CN105672743A
CN105672743A CN201610162212.9A CN201610162212A CN105672743A CN 105672743 A CN105672743 A CN 105672743A CN 201610162212 A CN201610162212 A CN 201610162212A CN 105672743 A CN105672743 A CN 105672743A
Authority
CN
China
Prior art keywords
base section
block
holding pole
rush
tower system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610162212.9A
Other languages
English (en)
Inventor
黄钰锡
杨磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Power Grid Co Ltd Power Transmission Operation Maintenance Branch
Original Assignee
Guizhou Power Grid Co Ltd Power Transmission Operation Maintenance Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Power Grid Co Ltd Power Transmission Operation Maintenance Branch filed Critical Guizhou Power Grid Co Ltd Power Transmission Operation Maintenance Branch
Priority to CN201610162212.9A priority Critical patent/CN105672743A/zh
Publication of CN105672743A publication Critical patent/CN105672743A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/348Arrangements for demolition towers or the like

Abstract

本发明公开了一种抢修塔组立拆卸轻型抱杆,包括至少两根基础节(1),基础节(1)之间通过连接件(2)相连,位于底端的基础节(1)与抱杆底部支架(5)相连,位于顶端的基础节(1)末端与可绕基础节轴线旋转的V形双滑轮(3)连接,基础节(1)上还连接有抱杆支架(4)。本发明的结构简单新颖,分段式抱杆(基础节),可以降低郊外抢修时运输携带的负载,更进一步,配合抱杆支架,实现抢修塔逐级向上组装的操作方式,相比现有组装好以后再整体吊装的方式速度更快,可靠性更高,难度降低。

Description

抢修塔组立拆卸轻型抱杆
技术领域
本发明涉及用于抢修塔组立拆卸用抱杆,特别是抱杆的结构。
背景技术
当前在组立、拆卸抢修塔时使用的抱杆都是一根整体式杆件,由于该杆件长度长,重量大,对于经常在郊外实施检修抢险工作的人员来说携带非常不方便。另一方面,现有抢修塔组立(拆卸)时基本采用地面组装后整体吊装(整体放倒地面拆卸)的方式,因此,指挥以及配合默契度要求高,难度大,这些问题对于抢修工作都是急需克服的。
发明内容
本发明要解决的技术问题是:提供一种内控自锁梯头滑轮锁定装置,能够快速简单的锁定梯头上端的滑轮,防止因其旋转而带动梯头左右移动,从而方便的固定作业人员的位置。
本发明采用的技术方案是:一种抢修塔组立拆卸轻型抱杆,包括至少两根基础节,基础节之间通过连接件相连,位于底端的基础节与抱杆底部支架相连,位于顶端的基础节末端与可绕基础节轴线旋转的V形双滑轮连接,基础节上还连接有抱杆支架。分段组合式的基础节相比整体式抱杆能够减少携带的负担,对于郊外作业更加便利。另一方面,分段组合的抱杆能够配合分节组立的抢修塔,相互依附,实现逐级安装,稳定可靠。
所述基础节为空心铝质圆管,两端内壁带有螺纹。空心铝质管能够降低组装后抱杆的整体质量,减少检修人员携带和操作的负担。
所述基础节内壁螺纹与连接件两端外缘螺纹匹配。螺纹连接可靠性高,为了提高安全性和防止意外,可设置一根贯穿基础节与连接件连接位置的长螺栓,两端螺母锁紧。
所述抱杆底部支架包括长条形板件,其上开有一对连接孔,连接孔之间为第一贴合块,第一贴合块上设置有弧形面,贴合块一侧为支撑板,长条形板件两端设置有第一连接块。
所述抱杆支架包括方形板件,方形板件中部开有插孔,插孔之间为第二贴合块,第二贴合块表面有凹形槽,方形板件两端设置有第二连接块。
所述V形双滑轮底座通过轴承及固定圈与顶端基础节末端相连。
抱杆支架以及抱杆底部支架均通过U形件插入插孔(连接孔)并旋入螺母实现与基础节的连接。第一、第二贴合块上的弧形面(凹形槽)均是为了增大接触面积和摩擦力,从而能够更好的与基础节表面结合而设置。
本发明的结构简单新颖,分段式抱杆(基础节),可以降低郊外抢修时运输携带的负载,更进一步,配合抱杆支架,实现抢修塔逐级向上组装的操作方式,相比现有组装好以后再整体吊装的方式速度更快,可靠性更高,难度降低。
附图说明
图1是本发明整体结构的示意图;
图2、图9是本发明基础节顶部V形双滑轮结构示意图;
图3、图8是本发明基础节之间连接结构示意图;
图4是本发明抱杆底部支架和抱杆支架与基础节连接示意图;
图5~图7是本发明抱杆底部支架和抱杆支架示意图。
具体实施方式
下面结合说明书附图对本发明进一步说明:
如图1~9所示,一种抢修塔组立拆卸轻型抱杆,包括两根基础节1,基础节1为空心铝质圆管,两端内壁带有螺纹。基础节1之间通过连接件2相连,基础节1内壁螺纹与连接件2两端外缘螺纹匹配。位于底端的基础节1与抱杆底部支架5通过U形件8及螺母相连,位于顶端的基础节1末端与可绕基础节轴线旋转的V形双滑轮3连接,基础节1上还连接有抱杆支架4。抱杆底部支架5包括长条形板件5-1,其上开有一对连接孔,连接孔的孔距等于基础节1的外径,连接孔的孔径等于U形件8的直径,连接孔之间为第一贴合块5-3,第一贴合块5-3上设置有弧形面5-4,贴合块5-3一侧为支撑板5-5,长条形板件5-1两端设置有第一连接块5-5,第一连接块5-5上开有螺孔。抱杆支架4包括方形板件4-1,方形板件4-1中部开有一对插孔4-2,插孔4-2的孔距等于基础节1的外径,插孔4-2的孔径等于U形件8的直径,插孔4-2之间为第二贴合块4-3,第二贴合块4-3表面有凹形槽4-5,方形板件4-1两端设置有第二连接块4-4。V形双滑轮3底座通过轴承9及固定圈7与顶端基础节1末端相连,固定圈7上有一根沿着直径方向贯穿设置的长螺杆10。

Claims (6)

1.一种抢修塔组立拆卸轻型抱杆,其特征在于:包括至少两根基础节(1),基础节(1)之间通过连接件(2)相连,位于底端的基础节(1)与抱杆底部支架(5)相连,位于顶端的基础节(1)末端与可绕基础节轴线旋转的V形双滑轮(3)连接,基础节(1)上还连接有抱杆支架(4)。
2.根据权利要求1所述的一种抢修塔组立拆卸轻型抱杆,其特征在于:所述基础节(1)为空心铝质圆管,两端内壁带有螺纹。
3.根据权利要求2所述的一种抢修塔组立拆卸轻型抱杆,其特征在于:所述基础节(1)内壁螺纹与连接件(2)两端外缘螺纹匹配。
4.根据权利要求1所述的一种抢修塔组立拆卸轻型抱杆,其特征在于:所述抱杆底部支架(5)包括长条形板件(5-1),其上开有一对连接孔,连接孔之间为第一贴合块(5-3),第一贴合块(5-3)上设置有弧形面(5-4),贴合块(5-3)一侧为支撑板(5-5),长条形板件(5-1)两端设置有第一连接块(5-5)。
5.根据权利要求1所述的一种抢修塔组立拆卸轻型抱杆,其特征在于:所述抱杆支架(4)包括方形板件(4-1),方形板件(4-1)中部开有插孔(4-2),插孔(4-2)之间为第二贴合块(4-3),第二贴合块(4-3)表面有凹形槽(4-5),方形板件(4-1)两端设置有第二连接块(4-4)。
6.根据权利要求1所述的一种抢修塔组立拆卸轻型抱杆,其特征在于:所述V形双滑轮(3)底座通过轴承(9)及固定圈(7)与顶端基础节(1)末端相连。
CN201610162212.9A 2016-03-22 2016-03-22 抢修塔组立拆卸轻型抱杆 Pending CN105672743A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610162212.9A CN105672743A (zh) 2016-03-22 2016-03-22 抢修塔组立拆卸轻型抱杆

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610162212.9A CN105672743A (zh) 2016-03-22 2016-03-22 抢修塔组立拆卸轻型抱杆

Publications (1)

Publication Number Publication Date
CN105672743A true CN105672743A (zh) 2016-06-15

Family

ID=56311283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610162212.9A Pending CN105672743A (zh) 2016-03-22 2016-03-22 抢修塔组立拆卸轻型抱杆

Country Status (1)

Country Link
CN (1) CN105672743A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108675159A (zh) * 2018-06-11 2018-10-19 国家电网有限公司 一种组立杆塔用抱杆
CN110697590A (zh) * 2019-11-13 2020-01-17 国网上海市电力公司 一种用于带电撤立电杆的导线提升装置及地电位撤立杆法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202534979U (zh) * 2012-03-23 2012-11-14 上海市电力公司 一种无拉线绝缘抱杆装置
CN202544475U (zh) * 2012-02-09 2012-11-21 湖北省输变电工程公司 一种钢管抱杆
CN102856838A (zh) * 2012-08-31 2013-01-02 国家电网公司 管型母线支柱绝缘子更换工具及更换方法
CN202689671U (zh) * 2012-04-27 2013-01-23 山西省电力公司大同供电分公司 升降式抱杆
CN203377549U (zh) * 2013-08-19 2014-01-01 国家电网公司 塔身附着小抱杆
US20140115977A1 (en) * 2012-10-26 2014-05-01 Emi Products, Inc. Tower structure
CN104453338A (zh) * 2014-10-29 2015-03-25 国家电网公司 一种电杆校正工具
CN205577583U (zh) * 2016-03-22 2016-09-14 贵州电网有限责任公司输电运行检修分公司 抢修塔组立拆卸轻型抱杆

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202544475U (zh) * 2012-02-09 2012-11-21 湖北省输变电工程公司 一种钢管抱杆
CN202534979U (zh) * 2012-03-23 2012-11-14 上海市电力公司 一种无拉线绝缘抱杆装置
CN202689671U (zh) * 2012-04-27 2013-01-23 山西省电力公司大同供电分公司 升降式抱杆
CN102856838A (zh) * 2012-08-31 2013-01-02 国家电网公司 管型母线支柱绝缘子更换工具及更换方法
US20140115977A1 (en) * 2012-10-26 2014-05-01 Emi Products, Inc. Tower structure
CN203377549U (zh) * 2013-08-19 2014-01-01 国家电网公司 塔身附着小抱杆
CN104453338A (zh) * 2014-10-29 2015-03-25 国家电网公司 一种电杆校正工具
CN205577583U (zh) * 2016-03-22 2016-09-14 贵州电网有限责任公司输电运行检修分公司 抢修塔组立拆卸轻型抱杆

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108675159A (zh) * 2018-06-11 2018-10-19 国家电网有限公司 一种组立杆塔用抱杆
CN110697590A (zh) * 2019-11-13 2020-01-17 国网上海市电力公司 一种用于带电撤立电杆的导线提升装置及地电位撤立杆法

Similar Documents

Publication Publication Date Title
US9821417B2 (en) System and method for replacing a pitch bearing
CN1856644B (zh) 在风轮机的轮毂已安装后对风轮机进行维护的方法和设备
US8596700B2 (en) Tower erection lift kit tools
EP3825548B1 (en) Device for mounting wind turbine components and mounting method using said device
CN108190725B (zh) 吊装装置以及机舱吊装方法
US10815687B2 (en) Wind turbine assembly system and associated method
US20140010661A1 (en) Wind turbine blade bearing removal apparatus and method
CN105398990A (zh) 电力角钢塔用辅助提升装置
CN110820522A (zh) 一种悬索桥更换主缆用吊索转换装置、吊索及施工方法
CN105672743A (zh) 抢修塔组立拆卸轻型抱杆
CN205577583U (zh) 抢修塔组立拆卸轻型抱杆
CN205187730U (zh) 电力角钢塔用辅助提升装置
CN203781693U (zh) 特高压输电线路酒杯型铁塔曲臂外侧横担辅助吊装装置
CN107043072B (zh) 免倒梁一体化内爬式塔吊支撑装置及实施方法
CN103950841A (zh) 特高压输电线路酒杯型铁塔曲臂外侧横担辅助吊装装置
CN111511670B (zh) 操纵风力涡轮机部件的方法和具有起重机的风力涡轮机
CN111285304A (zh) 一种具有较高安全性能的矿井升降设备
CN115492399A (zh) 一种从下到上安装调整吊挂钢结构的施工方法
CN115402922A (zh) 用于铁路箱梁防落梁挡块安装的专用吊具装置及使用方法
CN113307162A (zh) 一种塔机附墙的附着装置及其安装工艺
CN112390171A (zh) 一种液压爬模及其倒角模板悬吊机构
CN114059835A (zh) 直升机组立输电线铁塔用的导向组件及使用方法
CN216240392U (zh) 一种起重运输车用爬梯装置
CN220011928U (zh) 一种座地式四摇臂抱杆
CN215924314U (zh) 一种电力施工用排线起落装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160615