CN105544795B - Shear wall contrary sequence method design and construction processing method - Google Patents

Shear wall contrary sequence method design and construction processing method Download PDF

Info

Publication number
CN105544795B
CN105544795B CN201510911778.2A CN201510911778A CN105544795B CN 105544795 B CN105544795 B CN 105544795B CN 201510911778 A CN201510911778 A CN 201510911778A CN 105544795 B CN105544795 B CN 105544795B
Authority
CN
China
Prior art keywords
column
inverse
inverse conversion
floor
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510911778.2A
Other languages
Chinese (zh)
Other versions
CN105544795A (en
Inventor
张达生
宗静
袁强
王海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CITIC General Institute of Architectural Design and Research Co Ltd
Original Assignee
CITIC General Institute of Architectural Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CITIC General Institute of Architectural Design and Research Co Ltd filed Critical CITIC General Institute of Architectural Design and Research Co Ltd
Priority to CN201510911778.2A priority Critical patent/CN105544795B/en
Publication of CN105544795A publication Critical patent/CN105544795A/en
Application granted granted Critical
Publication of CN105544795B publication Critical patent/CN105544795B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a kind of shear wall contrary sequence method design and construction processing method, in the construction area including basement and basement upper floor, column is used as by the use of basement frame column or superstructure frame column, the floor beam constructed on column in inverse conversion beam and inverse conversion beam region, column is set to support inverse conversion beam and floor beam, by the use of inverse conversion beam as the temporary support component of superstructure shear wall, to superstructure and underground structure synchronous construction.Design concept of the present invention is ingenious, construction and installation are flexible, workable.The initial internal force of beam section need to be retained by the rearmounted inverse conversion beam of carrier band elimination that unloads, realize that inverse conversion beam unites two into one with the floor beam in the region, reduce inverse stage temporary support structures material usage.Expense, shortening duration can be saved by carrying out shear wall contrary sequence method design and construction processing using this method, and have very positive meaning to energy-conserving and environment-protective.

Description

Shear wall contrary sequence method design and construction processing method
Technical field
The invention belongs to building engineering field, and in particular to shear wall contrary sequence method design and construction processing method.
Background technology
With the development of urban construction, land resource becomes more and more rare, and space has become to underground extension The developing direction of large-scale construction engineering.At present, many large-scale construction engineerings for carrying multi-storey basement are occurred in that, such engineering Feature is that the basement scale of construction is big, and the number of plies is more, and the Underground Construction cycle is long.To shorten the duration, many need to take against work is occurred in that The architectural engineering of method construction.It can realize that superstructure shortens the duration with basement structure synchronous construction using contrary sequence method, and The temporary support component in foundation pit supporting system can be replaced to save cost using components such as basement agent structure beam, plate, posts. Though reverse construction possesses many advantages, to implement the reverse construction of architectural engineering also has many technological difficulties to need solution Certainly, the reverse construction of wherein shear wall is exactly one of difficult point.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of easy construction, the shear wall contrary sequence method design of section material timesaving Construction treating methods.
The technical scheme that the present invention is provided is:A kind of shear wall is inverse to make hair design and construction processing method, including basement And in the construction area of basement upper floor, by the use of basement frame column or superstructure frame column as column, in column The upper floor beam constructed in inverse conversion beam and inverse conversion beam region, makes column support inverse conversion beam and floor beam, utilizes Inverse conversion beam as superstructure shear wall temporary support component, to superstructure and basement structure synchronous construction.
The present invention after the completion of inverse by cutting to form unloading the concrete in floor girder span in 300mm wide scopes Band, eliminate needs to retain beam section in inverse conversion beam(Floor beam)Initial internal force, realize that inverse conversion beam and floor beam close two and be One.
Constructed on column inverse conversion beam and floor beam when by the reinforcing bar of floor beam by design requirement configure at inverse turn Change in beam, and inverse conversion beam steel is replaced with the part reinforcing bar of floor beam.
The column the inverse stage be steel core concrete column, it is inverse after the completion of column periphery parcel armored concrete shape Into profile steel concrete column.
Inverse conversion beam of the present invention refers to be used for the armored concrete of support superstructure shear wall in the construction stage Beam.
Design concept of the present invention is ingenious, construction and installation are flexible, workable.
Beneficial effect
Expense, shortening duration can be saved by carrying out shear wall contrary sequence method design and construction processing using this method, and to section Can environmental protection have very energetically meaning.
Brief description of the drawings
Fig. 1, which is that shear wall of the present invention is inverse, makees design and construction processing method schematic diagram.
Fig. 2 is that inverse conversion beam and floor beam unite two into one schematic cross-section.
Fig. 3 is that the embodiment of the present invention 1 is constructed the schematic diagram of inverse conversion beam 2 and floor beam 3 on column.
Fig. 4 is the schematic diagram of the superstructure of the embodiment of the present invention 1 and basement structure synchronous construction.
Fig. 5 is the structural representation after the superstructure of the embodiment of the present invention 1 and basement structure synchronous construction.
Fig. 6 is the schematic diagram that the embodiment of the present invention 1 unloads initial internal force to inverse conversion beam 2 and floor beam 3.
Fig. 7 is the embodiment of the present invention 1 by the schematic diagram for the concrete chisel removal being wrapped in around floor beam 3.
Fig. 8 is that the embodiment of the present invention 1 closes the schematic diagram unloaded after carrier band.
Embodiment
With reference to specific implementation case, the present invention is expanded on further.It should be understood that reading the content of the invention lectured Afterwards, those skilled in the art can make various changes or modifications to the present invention, and these equivalent form of values equally fall within the application institute Attached claims limited range.
As shown in figure 1, the present invention utilizes basement frame in the construction area including basement and basement upper floor Trestle or superstructure frame column 11 are as column 1, and construct inverse conversion beam 2 and inverse conversion beam region Nei Lou on column 1 Layer beam 3, makes column 1 support inverse conversion beam 2 and floor beam 3, utilizes inverse the facing as superstructure shear wall 5 of conversion beam 2 When supporting member, to superstructure and underground structure synchronous construction.
The present invention eliminates the initial internal force for needing to retain beam section [floor beam 3] in inverse conversion beam by the rearmounted carrier band 4 that unloads, real Existing inverse conversion beam 2 unites two into one with floor beam 3.Its section of floor beam 3 in the inverse region of conversion beam 2 is less than inverse conversion beam 2, floor beam 3 is wrapped in inverse conversion beam 2 when both merge construction.It is inverse to complete and treat bottom not influence normally to use Shear wall construction needs the concrete that will be wrapped in around floor beam 3 afterwards in place(Inverse conversion beam)Cut.Because the inverse stage should Two-in-one beam bears top shear wall as the conversion beam of top shear wall and transmits load, therefore, it is inverse after the completion of in the beam In the presence of a larger initial internal force, the internal force is more than internal force of the floor beam 3 in serviceability limit stage.To ensure structure safety, Need to unload inverse conversion beam 2 and floor beam 3 before cutting, to eliminate initial internal force in beam.The unloading manner that this case is recommended System is wrapped in around floor beam 3 cutting by eliminating initial internal force in beam in the rearmounted carrier band 4 that unloads of floor beam 3 span centre, i.e., Before concrete, a wide post-cast strip of 300mm is first dug out as rearmounted in the span centre of floor beam 3 and unloads carrier band unloading, is then dug again It is re-closed after the completion of work to be cut to unload carrier band except the concrete around the section of floor beam 3.
As shown in Fig. 2 it is described constructed on column 1 inverse conversion beam 2 and floor beam 3 when by the reinforcing bar of floor beam 3(A)Press Design requirement is configured in inverse conversion beam 2, and with the reinforcing bar of floor beam 3(A1)Instead of the part reinforcing bar of inverse conversion beam 2.
The column 1 is steel core concrete column in the inverse stage, it is inverse after the completion of in the periphery of column 1 parcel armored concrete Form profile steel concrete column.
Less than one layer of shear wall 6 treats basement after the completion of inverse using the construction of the positive practice.
Embodiment 1
Certain engineering superstructure uses frame-shear-wall structure system, if three layers of basement, basement construction area about 11 Ten thousand m2, to meet superstructure construction period, reverse construction need to be used.To realize inverse demand, design is proposed such as Fig. 3-8 institutes The inverse scheme shown is as follows:
1. as shown in figure 3, basis uses cast-in-situ bored pile 7, by the use of basement frame column or superstructure frame column as Column 1, column 1 uses steel core concrete column in the inverse stage, and cast-in-situ bored pile 7 inserts column 1 in stake 7 when constructing.
2. set inverse phase transition beam 2 in shearing wall zone and constitute frame structure with column 1;Inverse conversion beam is located at one Layer.
3. by the reinforcing bar of the floor beam 3 in region during the inverse conversion beam 2 of construction(A)By design requirement configuration in inverse conversion In beam 2, and with the reinforcing bar of floor beam 3(A1)Instead of the inverse part reinforcing bar of conversion beam 2, specific detail drawing 2.
4. it is as shown in Figure 4 and Figure 5, rest to superstructure with inverse conversion beam 2 and column 1(Cut including superstructure Power wall 5, frame column 11, beam 10, top floorboard)And basement structure(Including basement floor beam 9, basement floorboard and Cushion cap 8)Synchronous construction;Less than one layer of shear wall 6 treats basement after the completion of inverse using the construction of the positive practice.
5. its section of floor beam 3 and internal force in the inverse region of conversion beam 2 are respectively less than inverse conversion beam 2, both apply in merging Man-hour floor beam 3 is wrapped in inverse conversion beam 2.It is inverse to complete and treat that the construction of bottom shear wall 6 is arrived not influence normally to use The concrete chisel removal that will be wrapped in around floor beam 3 is needed behind position(As shown in Figure 7).Because the two-in-one beam of inverse stage is as upper The conversion beam of portion's shear wall 5 bears the load that top shear wall 5 is transmitted, therefore, it is inverse after the completion of exist in the beam one compared with Big initial internal force, the internal force is more than internal force of the floor beam 3 in serviceability limit stage.To ensure structure safety, needed before cutting pair Inverse conversion beam 2 and floor beam 3 are unloaded(As shown in Figure 6), to eliminate initial internal force in beam.This case unloading manner system passes through Bring initial internal force in elimination beam in rearmounted unload of the span centre of floor beam 3, i.e., cut the concrete that is wrapped in around floor beam 3 it Before, first dig out a wide post-cast strip of 300mm in the span centre of floor beam 3 and unloaded as the rearmounted carrier band 4 that unloads, floor beam is then cut again Concrete around 3 sections, it is re-closed after the completion of work to be cut to unload carrier band 4(As shown in Figure 8).

Claims (3)

  1. The processing method 1. a kind of shear wall contrary sequence method is designed and constructed, it is characterized in that:Including basement and basement upper floor Construction area in, by the use of basement frame column or superstructure frame column as column (1), inverse conversion of being constructed on column Floor beam in beam (2) and inverse conversion beam region(3), make column(1)Support inverse conversion beam(2)With floor beam(3), using inverse Apply conversion beam(2)It is used as superstructure shear wall(5)Temporary support component, to superstructure and underground structure synchronous construction; After the completion of inverse, by by floor beam(3)Carrier band is unloaded in concrete chisel removal formation in span centre 300mm wide scopes(4), eliminate inverse The initial internal force of reservation beam section is needed in conversion beam, inverse conversion beam is realized(2)With floor beam(3)Unite two into one.
  2. 2. according to the method described in claim 1, it is characterized in that:Constructed on column (1) inverse conversion beam(2)With floor beam (3)When by floor beam(3)Reinforcing bar(A1)By design requirement configuration in inverse conversion beam(2)It is interior, and with floor beam(3)Part Reinforcing bar replaces inverse conversion beam(2)Reinforcing bar.
  3. 3. according to the method described in claim 1, it is characterized in that:Column (1) is steel core concrete column in the inverse stage, inverse complete After in column (1) periphery parcel armored concrete formation profile steel concrete column.
CN201510911778.2A 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method Active CN105544795B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510911778.2A CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510911778.2A CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Publications (2)

Publication Number Publication Date
CN105544795A CN105544795A (en) 2016-05-04
CN105544795B true CN105544795B (en) 2017-09-01

Family

ID=55824310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510911778.2A Active CN105544795B (en) 2015-12-11 2015-12-11 Shear wall contrary sequence method design and construction processing method

Country Status (1)

Country Link
CN (1) CN105544795B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09228398A (en) * 1996-02-26 1997-09-02 Taisei Corp Construction method for pile support type multistoried building
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
KR100938916B1 (en) * 2009-06-29 2010-01-27 김미선 Downward method by front reaming
TW201022505A (en) * 2008-12-05 2010-06-16 jian-shun Huang Bottom-up and top-down combined construction method for building basement excavation
CN201598652U (en) * 2010-01-12 2010-10-06 上海市第一建筑有限公司 Bidirectional synchronous construction converting structure
CN201679147U (en) * 2009-12-04 2010-12-22 上海市第二建筑有限公司 Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09228398A (en) * 1996-02-26 1997-09-02 Taisei Corp Construction method for pile support type multistoried building
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
TW201022505A (en) * 2008-12-05 2010-06-16 jian-shun Huang Bottom-up and top-down combined construction method for building basement excavation
KR100938916B1 (en) * 2009-06-29 2010-01-27 김미선 Downward method by front reaming
CN201679147U (en) * 2009-12-04 2010-12-22 上海市第二建筑有限公司 Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building
CN201598652U (en) * 2010-01-12 2010-10-06 上海市第一建筑有限公司 Bidirectional synchronous construction converting structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
超高建筑虹口商城结构双向同步施工技术;黄玉林;《上海建设科技》;20100430;第45页第1段至第49页第47页第2栏尾端,图1-6 *

Also Published As

Publication number Publication date
CN105544795A (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN101787738B (en) Stair connection joint device
CN104895049A (en) Prefabrication-cast-in-situ mixed underground continuous wall and construction method thereof
CN102661010B (en) Composite shear wall
CN106835926A (en) A kind of small side main span is than prestressed concrete continuous beam and its construction method
CN105113537A (en) Vertical support system constructed through reverse construction method and method for vertical support system
CN202672335U (en) Pre-tensioned prestressing superposed beam building structural system
CN105544795B (en) Shear wall contrary sequence method design and construction processing method
KR19990078524A (en) Composite Underground Structure Construction Method
CN103696437B (en) A kind of construction method of cutting lattice column
CN105821908A (en) Multiple water stop belt, waterproof structure and construction method of waterproof structure
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN211115052U (en) Shaft type underground stereo garage structure
CN204570446U (en) The T-shaped simply supported beam of a kind of precast assembly
CN106285001A (en) A kind of little area segmentation quickly intersects flowing water construction method
JP2010116754A (en) Structure, and construction and designing method of structure
CN105386447A (en) Construction method for replacement support of post-cast strip in construction site
CN107012948A (en) A kind of basement floor building structural and its construction method
CN204676560U (en) The support changing structure for use of foundation ditch mid-board
CN211773695U (en) New and old structure multilayer basement trades and props biography power structure
CN106759882A (en) Prefabricated post composite beam top story exterior joints connection method in assembled RC frame-shear structures
CN106836473A (en) Prefabricated post composite beam intermediate layer mid-side node connection method in assembled RC frame-shear structures
CN102392459A (en) Construction method for straight manhole
CN207727587U (en) A kind of preassembling supporting beam composite structure suitable for deposited reinforced concrete pile
CN204983238U (en) Assembled shaped steel restraint concrete shear force wall connected node
CN201991015U (en) Foundation underpinning structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant