂线上。或,在步骤(1)的多排钢管如水平向钢管6或斜向钢管22中,相邻的上下两排钢管如水平向钢管6与斜向钢管22错开布置:相邻的上下两排的钢管如水平向钢管6与斜向钢管22不在同一铅垂线上。In the multiple rows of steel pipes in step (1), the adjacent upper and lower rows of steel pipes are staggered: the adjacent upper and lower rows of steel pipes are not on the same vertical line. Expanding speaking, in the multiple rows of steel pipes in step (1) such as horizontal steel pipes 6, the adjacent upper and lower rows of steel pipes are staggered such as horizontal steel pipes 6: the adjacent upper and lower rows of steel pipes such as horizontal steel pipes 6 are not in the same lead. vertical line. Or, in the multiple rows of steel pipes of step (1) such as oblique steel pipes 22, adjacent upper and lower two rows of steel pipes are staggered such as inclined steel pipes 22: adjacent upper and lower rows of steel pipes such as oblique steel pipes 22 are not in the same vertical on-line. Or, in the multi-row steel pipes of step (1) such as horizontal steel pipes 6 or oblique steel pipes 22, adjacent upper and lower two rows of steel pipes such as horizontal steel pipes 6 and oblique steel pipes 22 are staggered: Steel pipes such as horizontal steel pipes 6 and oblique steel pipes 22 are not on the same vertical line.

在步骤(2)中,设置径向纬向的多个如十几个、几十个或几十几个监测点26,利用监测设备获取沉降或横移或称水平向移动等值,以针对性地布置注浆管和浆囊袋等修复结构是本发明的发明点。不难理解,而监测点26的具体结构、监测设备和具体监测方法则属于现有技术,如竖向位移标杆如螺纹钢标杆插入路面结构硬壳层或地表土体内60mm以下,使用市售且精度为0.3mm/km电子水准仪,以高程已知的地表监测基点为标准水准点,监测时通过测得各监测点与水准点即基点的高程差ΔH,可得到各监测点的标准高程Δht,然后与上次测得高程进行比较,差值Δh即为该测点的沉降值。又如现有技术测量土体沉降过程中地下管水平位移量x的手段为,在施工前期勘探过程中测量出管道的埋藏深度h,并在管道旁埋入一个测斜仪,该测斜仪在经过沉降后能测出沉降前后的倾角变量Δθ,且由于x/h=tanΔθ,即x=h×tanΔθ,带入已知的h和Δθ,就能获得沉降过程中管道水平位移量x。如上所述,监测点的具体结构、监测设备和具体监测方法属于现有技术,在此不赘述。In step (2), multiple monitoring points 26 in the radial and latitudinal directions, such as dozens, dozens or dozens of points, are set up, and the monitoring equipment is used to obtain values such as settlement or lateral movement or horizontal movement, so as to detect The inventive point of the present invention is to arrange the repair structures such as the grouting pipe and the pulp sac bag randomly. It is not difficult to understand, but the specific structure, monitoring equipment and specific monitoring method of the monitoring point 26 belong to the prior art. The electronic level with an accuracy of 0.3mm/km takes the surface monitoring base point with known elevation as the standard benchmark point. During monitoring, by measuring the elevation difference ΔH between each monitoring point and the benchmark point, that is, the base point, the standard elevation Δht of each monitoring point can be obtained, Then compare it with the last measured elevation, and the difference Δh is the settlement value of the measuring point. Another example is the method of measuring the horizontal displacement x of the underground pipe in the process of soil settlement in the prior art: measuring the buried depth h of the pipe during the pre-construction exploration process, and burying an inclinometer next to the pipe. After settlement, the inclination variable Δθ before and after settlement can be measured, and since x/h=tanΔθ, that is, x=h×tanΔθ, by bringing in the known h and Δθ, the horizontal displacement x of the pipeline during the settlement process can be obtained. As mentioned above, the specific structure, monitoring equipment and specific monitoring method of the monitoring point belong to the prior art, and will not be described here.

