CN105544795B - Shear wall contrary sequence method design and construction processing method - Google Patents
Shear wall contrary sequence method design and construction processing method Download PDFInfo
- Publication number
- CN105544795B CN105544795B CN201510911778.2A CN201510911778A CN105544795B CN 105544795 B CN105544795 B CN 105544795B CN 201510911778 A CN201510911778 A CN 201510911778A CN 105544795 B CN105544795 B CN 105544795B
- Authority
- CN
- China
- Prior art keywords
- column
- inverse
- inverse conversion
- floor
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention relates to a kind of shear wall contrary sequence method design and construction processing method, in the construction area including basement and basement upper floor, column is used as by the use of basement frame column or superstructure frame column, the floor beam constructed on column in inverse conversion beam and inverse conversion beam region, column is set to support inverse conversion beam and floor beam, by the use of inverse conversion beam as the temporary support component of superstructure shear wall, to superstructure and underground structure synchronous construction.Design concept of the present invention is ingenious, construction and installation are flexible, workable.The initial internal force of beam section need to be retained by the rearmounted inverse conversion beam of carrier band elimination that unloads, realize that inverse conversion beam unites two into one with the floor beam in the region, reduce inverse stage temporary support structures material usage.Expense, shortening duration can be saved by carrying out shear wall contrary sequence method design and construction processing using this method, and have very positive meaning to energy-conserving and environment-protective.
Description
Technical field
The invention belongs to building engineering field, and in particular to shear wall contrary sequence method design and construction processing method.
Background technology
With the development of urban construction, land resource becomes more and more rare, and space has become to underground extension
The developing direction of large-scale construction engineering.At present, many large-scale construction engineerings for carrying multi-storey basement are occurred in that, such engineering
Feature is that the basement scale of construction is big, and the number of plies is more, and the Underground Construction cycle is long.To shorten the duration, many need to take against work is occurred in that
The architectural engineering of method construction.It can realize that superstructure shortens the duration with basement structure synchronous construction using contrary sequence method, and
The temporary support component in foundation pit supporting system can be replaced to save cost using components such as basement agent structure beam, plate, posts.
Though reverse construction possesses many advantages, to implement the reverse construction of architectural engineering also has many technological difficulties to need solution
Certainly, the reverse construction of wherein shear wall is exactly one of difficult point.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of easy construction, the shear wall contrary sequence method design of section material timesaving
Construction treating methods.
The technical scheme that the present invention is provided is:A kind of shear wall is inverse to make hair design and construction processing method, including basement
And in the construction area of basement upper floor, by the use of basement frame column or superstructure frame column as column, in column
The upper floor beam constructed in inverse conversion beam and inverse conversion beam region, makes column support inverse conversion beam and floor beam, utilizes
Inverse conversion beam as superstructure shear wall temporary support component, to superstructure and basement structure synchronous construction.
The present invention after the completion of inverse by cutting to form unloading the concrete in floor girder span in 300mm wide scopes
Band, eliminate needs to retain beam section in inverse conversion beam(Floor beam)Initial internal force, realize that inverse conversion beam and floor beam close two and be
One.
Constructed on column inverse conversion beam and floor beam when by the reinforcing bar of floor beam by design requirement configure at inverse turn
Change in beam, and inverse conversion beam steel is replaced with the part reinforcing bar of floor beam.
The column the inverse stage be steel core concrete column, it is inverse after the completion of column periphery parcel armored concrete shape
Into profile steel concrete column.
Inverse conversion beam of the present invention refers to be used for the armored concrete of support superstructure shear wall in the construction stage
Beam.
Design concept of the present invention is ingenious, construction and installation are flexible, workable.
Beneficial effect
Expense, shortening duration can be saved by carrying out shear wall contrary sequence method design and construction processing using this method, and to section
Can environmental protection have very energetically meaning.
Brief description of the drawings
Fig. 1, which is that shear wall of the present invention is inverse, makees design and construction processing method schematic diagram.
Fig. 2 is that inverse conversion beam and floor beam unite two into one schematic cross-section.
Fig. 3 is that the embodiment of the present invention 1 is constructed the schematic diagram of inverse conversion beam 2 and floor beam 3 on column.
Fig. 4 is the schematic diagram of the superstructure of the embodiment of the present invention 1 and basement structure synchronous construction.
Fig. 5 is the structural representation after the superstructure of the embodiment of the present invention 1 and basement structure synchronous construction.
Fig. 6 is the schematic diagram that the embodiment of the present invention 1 unloads initial internal force to inverse conversion beam 2 and floor beam 3.
Fig. 7 is the embodiment of the present invention 1 by the schematic diagram for the concrete chisel removal being wrapped in around floor beam 3.
Fig. 8 is that the embodiment of the present invention 1 closes the schematic diagram unloaded after carrier band.
Embodiment
With reference to specific implementation case, the present invention is expanded on further.It should be understood that reading the content of the invention lectured
Afterwards, those skilled in the art can make various changes or modifications to the present invention, and these equivalent form of values equally fall within the application institute
Attached claims limited range.
As shown in figure 1, the present invention utilizes basement frame in the construction area including basement and basement upper floor
Trestle or superstructure frame column 11 are as column 1, and construct inverse conversion beam 2 and inverse conversion beam region Nei Lou on column 1
Layer beam 3, makes column 1 support inverse conversion beam 2 and floor beam 3, utilizes inverse the facing as superstructure shear wall 5 of conversion beam 2
When supporting member, to superstructure and underground structure synchronous construction.
The present invention eliminates the initial internal force for needing to retain beam section [floor beam 3] in inverse conversion beam by the rearmounted carrier band 4 that unloads, real
Existing inverse conversion beam 2 unites two into one with floor beam 3.Its section of floor beam 3 in the inverse region of conversion beam 2 is less than inverse conversion beam
2, floor beam 3 is wrapped in inverse conversion beam 2 when both merge construction.It is inverse to complete and treat bottom not influence normally to use
Shear wall construction needs the concrete that will be wrapped in around floor beam 3 afterwards in place(Inverse conversion beam)Cut.Because the inverse stage should
Two-in-one beam bears top shear wall as the conversion beam of top shear wall and transmits load, therefore, it is inverse after the completion of in the beam
In the presence of a larger initial internal force, the internal force is more than internal force of the floor beam 3 in serviceability limit stage.To ensure structure safety,
Need to unload inverse conversion beam 2 and floor beam 3 before cutting, to eliminate initial internal force in beam.The unloading manner that this case is recommended
System is wrapped in around floor beam 3 cutting by eliminating initial internal force in beam in the rearmounted carrier band 4 that unloads of floor beam 3 span centre, i.e.,
Before concrete, a wide post-cast strip of 300mm is first dug out as rearmounted in the span centre of floor beam 3 and unloads carrier band unloading, is then dug again
It is re-closed after the completion of work to be cut to unload carrier band except the concrete around the section of floor beam 3.
As shown in Fig. 2 it is described constructed on column 1 inverse conversion beam 2 and floor beam 3 when by the reinforcing bar of floor beam 3(A)Press
Design requirement is configured in inverse conversion beam 2, and with the reinforcing bar of floor beam 3(A1)Instead of the part reinforcing bar of inverse conversion beam 2.
The column 1 is steel core concrete column in the inverse stage, it is inverse after the completion of in the periphery of column 1 parcel armored concrete
Form profile steel concrete column.
Less than one layer of shear wall 6 treats basement after the completion of inverse using the construction of the positive practice.
Embodiment 1
Certain engineering superstructure uses frame-shear-wall structure system, if three layers of basement, basement construction area about 11
Ten thousand m2, to meet superstructure construction period, reverse construction need to be used.To realize inverse demand, design is proposed such as Fig. 3-8 institutes
The inverse scheme shown is as follows:
1. as shown in figure 3, basis uses cast-in-situ bored pile 7, by the use of basement frame column or superstructure frame column as
Column 1, column 1 uses steel core concrete column in the inverse stage, and cast-in-situ bored pile 7 inserts column 1 in stake 7 when constructing.
2. set inverse phase transition beam 2 in shearing wall zone and constitute frame structure with column 1;Inverse conversion beam is located at one
Layer.
3. by the reinforcing bar of the floor beam 3 in region during the inverse conversion beam 2 of construction(A)By design requirement configuration in inverse conversion
In beam 2, and with the reinforcing bar of floor beam 3(A1)Instead of the inverse part reinforcing bar of conversion beam 2, specific detail drawing 2.
4. it is as shown in Figure 4 and Figure 5, rest to superstructure with inverse conversion beam 2 and column 1(Cut including superstructure
Power wall 5, frame column 11, beam 10, top floorboard)And basement structure(Including basement floor beam 9, basement floorboard and
Cushion cap 8)Synchronous construction;Less than one layer of shear wall 6 treats basement after the completion of inverse using the construction of the positive practice.
5. its section of floor beam 3 and internal force in the inverse region of conversion beam 2 are respectively less than inverse conversion beam 2, both apply in merging
Man-hour floor beam 3 is wrapped in inverse conversion beam 2.It is inverse to complete and treat that the construction of bottom shear wall 6 is arrived not influence normally to use
The concrete chisel removal that will be wrapped in around floor beam 3 is needed behind position(As shown in Figure 7).Because the two-in-one beam of inverse stage is as upper
The conversion beam of portion's shear wall 5 bears the load that top shear wall 5 is transmitted, therefore, it is inverse after the completion of exist in the beam one compared with
Big initial internal force, the internal force is more than internal force of the floor beam 3 in serviceability limit stage.To ensure structure safety, needed before cutting pair
Inverse conversion beam 2 and floor beam 3 are unloaded(As shown in Figure 6), to eliminate initial internal force in beam.This case unloading manner system passes through
Bring initial internal force in elimination beam in rearmounted unload of the span centre of floor beam 3, i.e., cut the concrete that is wrapped in around floor beam 3 it
Before, first dig out a wide post-cast strip of 300mm in the span centre of floor beam 3 and unloaded as the rearmounted carrier band 4 that unloads, floor beam is then cut again
Concrete around 3 sections, it is re-closed after the completion of work to be cut to unload carrier band 4(As shown in Figure 8).
Claims (3)
- The processing method 1. a kind of shear wall contrary sequence method is designed and constructed, it is characterized in that:Including basement and basement upper floor Construction area in, by the use of basement frame column or superstructure frame column as column (1), inverse conversion of being constructed on column Floor beam in beam (2) and inverse conversion beam region(3), make column(1)Support inverse conversion beam(2)With floor beam(3), using inverse Apply conversion beam(2)It is used as superstructure shear wall(5)Temporary support component, to superstructure and underground structure synchronous construction; After the completion of inverse, by by floor beam(3)Carrier band is unloaded in concrete chisel removal formation in span centre 300mm wide scopes(4), eliminate inverse The initial internal force of reservation beam section is needed in conversion beam, inverse conversion beam is realized(2)With floor beam(3)Unite two into one.
- 2. according to the method described in claim 1, it is characterized in that:Constructed on column (1) inverse conversion beam(2)With floor beam (3)When by floor beam(3)Reinforcing bar(A1)By design requirement configuration in inverse conversion beam(2)It is interior, and with floor beam(3)Part Reinforcing bar replaces inverse conversion beam(2)Reinforcing bar.
- 3. according to the method described in claim 1, it is characterized in that:Column (1) is steel core concrete column in the inverse stage, inverse complete After in column (1) periphery parcel armored concrete formation profile steel concrete column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510911778.2A CN105544795B (en) | 2015-12-11 | 2015-12-11 | Shear wall contrary sequence method design and construction processing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510911778.2A CN105544795B (en) | 2015-12-11 | 2015-12-11 | Shear wall contrary sequence method design and construction processing method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105544795A CN105544795A (en) | 2016-05-04 |
CN105544795B true CN105544795B (en) | 2017-09-01 |
Family
ID=55824310
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510911778.2A Active CN105544795B (en) | 2015-12-11 | 2015-12-11 | Shear wall contrary sequence method design and construction processing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105544795B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110017024A (en) * | 2019-04-22 | 2019-07-16 | 上海建工一建集团有限公司 | The construction method of the horizontal girder steel of contrary sequence method basement |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09228398A (en) * | 1996-02-26 | 1997-09-02 | Taisei Corp | Construction method for pile support type multistoried building |
CN1279319A (en) * | 1999-06-29 | 2001-01-10 | 陈星� | Full-reverse construction technology for basement |
KR100938916B1 (en) * | 2009-06-29 | 2010-01-27 | 김미선 | Downward method by front reaming |
TW201022505A (en) * | 2008-12-05 | 2010-06-16 | jian-shun Huang | Bottom-up and top-down combined construction method for building basement excavation |
CN201598652U (en) * | 2010-01-12 | 2010-10-06 | 上海市第一建筑有限公司 | Bidirectional synchronous construction converting structure |
CN201679147U (en) * | 2009-12-04 | 2010-12-22 | 上海市第二建筑有限公司 | Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building |
-
2015
- 2015-12-11 CN CN201510911778.2A patent/CN105544795B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09228398A (en) * | 1996-02-26 | 1997-09-02 | Taisei Corp | Construction method for pile support type multistoried building |
CN1279319A (en) * | 1999-06-29 | 2001-01-10 | 陈星� | Full-reverse construction technology for basement |
TW201022505A (en) * | 2008-12-05 | 2010-06-16 | jian-shun Huang | Bottom-up and top-down combined construction method for building basement excavation |
KR100938916B1 (en) * | 2009-06-29 | 2010-01-27 | 김미선 | Downward method by front reaming |
CN201679147U (en) * | 2009-12-04 | 2010-12-22 | 上海市第二建筑有限公司 | Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building |
CN201598652U (en) * | 2010-01-12 | 2010-10-06 | 上海市第一建筑有限公司 | Bidirectional synchronous construction converting structure |
Non-Patent Citations (1)
Title |
---|
超高建筑虹口商城结构双向同步施工技术;黄玉林;《上海建设科技》;20100430;第45页第1段至第49页第47页第2栏尾端,图1-6 * |
Also Published As
Publication number | Publication date |
---|---|
CN105544795A (en) | 2016-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101787738B (en) | Stair connection joint device | |
CN104895049A (en) | Prefabrication-cast-in-situ mixed underground continuous wall and construction method thereof | |
CN102661010B (en) | Composite shear wall | |
CN106835926A (en) | A kind of small side main span is than prestressed concrete continuous beam and its construction method | |
CN105113537A (en) | Vertical support system constructed through reverse construction method and method for vertical support system | |
CN202672335U (en) | Pre-tensioned prestressing superposed beam building structural system | |
CN105544795B (en) | Shear wall contrary sequence method design and construction processing method | |
KR19990078524A (en) | Composite Underground Structure Construction Method | |
CN103696437B (en) | A kind of construction method of cutting lattice column | |
CN105821908A (en) | Multiple water stop belt, waterproof structure and construction method of waterproof structure | |
CN104895221B (en) | Assembled shaped steel confined concrete shear wall structure | |
CN211115052U (en) | Shaft type underground stereo garage structure | |
CN204570446U (en) | The T-shaped simply supported beam of a kind of precast assembly | |
CN106285001A (en) | A kind of little area segmentation quickly intersects flowing water construction method | |
JP2010116754A (en) | Structure, and construction and designing method of structure | |
CN105386447A (en) | Construction method for replacement support of post-cast strip in construction site | |
CN107012948A (en) | A kind of basement floor building structural and its construction method | |
CN204676560U (en) | The support changing structure for use of foundation ditch mid-board | |
CN211773695U (en) | New and old structure multilayer basement trades and props biography power structure | |
CN106759882A (en) | Prefabricated post composite beam top story exterior joints connection method in assembled RC frame-shear structures | |
CN106836473A (en) | Prefabricated post composite beam intermediate layer mid-side node connection method in assembled RC frame-shear structures | |
CN102392459A (en) | Construction method for straight manhole | |
CN207727587U (en) | A kind of preassembling supporting beam composite structure suitable for deposited reinforced concrete pile | |
CN204983238U (en) | Assembled shaped steel restraint concrete shear force wall connected node | |
CN201991015U (en) | Foundation underpinning structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |