CN105421474A - Integral construction method of pile planting cofferdam platform used for rock strata low-pile cap - Google Patents

Integral construction method of pile planting cofferdam platform used for rock strata low-pile cap Download PDF

Info

Publication number
CN105421474A
CN105421474A CN201510735718.XA CN201510735718A CN105421474A CN 105421474 A CN105421474 A CN 105421474A CN 201510735718 A CN201510735718 A CN 201510735718A CN 105421474 A CN105421474 A CN 105421474A
Authority
CN
China
Prior art keywords
pile
cofferdam
platform
construction
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510735718.XA
Other languages
Chinese (zh)
Other versions
CN105421474B (en
Inventor
韩博
李艳哲
周燕飞
唐明
张红强
张超亮
全建淅
吴艳辉
张帅
张金豪
杨杰
王湘桥
张志勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
China Railway Major Bridge Engineering Group Co Ltd MBEC
1st Engineering Co Ltd of MBEC
Original Assignee
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Co Ltd Zhongtie Bridge Bureau Group, China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority to CN201510735718.XA priority Critical patent/CN105421474B/en
Publication of CN105421474A publication Critical patent/CN105421474A/en
Application granted granted Critical
Publication of CN105421474B publication Critical patent/CN105421474B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Abstract

The invention discloses an integral construction method of a pile planting cofferdam platform used for a rock strata low-pile cap and relates to the field of construction of rock stratum low-pile caps. The integral construction method comprises the following steps that S1, a lifting platform and a drilling platform are constructed on a rock stratum at the same time, and a cofferdam construction channel is reserved between the lifting platform and the drilling platform in the lifting platform and the drilling platform construction process; and S2, cofferdam construction is conducted on the drilling platform in the cofferdam construction channel, and pile foundation drilling is conducted on the drilling platform at the same time; during the cofferdam construction, after steel sheet piles required by a cofferdam are planted into the rock stratum through a static-pressure pile planting machine, a steel sheet pile cofferdam inner supporting structure is installed, water drawing is conducted in the cofferdam, and an excavator is lifted into the cofferdam for conducting no-water excavation.. According to the integral construction method, underwater blasting is changed into no-water excavation, the construction period is short, required manpower and material resources are few, and construction requirements can be met.

Description

Pile cofferdam platform integral construction method is planted for lithostratigraphy low pile cap
Technical field
The present invention relates to lithostratigraphy low pile cap construction field, be specifically related to a kind ofly plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap.
Background technology
At present, tradition to the construction method of the low pile cap of lithostratigraphy is: first carry out underwater demolition, then construction drill platform and cofferdam.But, very fast for flow velocity and cannot implement underwater demolition stake position for, when adopting traditional construction method to construct to stake position, not only need to drop into huge man power and material, and construction period is longer, is difficult to meet construction requirement.
Summary of the invention
For the defect existed in prior art, the object of the present invention is to provide and a kind ofly plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap.Underwater demolition is changed into anhydrous excavation operation by the present invention, and not only excavation area and side measure less, and construction period is shorter, and required man power and material is less, and is convenient to control absolute altitude and planeness at the bottom of cushion cap, can meet construction requirement.
For reaching above object, provided by the inventionly planting pile cofferdam platform integral construction method for lithostratigraphy low pile cap, comprising the following steps:
S1: simultaneously construct on lithostratigraphy hoisting platform and drilling platform, hoisting platform is positioned at around drilling platform; In the process of constructing hoisting platform and drilling platform, between hoisting platform and drilling platform, reserved and cofferdam construction passage, forwards S2 to;
S2: carry out cofferdam construction to drilling platform in cofferdam construction passage, meanwhile, drilling platform carries out pile foundation boring operation; When carrying out cofferdam construction, after the steel sheet pile needed for cofferdam being implanted lithostratigraphy by static-pressure pile planting machine, in cofferdam, carry out drawing water operation, excavator is hung in cofferdam and carry out anhydrous excavation operation.
On the basis of technique scheme, by static-pressure pile planting machine, the steel sheet pile needed for cofferdam is implanted in the process of lithostratigraphy in S2, high and the water level conditions according to steel sheet pile top mark, is welding cofferdam construction operating platform with the upper strata of the corresponding part of steel sheet pile below static-pressure pile planting machine; According to the height of steel sheet pile, at the lower floor's weldable steel sheet pile limiting platform with the corresponding part of steel sheet pile below static-pressure pile planting machine.
On the basis of technique scheme, the idiographic flow of hoisting platform of constructing in S1 is: by vibrating hammer after the inserted to play steel pipe pile of installation site, timely welded steel pipe pile connects system, forms overall stress system, at stress system top construction lifting stake top distribution beam and hoisting platform panel.
On the basis of technique scheme, in S1, the idiographic flow of construction drill platform is: inserted to play steel pipe pile within the scope of cushion cap, connects as one all steel pipe piles; At top construction steel pile tube top distribution beam and the drilling platform panel of steel pipe pile, reserve the installation site of main body drilled pile steel pile casting in work progress and steel pile casting guide frame is set in installation site; After steel pipe pile top distribution beam and drilling platform panel have been constructed, by steel pile casting guide frame construction steel casing; For preventing inclined rock base on the impact of steel pile casting verticality, do not consider that main body drilled pile steel pile casting bears working load.
On the basis of technique scheme, described in S1 between hoisting platform and drilling platform reserved with cofferdam construction passage after, further comprising the steps of: on cofferdam construction passage, to lay cofferdam platform panel, as cofferdam construction platform and drilling platform; In cofferdam construction passage, set up static-pressure pile planting machine described in S2 comprise the following steps: during erection static-pressure pile planting machine, remove the cofferdam platform panel of cofferdam construction platform corresponding part according to the decorating position of static-pressure pile planting machine.
On the basis of technique scheme, described in S1, between hoisting platform and drilling platform, idiographic flow that is reserved and cofferdam construction passage is: between hoisting platform and drilling platform, according to the type of static-pressure pile planting machine that need use and the size in cofferdam, reserved cofferdam construction passage.
On the basis of technique scheme, S2 is further comprising the steps of: after cofferdam construction completes, and repairs drilling platform.
Compared with prior art, the invention has the advantages that:
(1), after the present invention constructs hoisting platform and drilling platform, construction drill cofferdam in the cofferdam construction passage between hoisting platform and drilling platform, carries out anhydrous excavation operation in cofferdam.Compared with carrying out underwater demolition with low pile cap of constructing in prior art, underwater demolition is changed into anhydrous excavation operation by the present invention, and not only excavation area and side measure less, and required man power and material is less, and be convenient to control absolute altitude and planeness at the bottom of cushion cap, can construction requirement be met.
(2) the present invention carries out cofferdam construction to drilling platform on cofferdam construction platform, meanwhile, drilling platform carries out pile foundation boring operation; Construction is carried out in bore operation and cofferdam operation simultaneously can accelerate the construction period.
(3), when the present invention carries out cofferdam construction, cofferdam construction operating platform is being welded with the upper strata of the corresponding part of steel sheet pile below static-pressure pile planting machine, lower floor's weldable steel sheet pile limiting platform.Cofferdam construction operating platform and the steel sheet pile limiting platform of upper and lower two-layer layout take full advantage of platform space, avoid cross-operation, can not only accelerate construction period, and can save manpower.Meanwhile, cofferdam construction operating platform and steel sheet pile limiting platform can reduce the free height of steel sheet pile when static-pressure pile planting machine is constructed, and rocking when static-pressure pile planting machine drill is entered is controlled, and improve the operating efficiency of static-pressure pile planting machine.
Accompanying drawing explanation
Fig. 1 is the floor map of planting pile cofferdam platform integral construction method for lithostratigraphy low pile cap in the embodiment of the present invention;
Fig. 2 is the elevational schematic view of planting pile cofferdam platform integral construction method for lithostratigraphy low pile cap in the embodiment of the present invention.
In figure: 1-hoisting platform, 2-drilling platform, 3-cofferdam construction passage, 4-static-pressure pile planting machine, 5-cofferdam construction operating platform, 6-steel sheet pile limiting platform.
Detailed description of the invention
Below in conjunction with accompanying drawing, embodiments of the invention are described in further detail.
Shown in Figure 1, plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap in the embodiment of the present invention, comprise the following steps:
S1: simultaneously construct on lithostratigraphy hoisting platform 1 and drilling platform 2, hoisting platform 1 is positioned at drilling platform 2 around; In the process of constructing hoisting platform 1 and drilling platform 2, between hoisting platform 1 and drilling platform 2, reserved and cofferdam construction passage 3, cofferdam construction passage 3 is laid cofferdam platform panel, as cofferdam construction platform and drilling platform, forwards S2 to.
S2: carry out cofferdam construction to drilling platform 2 on cofferdam construction platform, meanwhile, drilling platform 2 carries out pile foundation boring operation.When carrying out cofferdam construction, in cofferdam construction passage 3, set up static-pressure pile planting machine 4, during erection, remove the cofferdam platform panel of cofferdam construction platform corresponding part according to the decorating position of static-pressure pile planting machine 4.After the steel sheet pile needed for cofferdam being implanted lithostratigraphy by static-pressure pile planting machine 4, steel sheet-pile cofferdam inner supporting structure is installed, after cofferdam construction completes, drilling platform 2 is repaired.In cofferdam, carry out drawing water operation, excavator is hung in cofferdam and carry out anhydrous excavation operation.
The idiographic flow of hoisting platform 1 of constructing in S1 is: by vibrating hammer after the inserted to play steel pipe pile of installation site, and timely welded steel pipe pile connects system, forms overall stress system, at stress system top construction lifting stake top distribution beam and hoisting platform panel.
In S1, the idiographic flow of construction drill platform 2 is: inserted to play steel pipe pile within the scope of cushion cap, connects as one all steel pipe piles, forms overall stool structure.At top construction steel pile tube top distribution beam and the drilling platform panel of steel pipe pile, reserve the installation site of main body drilled pile steel pile casting in work progress and steel pile casting guide frame is set in installation site.After steel pipe pile top distribution beam and drilling platform panel have been constructed, by steel pile casting guide frame construction steel casing; For preventing inclined rock base on the impact of steel pile casting verticality, do not consider that main body drilled pile steel pile casting bears working load.
In S1, between hoisting platform 1 and drilling platform 2, idiographic flow that is reserved and cofferdam construction passage 3 is: between hoisting platform 1 and drilling platform 2, according to the type of static-pressure pile planting machine 4 that need use and the size in cofferdam, reserved cofferdam construction passage 3.
Shown in Figure 2, by static-pressure pile planting machine 4, the steel sheet pile needed for cofferdam is implanted in the process of lithostratigraphy in S2, according to steel sheet pile top mark high (namely cofferdam top mark is high) and water level conditions, welding cofferdam construction operating platform 5 with the upper strata of the corresponding part of steel sheet pile below static-pressure pile planting machine 4; According to the height of steel sheet pile, at the lower floor's weldable steel sheet pile limiting platform 6 with the corresponding part of steel sheet pile below static-pressure pile planting machine 4.
Cofferdam construction operating platform 5 and steel sheet pile limiting platform 6 can reduce the free height of steel sheet pile when static-pressure pile planting machine 4 is constructed, and rocking when static-pressure pile planting machine 4 is crept into is controlled, and improve the operating efficiency of static-pressure pile planting machine 4.
The present invention is not limited to above-mentioned embodiment, and for those skilled in the art, under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications are also considered as within protection scope of the present invention.The content be not described in detail in this manual belongs to the known prior art of professional and technical personnel in the field.

Claims (7)

1. plant a pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that, comprise the following steps:
S1: simultaneously construct on lithostratigraphy hoisting platform (1) and drilling platform (2), hoisting platform (1) is positioned at drilling platform (2) around; In the process of constructing hoisting platform (1) and drilling platform (2), between hoisting platform (1) and drilling platform (2), reserved and cofferdam construction passage (3), forwards S2 to;
S2: carry out cofferdam construction to drilling platform (2) in cofferdam construction passage (3), meanwhile, drilling platform (2) carries out pile foundation boring operation; When carrying out cofferdam construction, after the steel sheet pile needed for cofferdam being implanted lithostratigraphy by static-pressure pile planting machine (4), in cofferdam, carry out drawing water operation, excavator is hung in cofferdam and carry out anhydrous excavation operation.
2. as claimed in claim 1 plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: by static-pressure pile planting machine (4), the steel sheet pile needed for cofferdam is implanted in the process of lithostratigraphy in S2, high and the water level conditions according to steel sheet pile top mark, welds cofferdam construction operating platform (5) on the upper strata of the corresponding part of steel sheet pile with static-pressure pile planting machine (4) below; According to the height of steel sheet pile, in lower floor's weldable steel sheet pile limiting platform (6) of the corresponding part of steel sheet pile with static-pressure pile planting machine (4) below.
3. as claimed in claim 1 plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: the idiographic flow of hoisting platform of constructing in S1 (1) is: by vibrating hammer after the inserted to play steel pipe pile of installation site, timely welded steel pipe pile connects system, form overall stress system, at stress system top construction lifting stake top distribution beam and hoisting platform panel.
4. as claimed in claim 1 plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: in S1, the idiographic flow of construction drill platform (2) is: inserted to play steel pipe pile within the scope of cushion cap, connects as one all steel pipe piles; At top construction steel pile tube top distribution beam and the drilling platform panel of steel pipe pile, reserve the installation site of main body drilled pile steel pile casting in work progress and steel pile casting guide frame is set in installation site; After steel pipe pile top distribution beam and drilling platform panel have been constructed, by steel pile casting guide frame construction steel casing; For preventing inclined rock base on the impact of steel pile casting verticality, do not consider that main body drilled pile steel pile casting bears working load.
5. as claimed in claim 1 plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: described in S1 between hoisting platform (1) and drilling platform (2) reserved with cofferdam construction passage (3) after, further comprising the steps of: at cofferdam construction passage (3) upper laying cofferdam platform panel, as cofferdam construction platform and drilling platform; Described in S2, in cofferdam construction passage (3), erection static-pressure pile planting machine (4) comprises the following steps: during erection static-pressure pile planting machine (4), removes the cofferdam platform panel of cofferdam construction platform corresponding part according to the decorating position of static-pressure pile planting machine (4).
6. as described in any one of claim 1 to 5, plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: described in S1, between hoisting platform (1) and drilling platform (2), idiographic flow that is reserved and cofferdam construction passage (3) is: between hoisting platform (1) and drilling platform (2), according to the type of static-pressure pile planting machine (4) that need use and the size in cofferdam, reserved cofferdam construction passage (3).
7. as described in any one of claim 1 to 5, plant pile cofferdam platform integral construction method for lithostratigraphy low pile cap, it is characterized in that: S2 is further comprising the steps of: after cofferdam construction completes, drilling platform (2) is repaired.
CN201510735718.XA 2015-11-03 2015-11-03 For the plant pile cofferdam platform integral construction method of lithostratigraphy low pile cap Active CN105421474B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510735718.XA CN105421474B (en) 2015-11-03 2015-11-03 For the plant pile cofferdam platform integral construction method of lithostratigraphy low pile cap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510735718.XA CN105421474B (en) 2015-11-03 2015-11-03 For the plant pile cofferdam platform integral construction method of lithostratigraphy low pile cap

Publications (2)

Publication Number Publication Date
CN105421474A true CN105421474A (en) 2016-03-23
CN105421474B CN105421474B (en) 2018-07-03

Family

ID=55499985

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510735718.XA Active CN105421474B (en) 2015-11-03 2015-11-03 For the plant pile cofferdam platform integral construction method of lithostratigraphy low pile cap

Country Status (1)

Country Link
CN (1) CN105421474B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106839907A (en) * 2017-02-07 2017-06-13 中铁二十三局集团第三工程有限公司 Underwater demolition construction method
CN107905244A (en) * 2017-12-12 2018-04-13 中交公局第二工程有限公司 A kind of three side combined cofferdam construction method of offshore region
CN109707307A (en) * 2018-12-11 2019-05-03 中铁五局集团贵州工程有限公司 At the construction method of polygon annular groove on a kind of rock stratum under water
CN112609591A (en) * 2020-12-22 2021-04-06 中铁建大桥工程局集团第一工程有限公司 Construction method for deep-water shallow-covering-layer fully-socketed bridge foundation
CN113737790A (en) * 2021-06-28 2021-12-03 中交第二航务工程局有限公司 Bridge pile and steel sheet pile synchronous construction method
CN114411780A (en) * 2021-12-29 2022-04-29 中铁十九局集团有限公司 Construction method of Larsen steel sheet pile cofferdam of static pressure pile planting machine for deep water rock stratum foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429761A (en) * 2008-11-18 2009-05-13 中铁大桥局集团第二工程有限公司 Deep sea bare rock pier protection barrel, positioning pile, underwater cofferdam integrated platform and construction method
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
JP5510692B1 (en) * 2013-09-04 2014-06-04 東洋建設株式会社 Steel temporary deadline installation method and low-air mobile crane carrier used therefor
CN103882881A (en) * 2014-04-11 2014-06-25 山东黄河工程集团有限公司 Underwater construction method for bearing platform deeply embedded in rock

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429761A (en) * 2008-11-18 2009-05-13 中铁大桥局集团第二工程有限公司 Deep sea bare rock pier protection barrel, positioning pile, underwater cofferdam integrated platform and construction method
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
JP5510692B1 (en) * 2013-09-04 2014-06-04 東洋建設株式会社 Steel temporary deadline installation method and low-air mobile crane carrier used therefor
CN103882881A (en) * 2014-04-11 2014-06-25 山东黄河工程集团有限公司 Underwater construction method for bearing platform deeply embedded in rock

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106839907A (en) * 2017-02-07 2017-06-13 中铁二十三局集团第三工程有限公司 Underwater demolition construction method
CN107905244A (en) * 2017-12-12 2018-04-13 中交公局第二工程有限公司 A kind of three side combined cofferdam construction method of offshore region
CN109707307A (en) * 2018-12-11 2019-05-03 中铁五局集团贵州工程有限公司 At the construction method of polygon annular groove on a kind of rock stratum under water
CN112609591A (en) * 2020-12-22 2021-04-06 中铁建大桥工程局集团第一工程有限公司 Construction method for deep-water shallow-covering-layer fully-socketed bridge foundation
CN113737790A (en) * 2021-06-28 2021-12-03 中交第二航务工程局有限公司 Bridge pile and steel sheet pile synchronous construction method
CN113737790B (en) * 2021-06-28 2023-02-24 中交第二航务工程局有限公司 Bridge pile and steel sheet pile synchronous construction method
CN114411780A (en) * 2021-12-29 2022-04-29 中铁十九局集团有限公司 Construction method of Larsen steel sheet pile cofferdam of static pressure pile planting machine for deep water rock stratum foundation

Also Published As

Publication number Publication date
CN105421474B (en) 2018-07-03

Similar Documents

Publication Publication Date Title
CN105421474A (en) Integral construction method of pile planting cofferdam platform used for rock strata low-pile cap
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN106522242B (en) For soft stratum close to underground structure foundation pit supporting system construction method
CN104846829B (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN103132908B (en) Device for drilling rock and embedding rock-socketed prestressed pipe pile by down-hole hammer and construction method of device
CN105862874A (en) Protection method for controlling deformation of building structure close to foundation pit
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN103851257B (en) Based on the trustship construction process in laying cable duct bank
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN106836839A (en) Fabric structure jacking increasing layer method
CN105064381B (en) A kind of back cover construction method of high-low cutting curb Double-Wall Steel Boxed Cofferdam armored concrete
CN104196044A (en) Cofferdam construction method with grooves milled through limited hole forming of percussion drill combined with steel sheet piles
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN110486034A (en) Subway station and construction method based on pile foundation in four pilot tunnel of single layer and middle drift
CN107575237A (en) A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN203114170U (en) In-hole hammer drilling embedding rock-socketed prestressed pipe pile device
CN104675405A (en) Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN105200994A (en) Construction method for reserved shield crossing composite foundation pit support device
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Han Bo

Inventor after: Zhang Jinhao

Inventor after: Yang Jie

Inventor after: Wang Xiangqiao

Inventor after: Zhang Zhiyong

Inventor after: Li Yanzhe

Inventor after: Zhou Yanfei

Inventor after: Tang Ming

Inventor after: Zhang Hongqiang

Inventor after: Zhang Chaoliang

Inventor after: Quan Jianxi

Inventor after: Wu Yanhui

Inventor after: Zhang Shuai

Inventor before: Han Bo

Inventor before: Zhang Jinhao

Inventor before: Yang Jie

Inventor before: Wang Xiangqiao

Inventor before: Zhang Zhiyong

Inventor before: Li Yanzhe

Inventor before: Zhou Yanfei

Inventor before: Tang Ming

Inventor before: Zhang Hongqiang

Inventor before: Zhang Chaoliang

Inventor before: Quan Jianxi

Inventor before: Wu Yanhui

Inventor before: Zhang Shuai

CB03 Change of inventor or designer information