CN105109939B - The transportation technology of longspan structure piece - Google Patents

The transportation technology of longspan structure piece Download PDF

Info

Publication number
CN105109939B
CN105109939B CN201510462819.4A CN201510462819A CN105109939B CN 105109939 B CN105109939 B CN 105109939B CN 201510462819 A CN201510462819 A CN 201510462819A CN 105109939 B CN105109939 B CN 105109939B
Authority
CN
China
Prior art keywords
large scale
structure piece
scale structure
ultromotivity
flat car
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510462819.4A
Other languages
Chinese (zh)
Other versions
CN105109939A (en
Inventor
徐善辉
姜立群
吕超
唐健
杨风艳
田旺生
石继程
窦星慧
黄先超
余明淦
徐学军
郭宁
吴强
马飞翔
王永兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, Offshore Oil Engineering Co Ltd, Offshore Oil Engineering Qingdao Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201510462819.4A priority Critical patent/CN105109939B/en
Publication of CN105109939A publication Critical patent/CN105109939A/en
Application granted granted Critical
Publication of CN105109939B publication Critical patent/CN105109939B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

A kind of transportation technology of longspan structure piece, using following steps:One:Large scale structure piece is carried out prefabricated;Two:Several hydraulic jacking devices are arranged at Jacking point below large scale structure piece;Three:After by large scale structure piece jacking to specified altitude assignment, temporary support is installed thereunder;Four:Transportation frame is connected with the dolly axis of ultromotivity hydraulic flat car;Five:Sail ultromotivity hydraulic flat car into large scale structure piece lower section, workshop to advance fitting-out place is transported out after jack-up;Six:Ultromotivity hydraulic flat car is withdrawn, is supported with temporary support;Seven:Sail ultromotivity hydraulic flat car into large scale structure piece lower section, painting workshop is transported to after jack-up large scale structure piece;Eight:After the completion of the spraying of large scale structure piece, then painting workshop to general assembly place is sailed out of into the large scale structure piece transport after application, carry out general assembly operation.The present invention solves the problems, such as that existing place haulage vehicle cannot realize the hauling operation of longspan structure piece;Realize safe and efficient hauling operation.

