Load bearing wall underground construction underpins support system Download PDF

Info

Publication number
CN208396338U
CN208396338U CN201820716859.6U CN201820716859U CN208396338U CN 208396338 U CN208396338 U CN 208396338U CN 201820716859 U CN201820716859 U CN 201820716859U CN 208396338 U CN208396338 U CN 208396338U
Authority
CN
China
Prior art keywords
support
bearing wall
load bearing
supporting leg
support system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820716859.6U
Other languages
Chinese (zh)
Inventor
卢明全
孙肃
许文贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiuding Sanli Construction Group Co ltd
Original Assignee
JIUDING SPECIAL ARCHITECTURE ENGINEERING Co Ltd DALIAN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIUDING SPECIAL ARCHITECTURE ENGINEERING Co Ltd DALIAN filed Critical JIUDING SPECIAL ARCHITECTURE ENGINEERING Co Ltd DALIAN
Priority to CN201820716859.6U priority Critical patent/CN208396338U/en
Application granted granted Critical
Publication of CN208396338U publication Critical patent/CN208396338U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of load bearing wall underground constructions to underpin support system, is used to support between the support beam of top bearing wall and supporting leg and is fixedly connected, and supporting leg is fixedly connected with the support raft plate of the stake holes two sides below pre-demolition wall.The technical effect of the utility model are as follows: the support system is the underpinning structure of an Iterim Change superstructure load transmission path, it may be implemented to form working space under masonry load bearing wall, shape-designing does not interfere to construct and there are enough operating spaces to construction.It is bolted easy for assemble or unload, using structure steel fabrication high-strength light, can recycle entirely.

Description

Load bearing wall underground construction underpins support system
Technical field
The utility model relates to a kind of load bearing wall support construction, in particular to a kind of load bearing wall underground construction underpins supporter System.
Background technique
In recent years, old residential area is transformed into the emphasis of city integrated transformation, and the house in old residential area is mostly last century The 80s and 90s builds earlier, and based on multistory brick-and-concrete structure, the underground space is not developed.And in the transformation of old residential area Old residential area value can most be promoted is exactly to add the underground space, solves the problems, such as that land utilization ratio is low with " parking difficulty ".It will be It is exactly that slab is applied to add artificial digging pile transformational structure that the optimal method of the underground space is added under brick mix structure, and wherein stake can be with Also serve as the use of basement column.Since the load bearing wall of multistory brick-and-concrete structure is densely distributed, and underground parking needs Large Column Spacing, often There is the case where top load bearing wall and stake bit swiping.For this problem, previous solution is as follows:
(1) load bearing wall is avoided when laying out pile, etc. the underground spaces formed after pull out the unreasonable column in position, and be displaced to conjunction Suitable position.Do so that design difficulty is big, construction risk is high, at high cost, although realizing the reasonable of the underground space under building It utilizes, but great number cost impact original building value promotion space.
(2) space directly under inhering architecture is only used as storage not as parking stall.Underground space utilization rate It is low, then it is substantially nonsensical to building functions and value promotion to add the underground space.
Utility model content
The utility model is used primarily in the stake raft transformational structure work progress for adding the underground space under brick mix structure, is one A temporary support structure mainly solves the problems, such as that artificial digging pile stake position conflicts and can not construct with masonry load-bearing wall displacement, for The deficiency of existing solution proposes a kind of method that assembling type steel structure support is added under masonry load bearing wall, this support Load bearing wall is temporarily held up, the operating space of construction stake under wall is formed in, realizes the requirement flexibly to lay out pile.
The technical solution adopted in the utility model is: load bearing wall underground construction underpins support system, is used to support top and holds It is fixedly connected between the support beam and supporting leg of weight wall, the support raft of the stake holes two sides below supporting leg and pre-demolition wall Plate is fixedly connected.
It is bolted between the support beam and supporting leg, is connected between supporting leg and support raft plate by bolt It connects.
Main view is in " n " shape after the support beam is connect with supporting leg, and overlooking is in " x " shape.
The support beam material is metal, and the supporting leg material is metal.
The support beam material is steel, and the supporting leg material is steel.
The technical effect of the utility model are as follows: the support system is an Iterim Change superstructure load transmission path Underpinning structure may be implemented to form working space under masonry load bearing wall, and shape-designing does not interfere to construct and to construction There are enough operating spaces.It is bolted entirely easy for assemble or unload, using structure steel fabrication high-strength light, benefit can be recycled With.
Detailed description of the invention
Fig. 1 is that load bearing wall underground construction underpins support system structural schematic diagram;
Fig. 2 is the A-A view of Fig. 1;
Fig. 3 is the B-B view of Fig. 1.
Appended drawing reference is as follows: the top 1- bearing wall;2- pre-demolition wall;3- support beam;4- supporting leg;5- supports raft Plate;6- stake holes
Specific embodiment
Support system is underpined to load bearing wall underground construction with reference to the accompanying drawing to be further described.
This load bearing wall underground construction underpins support system, and load bearing wall underground construction underpins support system, is used to support It is bolted to connection between the support beam 3 and supporting leg 4 of portion's bearing wall 1,2 lower section of supporting leg 4 and pre-demolition wall The support raft plates 5 of 6 two sides of stake holes be bolted to connection.Main view is in " n " shape after support beam 3 is connect with supporting leg 4, is bowed Depending on being in " x " shape.In order to increase the rigidity of support system, 3 material of support beam is steel, and 4 material of supporting leg is steel.
This steel structure support is fabricated, it can the support system under the masonry load bearing wall of recycling.Specially It is existing masonry structure house under the premise of retaining original superstructure, the basic components such as local excavation's underground artificial digging pile The temporary support of setting.It can guarantee that the load of top masonry structure is passed by the facility when excavating local underground installation To ground, guarantee the safety and stability of superstructure.
Installation process is as follows:
1, it first drills on former masonry wall, then the support beam 3 of the device is installed, support beam is installed in the two sides Yuan Qiang After 3, two support beams 3 are fixed on original wall body with bolt, are used to support top bearing wall 1.
2, it drills on support raft plate 5, bar planting bolt is installed, then the supporting leg 4 of four steel is installed in the two sides of former wall, Four supporting legs 4 are fixed on support raft plate 5 with bolt after positioning.
3, four supporting legs 4 and two installations of support beam 3 are linked together with installation bolt, such as Fig. 3.Thus shape At a complete force transfer system between stable wall and support raft plate 5, such as Fig. 1.
4, the device after the installation is completed, both can be in its lower construction for excavating the underground installations such as pile foundation.Underground pile driving construction is complete Cheng Hou, i.e., the detachable covering device, carries out repeated recycling utilize.

Claims (5)

1. load bearing wall underground construction underpins support system, it is characterised in that: be used to support the support beam of top bearing wall with It is fixedly connected between supporting leg, supporting leg is fixedly connected with the support raft plate of the stake holes two sides below pre-demolition wall.
2. load bearing wall underground construction according to claim 1 underpins support system, it is characterised in that: the support beam It is bolted between supporting leg, is bolted between supporting leg and support raft plate.
3. load bearing wall underground construction according to claim 1 underpins support system, it is characterised in that: the support beam Main view is in " n " shape after connecting with supporting leg, and overlooking is in " x " shape.
4. load bearing wall underground construction according to claim 1 underpins support system, it is characterised in that: the support beam Material is metal, and the supporting leg material is metal.
5. load bearing wall underground construction according to claim 4 underpins support system, it is characterised in that: the support beam Material is steel, and the supporting leg material is steel.
CN201820716859.6U 2018-05-15 2018-05-15 Load bearing wall underground construction underpins support system Active CN208396338U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820716859.6U CN208396338U (en) 2018-05-15 2018-05-15 Load bearing wall underground construction underpins support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820716859.6U CN208396338U (en) 2018-05-15 2018-05-15 Load bearing wall underground construction underpins support system

Publications (1)

Publication Number Publication Date
CN208396338U true CN208396338U (en) 2019-01-18

Family

ID=65136570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820716859.6U Active CN208396338U (en) 2018-05-15 2018-05-15 Load bearing wall underground construction underpins support system

Country Status (1)

Country Link
CN (1) CN208396338U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863714A (en) * 2021-11-08 2021-12-31 中铁上海工程局集团有限公司 Memorial archway in-situ protection foundation underpinning structure and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863714A (en) * 2021-11-08 2021-12-31 中铁上海工程局集团有限公司 Memorial archway in-situ protection foundation underpinning structure and construction method

Similar Documents

Publication Publication Date Title
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN105735325B (en) A kind of intensive permanent support assembled basement structure system and construction method
CN106088650B (en) A kind of method and building suitable for building with brick-concrete structure underground increasing layer
CN102477781A (en) Integrally assembled steel-concrete superposed component and manufacturing method thereof
CN101418569A (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN104179249A (en) Assembled composite-structure earthquake-resistant wall and assembly method thereof
CN106869567A (en) A kind of energy-dissipating type cold-formed thin-walled steel pipe concrete Lateral Resistant System
CN103397695B (en) The concrete filled steel tube coupled column high-position conjoined structure of two-way steel truss is set
CN100362200C (en) Supporting displacement method for lifting component and supporting system thereof
CN110387889B (en) Multi-arch foundation pit supporting method for strip-shaped deep foundation pit
CN208396338U (en) Load bearing wall underground construction underpins support system
CN205636751U (en) Assembled forming structures system towards secret building of multilayer
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN102003030A (en) Prefabricated coal gangue concrete hollow shear wallboard
WO2017024844A1 (en) Bolt connection structure between column and beam in aluminum alloy house
CN207211869U (en) A kind of basic digging-free assembled tower-type space garage
CN201133089Y (en) Loading transferring device for roof beam changing to floor joist
CN103469892B (en) The primary and secondary modular unit combining structure in high-rise building module space and method of attachment
CN102392417A (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN207121922U (en) A kind of foundation structure in digging-free assembled stereoscopic garage
CN211172365U (en) Assembled low-rise residential structure system
CN210395394U (en) Steel structure foundation for long-distance construction of large modular structure
CN201883422U (en) Fabricated steel guide wall for underground continuous wall
CN204960366U (en) Tunnel passes through device that underpins of existing large diameter pile building
Pujadas Gispert Prefabricated foundations for housing applied to room modules

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Room 815, Free Trade Building, Dalian Free Trade Zone, Liaoning Province, 116023

Patentee after: Jiuding Sanli Construction Group Co.,Ltd.

Address before: Room 2818, Chenxi Xinghai International Building, No. 692 Zhongshan Road, Shahekou District, Dalian City, Liaoning Province, 116023

Patentee before: DALIAN JIUDING SPECIAL CONSTRUCTION ENGINEERING CO.,LTD.

CP03 Change of name, title or address