在步骤(3)中,每排施工孔如第一施工孔28和第二施工孔布置在两排支撑围梁4上下之间的基坑围护墙如地下连续墙3上或外侧的止水帷幕加内侧的支护排桩构成的围护墙上。In step (3), each row of construction holes such as the first construction hole 28 and the second construction hole are arranged on the foundation pit enclosure wall between the upper and lower sides of the two rows of supporting enclosure beams 4, such as the water stop on the underground continuous wall 3 or on the outside Curtain plus inner supporting piles on the retaining wall.

图7所示为钻一个斜向孔19的示意图。FIG. 7 shows a schematic view of drilling an oblique hole 19 .

钻机31可采用市售的锚杆锚索钻机履带式KLD-200液压电动锚固钻机。The drilling rig 31 can be a commercially available rock bolt and cable drilling rig crawler type KLD-200 hydraulic electric anchoring drilling rig.

每排施工孔如图1、图2、图4、图5、图7所示是第一施工孔28布置在两排支撑围梁4上下之间的基坑围护墙如图1、图2、图4、图5、图7所示的地下连续墙3上。在步骤(5)中,基坑外侧地表1沉降土体的修复或变形地下管17的复位或称修复与基坑内开挖工程配合:基坑内挖土作业进行到一排施工孔如第一施工孔28或第二施工孔以下的基坑围梁4偏下的基坑开挖面32后,需要进行基坑钢筋混凝土内支撑5的浇筑工作,此时基坑内挖土作业暂停,等基坑钢筋混凝土内支撑5达到预定强度后再继续向下挖土,在这个位置和这个时间点进行步骤(5)的注浆施工。实际施工过程中,可利用基坑开挖面32,从上至下随着基坑开挖面32的逐步下挖,逐层施工操作。钻杆29固紧在钻杆夹具30上,钻杆夹具30安装在钻机31上,钻机31位于基坑开挖面32上。从第一施工孔28内进入钻孔,斜向孔19钻好后,将绑扎构成的多个土工布袋8随斜向锚杆和斜向注浆管20置入斜向孔19内,再注浆构成一串复位基坑外侧变形地下管17的斜向浆囊袋21,再旋紧密封盖13。水平向布置的施工操作也相同,只是角度不同。不难理解,以上钻孔的具体操作也属于现有技术,如针对软土可采用泥浆置换孔内土体的方式防止塌孔,可待置换的泥浆稍凝固后再抽出钻杆29。Each row of construction holes is shown in Figure 1, Figure 2, Figure 4, Figure 5, and Figure 7. The first construction hole 28 is arranged between the upper and lower sides of the two rows of supporting beams 4. Figure 1, Figure 2 , Figure 4, Figure 5, Figure 7 shown on the underground continuous wall 3. In step (5), the repair of the settlement soil body on the outer surface 1 of the foundation pit or the reset or repair of the deformed underground pipe 17 is coordinated with the excavation work in the foundation pit: the excavation operation in the foundation pit is carried out to a row of construction holes such as the first construction After the excavation surface 32 of the foundation pit below the hole 28 or the surrounding beam 4 of the foundation pit below the second construction hole, the pouring work of the support 5 in the reinforced concrete of the foundation pit needs to be carried out. At this time, the excavation operation in the foundation pit is suspended and the foundation pit is waiting After the reinforced concrete inner support 5 reaches the predetermined strength, the soil is continued to be excavated downward, and the grouting construction of step (5) is performed at this position and this time point. In the actual construction process, the excavation surface 32 of the foundation pit can be used, and the excavation surface 32 of the foundation pit can be gradually excavated from top to bottom, and the construction is performed layer by layer. The drill rod 29 is fastened on the drill rod clamp 30, and the drill rod clamp 30 is installed on the drilling rig 31, and the drilling rig 31 is located on the excavation surface 32 of the foundation pit. Enter the drilling hole from the first construction hole 28. After the oblique hole 19 is drilled, place the multiple geotextile bags 8 formed by binding into the oblique hole 19 along with the oblique anchor rod and the oblique grouting pipe 20, and then inject The slurry forms a series of oblique slurry pockets 21 that reset the deformed underground pipes 17 outside the foundation pit, and then tighten the sealing cover 13 . The construction operation for the horizontal arrangement is also the same, only the angle is different. It is not difficult to understand that the specific operation of the above drilling also belongs to the prior art. For example, for soft soil, the soil in the hole can be replaced with mud to prevent the hole from collapsing, and the drill pipe 29 can be pulled out after the replaced mud is solidified.

以上注浆体11为注浆浆液凝固后构成。不难理解,注浆浆液配比,具体注浆操作也均属于现有技术,如注浆浆液可采用42.5级普通硅酸盐水泥,水灰比为1:0.55。注浆可采用低压二次注浆,一次注浆压力一般小于0.6Mpa,二次注浆压力一般不宜小于1.5Mpa,预计注浆量已充盈一个土工布袋8绑扎后构成的多个土工布袋8的总体积后,可继续注浆2min左右,以保证不破袋的前提下使充盈量更好,使抬升土体或复位变形地下管17的技术效果更好。The above-mentioned grouting body 11 is formed after the grouting slurry is solidified. It is not difficult to understand that the ratio of grouting slurry and the specific grouting operation also belong to the prior art. For example, the grouting slurry can be made of 42.5 grade ordinary Portland cement, and the water-cement ratio is 1:0.55. Low-pressure secondary grouting can be used for grouting. The primary grouting pressure is generally less than 0.6Mpa, and the secondary grouting pressure generally should not be less than 1.5Mpa. After the total volume, grouting can be continued for about 2 minutes, so as to make the filling volume better without breaking the bag, so that the technical effect of lifting the soil body or resetting the deformed underground pipe 17 is better.

在步骤(5)中,连接在一根水平向注浆管9上的多个水平向浆囊袋12位于基坑外侧地表1下陷处如图1、图4、图5和图7所示的地表沉降曲线2以下土体的水平向孔7内或基坑外侧变形地下管17以下土体的水平向孔7内。连接在一根斜向注浆管20上的多个斜向浆囊袋21位于基坑外侧变形地下管17侧部土体的斜向孔19内或基坑外侧变形地下管17以下土体的斜向孔19内。In step (5), a plurality of horizontal slurry pockets 12 connected to a horizontal grouting pipe 9 are located at the depression of the ground surface 1 outside the foundation pit, as shown in Figures 1, 4, 5 and 7 The horizontal hole 7 of the soil body below the surface settlement curve 2 or the horizontal hole 7 of the soil body below the deformation underground pipe 17 on the outside of the foundation pit. A plurality of inclined slurry pockets 21 connected to an inclined grouting pipe 20 are located in the inclined holes 19 of the soil on the side of the deformed underground pipe 17 outside the foundation pit or in the soil below the deformed underground pipe 17 outside the foundation pit. Inside the oblique hole 19.

在步骤(5)中,水平向孔7内的水平向锚杆27远离基坑围护墙的一端固定在相邻的地下连续墙23的沉孔25内,水平向注浆管9也延伸至沉孔25内以向沉孔25内注浆以固定。换句话说,水平向孔7内的水平向锚杆27远离基坑围护墙的一端为固定端24。具体可为两种结构,一种在水平向锚杆位于沉孔25内的顶端焊接几个锚固钉,在施工孔这端借助一辅助加强杆和锤,敲击施工孔如第一施工孔28这端,使锚固钉扎紧在沉孔25的端壁上,再经注浆管向沉孔25内注浆并待凝固即到达固定效果。另一种,将水平向锚杆27位于沉孔25内,在施工孔这端借助一辅助加强杆和锤,敲击施工孔这端,如图6所示使水平向锚杆27位于沉孔25内的那端的端面顶至沉孔25的端壁上,再将施工孔这端的水平向锚杆临时轴向限位,如采用一根不妨碍注浆的钢杆如12mm的圆钢,一端抵紧水平向锚杆的施工孔的这端,另一端伸出钢管基坑端并点焊固定,再经注浆管向沉孔25内注浆并待凝固即到达固定效果,再用砂轮磨去焊点,抽出圆钢。In step (5), the end of the horizontal bolt 27 in the horizontal hole 7 away from the retaining wall of the foundation pit is fixed in the counterbore 25 of the adjacent underground continuous wall 23, and the horizontal grouting pipe 9 also extends to grouting into the counterbore 25 for fixing. In other words, the end of the horizontal bolt 27 in the horizontal hole 7 away from the retaining wall of the foundation pit is the fixed end 24 . Specifically, there are two structures. One is to weld several anchoring nails at the top of the horizontal bolt located in the counterbore 25, and at the end of the construction hole, with the help of an auxiliary reinforcing rod and a hammer, knock the construction hole such as the first construction hole 28. At this end, the anchoring pin is fastened on the end wall of the counterbore 25, and then grouting is poured into the counterbore 25 through the grouting pipe and the fixing effect is achieved after solidification. The other is to locate the horizontal bolt 27 in the counterbore 25, and tap the end of the construction hole with the aid of an auxiliary reinforcing rod and a hammer at the end of the construction hole, as shown in Figure 6, so that the horizontal bolt 27 is located in the counterbore The end face of the end inside 25 is pushed to the end wall of the countersunk hole 25, and then the horizontal bolt at this end of the construction hole is temporarily axially limited. Press the end of the construction hole of the horizontal anchor rod, and the other end extends out of the end of the steel pipe foundation pit and is fixed by spot welding, and then grouting into the counterbore 25 through the grouting pipe and waits for solidification to achieve the fixing effect, and then grind it with a grinding wheel. Remove the solder joints and pull out the round steel.

不难理解,在水平向孔7或斜向孔19内的锚杆的长度和注浆管的长度可以相等,土工布袋8可为沿锚杆和注浆管长度方向延长并且为一个完整的袋,经绑扎带10绑扎在水平向锚杆27和水平向注浆管9或斜向锚杆和斜向注浆管20上后,构成沿轴向连接成串的多个,多个土工布袋8的直径可相等,但一般会在施工现场根据需要做成直径大小不同和/或长短不同的土工布袋8,如上所述,每个土工布袋8对应水平向注浆管9或斜向注浆管20上的至少一个注浆口,注浆口优选为沿注浆管圆周布置的多个。不难理解,注浆管远离水平向孔7或斜向孔19的一端连接于注浆泵或称注浆泵机,而完成注浆后一般是从施工孔如第一施工孔内靠近锚杆处切断,以不妨碍密封盖13密封。当然,切断是很常规的操作,因为注浆管一般为PE塑料管,可采用伸入钢管内的电动切割刀切割。It is not difficult to understand that the length of the bolt in the horizontal hole 7 or the oblique hole 19 and the length of the grouting pipe can be equal, and the geotextile bag 8 can be extended along the length of the bolt and the grouting pipe and is a complete bag. , after being bound on the horizontal bolt 27 and the horizontal grouting pipe 9 or the oblique bolt and the oblique grouting pipe 20 by the binding tape 10, a plurality of geotextile bags 8 connected in series along the axial direction are formed. The diameters can be equal, but generally, geotextile bags 8 with different diameters and/or lengths will be made on the construction site according to needs. As mentioned above, each geotextile bag 8 corresponds to a horizontal grouting pipe 9 or an oblique grouting pipe. At least one grouting port on 20, preferably a plurality of grouting ports are arranged along the circumference of the grouting pipe. It is not difficult to understand that the end of the grouting pipe away from the horizontal hole 7 or the oblique hole 19 is connected to a grouting pump or a grouting pump, and after the grouting is completed, it is generally approached from the construction hole such as the first construction hole to the anchor rod. Cut off at the place so as not to prevent the sealing cap 13 from being sealed. Of course, cutting is a very common operation, because the grouting pipe is generally a PE plastic pipe, which can be cut with an electric cutting knife extending into the steel pipe.

以下为在外侧的止水帷幕加内侧的支护排桩构成的围护墙上采用本发明修复方法所施工的具体实施例:基坑围护墙为外侧的止水帷幕加内侧的支护排桩构成的围护墙,施工孔为在内侧的支护排桩相邻支护桩的缝隙的土体和外侧的止水帷幕上现场钻出的第二施工孔。在钻孔、置注浆管、锚杆、土工布袋及注浆施工完成后的每个第二施工孔内有防渗水密封封孔材料(本段的结构图中未示出)。本具体实施例除施工孔结构不同如不设钢管和第二施工孔的注浆管是从基坑内侧端切断外。其余操作均同以上具体实施例。The following is a specific embodiment constructed by adopting the repair method of the present invention on the enclosure wall formed by the outer water-stop curtain and the inner support row piles: the foundation pit enclosure wall is the outer water stop curtain and the inner support row. For the retaining wall composed of piles, the construction holes are the second construction holes drilled on site in the soil of the gap between the inner supporting piles adjacent to the supporting piles and the outer water-stop curtain. In each second construction hole after drilling, placing grouting pipe, anchor rod, geotextile bag and grouting, there is an anti-seepage water sealing material (not shown in the structural diagram of this section). In this specific embodiment, except that the construction hole structure is different, for example, the grouting pipe without the steel pipe and the second construction hole is cut from the inner end of the foundation pit. The rest of the operations are the same as the above specific embodiments.

以上所述仅为本发明的优选实施方式,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (7)

1. A method for repairing surface subsidence or deformation of an underground pipe outside a foundation pit enclosure wall is characterized by comprising the following steps: the method comprises the following construction steps:
(1) pre-burying one or more rows of steel pipes on the underground continuous wall in the foundation pit enclosure wall according to the prediction and evaluation data, wherein each row is provided with a plurality of steel pipes, and each steel pipe is in a horizontal state or in an inclined state that the inner side of the foundation pit is higher than the outer side of the foundation pit and is lower than the outer side of the foundation pit;
(2) a plurality of monitoring points are arranged in a surface subsidence area or an underground pipe control area outside the foundation pit enclosure wall, the monitoring points are arranged along the radial direction and the latitudinal direction, and monitoring equipment is adopted to timely acquire a surface soil body subsidence value or an underground pipe deformation horizontal movement value outside the foundation pit enclosure wall during foundation pit excavation;
(3) determining the position and the direction of a construction hole on the foundation pit enclosure wall according to the height position to be repaired, the transverse position and the horizontal direction or the oblique direction obtained according to the monitoring value: selecting first construction holes in the underground continuous wall from pre-buried steel pipes, wherein the first construction holes are arranged in one or more rows, and each row is provided with a plurality of first construction holes; a second construction hole of the enclosure wall formed by the waterproof curtain on the outer side and the supporting row piles on the inner side is selected and marked on soil bodies in gaps between the supporting piles adjacent to the supporting row piles, the second construction holes are arranged in one row or multiple rows, each row is multiple, and the second construction holes are in a horizontal state or in an inclined state that the inner side of the foundation pit is higher than the outer side of the foundation pit and is lower than the outer side of the foundation pit;
(4) determining the length of the geotextile bags, the length of anchor rods sleeved in the geotextile bags, the length of a grouting pipe and the diameter of each geotextile bag in a plurality of geotextile bags formed by binding according to the depth of the holes to be drilled, the height of the soil body to be lifted or the distance of the transverse movement, which are obtained according to the monitoring values, wherein the grouting pipe is reserved with the length connected with a grouting pump, and each geotextile bag corresponds to one or more grouting holes in the grouting pipe;
(5) drilling a horizontal hole by using a drilling machine, placing a horizontal grouting pipe, a horizontal anchor rod and a plurality of geotechnical cloth bags extending along the axial direction, and grouting to ensure that each geotechnical cloth bag is filled with cement slurry and solidified grouting body forms a group of horizontal grouting bag to lift the sunken soil body on the ground surface outside the foundation pit or lift the deformed underground pipe, wherein the number of the horizontal grouting bags is multiple, and each group is multiple; or
Drilling an oblique hole by using a drilling machine, placing an oblique grouting pipe, an oblique anchor rod and a plurality of geotechnical cloth bags extending along the axial direction, and grouting to ensure that each geotechnical cloth bag is filled with cement slurry and solidified grouting forms a group of oblique slurry bag to lift the deformed underground pipe outside the foundation pit or transversely support the deformed underground pipe, wherein the oblique slurry bags are arranged in a plurality of rows, and each row is a plurality of groups;
(6) grouting to enable a first construction hole at the outer side end of the steel pipe to be plugged and solidified so as to facilitate water stopping, and cutting a grouting pipe in the steel pipe; or: and (3) plugging and solidifying a second construction hole in the soil body of the gap between the waterproof curtain and the adjacent supporting pile of the supporting row pile by grouting to facilitate water stopping, and cutting a grouting pipe extending out of the inner side of the foundation pit of the second construction hole.
2. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1, wherein: in the step (1), the inner side of the foundation pit of each steel pipe is protruded inwards to the inner surface of the underground continuous wall, and a sealing cover is screwed at the inner side end of the foundation pit of the steel pipe before pre-embedding and after grouting construction is completed; and plugging the outer side end of the foundation pit of each steel pipe by using a temporary plugging material before pre-burying.
3. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1, wherein: in the multi-row steel pipes in the step (1), two rows of adjacent steel pipes are arranged in a staggered manner: the adjacent upper and lower rows of steel pipes are not on the same plumb line.
4. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1, wherein: in the step (3), each row of construction holes are arranged on the foundation pit enclosure wall between the upper part and the lower part of the two rows of support enclosing beams.
5. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1, wherein: in the step (5), the restoration of the ground surface settlement soil body outside the foundation pit or the restoration of the deformed underground pipe is matched with the excavation engineering in the foundation pit: and (3) after the excavation operation in the foundation pit is carried out to the excavation surface of the foundation pit below the foundation pit girth beam below the row of construction holes, pouring the reinforced concrete inner support of the foundation pit, suspending the excavation operation in the foundation pit at the moment, continuing excavating downwards after the reinforced concrete inner support of the foundation pit reaches the preset strength, and carrying out the construction in the step (5) at the position and at the time point.
6. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1, wherein: in the step (5), a plurality of horizontal grouting bags connected to one horizontal grouting pipe are positioned in horizontal holes of soil below the subsidence of the ground surface outside the foundation pit or horizontal holes of soil below the deformed underground pipe outside the foundation pit; the plurality of inclined grouting bags connected to one inclined grouting pipe are positioned in inclined holes of soil bodies on the lateral parts of the deformed underground pipes on the outer sides of the foundation pits or in inclined holes of soil bodies below the deformed underground pipes on the outer sides of the foundation pits.
7. The method for repairing settlement of the ground surface outside the foundation pit enclosure wall or deformation of the underground pipe according to claim 1 or 6, wherein: in the step (5), one end, far away from the foundation pit enclosure wall, of the horizontal anchor rod in the horizontal hole is fixed in the counter bore of the adjacent underground continuous wall, and the horizontal grouting pipe also extends into the counter bore to inject grouting into the counter bore for fixing.
CN202210459961.3A 2022-04-28 2022-04-28 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall Pending CN114687345A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210459961.3A CN114687345A (en) 2022-04-28 2022-04-28 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210459961.3A CN114687345A (en) 2022-04-28 2022-04-28 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Publications (1)

Publication Number Publication Date
CN114687345A true CN114687345A (en) 2022-07-01

Family

ID=82144219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210459961.3A Pending CN114687345A (en) 2022-04-28 2022-04-28 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Country Status (1)