Description

The transportation technology of longspan structure piece
Technical field
The present invention relates to transportation technology, more particularly to a kind of longspan structure piece for land liquefied natural gas module Transportation technology.Belong to Offshore Engineering field.
Background technology
Large-scale liquefied natural gas modularization processing factory in building course, because center piping lane modular structure form is similar, One layer of deck plate quite, in order to realize that integrated cleaning is built, generally, is divided into several knots by weight according to the span of its axis Tile is built.Consequently, it is possible to structure piece is more, general assembly workload is bigger, and the duration will extend, therefore, built in module Cheng Zhong, should try one's best increases the workload of shop-fabricated, to reduce the workload during general assembly.But, thus generate again new Problem, because structure burst has more hinged joint, and burst span is excessive, and the weight and flexibility of burst also can significantly increase Plus, therefore, burst is susceptible to bending deformation, especially in transportation.And existing transport vehicle is not enough to bearing structure Burst, even if by two 370 tons of flat car integrations of operation, solving the problems, such as Lack of support, but, in transportation, Due to the nonsynchronous problem of two chassis, in cornering operation, it is susceptible to structure piece and topples, there is larger potential safety hazard.
The content of the invention
It is a primary object of the present invention to the disadvantages mentioned above for overcoming prior art to exist, and provide a kind of longspan structure piece Transportation technology, it can not only be realized to being hinged more, the transport of the structure piece of large span, solve existing place haulage vehicle The hauling operation problem of longspan structure piece cannot be realized;And, in transportation, segment axis are replaced by transportation frame Means of transportation, greatly reduce the input amount of axis, saved dolly axis resource, and then save ultromotivity hydraulic flat The lease expenses of car;Additionally, also achieving safe and efficient hauling operation, the logistic efficiency for the treatment of of the earth piece transport is improve, While cost of transportation is reduced, the construction period is substantially reduced.
The purpose of the present invention is realized by following technical scheme:
1st, a kind of transportation technology of longspan structure piece, it is characterised in that:Using following steps:
The first step:Large scale structure piece is carried out in prefabricated workshop prefabricated;
Second step:Arrange that several hydraulic jacking devices carry out jacking work at the Jacking point specified below large scale structure piece Industry;
3rd step:After hydraulic jacking device is by large scale structure piece jacking to specified altitude assignment, below large scale structure piece Temporary support is installed, is used to be supported fixation to large scale structure piece, then, withdraw hydraulic jacking device;
4th step:The perfect ultromotivity hydraulic flat car of configuration, it is then determined that the dolly headstock of ultromotivity hydraulic flat car Position, dolly axis quantity, and transportation frame is connected with the dolly axis of ultromotivity hydraulic flat car;
5th step:In prefabricated workshop into, array ultromotivity hydraulic flat car is sailed the lower section of large scale structure piece, will be large-scale Workshop to advance fitting-out place is transported out after structure piece jack-up;
6th step:Ultromotivity hydraulic flat car is withdrawn, is continuing with temporary support and is supported, and in advance fitting-out Ground, completes the advanced outfitting work of the structure loose mail on large scale structure piece;
7th step:The lower section of the large scale structure piece where sailing ultromotivity hydraulic flat car into advance fitting-out place, and pass through Transport sails out of advance fitting-out place to spraying car after the hydraulic power unit jack-up large scale structure piece of ultromotivity hydraulic flat car itself Between;
8th step:Large scale structure piece is transported to outfitting shop's specified location, ultromotivity hydraulic flat car is withdrawn, after It is continuous to be supported using temporary support;In painting workshop, the spray coating operations of large scale structure piece are completed, after spraying, using ultromotivity Hydraulic flat car, then painting workshop to general assembly place is sailed out of into the large scale structure piece transport after application, carry out general assembly operation.
The Typical Disposition of the ultromotivity hydraulic flat car is:Every group of vehicle is made up of headstock, axis and transportation frame, matches somebody with somebody It is that the form of headstock+array axis+transportation frame+array axis+transportation frame+array axis is automatic with what is postponed to put order The car body total length of power hydraulic flat car reaches 40 meters.
Top lifting height of the large scale structure piece in workshop is more than 1.35 meters, and the exemplary height of interim pad pier is 1.35 Rice.
The ultromotivity hydraulic flat car need in advance arrange cushion block, and laid on cushion block using preceding on car body Glued board, to increase the frictional force of car body and deck structure piece;Ultromotivity hydraulic flat car enters large scale structure piece lower section and specifies Behind position, colligation need to be carried out at node on large scale structure piece using suspender belt and guide chain and fixed, to prevent large scale structure piece from sliding; Before transport large scale structure piece enters painting workshop, need to lay rubber on car body cushion block in advance, to prevent from destroying large scale structure piece Paint.
Beneficial effects of the present invention:Due to using above-mentioned technical proposal, it can not only be realized to being hinged, greatly the present invention more The transport of the structure piece of span, solves the problems, such as that existing place haulage vehicle cannot realize the hauling operation of longspan structure piece; And, in transportation, the means of transportation of segment axis is replaced by transportation frame, the input amount of axis is greatly reduced, Dolly axis resource is saved, and then has saved the lease expenses of ultromotivity hydraulic flat car;Additionally, also achieving safety, height The hauling operation of effect, improves the logistic efficiency for the treatment of of the earth piece transport, while cost of transportation is reduced, substantially reduces and applies The work duration.
Brief description of the drawings
Fig. 1 is the prefabricated schematic diagram of deck structure piece of the present invention.
Fig. 2 is arrangement hydraulic jacking device floor map under deck structure piece of the present invention.
Fig. 3 is arrangement hydraulic jacking device elevational schematic view under deck structure piece of the present invention.
Fig. 4 is the floor map of arrangement temporary support under deck structure piece of the present invention.
Fig. 5 is the elevational schematic view of arrangement temporary support under deck structure piece of the present invention.
Fig. 6 is ultromotivity hydraulic flat car Typical Disposition figure of the present invention.
Fig. 7 is the floor map of ultromotivity hydraulic flat car jack-up deck structure piece of the present invention.
Fig. 8 is the elevational schematic view of ultromotivity hydraulic flat car transport deck structure piece of the present invention.
Fig. 9 is that temporary support of the present invention is fixed deck structure piece and installs the elevational schematic view of other structures loose mail.
Major Symbol explanation in figure:
1. large scale structure piece, 2. hydraulic jacking device, 3. temporary support, 4. ultromotivity hydraulic flat car, 5. headstock, 6. axle Line, 7. transportation frame, 8. structure loose mail.
Specific embodiment
The present invention uses following steps:
The first step:As shown in figure 1, large scale structure piece 1 is carried out in prefabricated workshop prefabricated, and large scale structure piece 1 is noted Placing direction, is advisable in order to haulage vehicle turnover;
Second step:Such as Fig. 2, shown in Fig. 3, according to the size and weight of large scale structure piece 1, to jacking strength check after, The several hydraulic jacking devices 2 of arrangement carry out lifting operation at the Jacking point that the lower section of large scale structure piece 1 is specified;
3rd step:Such as Fig. 4, shown in Fig. 5, after hydraulic jacking device 2 is by the jacking of large scale structure piece 1 to specified altitude assignment, Specified location below large scale structure piece 1, temporary support 3 is installed using welding manner, is used to prop up large scale structure piece 1 Support is fixed, and then, withdraws hydraulic jacking device 2;
4th step:As shown in fig. 6, according to the size and weight of large scale structure piece 1, after being checked through traffic intensity, configuring Kind ultromotivity hydraulic flat car 4, it is then determined that the position of the dolly headstock 5 of ultromotivity hydraulic flat car 4, dolly axis 6 is counted Amount, and transportation frame 7 is connected using welding or bolt connecting mode with the dolly axis 6 of ultromotivity hydraulic flat car 4;
5th step:As shown in fig. 7, in prefabricated workshop, sailing array ultromotivity hydraulic flat car 4 into large scale structure piece 1 Lower section specified location, and after the hydraulic power unit jack-up large scale structure piece 1 for passing through ultromotivity hydraulic flat car 4 itself, so Afterwards, it is transported out workshop to advance fitting-out place;
6th step:Such as Fig. 8, shown in Fig. 9, using ultromotivity hydraulic flat car 4, large scale structure piece 1 is transported to advance fitting-out After the specified location of place, ultromotivity hydraulic flat car 4 is withdrawn, be continuing with temporary support 3 and be supported, in advance fitting-out Ground, completes the advanced outfitting work of the other structures loose mail 8 on large scale structure piece 1;
7th step:The lower section specific bit of the large scale structure piece 1 where sailing ultromotivity hydraulic flat car 4 into advance fitting-out place Put, and after the hydraulic power unit jack-up large scale structure piece 1 for passing through ultromotivity hydraulic flat car 4 itself, be transported sail out of it is pre- Fitting-out place is to painting workshop;
8th step:Using ultromotivity hydraulic flat car 4, large scale structure piece 1 is transported to outfitting shop's specified location, will Ultromotivity hydraulic flat car 4 is withdrawn, and is continuing with temporary support 3 and is supported, and in painting workshop, completes large scale structure piece 1 Spray coating operations, after spraying, using ultromotivity hydraulic flat car 4, then sail out of painting workshop by the transport of large scale structure piece 1 after application To general assembly place, general assembly operation is carried out.
Above-mentioned large scale structure piece 1 refers to offshore platform or liquid of the length and width of works more than 30 meters Change the structure piece of gas plant, can be deck structure piece, or platform deck, the vertical piece of construct platform, plain film Deng;Wherein, there is substantial amounts of being articulated and connected at the node of large scale structure piece 1.
What above-mentioned ultromotivity hydraulic flat car 4 was selected is:Two groups of KAMAG type ultromotivity hydraulic flat cars, model has 2 kinds, KAMAG2404, four groups of axis, KAMAG2406, six groups of axis;Its stroke height is 1.25 meters -1.75 meters.
The Typical Disposition of above-mentioned ultromotivity hydraulic flat car 4 is:Every group of vehicle is by 7 groups of headstock 5, axis 6 and transportation frame It is into, configuration sequence, tetra- groups of headstock 5+, six groups of axis 6+ transportation frames 7+ axis 6+ transportation frames tetra- groups of forms of axis 6 of 7+, Car body total length with the ultromotivity hydraulic flat car 4 for postponing reaches 40 meters.
The selection of above-mentioned hydraulic jacking device and arrangement, the type selecting and arrangement of ultromotivity hydraulic flat car 4 are passed through in advance Strength check, possesses Strength co-mputation report, and top lifting height of the above-mentioned large scale structure piece 1 in workshop is more than 1.35 meters, interim pad The exemplary height of pier is 1.35 meters.
Above-mentioned ultromotivity hydraulic flat car 4 need in advance arrange cushion block, and laid on cushion block using preceding on car body Glued board, to increase the frictional force of car body and deck structure piece;Ultromotivity hydraulic flat car 4 refers into the lower section of large scale structure piece 1 Positioning is postponed, and colligation need to be carried out at node on large scale structure piece 1 using suspender belt and guide chain and fixed, to prevent large scale structure piece 1 Sliding;Before transport large scale structure piece 1 enters painting workshop, need to lay rubber on car body cushion block in advance, to prevent destruction large-scale The paint of structure piece 1.
Above-mentioned hydraulic jacking device, cushion block, glued board, suspender belt, guide chain, rubber are prior art, therefore repeat no more.
The above, is only presently preferred embodiments of the present invention, and any formal limitation is not made to the present invention, all It is any simple modification, equivalent variations and the modification made to above example according to technical spirit of the invention, still falls within In the range of technical solution of the present invention.

Claims (1)

1. a kind of transportation technology of longspan structure piece, it is characterised in that:Using following steps:
The first step:Large scale structure piece is carried out in prefabricated workshop prefabricated;
Second step:Arrange that several hydraulic jacking devices carry out lifting operation at the Jacking point specified below large scale structure piece;
3rd step:After hydraulic jacking device is by large scale structure piece jacking to specified altitude assignment, installed below large scale structure piece Temporary support, is used to be supported fixation to large scale structure piece, then, withdraws hydraulic jacking device;
4th step:The perfect ultromotivity hydraulic flat car of configuration, it is then determined that the position of the dolly headstock of ultromotivity hydraulic flat car Put, dolly axis quantity, and transportation frame is connected with the dolly axis of ultromotivity hydraulic flat car;
5th step:In prefabricated workshop, array ultromotivity hydraulic flat car is sailed the lower section of large scale structure piece into, by large scale structure Workshop to advance fitting-out place is transported out after piece jack-up;
6th step:Ultromotivity hydraulic flat car is withdrawn, is continuing with temporary support and is supported, and in advance fitting-out place, it is complete Into the advanced outfitting work of the structure loose mail on large scale structure piece;
7th step:The lower section of the large scale structure piece where sailing ultromotivity hydraulic flat car into advance fitting-out place, and by automatic Advance fitting-out place to painting workshop is sailed out of in transport after the hydraulic power unit jack-up large scale structure piece of power hydraulic flat car itself;
8th step:Large scale structure piece is transported to outfitting shop's specified location, ultromotivity hydraulic flat car is withdrawn, continue to make It is supported with temporary support;In painting workshop, the spray coating operations of large scale structure piece are completed, after spraying, using ultromotivity hydraulic pressure Flat car, then painting workshop to general assembly place is sailed out of into the large scale structure piece transport after application, carry out general assembly operation;It is described automatic The Typical Disposition of power hydraulic flat car is:Every group of vehicle is made up of headstock, axis and transportation frame, and configuration sequence is, headstock+number The form of group axis+transportation frame+array axis+transportation frame+array axis, the car with the ultromotivity hydraulic flat car for postponing Body total length reaches 40 meters;Top lifting height of the large scale structure piece in workshop is more than 1.35 meters, and the typical case of interim pad pier is high Spend is 1.35 meters;The ultromotivity hydraulic flat car need in advance arrange cushion block using preceding on car body, and on cushion block upper berth If glued board, to increase the frictional force of car body and deck structure piece;Ultromotivity hydraulic flat car refers into large scale structure piece lower section Positioning is postponed, and colligation need to be carried out at node on large scale structure piece using suspender belt and guide chain and fixed, to prevent large scale structure piece from sliding Move;Before transport large scale structure piece enters painting workshop, need to lay rubber on car body cushion block in advance, to prevent from destroying large scale structure The paint of piece.
CN201510462819.4A 2015-07-31 2015-07-31 The transportation technology of longspan structure piece Active CN105109939B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510462819.4A CN105109939B (en) 2015-07-31 2015-07-31 The transportation technology of longspan structure piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510462819.4A CN105109939B (en) 2015-07-31 2015-07-31 The transportation technology of longspan structure piece

Publications (2)

Publication Number Publication Date
CN105109939A CN105109939A (en) 2015-12-02
CN105109939B true CN105109939B (en) 2017-06-13

Family

ID=54658119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510462819.4A Active CN105109939B (en) 2015-07-31 2015-07-31 The transportation technology of longspan structure piece

Country Status (1)

Country Link
CN (1) CN105109939B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106347577A (en) * 2016-09-26 2017-01-25 中国海洋石油总公司 Construction technology capable of shortening block slide way occupation and general assembly period
CN109747517B (en) * 2017-11-08 2021-10-01 上海宝冶集团有限公司 Method for modular transportation of support frame of radiant section of steam reformer
CN109972603A (en) * 2019-03-20 2019-07-05 海洋石油工程(青岛)有限公司 The technique of jacket sectional construction
CN110482151B (en) * 2019-07-25 2024-04-12 招商局邮轮制造有限公司 Trolley for luxury mailbox wheel sectional manufacturing and transporting assembly line
CN112937406B (en) * 2021-02-03 2023-06-16 中冶北方(大连)工程技术有限公司 Four-side type moving system of thickener and moving method of thickener
CN114701417A (en) * 2022-03-02 2022-07-05 海洋石油工程(青岛)有限公司 Ocean engineering large deck plate transportation device and transportation method thereof
CN115030522B (en) * 2022-06-30 2024-04-26 上海市机械施工集团有限公司 Construction method of large steel structure
CN115108295B (en) * 2022-07-29 2024-04-30 广船国际有限公司 Segmented stacking and transporting method for flaky decks
CN115445874B (en) * 2022-09-30 2024-05-07 上海外高桥造船海洋工程有限公司 Method for stacking, placing and coating binding bridge sheet bodies

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767549A (en) * 2008-12-31 2010-07-07 宝山钢铁股份有限公司 Power-driven lift platform carrier vehicle for steel mill
CN202557390U (en) * 2012-05-11 2012-11-28 苏州大方特种车股份有限公司 Bridge type frame vehicle special for large-size transformer transportation
CN204078409U (en) * 2014-08-25 2015-01-07 中国海洋石油总公司 The automobile-used auxiliary moulding bed of hydraulic flat
US9004832B1 (en) * 2012-05-14 2015-04-14 Raildecks (2009), Inc. Intermodal container
CN104691398A (en) * 2015-03-18 2015-06-10 上海振华重工(集团)股份有限公司 Method for land transfer of oversized gate

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767549A (en) * 2008-12-31 2010-07-07 宝山钢铁股份有限公司 Power-driven lift platform carrier vehicle for steel mill
CN202557390U (en) * 2012-05-11 2012-11-28 苏州大方特种车股份有限公司 Bridge type frame vehicle special for large-size transformer transportation
US9004832B1 (en) * 2012-05-14 2015-04-14 Raildecks (2009), Inc. Intermodal container
CN204078409U (en) * 2014-08-25 2015-01-07 中国海洋石油总公司 The automobile-used auxiliary moulding bed of hydraulic flat
CN104691398A (en) * 2015-03-18 2015-06-10 上海振华重工(集团)股份有限公司 Method for land transfer of oversized gate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
同步顶升系统在结构大片建造中的应用;杨伟旗等;《科技资讯》;20101231;64-66 *

Also Published As

Publication number Publication date
CN105109939A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN105109939B (en) The transportation technology of longspan structure piece
CN202669944U (en) Heavy semi-trailer for coiled tubing equipment
CN205527429U (en) Jib crane is from jacking device
CN105932191A (en) Battery fixing device and electric vehicle
CN104944300B (en) Arm crane foundation
CN102337736A (en) Installation process of upper module on offshore oil platform
CN104805857B (en) One detachably recycles bottomless steel jacket box and construction method thereof
CN208995937U (en) Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station
CN104372961A (en) Anti-seismic integrated lightweight steel construction house
CN102582786A (en) Building process for deep sea spar platform
CN201189944Y (en) Folding borehole work platform
CN208183643U (en) A kind of dock structure taking into account large ship and heavy mail mast and hanging
CN102817342A (en) Construction technology of in-situ assembly under pile foundation construction platform of double-wall steel cofferdam
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN103552800A (en) Translation method of large-scale canned equipment
CN109296082A (en) A kind of frame or half inverted construction structure of cylinder load-bearing high level modular architectural and construction method
CN208360186U (en) A kind of mine elevator diclinic ramp promotes that mine car is automatically-unhooked and separator
CN102530735B (en) Entire loading and transporting technology and equipment for portal crane
CN204151665U (en) A kind of cable-stayed type opens trestle
CN206544870U (en) A kind of car passenger ferry hoisting main door frame frock
CN206987058U (en) A kind of life building modular unit assembling splicing combination of nodes
CN205804178U (en) Scalable without holder device for the liftable of bridge coping construction
CN203127803U (en) Support device for rolling-on and rolling-off of heavy ocean structure
CN209455204U (en) Detachable transportation frame for Pipe rack module
CN204919348U (en) Supplementary head tower of using of self anchored suspension bridge installation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: Offshore Oil Engineering Co., Ltd.

Patentee after: China Offshore Oil Group Co., Ltd.

Co-patentee after: Offshore Oil Engineering (Qingdao) Co., Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: Offshore Oil Engineering Co., Ltd.

Patentee before: China National Offshore Oil Corporation

Co-patentee before: Offshore Oil Engineering (Qingdao) Co., Ltd.