CN105696796A - Cantilever scaffold steel girder anchoring method - Google Patents

Cantilever scaffold steel girder anchoring method Download PDF

Info

Publication number
CN105696796A
CN105696796A CN201610095282.7A CN201610095282A CN105696796A CN 105696796 A CN105696796 A CN 105696796A CN 201610095282 A CN201610095282 A CN 201610095282A CN 105696796 A CN105696796 A CN 105696796A
Authority
CN
China
Prior art keywords
floor
concrete
nut
anchor bolt
sleeve pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610095282.7A
Other languages
Chinese (zh)
Inventor
姜志勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huahai Steel Structure Co Ltd
Original Assignee
Jiangsu Huahai Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huahai Steel Structure Co Ltd filed Critical Jiangsu Huahai Steel Structure Co Ltd
Priority to CN201610095282.7A priority Critical patent/CN105696796A/en
Publication of CN105696796A publication Critical patent/CN105696796A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a cantilever scaffold steel girder anchoring method. The method comprises the following steps: after the mounting of a concrete floor bottom die and before the pouring of concrete, fixing a casing pipe on a casing pipe base so as to form a pre-buried pore forming device, and fixing the pre-buried pore forming device at a cantilever scaffold steel girder anchoring position; after the solidification of the concrete, forming two pores which are vertical to a floor; screwing a nut into the upper surface of the floor, screwing a nut into the lower surface of the floor, and after aligning the position of an anchoring bolt, screwing the nuts on the upper and lower surfaces of the floor at the same time so as to fix a steel girder on the floor; and when dismounting is needed after the construction, unscrewing the nut at any one of the upper and lower ends of the anchoring bolt so as to rapidly dismount the anchoring bolt without taking the pre-buried pore forming device out from the floor. Through the casing pipe base, the casing pipe can be vertical to the floor all the time and does not tilt during the pre-burying; the mounting and dismounting are convenient and the connection is stable, so that the construction safety can be ensured; and the method can be repeatedly used, so that the materials are saved, the labor is greatly saved and the working efficiency is improved.

Description

A kind of builder's jack girder steel anchoring process
Technical field
The present invention relates to a kind of builder's jack girder steel anchoring process, belong to building structure technology field。
Background technology
Recent two decades comes, and along with developing rapidly of China's building trade, building structure advances towards higher, more complicated form, and high level, irregular building structure are increasing, and overhanging scaffold ensures often and the necessary requirement of its smooth construction makes consumption huge。Wherein, in builder's jack, the anchoring of girder steel is again the key ensureing builder's jack safety。At present, the anchoring process of most traditional builder's jack girder steels mostly is and adopts crab-bolt cast-in-place among concrete floor。Crab-bolt can only single use, and use complete after also to take a lot of work the Partial Resection beyond floor。The method not only wastes great deal of steel, and a large amount of human and material resources are also wasted in the excision of unnecessary crab-bolt。
Summary of the invention
For above-mentioned prior art Problems existing, it is an object of the invention to provide a kind of stable connection, it is possible to repeatedly use, crab-bolt is installed simple, removes convenient builder's jack girder steel anchoring process。
For achieving the above object, the technical solution used in the present invention is: a kind of builder's jack girder steel anchoring process, comprises the steps:
Step 1: according to actual requirement of engineering, calculate anchorage length and the specification of anchor bolt, position and the quantity of builder's jack girder steel, so as to meet stress and detailing requiments, and then determine the size of pre-buried hole-forming device, position and quantity。
Step 2: after concrete floor bed die is installed, before concreting, sleeve pipe is fixed on sleeve pipe base, forms pre-buried hole-forming device, be fixed on the anchorage point place of builder's jack girder steel;During casting concrete floor, the sleeve position keeping pre-buried is stable, after concrete setting, forms two pore-formings being perpendicular to floor;
Step 3: meet after installation foot hand cradle intensity until concrete strength, cantilever steel girder is placed by design attitude, inserting anchor bolt from floor upper surface, described anchor bolt is respectively successively from being provided with the angle steel pressing plate of through hole, sleeve pipe and sleeve pipe base traverse, and passes from underfloor surface;
Step 4: screwing in nut then the lower surface screw-in nut at floor from the upper surface of floor, behind the position of levelling anchor bolt, girder steel can be fixed on floor by the upper and lower surface of floor tightening nut simultaneously;
Step 5: construct complete need remove time, unscrew the nut of the upper and lower either end of crab-bolt, quickly anchor bolt can be unloaded, remove cantilever steel girder;
Step 6: adopt pea gravel concreten to irrigate closely knit by the anchor bolt reserving hole channel in floorslab concrete。
Preferably, before casting concrete floor, at described sleeve surface brushing interleaving agent。
Preferably, described sleeve pipe surfaces externally and internally is coarse。
The sleeve pipe base of the present invention ensure that sleeve pipe is perpendicular to floor all the time, and will not skew time pre-buried inclination;Installation and removal are convenient, stable connection, it is possible to ensure construction safety;Can repeatedly use, save material, and significantly saved labour, improve work efficiency。
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention;
In figure, 1. sleeve pipe, 2. sleeve pipe base, 3. floor, 4. anchor bolt, 5. angle steel pressing plate, 6. girder steel, 7. nut。
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in further detail。
As it is shown in figure 1, builder's jack girder steel anchoring process comprises the steps:
Step 1: according to actual requirement of engineering, calculate anchorage length and the specification of anchor bolt, position and the quantity of builder's jack girder steel, so as to meet stress and detailing requiments, and then determine the size of pre-buried hole-forming device, position and quantity。
Step 2: after concrete floor bed die is installed, before concreting, sleeve pipe 1 is fixed on sleeve pipe base 2, forms pre-buried hole-forming device, be fixed on the anchorage point place of builder's jack girder steel;During casting concrete floor, keep pre-buried sleeve pipe 1 position stability, after concrete setting, form two pore-formings being perpendicular to floor;
Step 3: meet after installation foot hand cradle intensity until concrete strength, by design attitude placing steel beam 6, inserting anchor bolt 4 from floor 3 upper surface, described anchor bolt 4 is respectively successively from being provided with the angle steel pressing plate 5 of through hole, sleeve pipe 1 and sleeve pipe base 2 traverse, and passes from floor 3 lower surface;
Step 4: screwing in nut 7 then the lower surface screw-in nut 7 at floor 3 from the upper surface of floor 3, behind the position of levelling anchor bolt 4, girder steel 6 can be fixed on floor 3 by the upper and lower surface of floor 3 tightening nut 7 simultaneously;
Step 5: construct complete need remove time, unscrew the nut 7 of the upper and lower either end of crab-bolt, can quickly anchor bolt 4 be unloaded, remove girder steel 6, pre-buried hole-forming device is embedded in floor 3 and does not take out;
Step 6: adopt pea gravel concreten to irrigate closely knit by the anchor bolt reserving hole channel in floor 3 concrete。
Preferably, before casting concrete floor 3, at described sleeve pipe 1 external coating interleaving agent。
Preferably, in order to ensure to combine closely between sleeve pipe 1 energy and surrounding concrete, described sleeve pipe 1 surfaces externally and internally is coarse。Due to sleeve pipe 1 rough inner surface, it is possible to combine closely with the pea gravel concreten poured into, thus the damage that concrete floor is caused reaches minimum。This device convenient disassembly, it is possible to repeatedly use, saves material;Unnecessary part need not be excised, saved manpower and materials。

Claims (3)

1. a builder's jack girder steel anchoring process, it is characterised in that comprise the steps:
Step 1: according to actual requirement of engineering, calculate anchorage length and the specification of anchor bolt, position and the quantity of builder's jack girder steel, so as to meet stress and detailing requiments, and then determine the size of pre-buried hole-forming device, position and quantity。
Step 2: after concrete floor bed die is installed, before concreting, sleeve pipe is fixed on sleeve pipe base, forms pre-buried hole-forming device, be fixed on the anchorage point place of builder's jack girder steel;During casting concrete floor, the sleeve position keeping pre-buried is stable, after concrete setting, forms two pore-formings being perpendicular to floor;
Step 3: meet after installation foot hand cradle intensity until concrete strength, cantilever steel girder is placed by design attitude, inserting anchor bolt from floor upper surface, described anchor bolt is respectively successively from being provided with the angle steel pressing plate of through hole, sleeve pipe and sleeve pipe base traverse, and passes from underfloor surface;
Step 4: screwing in nut then the lower surface screw-in nut at floor from the upper surface of floor, behind the position of levelling anchor bolt, girder steel can be fixed on floor by the upper and lower surface of floor tightening nut simultaneously;
Step 5: construct complete need remove time, unscrew the nut of the upper and lower either end of crab-bolt, quickly anchor bolt can be unloaded, remove cantilever steel girder;
Step 6: adopt pea gravel concreten to irrigate closely knit by the anchor bolt reserving hole channel in floorslab concrete。
2. builder's jack girder steel anchoring process according to claim 1, it is characterised in that before casting concrete floor, at described sleeve surface brushing interleaving agent。
3. builder's jack girder steel anchoring process according to claim 1, it is characterised in that described sleeve pipe surfaces externally and internally is coarse。
CN201610095282.7A 2016-02-19 2016-02-19 Cantilever scaffold steel girder anchoring method Pending CN105696796A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610095282.7A CN105696796A (en) 2016-02-19 2016-02-19 Cantilever scaffold steel girder anchoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610095282.7A CN105696796A (en) 2016-02-19 2016-02-19 Cantilever scaffold steel girder anchoring method

Publications (1)

Publication Number Publication Date
CN105696796A true CN105696796A (en) 2016-06-22

Family

ID=56223285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610095282.7A Pending CN105696796A (en) 2016-02-19 2016-02-19 Cantilever scaffold steel girder anchoring method

Country Status (1)

Country Link
CN (1) CN105696796A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952153A (en) * 2018-07-09 2018-12-07 盐城鑫素元机械制造有限公司 A kind of pre-buried hole-forming device of cast-in-place concrete
CN111395725A (en) * 2020-04-22 2020-07-10 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure
CN111608377A (en) * 2019-02-25 2020-09-01 陕西建工第六建设集团有限公司 Set up overhanging scaffold and comprehensive construction method thereof
CN113152871A (en) * 2021-04-18 2021-07-23 广西建工第一建筑工程集团有限公司 Tool type temporary cantilever steel beam foundation system device and mounting and dismounting use method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306473A (en) * 2012-03-09 2013-09-18 张全胜 Tool type anchoring part for overhanging scaffold
CN104196226A (en) * 2014-09-18 2014-12-10 中建一局集团第二建筑有限公司 Profiled-steel beam fixing anchor structure and construction method thereof
CN204059920U (en) * 2014-09-18 2014-12-31 中建一局集团第二建筑有限公司 A kind of section steel beam fixes earth anchor structure
CN204212392U (en) * 2014-10-16 2015-03-18 中建三局第一建设工程有限责任公司 I iron anchor system
CN204386139U (en) * 2014-12-19 2015-06-10 中建三局集团有限公司 Detachable structural steel anchor device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306473A (en) * 2012-03-09 2013-09-18 张全胜 Tool type anchoring part for overhanging scaffold
CN104196226A (en) * 2014-09-18 2014-12-10 中建一局集团第二建筑有限公司 Profiled-steel beam fixing anchor structure and construction method thereof
CN204059920U (en) * 2014-09-18 2014-12-31 中建一局集团第二建筑有限公司 A kind of section steel beam fixes earth anchor structure
CN204212392U (en) * 2014-10-16 2015-03-18 中建三局第一建设工程有限责任公司 I iron anchor system
CN204386139U (en) * 2014-12-19 2015-06-10 中建三局集团有限公司 Detachable structural steel anchor device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952153A (en) * 2018-07-09 2018-12-07 盐城鑫素元机械制造有限公司 A kind of pre-buried hole-forming device of cast-in-place concrete
CN108952153B (en) * 2018-07-09 2023-09-12 盐城鑫素元机械制造有限公司 Cast-in-place concrete pre-buried pore-forming device
CN111608377A (en) * 2019-02-25 2020-09-01 陕西建工第六建设集团有限公司 Set up overhanging scaffold and comprehensive construction method thereof
CN111608377B (en) * 2019-02-25 2021-09-10 陕西建工第六建设集团有限公司 Comprehensive construction method for building overhanging scaffold
CN111395725A (en) * 2020-04-22 2020-07-10 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure
CN111395725B (en) * 2020-04-22 2021-07-09 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure
CN113152871A (en) * 2021-04-18 2021-07-23 广西建工第一建筑工程集团有限公司 Tool type temporary cantilever steel beam foundation system device and mounting and dismounting use method

Similar Documents

Publication Publication Date Title
CN105220874B (en) The construction method of basement superelevation exterior wall self-supporting single side formwork system
CN105696796A (en) Cantilever scaffold steel girder anchoring method
CN104453224A (en) Formwork support structure of basement exterior wall and construction method of formwork support structure
CN109930455B (en) Municipal road curb mounting structure, construction device and construction method
CN103556819B (en) A kind of construction method of reserved constructional column hole on beam slab
CN105464216A (en) Construction method for ultrahigh oblique post with super-large cross section based on integral lifting formwork reinforcing system
CN207863507U (en) A kind of vertical member displacement apparatus for skyscraper floor
CN207063522U (en) A kind of frame column high-supported formwork
CN205077856U (en) A control of concrete protection layer and horizontal rebar positioning device for silo sliding formwork construction
CN209723607U (en) Adjustable entirety stair tread formwork
CN104213708A (en) Integral construction method of anchor bolt-free fireproof wall
CN105735630A (en) Fixing method for steel beam
CN203452273U (en) Mobile support stool for controlling thickness of cast-in-place slab
CN105220882A (en) A kind of cement waters smashes thickness control device and using method thereof
CN202596148U (en) Reusable cantilever scaffold anchoring compression ring
CN110158424B (en) Concrete pouring template
CN103132494B (en) Embedded anchor cone accurate positioning method
CN204299162U (en) To encorbelment steel I-beam anchor structure
CN110043060A (en) A method of landing frame column is changed to beam post structures
CN204386139U (en) Detachable structural steel anchor device
CN102943484B (en) Tapered-iron pulp-bedding rapid leveling method for large-size and middle-size equipment installation
CN208858150U (en) A kind of close rib building roof mold
CN207295497U (en) A kind of interim steel pipe support base steel plate installation leveling structure
CN112538976A (en) Positioning device and method for pre-buried screw of assembled stair
CN105735631A (en) Anchoring device for cantilever scaffold steel beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160622

RJ01 Rejection of invention patent application after publication