CN105178143A - 一种沥青摊铺过程中路缘石保护装置及其保护方法 - Google Patents
一种沥青摊铺过程中路缘石保护装置及其保护方法 Download PDFInfo
- Publication number
- CN105178143A CN105178143A CN201510605817.6A CN201510605817A CN105178143A CN 105178143 A CN105178143 A CN 105178143A CN 201510605817 A CN201510605817 A CN 201510605817A CN 105178143 A CN105178143 A CN 105178143A
- Authority
- CN
- China
- Prior art keywords
- kerb
- road kerb
- road
- plate
- protective device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000010426 asphalt Substances 0.000 title claims abstract description 18
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000005096 rolling process Methods 0.000 claims abstract description 12
- 230000001681 protective Effects 0.000 claims description 23
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 238000005755 formation reaction Methods 0.000 claims description 3
- 239000005028 tinplate Substances 0.000 claims description 3
- 229910000831 Steel Inorganic materials 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 3
- 239000010959 steel Substances 0.000 abstract description 3
- 238000010276 construction Methods 0.000 abstract description 2
- 238000001125 extrusion Methods 0.000 abstract 1
- 230000004075 alteration Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005498 polishing Methods 0.000 description 1
Abstract
本发明公开了一种沥青摊铺过程中路缘石保护装置及其保护方法,包括内侧板、上顶板和外侧板,内侧板、上顶板和外侧板依次固定连接形成一个下方开口的方形上罩罩在路缘石上,内侧板位于路缘石靠近沥青路面一侧,该内侧板高度高于路缘石裸露高度1-3mm,上顶板平行于路缘石上表面,上顶板上安装有提手,该上顶板宽度宽于路缘石宽度1-3mm,外侧板位于路缘石外侧。本发明可有效解决沥青摊铺过程中碾压车对路缘石造成的划痕问题并避免沥青摊铺过程中施工人员踩踏路缘石对路缘石造成污染,经过保护的路缘石无钢轮挤压、划痕、踩踏污染等现象,应用效果较好。
Description
技术领域
本发明涉及一种路缘石保护装置,具体涉及一种沥青摊铺过程中路缘石保护装置及其保护方法。
背景技术
在道路建设中,沥青摊铺时碾压车两侧的钢轮容易将路缘石挤坏或产生划痕,这种划痕在后期维修时很难清除,即使用磨光机打磨也会引起色差,并且耗费大量时间、人力和物力。
发明内容
为弥补现有技术的不足,本发明提供一种沥青摊铺过程中路缘石保护装置及其保护方法。
本发明是通过如下技术方案实现的:
一种沥青摊铺过程中路缘石保护装置,其特殊之处在于:包括内侧板、上顶板和外侧板,所述内侧板、上顶板和外侧板依次固定连接形成一个下方开口的方形上罩罩在路缘石上;所述内侧板位于路缘石靠近沥青路面一侧,该内侧板高度高于路缘石裸露高度1-3mm;所述上顶板平行于路缘石上表面,上顶板上安装有提手,该上顶板宽度宽于路缘石宽度1-3mm;所述外侧板位于路缘石外侧。
本发明的沥青摊铺过程中路缘石保护装置,所述外侧板高度为30-50mm,所述内侧板、上顶板和外侧板采用1mm厚的白铁皮制成。
本发明的一种沥青摊铺过程中路缘石保护装置的保护方法,包括以下步骤:
(1)根据路缘石尺寸定制路缘石保护装置,内侧板、上顶板和外侧板与路缘石之间保留1-3mm距离;
(2)将路缘石保护装置罩在路缘石上,沥青碾压车开始碾压路面,提起路缘石保护装置上顶板上的提手,将碾压过的路面旁边的路缘石保护装置取下移至下一处准备碾压路面的路缘石上。
本发明的有益效果是:本发明可有效解决沥青摊铺过程中碾压车对路缘石造成的划痕问题,也可避免沥青摊铺过程中施工人员踩踏路缘石对路缘石造成污染,经过保护的路缘石无钢轮挤压、划痕、踩踏污染等现象,应用效果较好。
附图说明
附图1是本发明的结构示意图。
图中,1内侧板,2上顶板,3外侧板,4路缘石,5沥青路面,6提手。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步详细的说明。
附图是本发明的一种具体实施方式。该实施例包括内侧板1、上顶板2和外侧板3,内侧板1、上顶板2和外侧板3依次固定连接形成一个下方开口的方形上罩罩在路缘石4上;内侧板1位于路缘石4靠近沥青路面5一侧,该内侧板1高度高于路缘石4裸露高度3mm;所述上顶板2平行于路缘石4上表面,上顶板2上安装有两个提手6,该上顶板2宽度宽于路缘石4宽度3mm;外侧板3位于路缘石4外侧,外侧板(3)高度为40mm,内侧板1、上顶板2和外侧板3采用1mm厚的白铁皮制成。
本实施例的一种沥青摊铺过程中路缘石保护装置的保护方法,包括以下步骤:
(1)根据路缘石4尺寸定制路缘石保护装置,缘石顶宽20cm,高39cm,内侧板1、上顶板2和外侧板3与路缘石4之间保留3mm距离;
(2)将路缘石保护装置罩在路缘石4上,沥青碾压车开始碾压路面,提起路缘石保护装置上顶板2上的提手,将碾压过的路面旁边的路缘石保护装置取下移至下一处准备碾压路面的路缘石4上。
Claims (3)
1.一种沥青摊铺过程中路缘石保护装置,其特征在于:包括内侧板(1)、上顶板(2)和外侧板(3),所述内侧板(1)、上顶板(2)和外侧板(3)依次固定连接形成一个下方开口的方形上罩罩在路缘石(4)上;所述内侧板(1)位于路缘石(4)靠近沥青路面(5)一侧,该内侧板(1)高度高于路缘石(4)裸露高度1-3mm;所述上顶板(2)平行于路缘石(4)上表面,上顶板(2)上安装有提手(6),该上顶板(2)宽度宽于路缘石(4)宽度1-3mm;所述外侧板(3)位于路缘石(4)外侧。
2.根据权利要求1所述的一种沥青摊铺过程中路缘石保护装置,其特征在于:所述外侧板(3)高度为30-50mm,所述内侧板(1)、上顶板(2)和外侧板(3)采用1mm厚的白铁皮制成。
3.根据权利要求1或2所述的一种沥青摊铺过程中路缘石保护装置的保护方法,其特征在于:包括以下步骤:
(1)根据路缘石(4)尺寸定制路缘石保护装置,内侧板(1)、上顶板(2)和外侧板(3)与路缘石(4)之间保留1-3mm距离;
(2)将路缘石保护装置罩在路缘石(4)上,沥青碾压车开始碾压路面,提起路缘石保护装置上顶板(2)上的提手,将碾压过的路面旁边的路缘石保护装置取下移至下一处准备碾压路面的路缘石(4)上。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510605817.6A CN105178143A (zh) | 2015-09-22 | 2015-09-22 | 一种沥青摊铺过程中路缘石保护装置及其保护方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510605817.6A CN105178143A (zh) | 2015-09-22 | 2015-09-22 | 一种沥青摊铺过程中路缘石保护装置及其保护方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105178143A true CN105178143A (zh) | 2015-12-23 |
Family
ID=54900534
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510605817.6A Pending CN105178143A (zh) | 2015-09-22 | 2015-09-22 | 一种沥青摊铺过程中路缘石保护装置及其保护方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105178143A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105951562A (zh) * | 2016-06-12 | 2016-09-21 | 天津康远工程机械有限公司 | 用于路面摊铺作业的多功能双层预应力烫平板 |
CN107447621A (zh) * | 2017-08-17 | 2017-12-08 | 连云港市惠城市政工程有限公司 | 一种带有坡度和转弯的路面沥青铺设方法 |
CN111041951A (zh) * | 2019-12-24 | 2020-04-21 | 中交一公局西北工程有限公司 | 一种路缘石防沥青污染保护装置 |
CN113152225A (zh) * | 2021-04-19 | 2021-07-23 | 安徽开源路桥有限责任公司 | 降低压路机对现浇混凝土挡块路缘石多次碾压造成不可修复性破坏的施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200992671Y (zh) * | 2007-01-09 | 2007-12-19 | 李振江 | 金属贴面边石 |
JP2011038351A (ja) * | 2009-08-15 | 2011-02-24 | Shinichi Tsubakimori | アスファルト舗装地用pc構造体の設置工法 |
CN103233409A (zh) * | 2013-04-18 | 2013-08-07 | 济南城建集团有限公司 | 立沿石安装施工方法 |
GB2519168A (en) * | 2013-10-11 | 2015-04-15 | Plas Guard Ltd | A kerb arrangement |
CN205062618U (zh) * | 2015-09-22 | 2016-03-02 | 济南城建集团有限公司 | 一种沥青摊铺过程中路缘石保护装置 |
-
2015
- 2015-09-22 CN CN201510605817.6A patent/CN105178143A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200992671Y (zh) * | 2007-01-09 | 2007-12-19 | 李振江 | 金属贴面边石 |
JP2011038351A (ja) * | 2009-08-15 | 2011-02-24 | Shinichi Tsubakimori | アスファルト舗装地用pc構造体の設置工法 |
CN103233409A (zh) * | 2013-04-18 | 2013-08-07 | 济南城建集团有限公司 | 立沿石安装施工方法 |
GB2519168A (en) * | 2013-10-11 | 2015-04-15 | Plas Guard Ltd | A kerb arrangement |
CN205062618U (zh) * | 2015-09-22 | 2016-03-02 | 济南城建集团有限公司 | 一种沥青摊铺过程中路缘石保护装置 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105951562A (zh) * | 2016-06-12 | 2016-09-21 | 天津康远工程机械有限公司 | 用于路面摊铺作业的多功能双层预应力烫平板 |
CN107447621A (zh) * | 2017-08-17 | 2017-12-08 | 连云港市惠城市政工程有限公司 | 一种带有坡度和转弯的路面沥青铺设方法 |
CN111041951A (zh) * | 2019-12-24 | 2020-04-21 | 中交一公局西北工程有限公司 | 一种路缘石防沥青污染保护装置 |
CN113152225A (zh) * | 2021-04-19 | 2021-07-23 | 安徽开源路桥有限责任公司 | 降低压路机对现浇混凝土挡块路缘石多次碾压造成不可修复性破坏的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105178143A (zh) | 一种沥青摊铺过程中路缘石保护装置及其保护方法 | |
CN103410115B (zh) | 一种可以破冰除雪的道路清扫装置 | |
MX350305B (es) | Sistema de reparación de pavimento. | |
CN105160094B (zh) | 沥青路面车辙模拟方法 | |
CN205062618U (zh) | 一种沥青摊铺过程中路缘石保护装置 | |
CN205296056U (zh) | 一种破冰机 | |
CN201605514U (zh) | 砂加热撒布车 | |
CN103015303A (zh) | 一种修复沥青路面表面构造和裂缝的施工方法 | |
CN203960785U (zh) | 桥墩防撞桶 | |
CN204551293U (zh) | 一种隧道出口处遮雪棚装置 | |
CN203613485U (zh) | 一种防护栏 | |
CN203080394U (zh) | 液压破碎锤防飞溅装置 | |
CN202164567U (zh) | 除雪车空气压缩机吹雪装置 | |
CN205529809U (zh) | 一种沥青碎石同步封层车 | |
CN103911934A (zh) | 融雪装置 | |
CN203684147U (zh) | 一种桥梁缓冲防撞装置 | |
CN103422409B (zh) | 一种长大下坡消能减速路面及其施工工艺 | |
CN201826329U (zh) | 安全井盖 | |
CN206267069U (zh) | 一种可拆卸的移动式交通护栏 | |
CN202000240U (zh) | 一种道路拦水带 | |
CN204266073U (zh) | 一种高速公路避险车道 | |
CN202482789U (zh) | 非机动车限行带 | |
CN104005327A (zh) | 一种新型的路面切割机 | |
CN206887719U (zh) | 碎石封层稳压回收车的移动式吸盘 | |
CN202989751U (zh) | 一种用于沥青路面热刺碾压的碾压轮 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20151223 |
|