CN105544795A - Shear wall reverse building method design and construction processing method - Google Patents

Shear wall reverse building method design and construction processing method Download PDF

Info

Publication number
CN105544795A
CN105544795A CN201510911778.2A CN201510911778A CN105544795A CN 105544795 A CN105544795 A CN 105544795A CN 201510911778 A CN201510911778 A CN 201510911778A CN 105544795 A CN105544795 A CN 105544795A
Authority
CN
China
Prior art keywords
construction
column
inverse conversion
floor
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510911778.2A
Other languages
Chinese (zh)
Other versions
CN105544795B (en
Inventor
张达生
宗静
袁强
王海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CITIC General Institute of Architectural Design and Research Co Ltd
Original Assignee
CITIC General Institute of Architectural Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CITIC General Institute of Architectural Design and Research Co Ltd filed Critical CITIC General Institute of Architectural Design and Research Co Ltd
Priority to CN201510911778.2A priority Critical patent/CN105544795B/en
Publication of CN105544795A publication Critical patent/CN105544795A/en
Application granted granted Critical
Publication of CN105544795B publication Critical patent/CN105544795B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention relates to a shear wall reverse building method design and construction processing method. The method comprises: in construction regions including basement and floors on the upper part of the basement, using basement frame columns or upper structure frame columns as stand columns, constructing reverse construction transfer beams on the stand columns and floor beams in reverse construction transfer beam regions, to make the stand columns support the reverse construction transfer beams and the floor beams, and using the reverse construction transfer beams as temporary supporting members of an upper structure shear wall, and synchronously constructing the upper structure and the underground structure. The method is clever in design concept, flexible in construction and installation, and good in operationality. Through arranging an unloading band on the rear, initial internal force of the beam section of the reverse construction transfer beam, the beam section being required to reserve, so as to realize to combine the reverse construction transfer beam with the floor beams in the region, and reduce material utilization amount of temporary support structures in a reverse construction stage. Using the method to perform shear wall reverse building method design and construction can save cost and reduce construction period, and the method has positive meaning on energy conservation and environment protection.