Country Link
CN (1) CN114687345A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538412A (en) * 2022-09-23 2022-12-30 上海建工集团股份有限公司 Building deflection accurate control method in existing building underground horizontal building process
CN117721683A (en) * 2024-01-11 2024-03-19 天津大学 An autonomous lifting control device and method for embankment
CN119571796A (en) * 2024-12-10 2025-03-07 湖南科技大学 Inclined recyclable bladder grouting device and construction method for controlling soil deformation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101798823A (en) * 2010-03-26 2010-08-11 张继红 Construction method of performing remote deviation rectification by passageway method
CN104074195A (en) * 2014-07-21 2014-10-01 浙江华展工程研究设计院有限公司 Method for controlling sedimentation of ground outside foundation pit through horizontal grouting
US20140314502A1 (en) * 2013-04-19 2014-10-23 Henan Polytech Infrastructure Rehabilitation LTD. Polymer grouting method for uplifting ballastless track of high-speed rail
CN105649089A (en) * 2016-01-13 2016-06-08 江西博慧工程技术服务有限公司 Construction method for excavating foundation pit close to existing shallow foundation protection structure
CN205329735U (en) * 2016-01-13 2016-06-22 江西博慧工程技术服务有限公司 Foundation ditch excavation closes on existing shallow foundation protection architecture
CN113737624A (en) * 2021-09-13 2021-12-03 天津大学 Bridge head bump bag type grouting repair construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101798823A (en) * 2010-03-26 2010-08-11 张继红 Construction method of performing remote deviation rectification by passageway method
US20140314502A1 (en) * 2013-04-19 2014-10-23 Henan Polytech Infrastructure Rehabilitation LTD. Polymer grouting method for uplifting ballastless track of high-speed rail
CN104074195A (en) * 2014-07-21 2014-10-01 浙江华展工程研究设计院有限公司 Method for controlling sedimentation of ground outside foundation pit through horizontal grouting
CN105649089A (en) * 2016-01-13 2016-06-08 江西博慧工程技术服务有限公司 Construction method for excavating foundation pit close to existing shallow foundation protection structure
CN205329735U (en) * 2016-01-13 2016-06-22 江西博慧工程技术服务有限公司 Foundation ditch excavation closes on existing shallow foundation protection architecture
CN113737624A (en) * 2021-09-13 2021-12-03 天津大学 Bridge head bump bag type grouting repair construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538412A (en) * 2022-09-23 2022-12-30 上海建工集团股份有限公司 Building deflection accurate control method in existing building underground horizontal building process
CN117721683A (en) * 2024-01-11 2024-03-19 天津大学 An autonomous lifting control device and method for embankment
CN117721683B (en) * 2024-01-11 2024-09-17 天津大学 Embankment autonomous lifting regulation and control device and method
WO2025149073A1 (en) * 2024-01-11 2025-07-17 天津大学 Composite capsule-based control apparatus and method for actively controlling soil deformation
CN119571796A (en) * 2024-12-10 2025-03-07 湖南科技大学 Inclined recyclable bladder grouting device and construction method for controlling soil deformation
CN119571796B (en) * 2024-12-10 2025-09-23 湖南科技大学 Inclined recyclable bladder grouting device for controlling soil deformation and construction method

Similar Documents

Publication Publication Date Title
CN109723065B (en) Reinforcement device and local freezing reinforcement construction method for deep foundation pits in water-rich gravel strata
CN108914931B (en) An assembled vertical shield ring foundation pile and construction method
CN110093928A (en) A kind of foundation pit supporting construction and earth excavation construction method
CN109778992B (en) A horse-riding well device for pipeline construction and its construction method
CN114687345A (en) Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall
CN107542108A (en) A kind of reverse construction method of building basement structure
CN111622268A (en) Protection construction method based on large rigid box culvert passing under power pipe gallery
CN111101540B (en) A construction method for an open-cut tunnel passing through an existing power tunnel
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN1109165C (en) Reinforced concrete post containing steel pipe high-strength column for basement building and construction method
CN212052725U (en) Karst cave area stake construction structures
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN115217098A (en) A cast-in-place pile construction technology
CN113266392B (en) A construction method of pipe jacking through existing anchor cable groups
CN217204058U (en) Foundation pit enclosure wall outside surface subsides or underground pipe deformation repair structure
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
CN110241863B (en) Pipe gallery deformation control device and control method during soft soil foundation pit excavation
CN210766754U (en) Recoverable prestressed anchorage cable stock supporting construction
CN113266362B (en) A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area
CN114215090B (en) Construction method of raft and pile pressing in closed space
CN120486436A (en) Permanent-facing combined enclosure structure suitable for high slope excavation and construction method
CN206157860U (en) Drainage pipeline
CN118911155A (en) Deep foundation pit supporting device and construction method
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220701