CN204151665U - A kind of cable-stayed type opens trestle - Google Patents

A kind of cable-stayed type opens trestle Download PDF

Info

Publication number
CN204151665U
CN204151665U CN201420549205.0U CN201420549205U CN204151665U CN 204151665 U CN204151665 U CN 204151665U CN 201420549205 U CN201420549205 U CN 201420549205U CN 204151665 U CN204151665 U CN 204151665U
Authority
CN
China
Prior art keywords
fixed
bridge
opening section
lattice columns
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420549205.0U
Other languages
Chinese (zh)
Inventor
周俊龙
余流
高璞
刘晓敏
李飞
石丰祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201420549205.0U priority Critical patent/CN204151665U/en
Application granted granted Critical
Publication of CN204151665U publication Critical patent/CN204151665U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种斜拉式开启栈桥,它包括四组格构柱,在格构柱的顶部固定有分配底座,在两侧格构柱的内侧分别打设有支撑桩,在同侧两组格构柱之间设置有至少一个加强排架临时墩,在同侧的多根排架墩管桩桩顶焊接固定一根工字钢横梁,两个相同的单侧桥梁上部结构组成一个可以开启的整体桥梁上部结构,贝雷片包括固定段、后开启段以及前开启段,在分配底座上固定有卷扬机,与一侧的四台卷扬机中的两台卷扬机相连的前斜拉索的拉力端固定在同侧的前开启段的前端部并且与该侧的另外两台卷扬机相连的后斜拉索的拉力端固定在该侧的后开启段的前端。采用本装置可增大栈桥允许通航净空。

The utility model discloses a cable-stayed open trestle bridge, which comprises four sets of lattice columns, a distribution base is fixed on the top of the lattice columns, support piles are respectively driven inside the lattice columns on both sides, and on the same side At least one reinforced bent temporary pier is set between two groups of lattice columns, and an I-beam beam is welded and fixed on the top of multiple bent piers on the same side. Two identical single-sided bridge superstructures form a The overall bridge superstructure that can be opened, the Bailey sheet includes a fixed section, a rear opening section and a front opening section, a winch is fixed on the distribution base, and the front stay cables connected to two of the four winches on one side The tension end is fixed on the front end of the front opening section of the same side and the tension end of the rear stay cable connected to the other two winches of this side is fixed on the front end of the rear opening section of this side. The adoption of the device can increase the navigation clearance of the trestle bridge.

Description

一种斜拉式开启栈桥A cable-stayed open trestle bridge

技术领域technical field

本实用新型涉及桥梁工程施工领域,具体来说涉及一种用于有通航需求的桥梁施工中栈桥的结构。The utility model relates to the field of bridge engineering construction, in particular to a trestle bridge structure used in bridge construction with navigation requirements.

背景技术Background technique

目前公知的在有通航需求的水域进行桥梁施工时主要采用门式结构栈桥方式,该种施工方法仅能允许小型、低矮的船舶通过,且如通航净空过大则会对桥梁两侧施工造成影响,使交通不便,不利于施工机械、材料的周转。此外,公开号CN202369929 U和CN202688850U的专利中公开了一种提升装置,该装置仅可提供有限的通航净空,其通航净空的高度极限为其设置的格构柱的高出水面的高度与便桥高度之差。At present, the known bridge construction in waters with navigation needs mainly adopts the portal structure trestle method. This construction method can only allow small and low ships to pass through, and if the navigation clearance is too large, it will cause damage to the construction on both sides of the bridge. The impact makes the transportation inconvenient, which is not conducive to the turnover of construction machinery and materials. In addition, the patents of publication numbers CN202369929 U and CN202688850U disclose a lifting device, which can only provide limited navigation clearance, and the height limit of its navigation clearance is the height above the water surface of the lattice column and the height of the temporary bridge. Difference.

发明内容Contents of the invention

本实用新型的目的在于克服已有技术的不足,提供一种通航宽度宽并且能够提供无限的通航净空,同时能够保证栈桥复原后结构表面的平坦的一种斜拉式开启栈桥。The purpose of the utility model is to overcome the deficiencies of the prior art, and provide a cable-stayed open trestle with a wide navigation width, which can provide unlimited navigation clearance, and at the same time, can ensure the flat structure surface of the restored trestle.

本实用新型是通过以下技术方案实现的:The utility model is achieved through the following technical solutions:

一种斜拉式开启栈桥,它包括沿纵桥向桥面两侧间隔设置的四组用于竖向承重的格构柱,每一组格构柱的4根钢管之间焊接固定相连,在每一组格构柱的顶部固定有分配底座,在两侧格构柱的内侧分别打设有支撑桩,在同侧两组格构柱之间设置有至少一个加强排架临时墩,所述的加强排架临时墩包括插打在同侧两组格构柱之间的多根排架墩管桩,所述的排架墩管桩之间焊接相连,在同侧的多根排架墩管桩桩顶焊接固定一根工字钢横梁,两个相同的单侧桥梁上部结构组成一个可以开启的整体桥梁上部结构,每一个单侧桥梁上部结构均包括多个彼此相连的贝雷片,在所述的贝雷片的上弦杆上固定有多根间隔设置的横向工字钢,在所述的横向工字钢上固定有多根间隔设置的纵向工字钢,在所述的纵向工字钢上固定有桥面系结构,所述的多个彼此相连的贝雷片包括通过贝雷片的加强弦杆焊接固定在相应侧的工字钢横梁上的固定段,所述的固定段前端通过转铰与向桥中央延伸的后开启段后端相连,所述的后开启段前端通过转铰与向桥中央延伸的前开启段后端相连,所述的后开启段后端和前部分别支撑在工字钢横梁上以及支撑桩上,所述的桥两侧的前开启段的前端在栈桥结构放平时采用销栓进行连接,在每一个分配底座上均固定有四台卷扬机,在每一个格构柱的内侧分别设置有上、下限位横梁,与一侧的四台卷扬机中的两台卷扬机相连的前斜拉索的拉力端固定在同侧的前开启段的前端部并且与该侧的另外两台卷扬机相连的后斜拉索的拉力端固定在该侧的后开启段的前端,所述的前开启段能够在卷扬机的带动下翻转支撑在上限位横梁上,所述的后开启段能够在卷扬机的带动下翻转支撑在下限位横梁上。A cable-stayed open trestle bridge, which includes four groups of lattice columns for vertical load-bearing arranged at intervals along the longitudinal bridge to both sides of the bridge deck, and the four steel pipes of each group of lattice columns are welded and fixedly connected. The distribution base is fixed on the top of each group of lattice columns, support piles are installed on the inner sides of the lattice columns on both sides, and at least one temporary pier for strengthening bent frames is arranged between the two groups of lattice columns on the same side. The reinforced bent-frame temporary pier includes multiple bent-pier pipe piles inserted between two sets of lattice columns on the same side, the bent-pier pipe piles are connected by welding, and the multiple bent-pier pipe piles on the same side The top of the pipe pile is welded and fixed with an I-beam beam. Two identical unilateral bridge superstructures form a whole bridge superstructure that can be opened. Each unilateral bridge superstructure includes multiple Bailey sheets connected to each other. On the upper chord of the Bailey sheet, a plurality of horizontal I-beams arranged at intervals are fixed, and a plurality of longitudinal I-beams arranged at intervals are fixed on the described transverse I-beams. A bridge deck system structure is fixed on the beam, and the plurality of Bailey sheets connected to each other include a fixed section that is welded and fixed on the I-beam beam on the corresponding side through the reinforcing chord of the Bailey sheet. The fixed section The front end is connected to the rear end of the rear opening section extending to the center of the bridge through a hinge, and the front end of the rear opening section is connected to the rear end of the front opening section extending to the center of the bridge through a rotating hinge. Parts are supported on the I-beam beams and support piles respectively. The front ends of the front opening sections on both sides of the bridge are connected by pins when the trestle structure is laid out, and four winches are fixed on each distribution base. The upper and lower limit beams are respectively arranged on the inner side of each lattice column, and the tension ends of the front stay cables connected to two of the four winches on one side are fixed at the front end of the front opening section on the same side and The tension end of the rear stay cable connected to the other two winches on this side is fixed on the front end of the rear opening section on this side, and the front opening section can be turned over and supported on the upper limit beam under the drive of the winch. The rear opening section can be turned over and supported on the lower limit beam under the drive of the winch.

本实用新型与已有技术相比具有的有益效果是:Compared with the prior art, the utility model has the beneficial effects that:

(1)采用斜拉式结构可增大栈桥允许通航净空。(1) The use of cable-stayed structure can increase the allowable navigation clearance of the trestle.

(2)栈桥放平后不影响栈桥的施工功能。(2) The construction function of the trestle will not be affected after the trestle is leveled.

附图说明Description of drawings

图1为本实用新型斜拉式开启栈桥的结构示意图。Fig. 1 is the structural representation of the cable-stayed open trestle of the utility model.

图2为本实用新型一种斜拉式开启栈桥中栈桥未开启状态示意图。Fig. 2 is a schematic diagram of the unopened state of the trestle in a cable-stayed open trestle of the present invention.

图3为本实用新型一种斜拉式开启栈桥中转铰的示意图。Fig. 3 is a schematic diagram of a cable-stayed open trestle transfer hinge of the present invention.

图4为本实用新型一种斜拉式开启栈桥中栈桥上部结构示意图。Fig. 4 is a schematic diagram of the upper structure of the trestle in a cable-stayed open trestle of the present invention.

图5为本实用新型一种斜拉式开启栈桥加强排架临时墩的结构示意图。Fig. 5 is a structural schematic diagram of a temporary pier for reinforcing bent frames of a cable-stayed open trestle bridge according to the present invention.

具体实施方式Detailed ways

下面结合附图和具体实施例对本实用新型的使用作进一步说明。Below in conjunction with accompanying drawing and specific embodiment the use of the utility model is further described.

如附图所示的本实用新型的一种斜拉式开启栈桥,它包括沿纵桥向桥面两侧间隔设置的四组用于竖向承重的格构柱1。每一组格构柱1的4根钢管之间焊接固定相连,优选的每一组格构柱1的4根钢管之间的上部和下部分别通过斜撑和横撑2结构焊接相连。在每一组格构柱1的顶部固定有分配底座3,在两侧格构柱1的内侧分别打设有支撑桩9,在同侧两组格构柱1之间设置有至少一个加强排架临时墩22,作为本实用新型的一种实施方式,所述的加强排架临时墩22包括插打在同侧两组格构柱1之间的多根排架墩管桩24,所述的排架墩管桩24之间焊接相连,优选的排架墩管桩24之间采用上下间隔设置的钢管23进行水平向焊接相连,并采用槽钢21在上下钢管23之间将相邻的排架墩管桩24剪刀向焊接相连。在同侧的多根排架墩管桩24桩顶焊接固定一根工字钢横梁13,两个相同的单侧桥梁上部结构组成一个可以开启的整体桥梁上部结构,每一个单侧桥梁上部结构均包括多个彼此相连的贝雷片14,贝雷片14之间通常采用定型支撑片16相连。在所述的贝雷片14的上弦杆上固定有多根间隔设置的横向工字钢17,在所述的横向工字钢17上固定有多根间隔设置的纵向工字钢18,在所述的纵向工字钢18上固定有桥面系结构,所述的桥面系结构通常包括安装在所述的纵向工字钢18上的作为桥面的压花钢板19,在所述的压花钢板19上固定有栏杆20。所述的多个彼此相连的贝雷片14包括通过贝雷片的加强弦杆15焊接固定在相应侧的工字钢横梁13上的固定段,所述的固定段前端通过转铰12与向桥中央延伸的后开启段8后端相连,所述的后开启段8前端通过转铰12与向桥中央延伸的前开启段7后端相连,所述的后开启段8后端和前部分别支撑在工字钢横梁13上以及支撑桩9上,所述的桥两侧的前开启段7的前端在栈桥结构放平时采用销栓进行连接,在每一个分配底座3上均固定有四台卷扬机4,在每一个格构柱的内侧分别设置有上、下限位横梁10,与一侧的四台卷扬机4中的两台相连的前斜拉索5的拉力端固定在同侧的前开启段7的前端部并且与该侧的另外两台卷扬机4相连的后斜拉索6的拉力端固定在该侧的后开启段8的前端,所述的前开启段7能够在卷扬机4的带动下翻转支撑在上限位横梁上,所述的后开启段8能够在卷扬机4的带动下翻转支撑在下限位横梁上。As shown in the accompanying drawings, a cable-stayed open trestle bridge of the present utility model includes four groups of lattice columns 1 for vertical load-bearing arranged at intervals along the longitudinal bridge to both sides of the bridge deck. The 4 steel pipes of each group of lattice columns 1 are fixedly connected by welding, preferably the upper and lower parts of the 4 steel pipes of each group of lattice columns 1 are connected by structural welding of diagonal braces and cross braces 2 respectively. A distribution base 3 is fixed on the top of each group of lattice columns 1, and support piles 9 are drilled on the inner sides of the lattice columns 1 on both sides, and at least one reinforcing row is arranged between two groups of lattice columns 1 on the same side. Frame temporary piers 22, as an embodiment of the present utility model, said reinforced bent frame temporary piers 22 include a plurality of bent frame pier pipe piles 24 inserted between two groups of lattice columns 1 on the same side, said The pipe piles 24 of the bent pier are welded and connected, and the steel pipes 23 arranged at intervals up and down are preferably used for horizontal welding connection between the pipe piles 24 of the bent pier, and channel steel 21 is used to connect the adjacent steel pipes 23 between the upper and lower steel pipes The 24 scissors of the bent pier pipe piles are connected to each other by welding. An I-beam beam 13 is welded and fixed on the pile tops of multiple bent pier piles 24 on the same side. Two identical unilateral bridge superstructures form an openable overall bridge superstructure. Each unilateral bridge superstructure Each includes a plurality of Bailey sheets 14 connected to each other, and the Bailey sheets 14 are usually connected by a shaped support sheet 16 . On the upper chord of the Bailey sheet 14, a plurality of horizontal I-beams 17 arranged at intervals are fixed, and a plurality of longitudinal I-beams 18 arranged at intervals are fixed on the described transverse I-beams 17. A bridge deck system structure is fixed on the longitudinal I-beam 18, and the bridge deck system generally includes an embossed steel plate 19 installed on the longitudinal I-beam 18 as a bridge deck. Railing 20 is fixed on flower plate 19. The plurality of Bailey sheets 14 connected to each other includes a fixed section that is welded and fixed on the I-beam beam 13 on the corresponding side through the reinforcing chord 15 of the Bailey sheet. The rear end of the rear opening section 8 extending from the center of the bridge is connected to each other. The front end of the rear opening section 8 is connected to the rear end of the front opening section 7 extending to the center of the bridge through a hinge 12. The rear end of the rear opening section 8 and the front part Respectively supported on the I-beam beam 13 and the supporting pile 9, the front ends of the front opening sections 7 on both sides of the bridge are connected by pins when the trestle structure is laid flat, and four distribution bases are fixed on each distribution base 3 Each winch 4 is provided with upper and lower limit beams 10 on the inner side of each lattice column, and the tension end of the front stay cable 5 connected to two of the four winches 4 on one side is fixed on the same side. The front end of the opening section 7 and the tension end of the rear stay cable 6 connected to the other two winches 4 on this side are fixed on the front end of the rear opening section 8 on this side, and the front opening section 7 can be placed on the front end of the hoisting machine 4. Driven and flipped and supported on the upper limit beam, the rear opening section 8 can be turned and supported on the lower limit beam under the drive of the hoist 4 .

本结构施工方法包括以下步骤:This structure construction method comprises the following steps:

(1)在设定的桥面位置每一侧分别设置两组格构柱,每一组格构柱由4根钢管组成,每一组格构柱1的4根钢管之间焊接固定相连,优选的每一组格构柱1的4根钢管之间通过斜撑和横撑2固定焊接相连形成剪刀撑形式,然后在每一个格构柱顶端安装分配底座3,再在每一个分配底座3上安装四台卷扬机4并在每一个格构柱内侧上下间隔的分别焊接上、下限位横梁10;(1) Set two sets of lattice columns on each side of the set bridge deck position, each set of lattice columns is composed of 4 steel pipes, and the 4 steel pipes of each set of lattice columns 1 are welded and fixedly connected. Preferably, the 4 steel pipes of each group of lattice columns 1 are fixedly welded and connected by diagonal braces and cross braces 2 to form a scissors brace, and then a distribution base 3 is installed on the top of each lattice column, and then each distribution base 3 Four winches 4 are installed on the top and the upper and lower limit beams 10 are respectively welded up and down on the inner side of each lattice column;

(2)在两侧格构柱1的内侧顺桥向分别插打固定支撑桩9至设定标高;(2) Insert and drive fixed support piles 9 to the set elevation respectively along the bridge direction on the inner sides of the lattice columns 1 on both sides;

(3)在同侧两组格构柱1之间插打排架墩管桩24至设定标高,然后将所述的排架墩管桩24之间焊接相连形成至少一个加强排架临时墩22,优选的排架墩管桩24之间采用上下间隔设置的钢管23进行水平向焊接相连,并采用槽钢21在上下钢管23之间将相邻的排架墩管桩24剪刀向焊接相连,使得排架墩管桩24之间形成剪刀撑形式;(3) Insert bent pier pipe piles 24 between the two groups of lattice columns 1 on the same side to the set elevation, and then weld and connect the bent pier pipe piles 24 to form at least one reinforced bent frame temporary pier 22. Preferably, the pipe piles 24 of the bent pier are connected by horizontal welding with steel pipes 23 arranged at intervals up and down, and channel steel 21 is used to connect the adjacent pipe piles 24 of the bent pier between the upper and lower steel pipes 23 by scissors welding. , so that the form of scissors bracing is formed between the pipe piles 24 of the bent piers;

(4)在每侧的多根排架墩管桩桩顶吊放一根工字钢横梁13,工字钢横梁13放置在排架墩管桩桩顶中心位置并调整水平后,将工字钢横梁与排架墩管桩桩顶焊接连接。(4) Place an I-shaped steel crossbeam 13 on the top of a plurality of bent pier pipe piles on each side. The steel beam is welded to the top of the pipe pile of the bent pier.

(5)在每侧的工字钢横梁上安装一个单侧桥梁上部结构,两个相同的单侧桥梁上部结构组成一个可以开启的整体桥梁上部结构,每一个单侧桥梁上部结构均包括多个彼此相连的贝雷片14,所述的多个彼此相连的贝雷片14包括通过贝雷片的加强弦杆15固定在相应侧的工字钢横梁13上的固定段,优选的工字钢横梁13与固定段相交部位采用U型件固定,并将工字钢横梁13与固定段焊接固定;所述的固定段前端通过转铰12与向桥中央延伸的后开启段8后端相连,所述的后开启段8后端和前部分别支撑在工字钢横梁13上以及支撑桩9上,所述的后开启段8前端通过转铰12与向桥中央延伸的前开启段7后端相连,所述的桥两侧的前开启段7的前端在栈桥结构放平时采用销栓进行临时连接;(5) Install a unilateral bridge superstructure on each side of the I-beam beam. Two identical unilateral bridge superstructures form an openable overall bridge superstructure. Each unilateral bridge superstructure includes multiple Bailey sheets 14 connected to each other, the plurality of Bailey sheets 14 connected to each other include a fixed section fixed on the I-beam beam 13 on the corresponding side through the reinforcing chord 15 of the Bailey sheet, preferably I-beam The intersecting part of the beam 13 and the fixed section is fixed with a U-shaped piece, and the I-beam beam 13 and the fixed section are welded and fixed; the front end of the fixed section is connected to the rear end of the rear opening section 8 extending to the center of the bridge through a hinge 12, The rear end and front part of the rear opening section 8 are respectively supported on the I-beam beam 13 and the support pile 9, and the front end of the rear opening section 8 is connected to the rear of the front opening section 7 extending to the center of the bridge through a hinge 12. The front ends of the front opening sections 7 on both sides of the bridge are temporarily connected by pins when the trestle bridge structure is laid;

(6)在每一侧所述的贝雷片的上弦杆上均铺设固定多根间隔设置的横向工字钢,优选的横向工字钢17与贝雷片间用U型件联结以防滑动,并用满焊焊接进行固定;(6) On the upper chord of the Bailey sheet described on each side, a plurality of horizontal I-beams arranged at intervals are laid and fixed, and the preferred horizontal I-beam 17 is connected with the Bailey sheet to prevent sliding , and fixed by full welding;

(7)在横向工字钢上铺设多根间隔设置的纵向工字钢,横向工字钢17和纵向工字钢18相交部位采用满焊焊接固定,然后在所述的纵向工字钢上固定桥面系结构。桥面系结构通常包括安装在所述的纵向工字钢18上的作为桥面的压花钢板19,在所述的压花钢板19上固定有栏杆20,横向工字钢17和纵向工字钢18作为分配梁。压花钢板19的固定可以采用以下方式:在压花钢板19上钻孔,用螺栓与贝雷片14联结,并将压花钢板19与纵向工字钢18焊接固定。(7) Lay a plurality of vertical I-beams arranged at intervals on the horizontal I-beam, and the intersection of the horizontal I-beam 17 and the longitudinal I-beam 18 is fixed by full welding, and then fixed on the longitudinal I-beam Bridge deck structure. The bridge deck structure usually includes an embossed steel plate 19 installed on the longitudinal I-beam 18 as a bridge deck, on which the embossed steel plate 19 is fixed with railings 20, the horizontal I-beam 17 and the longitudinal I-beam Steel 18 as distribution beam. The fixing of embossed steel plate 19 can adopt following mode: drill hole on embossed steel plate 19, connect with Bai Lei sheet 14 with bolt, and embossed steel plate 19 and longitudinal I-beam 18 welding fixation.

(8)与一侧的四台卷扬机中的两台相连的前斜拉索的拉力端固定在同侧的前开启段的前端部并且与该侧的另外两台卷扬机相连的后斜拉索的拉力端固定在该侧的后开启段的前端,始终保持前斜拉索5和后斜拉索6和前、后开启段相连接。(8) The tension end of the front stay cable connected to two of the four winches on one side is fixed at the front end of the front opening section on the same side and the rear stay cable connected to the other two winches on this side The tension end is fixed on the front end of the rear opening section of this side, and the front stay cable 5 and the rear stay cable 6 are connected with the front and rear opening sections all the time.

当有通航净空要求时,同时启动卷扬机4,将斜拉式可弯折开启栈桥开启。开启至一定角度后,前开启段7将接触到上限位横梁,此时,停止前斜拉索5的牵拉。继续牵拉后斜拉索6,直到后开启段8接触到下限位横梁,此时,停止后斜拉索6的牵拉。由于前开启段7和后开启段8都最大限度靠近格构柱1,此时可为桥跨部分一定宽度内提供无限的通航净空和通航宽度,允许船只11通过。When there is a navigation clearance requirement, start the winch 4 simultaneously, and the cable-stayed bendable opening trestle is opened. After opening to a certain angle, the front opening section 7 will touch the upper limit beam, and at this moment, stop the pulling of the front stay cable 5. Continue to pull the rear stay cable 6 until the rear opening section 8 touches the lower limit beam, at this moment, stop the pulling of the rear stay cable 6. Since the front opening section 7 and the rear opening section 8 are as close as possible to the lattice column 1, unlimited navigation clearance and navigation width can be provided within a certain width of the bridge span at this time, allowing ships 11 to pass through.

当通航净空要求取消时,先释放前斜拉索5,使前开启段7降落至与后开启段8相平的时候再同时释放后斜拉索6,直至斜拉式可弯折开启栈桥平面重新落在支撑桩9上。When the navigation clearance requirement is canceled, release the front stay cable 5 first, and then release the rear stay cable 6 at the same time when the front opening section 7 is lowered to be level with the rear opening section 8, until the cable-stayed bendable open trestle plane Fall on support pile 9 again.

Claims (4)

1.一种斜拉式开启栈桥,其特征在于:它包括沿纵桥向桥面两侧间隔设置的四组用于竖向承重的格构柱,每一组格构柱的4根钢管之间焊接固定相连,在每一组格构柱的顶部固定有分配底座,在两侧格构柱的内侧分别打设有支撑桩,在同侧两组格构柱之间设置有至少一个加强排架临时墩,所述的加强排架临时墩包括插打在同侧两组格构柱之间的多根排架墩管桩,所述的排架墩管桩之间焊接相连,在同侧的多根排架墩管桩桩顶焊接固定一根工字钢横梁,两个相同的单侧桥梁上部结构组成一个可以开启的整体桥梁上部结构,每一个单侧桥梁上部结构均包括多个彼此相连的贝雷片,在所述的贝雷片的上弦杆上固定有多根间隔设置的横向工字钢,在所述的横向工字钢上固定有多根间隔设置的纵向工字钢,在所述的纵向工字钢上固定有桥面系结构,所述的多个彼此相连的贝雷片包括通过贝雷片的加强弦杆焊接固定在相应侧的工字钢横梁上的固定段,所述的固定段前端通过转铰与向桥中央延伸的后开启段后端相连,所述的后开启段前端通过转铰与向桥中央延伸的前开启段后端相连,所述的后开启段后端和前部分别支撑在工字钢横梁上以及支撑桩上,所述的桥两侧的前开启段的前端在栈桥结构放平时采用销栓进行连接,在每一个分配底座上均固定有四台卷扬机,在每一个格构柱的内侧分别设置有上、下限位横梁,与一侧的四台卷扬机中的两台相连的前斜拉索的拉力端固定在同侧的前开启段的前端部并且与该侧的另外两台卷扬机相连的后斜拉索的拉力端固定在该侧的后开启段的前端,所述的前开启段能够在卷扬机的带动下翻转支撑在上限位横梁上,所述的后开启段能够在卷扬机的带动下翻转支撑在下限位横梁上。1. A cable-stayed open trestle bridge is characterized in that: it includes four groups of lattice columns for vertical load-bearing that are arranged at intervals along the longitudinal bridge to both sides of the bridge deck, and the four steel pipes of each group of lattice columns The distribution base is fixed on the top of each group of lattice columns, supporting piles are installed on the inner sides of the lattice columns on both sides, and at least one reinforcement row is arranged between the two groups of lattice columns on the same side. Temporary piers, the reinforced temporary piers include a plurality of bent pier pipe piles inserted between two groups of lattice columns on the same side, the pipe piles of the bent piers are connected by welding, and the pipe piles on the same side The pile tops of multiple bent piers are welded and fixed with an I-beam beam. Two identical unilateral bridge superstructures form an openable overall bridge superstructure. Each unilateral bridge superstructure includes multiple Connected Bailey sheets, on the upper chord of the Bailey sheets, a plurality of horizontal I-beams arranged at intervals are fixed, and a plurality of longitudinal I-beams arranged at intervals are fixed on the described transverse I-beams, The bridge deck structure is fixed on the longitudinal I-beam, and the plurality of Bailey sheets connected to each other include fixed sections that are welded and fixed on the corresponding side I-beam beams through the reinforcing chords of the Bailey sheets The front end of the fixed section is connected to the rear end of the rear opening section extending to the center of the bridge through a hinge, the front end of the rear opening section is connected to the rear end of the front opening section extending to the center of the bridge through a hinge, and the rear opening section is connected to the rear end of the front opening section extending to the center of the bridge. The rear end and the front part of the opening section are respectively supported on the I-beam beam and the supporting piles. The front ends of the front opening sections on both sides of the bridge are connected by pins when the trestle structure is laid flat. Four winches are fixed, and upper and lower limit beams are respectively set on the inner side of each lattice column. The tension ends of the front stay cables connected to two of the four winches on one side are fixed on the front opening on the same side. The front end of the section and the tension end of the rear stay cable connected to the other two winches on this side are fixed at the front end of the rear opening section on this side, and the front opening section can be turned over and supported at the upper limit under the drive of the winch. On the beam, the rear opening section can be turned over and supported on the lower limit beam under the drive of the winch. 2.根据权利要求1所述的斜拉式开启栈桥,其特征在于:每一组格构柱的4根钢管之间的上部和下部分别通过斜撑和横撑结构焊接相连。2. The cable-stayed open trestle according to claim 1, characterized in that: the upper part and the lower part between the four steel pipes of each group of lattice columns are respectively connected by welding of diagonal braces and cross braces. 3.根据权利要求1或2所述的斜拉式开启栈桥,其特征在于:所述的排架墩管桩之间采用上下间隔设置的钢管进行水平向焊接相连,并采用槽钢在上下钢管之间将相邻的排架墩管桩剪刀向焊接相连。3. The cable-stayed open trestle according to claim 1 or 2, characterized in that: the pipe piles of the bent piers are connected by horizontal welding with steel pipes arranged at intervals up and down, and channel steel is used to connect the upper and lower steel pipes. The adjacent bent pier pipe piles are connected by scissors to welding. 4.根据权利要求3所述的斜拉式开启栈桥,其特征在于:所述的工字钢横梁与固定段相交部位采用U型件固定,并将工字钢横梁与固定段焊接固定。4. The cable-stayed open trestle according to claim 3, characterized in that: the intersecting part of the I-shaped steel beam and the fixed section is fixed by a U-shaped piece, and the I-shaped steel beam and the fixed section are fixed by welding.
CN201420549205.0U 2014-09-23 2014-09-23 A kind of cable-stayed type opens trestle Expired - Fee Related CN204151665U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420549205.0U CN204151665U (en) 2014-09-23 2014-09-23 A kind of cable-stayed type opens trestle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420549205.0U CN204151665U (en) 2014-09-23 2014-09-23 A kind of cable-stayed type opens trestle

Publications (1)

Publication Number Publication Date
CN204151665U true CN204151665U (en) 2015-02-11

Family

ID=52509793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420549205.0U Expired - Fee Related CN204151665U (en) 2014-09-23 2014-09-23 A kind of cable-stayed type opens trestle

Country Status (1)

Country Link
CN (1) CN204151665U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104213501A (en) * 2014-09-23 2014-12-17 中国建筑第六工程局有限公司 Cable-stayed bendable opening trestle structure and construction method thereof
CN105570539A (en) * 2015-12-21 2016-05-11 广州机施建设集团有限公司 Construction method of pipeline protection structure
CN115075117A (en) * 2022-06-06 2022-09-20 中国能源建设集团广东省电力设计研究院有限公司 Trestle structure for offshore platform

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104213501A (en) * 2014-09-23 2014-12-17 中国建筑第六工程局有限公司 Cable-stayed bendable opening trestle structure and construction method thereof
CN104213501B (en) * 2014-09-23 2016-03-30 中国建筑第六工程局有限公司 A kind of cable-stayed type bent unlatching trestle work structure construction method
CN105570539A (en) * 2015-12-21 2016-05-11 广州机施建设集团有限公司 Construction method of pipeline protection structure
CN105570539B (en) * 2015-12-21 2018-03-20 广州机施建设集团有限公司 The construction method of pipeline protection structure
CN115075117A (en) * 2022-06-06 2022-09-20 中国能源建设集团广东省电力设计研究院有限公司 Trestle structure for offshore platform

Similar Documents

Publication Publication Date Title
CN104213501B (en) A kind of cable-stayed type bent unlatching trestle work structure construction method
CN108532465B (en) Construction method of the main bridge of a bottom-supported steel box arch bridge
CN102953342B (en) Assembling and lifting method of half-span skeleton of tied arch bridge
CN104963301B (en) The dilatory translation downward putting device and method removed for pier top beam section and bridge pier
CN100476076C (en) Mobile integral construction platform, construction method and special spreader
CN101949146B (en) Offshore auxiliary construction platform device and using method thereof
CN204753354U (en) Cover worker's board landing stage
CN105088957A (en) Construction method for underwater reinforced concrete composite pile of cast-in-situ support of concrete ballast box beam of cable-stayed bridge
CN102367650A (en) Construction method of steel pipe arch bridge
CN107190647A (en) A kind of alignment control apparatus and method suitable for the special-shaped tower of steel construction
CN104372743A (en) Rapid construction method for trestle
CN106192776A (en) A kind of big Span Continuous Flexible arch bridge with steel truss beam free cantilever erection construction technology
CN102653938B (en) Offshore dismantling construction method for descending movable formwork
CN204151664U (en) A kind of cable-stayed type opens trestle
CN106522112A (en) System and method for erecting side-span girder section of cable-stayed bridge
CN101122115A (en) A construction method for tower crane displacement
CN206986743U (en) A kind of fixed trestle navigable vertical lift device
CN115058957A (en) Dual-purpose trestle support structure
CN115748512A (en) Main bridge main span steel structure segment construction method based on cantilever aerial work platform
CN103741964B (en) The method for dismounting of rake mast-up and armored concrete channel roof slab
CN205474862U (en) Wet seam template operation platform of portable case roof beam
CN204151665U (en) A kind of cable-stayed type opens trestle
CN208009277U (en) A kind of short sliding installation system of land-based area large-tonnage steel box beam
CN209906222U (en) A loop wheel machine that descends river for large-span steel pipe encircles segment lift shipment
CN206538687U (en) Erection System of Side Span Beam Section of Cable-Stayed Bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150211

Termination date: 20190923

CF01 Termination of patent right due to non-payment of annual fee