Description

Shear wall contrary sequence method design and construction processing method
Technical field
The invention belongs to building engineering field, be specifically related to shear wall contrary sequence method design and construction processing method.
Background technology
Along with the development of urban construction, land resources becomes more and more rare, and architectural space has become the developing direction of large-scale construction engineering to ground downward-extension.At present, occurred many large-scale construction engineerings with multi-storey basement, the feature of such engineering is that the basement scale of construction is large, and the number of plies is many, and the Underground Construction cycle is long.For the reduction of erection time, occur that the construction work of reverse construction taked by many need.Adopt contrary sequence method can realize superstructure and basement structure synchronous construction reduction of erection time, and the components such as basement agent structure beam, plate, post can be utilized to replace the temporary support component in foundation pit supporting system to save cost.Though reverse construction possesses many advantages, the reverse construction implementing construction work also has many technological difficulties to need to solve, and wherein the reverse construction of shear wall is exactly one of difficult point.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of easy construction, material-saving timesaving shear wall contrary sequence method design and construction processing method.
Technical scheme provided by the invention is: the inverse work of a kind of shear wall sends out design and construction processing method, in the construction area comprising basement and basement upper floor, utilize basement frame column or superstructure frame column as column, the floor beam of column being constructed in inverse conversion beam and inverse conversion beam region, column is made to support inverse conversion beam and floor beam, utilize inverse conversion beam as the temporary support component of superstructure shear wall, to superstructure and basement structure synchronous construction.
The present invention unloads carrier band by the concrete in 300mm wide region in floor girder span is cut formation after inverse completing, and eliminates in inverse conversion beam the initial internal force needing to retain beam section (floor beam), realizes inverse conversion beam and floor beam unites two into one.
Column is constructed inverse conversion beam and floor beam time the reinforcing bar of floor beam is configured in inverse conversion beam by designing requirement, and replace inverse conversion beam reinforcing bar with the part reinforcing bar of floor beam.
Described column is steel core concrete column in the inverse stage, inverse complete after column periphery parcel steel concrete formed profile steel concrete column.
Inverse conversion beam of the present invention refers to the reinforced concrete beam in the construction stage for support superstructure shear wall.
Design concept of the present invention is ingenious, construction and installation are flexible, workable.
Beneficial effect
Adopt this method carry out shear wall contrary sequence method design and construction process can cost saving, the reduction of erection time, and have meaning very energetically to energy-conserving and environment-protective.
Accompanying drawing explanation
Fig. 1 is shear wall of the present invention inverse do design and construction processing method schematic diagram.
Fig. 2 is that inverse conversion beam and floor beam unite two into one schematic cross-section.
Fig. 3 is that the embodiment of the present invention 1 is constructed the schematic diagram of inverse conversion beam 2 and floor beam 3 on column.
Fig. 4 is the schematic diagram of the embodiment of the present invention 1 superstructure and basement structure synchronous construction.
Fig. 5 is the structural representation after the embodiment of the present invention 1 superstructure and basement structure synchronous construction.
Fig. 6 is that the embodiment of the present invention 1 unloads the schematic diagram of initial internal force to inverse conversion beam 2 and floor beam 3.
Fig. 7 is the embodiment of the present invention 1 by the schematic diagram of the concrete chisel removal be wrapped in around floor beam 3.
Fig. 8 is that the embodiment of the present invention 1 closes the schematic diagram after unloading carrier band.
Detailed description of the invention
Below in conjunction with concrete case study on implementation, set forth the present invention further.Should be understood that those skilled in the art can make various changes or modifications the present invention, and these equivalent form of values fall within the application's appended claims limited range equally after the content of having read the present invention's instruction.
As shown in Figure 1, the present invention is in the construction area comprising basement and basement upper floor, utilize basement frame column or superstructure frame column 11 as column 1, column 1 to be constructed floor beam 3 in inverse conversion beam 2 and inverse conversion beam region, column 1 is made to support inverse conversion beam 2 and floor beam 3, utilize inverse conversion beam 2 as the temporary support component of superstructure shear wall 5, to superstructure and underground structure synchronous construction.
The present invention eliminates in inverse conversion beam by the rearmounted carrier band 4 that unloads the initial internal force needing to retain beam section [floor beam 3], realizes inverse conversion beam 2 and unites two into one with floor beam 3.Its cross section of floor beam 3 in inverse conversion beam 2 region is less than inverse conversion beam 2, and when both merge construction, floor beam 3 is wrapped in inverse conversion beam 2.For not affecting normal use, inversely completing and after bottom shear wall construction puts in place, needing the concrete be wrapped in around floor beam 3 (inverse conversion beam) to cut.Transmit load because this two-in-one beam of inverse stage bears top shear wall as the conversion beam of top shear wall, therefore, inverse complete after there is a larger initial internal force in this beam, this internal force is greater than the internal force of floor beam 3 at serviceability limit stage.For guaranteeing structural safety, need before cutting to unload inverse conversion beam 2 and floor beam 3, to eliminate initial internal force in beam.The unloading manner system that this case is recommended is by eliminating initial internal force in beam at the rearmounted carrier band 4 that unloads of floor beam 3 span centre, namely before cutting the concrete be wrapped in around floor beam 3, first dig out the wide ater-casting of 300mm at floor beam 3 span centre and unload carrier band unloading as rearmounted, and then the concrete cut around floor beam 3 cross section, close again after the work of cutting completes and unload carrier band.
As shown in Figure 2, described construct on column 1 inverse conversion beam 2 and floor beam 3 time the reinforcing bar (A) of floor beam 3 is configured in inverse conversion beam 2 by designing requirement, and replace the part reinforcing bar of inverse conversion beam 2 with the reinforcing bar of floor beam 3 (A1).
Described column 1 is steel core concrete column in the inverse stage, inverse complete after column 1 periphery parcel steel concrete formed profile steel concrete column.
Shear wall 6 below one deck until basement is inverse complete after adopt the positive practice to construct.
Embodiment 1
Certain engineering superstructure adopts frame-shear-wall structure system, if three layers of basement, and basement building area about 110,000 m 2, for meeting superstructure construction period, need reverse construction be adopted.For realizing inverse demand, the inverse scheme that design proposes as shown in figures 3-8 is as follows:
1. as shown in Figure 3, basis adopts bored pile 7, utilizes basement frame column or superstructure frame column as column 1, and column 1 adopts steel core concrete column in the inverse stage, is inserted in stake 7 by column 1 when bored pile 7 is constructed.
2. establish inverse phase transition beam 2 in shear wall region and form frame construction with column 1; Inverse conversion beam is located at one deck.
3. during construction inverse conversion beam 2, the reinforcing bar (A) of the floor beam 3 in region is configured in inverse conversion beam 2 by designing requirement, and replaces inverse conversion beam 2 part reinforcing bar with the reinforcing bar of floor beam 3 (A1), concrete detail drawing 2.
4. as shown in Figure 4 and Figure 5, with inverse conversion beam 2 and column 1 for rest is to superstructure (comprising superstructure shear wall 5, frame column 11, beam 10, top floor plate) and basement structure (comprising basement floor beam 9, basement floor plate and cushion cap 8) synchronous construction; Shear wall 6 below one deck until basement is inverse complete after adopt the positive practice to construct.
5. its cross section of floor beam 3 in inverse conversion beam 2 region and internal force are all less than inverse conversion beam 2, and when both merge construction, floor beam 3 is wrapped in inverse conversion beam 2.For not affecting normal use, inversely completing and need the concrete chisel removal (as shown in Figure 7) that will be wrapped in around floor beam 3 after bottom shear wall 6 construction puts in place.Because this two-in-one beam of inverse stage bears as the conversion beam of top shear wall 5 load that top shear wall 5 transmits, therefore, inverse complete after there is a larger initial internal force in this beam, this internal force is greater than the internal force of floor beam 3 at serviceability limit stage.For guaranteeing structural safety, need before cutting to unload (as shown in Figure 6) inverse conversion beam 2 and floor beam 3, to eliminate initial internal force in beam.This case unloading manner system is by bringing initial internal force in elimination beam rearmounted the unloading of floor beam 3 span centre, namely before cutting the concrete be wrapped in around floor beam 3, the ater-casting of first digging out 300mm wide at floor beam 3 span centre unloads as the rearmounted carrier band 4 that unloads, and then the concrete cut around floor beam 3 cross section, close again after the work of cutting completes and unload carrier band 4(as shown in Figure 8).

Claims (4)

1. a shear wall contrary sequence method design and construction processing method, it is characterized in that: in the construction area comprising basement and basement upper floor, utilize basement frame column or superstructure frame column as column (1), column to be constructed floor beam (3) in inverse conversion beam (2) and inverse conversion beam region, column (1) is made to support inverse conversion beam (2) and floor beam (3), utilize inverse conversion beam (2) as the temporary support component of superstructure shear wall (5), to superstructure and underground structure synchronous construction.
2. method according to claim 1, it is characterized in that: inverse complete after, carrier band (4) is unloaded by being formed by the concrete chisel removal in floor beam (3) span centre 300mm wide region, eliminate in inverse conversion beam the initial internal force needing to retain beam section, realize inverse conversion beam (2) and unite two into one with floor beam (3).
3. method according to claim 1, it is characterized in that: when column (1) upper construction inverse conversion beam (2) and floor beam (3), the reinforcing bar (A1) of floor beam (3) is configured in inverse conversion beam (2) by designing requirement, and replaces inverse conversion beam (2) reinforcing bar with the part reinforcing bar of floor beam (3).
4. method according to claim 1, is characterized in that: column (1) is steel core concrete column in the inverse stage, inverse complete after column (1) periphery parcel steel concrete formed profile steel concrete column.
CN201510911778.2A 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method Active CN105544795B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510911778.2A CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510911778.2A CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Publications (2)

Publication Number Publication Date
CN105544795A true CN105544795A (en) 2016-05-04
CN105544795B CN105544795B (en) 2017-09-01

Family

ID=55824310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510911778.2A Active CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Country Status (1)

Country Link
CN (1) CN105544795B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09228398A (en) * 1996-02-26 1997-09-02 Taisei Corp Construction method for pile support type multistoried building
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
KR100938916B1 (en) * 2009-06-29 2010-01-27 김미선 Downward method by front reaming
TW201022505A (en) * 2008-12-05 2010-06-16 jian-shun Huang Bottom-up and top-down combined construction method for building basement excavation
CN201598652U (en) * 2010-01-12 2010-10-06 上海市第一建筑有限公司 Bidirectional synchronous construction converting structure
CN201679147U (en) * 2009-12-04 2010-12-22 上海市第二建筑有限公司 Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09228398A (en) * 1996-02-26 1997-09-02 Taisei Corp Construction method for pile support type multistoried building
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
TW201022505A (en) * 2008-12-05 2010-06-16 jian-shun Huang Bottom-up and top-down combined construction method for building basement excavation
KR100938916B1 (en) * 2009-06-29 2010-01-27 김미선 Downward method by front reaming
CN201679147U (en) * 2009-12-04 2010-12-22 上海市第二建筑有限公司 Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building
CN201598652U (en) * 2010-01-12 2010-10-06 上海市第一建筑有限公司 Bidirectional synchronous construction converting structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄玉林: "超高建筑虹口商城结构双向同步施工技术", 《上海建设科技》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement

Also Published As

Publication number Publication date
CN105544795B (en) 2017-09-01

Similar Documents

Publication Publication Date Title
CN102877582B (en) Composite floor with steel bar trusses, profiled steel plate and regenerated concrete, and manufacturing method for composite floor
CN103161168A (en) Detachable prestress supporting frame system
CN103147526A (en) Strip-shaped grate concrete filled steel tube combined structure shear wall and preparation method thereof
CN105133731B (en) A kind of assembled steel performance
CN105113537A (en) Vertical support system constructed through reverse construction method and method for vertical support system
CN104790675A (en) Reinforced concrete block masonry structure assemblage construction method
CN104389364A (en) Profiled steel plate concrete reinforcing steel plate energy dissipation wall
WO2018068504A1 (en) N-type connection prefabricated split column used for underground structure
CN201901879U (en) Nonstandard foundation used for fixing tower crane
CN106088657A (en) The ruggedized construction of a kind of rowlock wall body and construction method thereof
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN103046743B (en) A kind of Super High conversion layer steel reinforced concrete crossbeam suspension type form bracing system and construction method
CN203640061U (en) Node connecting structure of reinforced concrete column of basement
CN104060763A (en) Z-shaped steel pipe-steel framework recycled concrete combined pillar
CN104594389A (en) Post-cast strip external wall plugging structure with elastic water stoppers
CN105544795A (en) Shear wall reverse building method design and construction processing method
CN107313551A (en) A kind of concrete prefabricated wallboard of steel bar girder and structural system and its construction method
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN107816126A (en) A kind of embedded prefabricated post of assembly concrete and prefabricated balcony
CN103437349B (en) The construction method of steel concrete perfusion shaped pile
CN104060762A (en) L-shaped steel pipe-steel framework recycled concrete combined pillar
CN104088400A (en) T-shaped steel pipe-steel rib recycled concrete combination column
CN207739510U (en) A kind of reinforced cold-bent pipe concrete column and structural system
CN208396338U (en) Load bearing wall underground construction underpins support system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant