CN104850940A - 基于工程全过程管理的竣工决算编制方法及系统 - Google Patents
基于工程全过程管理的竣工决算编制方法及系统 Download PDFInfo
- Publication number
- CN104850940A CN104850940A CN201510212371.0A CN201510212371A CN104850940A CN 104850940 A CN104850940 A CN 104850940A CN 201510212371 A CN201510212371 A CN 201510212371A CN 104850940 A CN104850940 A CN 104850940A
- Authority
- CN
- China
- Prior art keywords
- project
- management module
- engineering
- completion
- projects
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 34
- 230000008569 process Effects 0.000 claims abstract description 26
- 238000010276 construction Methods 0.000 claims abstract description 16
- 239000000463 material Substances 0.000 claims abstract description 16
- 238000007726 management method Methods 0.000 claims description 112
- 238000002360 preparation method Methods 0.000 claims description 13
- 238000012544 monitoring process Methods 0.000 claims description 12
- 230000008676 import Effects 0.000 claims description 10
- 238000009434 installation Methods 0.000 claims description 6
- 230000015572 biosynthetic process Effects 0.000 claims description 5
- 230000003993 interaction Effects 0.000 claims description 4
- 239000004566 building material Substances 0.000 claims description 3
- 230000008878 coupling Effects 0.000 claims description 3
- 238000010168 coupling process Methods 0.000 claims description 3
- 238000005859 coupling reaction Methods 0.000 claims description 3
- 238000000605 extraction Methods 0.000 claims description 3
- 238000010223 real-time analysis Methods 0.000 claims description 3
- 238000004088 simulation Methods 0.000 claims description 3
- 238000013439 planning Methods 0.000 description 3
- 238000012795 verification Methods 0.000 description 3
- 241001269238 Data Species 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 206010033307 Overweight Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012790 confirmation Methods 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 235000020825 overweight Nutrition 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000031877 prophase Effects 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明涉及一种基于工程全过程管理的竣工决算编制方法及系统,其中方法包括:1)将工程项目计划及预算、概算信息导入项目前期管理模块中;将此数据和主管单位信息集成到项目权限管理模块中;2)采集设备费用、材料费用、施工费用及其他费用信息,集成到项目中期管理模块中;3)在项目后期管理模块中建立资产BOM,生成资产卡片,并进行费用分摊;4)由报表管理模块生成竣工决算报表。本发明通过对工程各环节产生的数据进行收集、整理、传输、对比,实现对工程全过程的实时监控,同一设备在物资、设备、资产模块中实现编码联动,并具有自动成本预警,自动形成资产台账,自动分摊资产价值,自动生成竣工决算报表等功能。
Description
技术领域
本发明涉及电力系统信息管理技术领域,尤其涉及一种基于工程全过程管理的竣工决算编制方法及系统。
背景技术
电网工程项目要经历前期可研、实施、结算、转资和决算报告生成等阶段,每个阶段都会产生大量的信息和数据(如图1所示),这些资料种类繁多,来源复杂,且系统数据均通过前端业务部门操作生成,财务部门成为整个流程的最末端和被动接收者。部分前端业务处理随意性大,录入数据信息质量不高,前端业务信息不能满足财务管理需求;有的项目长期挂账、久拖不决,存在不及时转资情况。
长期以来,基建财务工作侧重于资金支付、成本核算和决算报告编制,对规划设计、招标采购、评估评价等环节管理的参与度不够,“重中间、轻两头”的现象仍然存在。职责细分、流程固化、过程控制等方面的管理工具及手段有待丰富健全。财力集约化又要求财务与业务高度融合,要对工程预算全过程管控,庞大的资金量、数据量与工程财务精益化、动态化管理存在落差。
在电力系统领域,资产BOM是指电网企业在设备资产管理过程中各个主要要素(项目、物料、资产、主设备及重要组成设备)的关系集合,以及这种关系在实际业务管理过程中的演变过程。
目前,随着电网的规模不断扩大,电力公司不断加大对电力基础建设及电力改造项目的投入,每年工程项目、固定资产数量庞大,工程项目的竣工决算更多的是针对工程实施过程的一种事后决算管理,而对于工程实施过程中可能发生的问题,如工期延误、工程成本不合理等问题的解决,无法给以更大的帮助。同时,无法在ERP系统中直观地查询项目的转资情况,资产与设备、物料没有紧密的联系,无法直观地了解三者的联动关系。
为了有效解决工程财务管理过程中存在的问题,本发明通过信息化手段搭建高效、智能的信息平台,将工程实施的事后决算扩展到事中监控,在工程实施过程中即届入管理,变被动为主动,提高内控管理效率。改变以往竣工决算过程中需要大量重复、机械性手工操作的方式,实现资料信息的高度共享,有利于资产精益化管理的提升。
发明内容
本发明提供了一种基于工程全过程管理的竣工决算编制方法及系统,通过对工程各环节产生的数据进行收集、整理、传输、对比,实现对工程全过程的实时监控,同一设备在物资、设备、资产模块中实现编码联动,并具有自动成本预警,自动形成资产台账,自动分摊资产价值,自动生成竣工决算报表等功能。
为了达到上述目的,本发明采用以下技术方案实现:
基于工程全过程管理的竣工决算编制方法,包括如下步骤:
1)将工程项目计划及预算、概算信息导入数据库中,建立工程项目目录并导入到项目前期管理模块中;将项目前期管理模块中的数据和主管单位信息集成到项目权限管理模块中,并建立监控预警规则;
2)利用统一数据接口进行数据采集,包括工程实施过程中发生的设备费用、材料费用、施工费用及其他费用信息,集成到项目中期管理模块中;同时项目权限管理模块中的数据也发送到项目中期管理模块中进行数据对比;
3)项目中期管理模块的数据发送到项目后期管理模块,在项目后期管理模块中根据“物料—设备—资产”联动关系建立资产BOM,生成资产卡片,并进行费用分摊,确认资产卡片初始价值,并将数据发送到报表管理模块中;
4)由报表管理模块生成竣工决算报表。
所述步骤1)中,建立工程项目目录包括以下步骤:
a.由项目前期管理部门依据数据模板输入工程基本信息;
b.由项目管理部门依据数据模板输入预算、概算信息。
所述步骤2)中,数据采集包括以下步骤:
a.通过物资部门采集工程项目的设备及材料费用信息;
b.从ERP财务系统中采集工程项目的施工费用及其他费用信息;
c.依据事先设定的工程项目进度限定值,对工程进度进行监控,超出进度要求及时告警,并向施工管理人员发送工程进度告警通知书;
d.依据事先设定的工程项目分项成本预算值,对工程成本进行实时分析监控,超出成本预算及时告警,并向项目管理人员发送工程费用告警通知书。
所述步骤3)中,生成资产卡片并分摊费用包括以下步骤:
a.根据数据模板,输入工程项目的资产移交数据;
b.从项目中期管理模块中提取设备信息,建立匹配规则,与项目前期管理模块中的资产信息进行匹配,匹配通过即确定一一对应关系,并形成“物料—设备—资产”联动;匹配没通过,则根据设备及资产信息,手动建立对应关系;
c.根据数据模板,输入工程项目的结算信息;
d.根据资产BOM中的物料购置价格确定资产卡片的初始价值;
e.根据工程项目的概算、结算信息,将工程实施过程中发生的费用分步骤、按比例自动分摊到资产卡片,其中:
“建筑工程”挂接建筑材料及建筑施工费用的分摊;
“安装设备”挂接不直接形成设备的物料价值分摊;
“安装工程”挂接安装施工费用的分摊;
“其他费用”挂接其他费用的分摊;
根据上述自动分摊结果,调整并确认资产卡片最终价值,初始价值加上分摊价值等于资产卡片的最终价值。
所述步骤4)中,生成竣工决算报表包括如下步骤:
a.根据竣工决算报表模板组,在系统中建立报表自动生成规则;
b.根据工程项目的专业性质,确定对应的竣工决算报表模板;
c.根据确认的分摊结果及系统上维护好的竣工决算报表生成规则,进行模拟竣工决算,自动生成初始竣工决算报表;
d.合同结算审计完成后,若存在未完工程则将未完工作量预计入项目,并再次分摊,生成调整后的竣工决算报表。
用于实现基于工程全过程管理的竣工决算编制方法的系统,包括用于形成基础信息的项目前期管理模块;用于建立监控预警规则的项目权限管理模块;用于项目实施过程管理的项目中期管理模块;用于进行费用分摊的项目后期管理模块;用于竣工决算报表输出的报表管理模块;其中项目前期管理模块的输出端连接项目权限管理模块的输入端,项目权限管理模块的输出端连接项目中期管理模块的输入端,项目中期管理模块的输出端连接项目后期管理模块的输入端,项目后期管理模块的输出端连接报表管理模块的输入端。
与现有技术相比,本发明的有益效果是:
1)通过对工程各环节产生的数据进行收集、整理、传输、对比,实现对工程全过程的实时监控,同一设备在物资、设备、资产模块中实现编码联动,并具有自动成本预警,自动形成资产台账,自动分摊资产价值,自动生成竣工决算报表等功能;
2)在电力系统的工程管理中,引入了全过程管理的理念,在工程实施管理过程中,增加了工程成本监控预警机制,使得电力工程管理可操作性更强,工程成本管理更科学。
附图说明
图1是电网工程项目管理数据流向图。
图2是基于工程全过程管理的竣工决算编制流程图。
图3是基于工程全过程管理的竣工决算编制系统职能部门关系图。
具体实施方式
下面结合附图对本发明的具体实施方式作进一步说明:
见图2,是基于工程全过程管理的竣工决算编制流程图。本发明所述基于工程全过程管理的竣工决算编制方法,包括如下步骤:
1)将工程项目计划及预算、概算信息导入数据库中,建立工程项目目录并导入到项目前期管理模块中;将项目前期管理模块中的数据和主管单位信息集成到项目权限管理模块中,并建立监控预警规则;
2)利用统一数据接口进行数据采集,包括工程实施过程中发生的设备费用、材料费用、施工费用及其他费用信息,集成到项目中期管理模块中;同时项目权限管理模块中的数据也发送到项目中期管理模块中进行数据对比;
3)项目中期管理模块的数据发送到项目后期管理模块,在项目后期管理模块中根据“物料—设备—资产”联动关系建立资产BOM,生成资产卡片,并进行费用分摊,确认资产卡片初始价值,并将数据发送到报表管理模块中;
4)由报表管理模块生成竣工决算报表。
所述步骤1)中,建立工程项目目录包括以下步骤:
a.由项目前期管理部门依据数据模板输入工程基本信息;
b.由项目管理部门依据数据模板输入预算、概算信息。
所述步骤2)中,数据采集包括以下步骤:
a.通过物资部门采集工程项目的设备及材料费用信息;
b.从ERP财务系统中采集工程项目的施工费用及其他费用信息;
c.依据事先设定的工程项目进度限定值,对工程进度进行监控,超出进度要求及时告警,并向施工管理人员发送工程进度告警通知书;
d.依据事先设定的工程项目分项成本预算值,对工程成本进行实时分析监控,超出成本预算及时告警,并向项目管理人员发送工程费用告警通知书。
所述步骤3)中,生成资产卡片并分摊费用包括以下步骤:
a.根据数据模板,输入工程项目的资产移交数据;
b.从项目中期管理模块中提取设备信息,建立匹配规则,与项目前期管理模块中的资产信息进行匹配,匹配通过即确定一一对应关系,并形成“物料—设备—资产”联动;匹配没通过,则根据设备及资产信息,手动建立对应关系;
c.根据数据模板,输入工程项目的结算信息;
d.根据资产BOM中的物料购置价格确定资产卡片的初始价值;
e.根据工程项目的概算、结算信息,将工程实施过程中发生的费用分步骤、按比例自动分摊到资产卡片,其中:
“建筑工程”挂接建筑材料及建筑施工费用的分摊;
“安装设备”挂接不直接形成设备的物料价值分摊;
“安装工程”挂接安装施工费用的分摊;
“其他费用”挂接其他费用的分摊;
根据上述自动分摊结果,调整并确认资产卡片最终价值,初始价值加上分摊价值等于资产卡片的最终价值。
所述步骤4)中,生成竣工决算报表包括如下步骤:
a.根据竣工决算报表模板组,在系统中建立报表自动生成规则;
b.根据工程项目的专业性质,确定对应的竣工决算报表模板;
c.根据确认的分摊结果及系统上维护好的竣工决算报表生成规则,进行模拟竣工决算,自动生成初始竣工决算报表;
d.合同结算审计完成后,若存在未完工程则将未完工作量预计入项目,并再次分摊,生成调整后的竣工决算报表。
本发明所述用于实现基于工程全过程管理的竣工决算编制方法的系统,包括用于形成基础信息的项目前期管理模块;用于建立监控预警规则的项目权限管理模块;用于项目实施过程管理的项目中期管理模块;用于进行费用分摊的项目后期管理模块;用于竣工决算报表输出的报表管理模块;其中项目前期管理模块的输出端连接项目权限管理模块的输入端,项目权限管理模块的输出端连接项目中期管理模块的输入端,项目中期管理模块的输出端连接项目后期管理模块的输入端,项目后期管理模块的输出端连接报表管理模块的输入端。
见图3,是基于工程全过程管理的竣工决算编制系统职能部门关系图。按照本发明所述方法,工程管理工作是以财务资产部为核心,其他各管理部门辅助,实现对工程的全过程管控。各部门具体职能如下:
(1)工程前期阶段:工程前期管理部门将计划文件、工程编码导入系统,工程管理部门将概算、中标通知书、合同等文件导入系统。财务资产部核对导入信息,并在系统中按照全面预算管理的要求设置预算控制。
(2)工程实施阶段:工程管理部门和物资供应公司将ERP系统中发生的设备、材料、施工费用及其他费用数据批量导入系统,同时将开工报告、工程进度款确认单等资料上传到系统中备查,财务资产部核对导入信息,分析各项工程相关数据。
(3)工程结算阶段:工程竣工后,工程管理部门将竣工报告、预转资申请、固定资产清册上传到系统中,财务资产部核对后进行预转资。在工程结算批复后,工程管理部门将结算复核意见等相关资料上传到系统中,经审核通过后,工程管理部门在ERP系统中完成工程结算过账工作,并将结算数据导入系统。
(4)工程竣工决算阶段:财务资产部核对系统数据生成决算报告,同时在ERP系统中完成工程转资。
(5)工程资产处置阶段:工程管理部门将固定资产报废审批单等资料导入系统中,经财务资产部审核后,实物管理部门、财务资产部在ERP系统中完成固定资产报废流程操作。同时物资供应公司将废旧物资处置收入清单等资料按项目导入到系统中,财务资产部审核后进行账务处理。
Claims (6)
1.基于工程全过程管理的竣工决算编制方法,其特征在于,包括如下步骤:
1)将工程项目计划及预算、概算信息导入数据库中,建立工程项目目录并导入到项目前期管理模块中;将项目前期管理模块中的数据和主管单位信息集成到项目权限管理模块中,并建立监控预警规则;
2)利用统一数据接口进行数据采集,包括工程实施过程中发生的设备费用、材料费用、施工费用及其他费用信息,集成到项目中期管理模块中;同时项目权限管理模块中的数据也发送到项目中期管理模块中进行数据对比;
3)项目中期管理模块的数据发送到项目后期管理模块,在项目后期管理模块中根据“物料—设备—资产”联动关系建立资产BOM,生成资产卡片,并进行费用分摊,确认资产卡片初始价值,并将数据发送到报表管理模块中;
4)由报表管理模块生成竣工决算报表。
2.根据权利要求1所述的基于工程全过程管理的竣工决算编制方法,其特征在于,所述步骤1)中,建立工程项目目录包括以下步骤:
a.由项目前期管理部门依据数据模板输入工程基本信息;
b.由项目管理部门依据数据模板输入预算、概算信息。
3.根据权利要求1所述的基于工程全过程管理的竣工决算编制方法,其特征在于,所述步骤2)中,数据采集包括以下步骤:
a.通过物资部门采集工程项目的设备及材料费用信息;
b.从ERP财务系统中采集工程项目的施工费用及其他费用信息;
c.依据事先设定的工程项目进度限定值,对工程进度进行监控,超出进度要求及时告警,并向施工管理人员发送工程进度告警通知书;
d.依据事先设定的工程项目分项成本预算值,对工程成本进行实时分析监控,超出成本预算及时告警,并向项目管理人员发送工程费用告警通知书。
4.根据权利要求1所述的基于工程全过程管理的竣工决算编制方法,其特征在于,所述步骤3)中,生成资产卡片并分摊费用包括以下步骤:
a.根据数据模板,输入工程项目的资产移交数据;
b.从项目中期管理模块中提取设备信息,建立匹配规则,与项目前期管理模块中的资产信息进行匹配,匹配通过即确定一一对应关系,并形成“物料—设备—资产”联动;匹配没通过,则根据设备及资产信息,手动建立对应关系;
c.根据数据模板,输入工程项目的结算信息;
d.根据资产BOM中的物料购置价格确定资产卡片的初始价值;
e.根据工程项目的概算、结算信息,将工程实施过程中发生的费用分步骤、按比例自动分摊到资产卡片,其中:
“建筑工程”挂接建筑材料及建筑施工费用的分摊;
“安装设备”挂接不直接形成设备的物料价值分摊;
“安装工程”挂接安装施工费用的分摊;
“其他费用”挂接其他费用的分摊;
根据上述自动分摊结果,调整并确认资产卡片最终价值,初始价值加上分摊价值等于资产卡片的最终价值。
5.根据权利要求1所述的基于工程全过程管理的竣工决算编制方法,其特征在于,所述步骤4)中,生成竣工决算报表包括如下步骤:
a.根据竣工决算报表模板组,在系统中建立报表自动生成规则;
b.根据工程项目的专业性质,确定对应的竣工决算报表模板;
c.根据确认的分摊结果及系统上维护好的竣工决算报表生成规则,进行模拟竣工决算,自动生成初始竣工决算报表;
d.合同结算审计完成后,若存在未完工程则将未完工作量预计入项目,并再次分摊,生成调整后的竣工决算报表。
6.用于实现权利要求1所述的基于工程全过程管理的竣工决算编制方法的系统,其特征在于,包括用于形成基础信息的项目前期管理模块;用于建立监控预警规则的项目权限管理模块;用于项目实施过程管理的项目中期管理模块;用于进行费用分摊的项目后期管理模块;用于竣工决算报表输出的报表管理模块;其中项目前期管理模块的输出端连接项目权限管理模块的输入端,项目权限管理模块的输出端连接项目中期管理模块的输入端,项目中期管理模块的输出端连接项目后期管理模块的输入端,项目后期管理模块的输出端连接报表管理模块的输入端。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510212371.0A CN104850940B (zh) | 2015-04-29 | 2015-04-29 | 基于工程全过程管理的竣工决算编制方法及系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510212371.0A CN104850940B (zh) | 2015-04-29 | 2015-04-29 | 基于工程全过程管理的竣工决算编制方法及系统 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104850940A true CN104850940A (zh) | 2015-08-19 |
CN104850940B CN104850940B (zh) | 2018-08-31 |
Family
ID=53850572
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510212371.0A Active CN104850940B (zh) | 2015-04-29 | 2015-04-29 | 基于工程全过程管理的竣工决算编制方法及系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104850940B (zh) |
Cited By (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105335820A (zh) * | 2015-10-16 | 2016-02-17 | 新乡学院 | 一种经济管理系统 |
CN105389661A (zh) * | 2015-11-16 | 2016-03-09 | 苏州天地微易智能科技有限公司 | 计量支付管理系统及其方法 |
CN106599203A (zh) * | 2016-12-15 | 2017-04-26 | 中国南方电网有限责任公司超高压输电公司 | 针对资产全生命周期的数据质量提升方法 |
CN107578150A (zh) * | 2017-08-18 | 2018-01-12 | 国网浙江省电力公司湖州供电公司 | 电力系统工程自动竣工决算方法 |
CN108154314A (zh) * | 2018-01-19 | 2018-06-12 | 国家电网公司 | 工程项目竣工决算方法及终端设备 |
CN108171484A (zh) * | 2018-01-29 | 2018-06-15 | 国网上海市电力公司 | 采集设备资产生成系统及方法 |
CN108764846A (zh) * | 2018-05-30 | 2018-11-06 | 福泽润森(武汉)科技股份有限公司 | 一种团队级建筑工程管理系统 |
CN108805529A (zh) * | 2018-05-30 | 2018-11-13 | 福泽润森(武汉)科技股份有限公司 | 一种建筑工程管理平台 |
CN109064306A (zh) * | 2018-08-14 | 2018-12-21 | 石榴籽科技有限公司 | 一种基于互联网的财务分析系统及方法 |
CN109446597A (zh) * | 2018-10-10 | 2019-03-08 | 广联达科技股份有限公司 | 一种施工设备用量的个性化定制统计方法和设备 |
CN109559054A (zh) * | 2018-12-04 | 2019-04-02 | 国网山东省电力公司无棣县供电公司 | 一种电力工程施工信息处理系统 |
CN109767186A (zh) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | 一种项目全过程管理方法及系统 |
CN109886613A (zh) * | 2017-12-06 | 2019-06-14 | 广东电网有限责任公司物流服务中心 | 一种物资需求预测数据实时共享平台 |
CN110288326A (zh) * | 2019-07-04 | 2019-09-27 | 广州发展集团股份有限公司 | 基于erp和tim系统的项目成本过账方法与系统 |
CN110298562A (zh) * | 2019-06-14 | 2019-10-01 | 国网湖北省电力有限公司孝感供电公司 | 一种配电网建设审计网格化管理方法 |
CN110659868A (zh) * | 2019-06-19 | 2020-01-07 | 陕西省地方电力(集团)有限公司 | 一种用于电网资产设备的辅助决算转资方法及系统 |
CN111798209A (zh) * | 2020-06-30 | 2020-10-20 | 远光软件股份有限公司 | 基于区块链的工程项目管理方法、电子设备和存储介质 |
CN111882165A (zh) * | 2020-07-01 | 2020-11-03 | 国网河北省电力有限公司经济技术研究院 | 一种综合项目造价分析数据拆分装置及方法 |
CN112085361A (zh) * | 2020-08-28 | 2020-12-15 | 上海谊逅信息技术有限公司 | 一种建筑工程全过程管理方法 |
CN112258050A (zh) * | 2020-10-26 | 2021-01-22 | 厦门海迈科技股份有限公司 | 一种基于概算的工程资金管控的方法及设备 |
CN112330097A (zh) * | 2020-10-15 | 2021-02-05 | 远光软件股份有限公司 | 一种项目竣工决算的方法、装置及电子设备 |
CN112446680A (zh) * | 2020-11-03 | 2021-03-05 | 国网天津静海供电有限公司 | 一种电力工程结决算进度管控系统及方法 |
CN112686579A (zh) * | 2021-01-31 | 2021-04-20 | 重庆渝高科技产业(集团)股份有限公司 | 一种工程项目的结决算管控超概算预警方法及系统 |
CN112766826A (zh) * | 2021-03-11 | 2021-05-07 | 佛山市硅集财务软件有限公司 | 研发费用风险导向审计方法、装置、电子设备及存储介质 |
CN113256232A (zh) * | 2020-02-11 | 2021-08-13 | 厦门九嘉信息科技有限公司 | 一种电力工程监控方法及系统 |
CN113674073A (zh) * | 2021-08-20 | 2021-11-19 | 广东电网有限责任公司 | 一种财务跨域融合统计报表系统 |
CN114722790A (zh) * | 2022-04-24 | 2022-07-08 | 北京京航计算通讯研究所 | 一种非嵌入式的全面预算管理方法和系统 |
CN114841788A (zh) * | 2022-05-23 | 2022-08-02 | 北京新机场建设指挥部 | 一种工程项目建设管理竣工决算全过程管理系统 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102142111A (zh) * | 2010-02-03 | 2011-08-03 | 上海市电力公司 | 适用于电力系统的资产全寿命信息集成控制方法及装置 |
CN102819774A (zh) * | 2011-06-09 | 2012-12-12 | 上海市第七建筑有限公司 | 工程项目成本管理系统及其构架 |
KR101219079B1 (ko) * | 2012-07-03 | 2013-01-17 | 웹케시 주식회사 | 노무비 지급을 보증하는 실시간 노무비 지급 시스템 및 그 시스템의 정보 처리 방법 |
CN103606038A (zh) * | 2013-11-06 | 2014-02-26 | 远光软件股份有限公司 | 基于企业整体业务流程体系的在线稽核方法及系统 |
CN104021455A (zh) * | 2014-06-23 | 2014-09-03 | 国家电网公司 | 一种设备资产精细化管理系统及方法 |
US20140278819A1 (en) * | 2013-03-14 | 2014-09-18 | Professional Project Services, Inc. | Alternate Scenario Analysis for Project Management |
-
2015
- 2015-04-29 CN CN201510212371.0A patent/CN104850940B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102142111A (zh) * | 2010-02-03 | 2011-08-03 | 上海市电力公司 | 适用于电力系统的资产全寿命信息集成控制方法及装置 |
CN102819774A (zh) * | 2011-06-09 | 2012-12-12 | 上海市第七建筑有限公司 | 工程项目成本管理系统及其构架 |
KR101219079B1 (ko) * | 2012-07-03 | 2013-01-17 | 웹케시 주식회사 | 노무비 지급을 보증하는 실시간 노무비 지급 시스템 및 그 시스템의 정보 처리 방법 |
US20140278819A1 (en) * | 2013-03-14 | 2014-09-18 | Professional Project Services, Inc. | Alternate Scenario Analysis for Project Management |
CN103606038A (zh) * | 2013-11-06 | 2014-02-26 | 远光软件股份有限公司 | 基于企业整体业务流程体系的在线稽核方法及系统 |
CN104021455A (zh) * | 2014-06-23 | 2014-09-03 | 国家电网公司 | 一种设备资产精细化管理系统及方法 |
Cited By (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105335820A (zh) * | 2015-10-16 | 2016-02-17 | 新乡学院 | 一种经济管理系统 |
CN105389661A (zh) * | 2015-11-16 | 2016-03-09 | 苏州天地微易智能科技有限公司 | 计量支付管理系统及其方法 |
CN106599203A (zh) * | 2016-12-15 | 2017-04-26 | 中国南方电网有限责任公司超高压输电公司 | 针对资产全生命周期的数据质量提升方法 |
CN106599203B (zh) * | 2016-12-15 | 2021-01-01 | 中国南方电网有限责任公司超高压输电公司 | 针对资产全生命周期的数据质量提升方法 |
CN107578150A (zh) * | 2017-08-18 | 2018-01-12 | 国网浙江省电力公司湖州供电公司 | 电力系统工程自动竣工决算方法 |
CN107578150B (zh) * | 2017-08-18 | 2023-05-26 | 国网浙江省电力公司湖州供电公司 | 电力系统工程自动竣工决算方法 |
CN109886613A (zh) * | 2017-12-06 | 2019-06-14 | 广东电网有限责任公司物流服务中心 | 一种物资需求预测数据实时共享平台 |
CN108154314A (zh) * | 2018-01-19 | 2018-06-12 | 国家电网公司 | 工程项目竣工决算方法及终端设备 |
CN108171484A (zh) * | 2018-01-29 | 2018-06-15 | 国网上海市电力公司 | 采集设备资产生成系统及方法 |
CN108805529A (zh) * | 2018-05-30 | 2018-11-13 | 福泽润森(武汉)科技股份有限公司 | 一种建筑工程管理平台 |
CN108764846A (zh) * | 2018-05-30 | 2018-11-06 | 福泽润森(武汉)科技股份有限公司 | 一种团队级建筑工程管理系统 |
CN109064306A (zh) * | 2018-08-14 | 2018-12-21 | 石榴籽科技有限公司 | 一种基于互联网的财务分析系统及方法 |
CN109446597A (zh) * | 2018-10-10 | 2019-03-08 | 广联达科技股份有限公司 | 一种施工设备用量的个性化定制统计方法和设备 |
CN109559054A (zh) * | 2018-12-04 | 2019-04-02 | 国网山东省电力公司无棣县供电公司 | 一种电力工程施工信息处理系统 |
CN109767186A (zh) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | 一种项目全过程管理方法及系统 |
CN110298562A (zh) * | 2019-06-14 | 2019-10-01 | 国网湖北省电力有限公司孝感供电公司 | 一种配电网建设审计网格化管理方法 |
CN110659868A (zh) * | 2019-06-19 | 2020-01-07 | 陕西省地方电力(集团)有限公司 | 一种用于电网资产设备的辅助决算转资方法及系统 |
CN110288326A (zh) * | 2019-07-04 | 2019-09-27 | 广州发展集团股份有限公司 | 基于erp和tim系统的项目成本过账方法与系统 |
CN113256232A (zh) * | 2020-02-11 | 2021-08-13 | 厦门九嘉信息科技有限公司 | 一种电力工程监控方法及系统 |
CN111798209A (zh) * | 2020-06-30 | 2020-10-20 | 远光软件股份有限公司 | 基于区块链的工程项目管理方法、电子设备和存储介质 |
CN111882165A (zh) * | 2020-07-01 | 2020-11-03 | 国网河北省电力有限公司经济技术研究院 | 一种综合项目造价分析数据拆分装置及方法 |
CN112085361A (zh) * | 2020-08-28 | 2020-12-15 | 上海谊逅信息技术有限公司 | 一种建筑工程全过程管理方法 |
CN112330097A (zh) * | 2020-10-15 | 2021-02-05 | 远光软件股份有限公司 | 一种项目竣工决算的方法、装置及电子设备 |
CN112258050A (zh) * | 2020-10-26 | 2021-01-22 | 厦门海迈科技股份有限公司 | 一种基于概算的工程资金管控的方法及设备 |
CN112446680A (zh) * | 2020-11-03 | 2021-03-05 | 国网天津静海供电有限公司 | 一种电力工程结决算进度管控系统及方法 |
CN112686579A (zh) * | 2021-01-31 | 2021-04-20 | 重庆渝高科技产业(集团)股份有限公司 | 一种工程项目的结决算管控超概算预警方法及系统 |
CN112766826A (zh) * | 2021-03-11 | 2021-05-07 | 佛山市硅集财务软件有限公司 | 研发费用风险导向审计方法、装置、电子设备及存储介质 |
CN112766826B (zh) * | 2021-03-11 | 2024-02-27 | 汤达键 | 研发费用风险导向审计方法、装置、电子设备及存储介质 |
CN113674073A (zh) * | 2021-08-20 | 2021-11-19 | 广东电网有限责任公司 | 一种财务跨域融合统计报表系统 |
CN113674073B (zh) * | 2021-08-20 | 2023-09-19 | 广东电网有限责任公司 | 一种财务跨域融合统计报表系统 |
CN114722790B (zh) * | 2022-04-24 | 2023-09-05 | 北京京航计算通讯研究所 | 一种非嵌入式的全面预算管理方法和系统 |
CN114722790A (zh) * | 2022-04-24 | 2022-07-08 | 北京京航计算通讯研究所 | 一种非嵌入式的全面预算管理方法和系统 |
CN114841788B (zh) * | 2022-05-23 | 2022-11-22 | 北京新机场建设指挥部 | 一种工程项目建设管理竣工决算全过程管理系统 |
CN114841788A (zh) * | 2022-05-23 | 2022-08-02 | 北京新机场建设指挥部 | 一种工程项目建设管理竣工决算全过程管理系统 |
Also Published As
Publication number | Publication date |
---|---|
CN104850940B (zh) | 2018-08-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104850940A (zh) | 基于工程全过程管理的竣工决算编制方法及系统 | |
CN107358340B (zh) | 一种基于工程清单的工程项目管理系统 | |
CN103020873B (zh) | 一种用于电力系统的自动转资方法和系统 | |
CN108009758B (zh) | 一种基于bim的现场施工材料智能管理方法 | |
Li et al. | Risk-constrained bidding strategy with stochastic unit commitment | |
CN110766528A (zh) | 一种客户信用自评估工厂实时智能分析管理系统 | |
CN103679373A (zh) | 生产基建标准成本体系的全链条预算数据处理系统及方法 | |
CN104240024A (zh) | 一种基于b/s结构的财务预算系统及方法 | |
CN107945000A (zh) | 一种电网技改大修工程结算管理系统及其控制方法 | |
CN109493003A (zh) | 项目数据管理方法及终端设备 | |
CN113112233A (zh) | 一种基于bim的风电项目全寿命周期智慧管理方法及平台 | |
CN113656505B (zh) | 一种分布式项目管理系统的数字化及其同步数据的方法 | |
CN109978676A (zh) | 一种自动结算方法、系统以及存储介质 | |
CN111178680A (zh) | 风电场工程质量全过程管理系统、方法及设备 | |
CN103761618A (zh) | 一种电网科技项目控制方法及系统 | |
CN104021455A (zh) | 一种设备资产精细化管理系统及方法 | |
York et al. | Three Decades and Counting: A Historical Review and Current Assessment of Electric Utility Energy Efficiency Activity in the States | |
CN112434995A (zh) | 一种基于财务数据的仓库管理系统 | |
CN104112174A (zh) | 核电站的项目调控方法及系统 | |
CN112365233A (zh) | 一种项目成本信息化管理方法 | |
Yan et al. | Dynamic control of integrated project management system based on engineering projects | |
Leysen | An analysis of smart meter deployment in Sweden with applicability to the case of India | |
CN108805529B (zh) | 一种建筑工程管理平台 | |
CN114154862A (zh) | 基于工程全过程管理的工程成本自动分摊方法及系统 | |
CN110298562A (zh) | 一种配电网建设审计网格化管理方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |