CN208995937U - Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station - Google Patents

Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station Download PDF

Info

Publication number
CN208995937U
CN208995937U CN201821372573.7U CN201821372573U CN208995937U CN 208995937 U CN208995937 U CN 208995937U CN 201821372573 U CN201821372573 U CN 201821372573U CN 208995937 U CN208995937 U CN 208995937U
Authority
CN
China
Prior art keywords
bracket
steel
basis
bridge
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821372573.7U
Other languages
Chinese (zh)
Inventor
侯兆隆
邱伟超
张雨宾
朱丹丹
李玉府
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201821372573.7U priority Critical patent/CN208995937U/en
Application granted granted Critical
Publication of CN208995937U publication Critical patent/CN208995937U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a kind of S type steel box girder of cable stayed bridge sliding mounting bracket suitable for above subway station, and including bracket basis and the steel-pipe pile bracket being arranged on bracket basis, bracket basis is to pour monolithic concrete structure on the ground along bracket sliding zones;Steel-pipe pile bracket includes multiple carrier units, each carrier unit includes the steel pipe post that 4 lower ends are fixed on bracket basis, multiple carrier units are on bracket basis along bridge to lining up two parallel column, direction across bridge is erected with crossbeam between two steel pipe post upper ends on each carrier unit, it is located on the outside of track girder on every crossbeam to the track girder being supported on crossbeam is set up along bridge on each column carrier unit and is equipped with support jack.The utility model can be used beam car and transport steel box-girder along track on bracket, avoid causing excessive concentration pressure loading above subway station.

Description

Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station
Technical field
The utility model belongs to CONSTRUCTION OF CABLE-STAYED BRIDGE technical field, and in particular to a kind of " S " above city underground station Type cable-stayed bridge slides mounting bracket.
Background technique
For municipal cable-stayed bridge when land is constructed, steel box-girder generally carries out lifting installation using large-scale crane.Due to cable-stayed bridge The every segment length of steel box-girder is longer so overall weight is larger, and load is larger on the ground for crane position when will lead to lifting. There are subway or underground parkings when in urban district, some Special zones carry out bridge construction, such as below earth's surface, to foundation bearing Power there are certain requirements, and foundation bearing capacity in its top range is distinctly claimed in job specfication and is not greater than 20KN/ ㎡, therefore herein When class area is constructed, lift-on/lift-off system construction is subject to certain restrictions.For example, certain municipal cable-stayed bridge of the applicant's construction, steel box girder section Section is generally in 17m or so, and about more than 20 tons of every linear meter(lin.m.) weight, steel box-girder integral linear is " S " type and upper trans-city subway station, if It is constructed using lift-on/lift-off system, the limitation far beyond 20KN/ ㎡ is transported safety battalion to subway by the ground concentrfated load in crane lifting area It impacts, it is therefore necessary to explore a kind of form of construction work for being able to satisfy above-mentioned environmental condition.
Summary of the invention
The purpose of this utility model is that being not applied for construction above subway station for steel box girder of cable stayed bridge lift-on/lift-off system Problem proposes that a kind of S type steel box girder of cable stayed bridge suitable for above subway station slides mounting bracket, sliding method can be used and carry out steel Pile equipment construction, and it is able to satisfy the limitation requirement above subway station to foundation bearing capacity.
The technical solution of the utility model is as follows:
A kind of S type steel box girder of cable stayed bridge sliding mounting bracket suitable for above subway station, including bracket basis and setting Steel-pipe pile bracket on bracket basis, it is characterised in that: the bracket basis is to pour on the ground along bracket sliding zones Monolithic concrete structure;The steel-pipe pile bracket includes multiple carrier units, and each carrier unit includes that 4 lower ends are fixed on Steel pipe post on bracket basis is connected by diagonal brace with lateral between 4 steel pipe posts;Multiple carrier units are on bracket basis Along bridge to two parallel column are lined up, direction across bridge is erected with crossbeam between two steel pipe post upper ends on each carrier unit, Sliding rail is welded on the track girder to the track girder being supported on the crossbeam is set up along bridge on each column carrier unit;Every It is located on the outside of the track girder on root crossbeam, is equipped with a support jack.
The utility model support configurations are simple, and raft template concrete foundation, bracket counter-force energy are arranged below bracket Meet above subway no more than 20KN/m2Requirement;Sliding rail is set on bracket, is constructed using sliding method, large size lifting is set It is standby not have to carry out steel box-girder lifting right above subway, it can ensure that subway station safety.
Detailed description of the invention
Fig. 1 is the overlooking structure diagram of the utility model;
Fig. 2 is partial enlarged view at A in Fig. 1, shows the overlooking structure diagram of a carrier unit;
Fig. 3 is the suitable bridge an of carrier unit to structural schematic diagram;
Fig. 4 is the direction across bridge structural schematic diagram an of carrier unit;
Fig. 5 is the partial elevation view of bracket basis;
Fig. 6 is the direction across bridge use state diagram of the utility model.
Specific embodiment
As shown in Figure 1, the utility model includes bracket basis 1 and the steel-pipe pile bracket 2 that is arranged on bracket basis, it is described Bracket basis 1 is raft plate form, is the monolithic concrete structure poured along bracket sliding zones on the ground;The steel-pipe pile branch Frame 2 includes multiple carrier units.As shown in Figure 2, Figure 3, Figure 4, each carrier unit includes that 4 lower ends are fixed on bracket basis 21,4 steel pipe posts 21 of steel pipe post between connected by diagonal brace 22 and lateral 23;Multiple carrier units are on bracket basis 1 Along bridge to two parallel column are lined up, direction across bridge is erected with crossbeam 24 between two steel pipe post upper ends on each carrier unit, Sliding rail is welded on the track girder to the track girder 3 being supported on the crossbeam is set up along bridge on each column carrier unit;? It is located on the outside of the track girder on every crossbeam, is equipped with a support jack 4.
As shown in figure 5, the utility model is when it is implemented, be the globality for guaranteeing bracket basis, in the mixed of bracket basis 1 It is equipped with horizontal steel mesh 11 in Xtah Crude Clay structure, and is equipped with lower reversed beam 12 that is a plurality of horizontally disposed and intersecting in length and breadth, it is described lower anti- Beam 12 is equipped with elongated bottom and indulges muscle 13 and upper longitudinal bar 14, indulges muscle 13 around bottom and upper longitudinal bar 14 is welded at spacing intervals Connect a ring-shaped stirrup 15;In the top surface of each infall for descending reversed beam in length and breadth, if a horizontal top plate 16,16 bottom of top plate 3 annular dowels 17 are welded, the annular dowel 17 is also welded with the upper longitudinal bar 14 of lower reversed beam simultaneously;The lower reversed beam 12 are integrated with bracket concreting.When bracket is installed, 21 lower end of every steel pipe post of steel-pipe pile bracket and bracket basis On a top plate 16 be welded and fixed.
It,, can be along bridge in each column for convenience of constructing and guaranteeing construction safety when steel box-girder slides as shown in Fig. 4, Fig. 6 Operation platform 5 is set on the outside of cradle top, guardrail 6 is set on the outside of operation platform.It can be thick with 3cm directly on the crossbeam of bracket 24 6 meters long plank is arranged elongated scaffold board and has been fixedly secured plank as operation platform 5, and with iron wire.
The utility model is when it is implemented, bracket basis is installed by pouring other than load limitation area above subway to steel box-girder Area;Multiple carrier units are in the unified production in production area, and each carrier unit is using 4 Φ 325*6 steel pipes as steel pipe post, cross Beam uses Two bors d's oeuveres 32a# I-steel, and track girder uses Two bors d's oeuveres 40a I-steel, and upper welding 70*30mm rail steel is adopted between steel pipe post Use 10# channel steel as lateral and diagonal brace.According to Bridge Beam baseline shape absolute altitude and bracket basis top surface built-in fitting elevation, by bracket steel Tube column top cross-bar elevation of top surface control 125cm under bridge Beam Elevation.Carrier unit is refuted using automobile is short to installing zone Domain install using 25 tons of truck cranes in place.Each carrier unit most weighs 3.5 tons, and 25 tons 24.5 meters of truck crane length of boom, 12 meters of work range, rated load weight is 4.2 tons, is able to satisfy bracket lifting requirements.
As shown in fig. 6, when the utility model is used, beam car 7 is installed on the track girder on bracket 2, on subway Steel box-girder 8 is lifted on beam car 7 by square load limitation area external application loop wheel machine, and beam car 7 transports steel box-girder 8 to installation along track girder Behind position, steel box-girder 8 is lifted off 7 top surface of beam car upwards by jack 4, and beam car 7 retracts hoisting area and transports next beam section.

Claims (3)

1. a kind of S type steel box girder of cable stayed bridge suitable for above subway station slides mounting bracket, including bracket basis and setting exist Steel-pipe pile bracket on bracket basis, it is characterised in that: the bracket basis is to pour on the ground along bracket sliding zones Monolithic concrete structure;The steel-pipe pile bracket includes multiple carrier units, and each carrier unit includes that 4 lower ends are fixed on branch Steel pipe post on the basis of frame is connected by diagonal brace with lateral between 4 steel pipe posts;Multiple carrier units are suitable on bracket basis Bridge is to two parallel column are lined up, and direction across bridge is erected with crossbeam between two steel pipe post upper ends on each carrier unit, every Sliding rail is welded on the track girder to the track girder being supported on the crossbeam is set up along bridge on column carrier unit;At every It is located on the outside of the track girder on crossbeam, is equipped with a support jack.
2. the S type steel box girder of cable stayed bridge according to claim 1 suitable for above subway station slides mounting bracket, feature It is: is equipped with horizontal steel mesh in the concrete of the bracket basis;It is additionally provided with a plurality of horizontally disposed in substrate and hands in length and breadth The lower reversed beam of fork, the lower reversed beam are equipped with elongated bottom and indulge muscle and upper longitudinal bar, around bottom indulge muscle and upper longitudinal bar every One fixed spacing welds a ring-shaped stirrup;In the top surface of each infall for descending reversed beam in length and breadth, if a horizontal top plate, the top plate 3 annular dowels are welded in bottom, and the annular dowel is also welded with the upper longitudinal bar of lower reversed beam simultaneously;The lower reversed beam with Bracket basis concreting is integrated;Every steel pipe post lower end of steel-pipe pile bracket and the top plate on bracket basis weld It is fixed.
3. the S type steel box girder of cable stayed bridge according to claim 1 suitable for above subway station slides mounting bracket, feature It is: along bridge to operation platform is provided on the outside of each column cradle top, is equipped with guardrail on the outside of the operation platform.
CN201821372573.7U 2018-08-23 2018-08-23 Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station Active CN208995937U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821372573.7U CN208995937U (en) 2018-08-23 2018-08-23 Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821372573.7U CN208995937U (en) 2018-08-23 2018-08-23 Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station

Publications (1)

Publication Number Publication Date
CN208995937U true CN208995937U (en) 2019-06-18

Family

ID=66798975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821372573.7U Active CN208995937U (en) 2018-08-23 2018-08-23 Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station

Country Status (1)

Country Link
CN (1) CN208995937U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535158A (en) * 2020-05-14 2020-08-14 中国五冶集团有限公司 Temporary buttress for installing box girder pushing equipment and construction method thereof
CN114671265A (en) * 2022-04-13 2022-06-28 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114703757A (en) * 2022-04-13 2022-07-05 中交路桥建设有限公司 Multifunctional support for steel cross beam of cable-stayed bridge and assembling method of steel cross beam
CN114775432A (en) * 2022-04-13 2022-07-22 中交路桥建设有限公司 Assembling support of large-tonnage reinforced concrete combined cross beam of cable-stayed bridge cable tower

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535158A (en) * 2020-05-14 2020-08-14 中国五冶集团有限公司 Temporary buttress for installing box girder pushing equipment and construction method thereof
CN114671265A (en) * 2022-04-13 2022-06-28 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114703757A (en) * 2022-04-13 2022-07-05 中交路桥建设有限公司 Multifunctional support for steel cross beam of cable-stayed bridge and assembling method of steel cross beam
CN114775432A (en) * 2022-04-13 2022-07-22 中交路桥建设有限公司 Assembling support of large-tonnage reinforced concrete combined cross beam of cable-stayed bridge cable tower
CN114671265B (en) * 2022-04-13 2023-10-20 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114775432B (en) * 2022-04-13 2024-04-19 中交路桥建设有限公司 Splicing bracket of large-tonnage steel-concrete combined beam of cable-stayed bridge cable tower
CN114703757B (en) * 2022-04-13 2024-04-19 中交路桥建设有限公司 Multifunctional bracket for steel cross beam of cable-stayed bridge and assembly method of steel cross beam

Similar Documents

Publication Publication Date Title
CN208995937U (en) Mounting bracket is slid suitable for the S type steel box girder of cable stayed bridge above subway station
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN101435276B (en) Hydraulic lifting and positioning device for steel beam at top of silo structure and construction method thereof
CN203334730U (en) Split mounting type steel-structure movable workshop in construction site
CN104878693A (en) Lateral girder erection and construction method for truss double-girder type bridge girder erection machine
CN101761031B (en) Continuous and perpendicular lifting apparatus for large segmental bridge floor beam
CN203452009U (en) Self-walking device for mounting steel beam
CN102979038A (en) Cast-in-place box beam mobile bracket with increased width
CN202658590U (en) Integral assembled drilling platform
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
CN103266567B (en) Steel truss cantilever supporting frame and its implementation
CN208995936U (en) S type steel box girder of cable stayed bridge on across ground rail traffic slides mounting bracket
CN103114754A (en) Alternative hoisting method for conjoined coal bunker top truss girder pre-placing
CN205257790U (en) Fixed high -low leg handle portal crane
CN203684060U (en) Temporary steel-frame bridge
CN202989781U (en) Width widened cast-in-place box beam moving support
CN215591798U (en) Curtain wall plate traction transfer device for tower crane dismantling part
CN203129581U (en) Slip form system
CN203429556U (en) System for quickly installing and positioning cable saddle
CN102619335A (en) Construction method of large-height small-sized cast-in-place concrete beam slab
CN206581682U (en) A kind of interim transition structure in jacking framed bridge steel column for contacting net basis
CN106245531B (en) Steel structural bridge installation method is hung under bilateral derrick type
CN105625177A (en) Steel truss suspending support construction method
CN205934962U (en) A system of sliding for underground pipe gallery cast -in -situ construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant