CN104846726A - Road construction method for strip mine - Google Patents

Road construction method for strip mine Download PDF

Info

Publication number
CN104846726A
CN104846726A CN201510198559.4A CN201510198559A CN104846726A CN 104846726 A CN104846726 A CN 104846726A CN 201510198559 A CN201510198559 A CN 201510198559A CN 104846726 A CN104846726 A CN 104846726A
Authority
CN
China
Prior art keywords
road
opencut
construction method
soil property
road construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510198559.4A
Other languages
Chinese (zh)
Inventor
李伟
李继
潘博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaneng Yimin Coal and Electricity Co Ltd
Original Assignee
Huaneng Yimin Coal and Electricity Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaneng Yimin Coal and Electricity Co Ltd filed Critical Huaneng Yimin Coal and Electricity Co Ltd
Priority to CN201510198559.4A priority Critical patent/CN104846726A/en
Publication of CN104846726A publication Critical patent/CN104846726A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a road construction method for strip mine. The road construction method includes the steps of: firstly, clearing the soil materials below the road pressure surface; then, mixing the cleared soil materials with sand and performing stirring; and finally, refilling the road with the mixed and stirred mixture, and spreading a wearing layer on the top, and then conducting maintenance work. According to the road construction method for strip mine, sand is mixed in a single soil material to change the road material structure and enhance the material hardness, the road transportation quality is enhanced, and the integrated road bears more enormous upper pressure in the truck transportation process. And the difficulty that existing road construction methods are difficult to meet normal transportation operation of large mechanical equipment in strip mine can be overcome.

Description

The constructing road method of opencut
Technical field
The present invention relates to opencast mining field, particularly a kind of constructing road method of opencut.
Background technology
At present, domestic large, medium and small opencut main production program comprises digging coal petrography, transport and disposing three phases, and part opencut comprises explosion.Under normal condition, transport routes (soil road) are struck off by blade machine process and just can travel for vehicle.
But along with the maximization day by day of mine transportation equipment, truck carries goods weight and day by day strengthens, and therefore road is out of shape gradually because reaching the bearing pressure limit, finally causes road destroyed, and truck transport efficiency straight line declines.This situation is especially serious in geology softly mine.
The information being disclosed in this background technology part is only intended to increase the understanding to general background of the present invention, and should not be regarded as admitting or imply in any form that this information structure has been prior art that persons skilled in the art are known.
Summary of the invention
The object of the present invention is to provide a kind of constructing road method of opencut of simple and reasonable steps, the constructing road method of this opencut changes road materials structure by being mixed into sandstone in single soil property material, improving material hardness, improve road transport quality, make integrated road in truck transport process bear huger upper pressure.Overcome the difficulty that the existing method of repairing the roads is difficult to meet the operation of opencut heavy mechanical equipment normal transport.
For achieving the above object, the invention provides the constructing road method of opencut, comprise the following steps: first, clear out the soil property material of below road pressure-bearing surface; Then, the soil property material cleared out and sandstone are carried out mixing, stirring; Finally, the mixed material after mix and blend is filled out back in road again, and at its top spreading wearing layer, then carry out health work.
Preferably, in technique scheme, the soil property material thickness cleared out below road pressure-bearing surface is two meters.
Preferably, in technique scheme, the soil property material cleared out and sandstone are undertaken mixing, stirring by the volume ratio of 2:1.
Preferably, in technique scheme, in the middle of the road surface adopting this constructing road method to build, high both sides are low.
Compared with prior art, the present invention has following beneficial effect: the constructing road method of this opencut changes road materials structure by being mixed into sandstone in single soil property material, improving material hardness, improve road transport quality, make integrated road in truck transport process bear huger upper pressure.Overcome the difficulty that the existing method of repairing the roads is difficult to meet the operation of opencut heavy mechanical equipment normal transport.
Accompanying drawing explanation
Fig. 1 is the road longitudinal section that the constructing road method of existing opencut is built.
Fig. 2 is the road longitudinal section that the constructing road method of opencut of the present invention is built.
Fig. 3 is the path formation longitudinal section that the constructing road method of opencut of the present invention is built.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in detail, but is to be understood that protection scope of the present invention not by the restriction of detailed description of the invention.
Clearly represent unless otherwise other, otherwise in whole manual and claims, term " comprise " or its conversion as " comprising " or " including " etc. by be understood to include the element of stating or ingredient, and do not get rid of other element or other ingredient.
Pass through to change the single soil property material structure of road according to the constructing road method of the opencut of the specific embodiment of the invention, sandstone are mixed in material, improving material hardness, concrete experience in incorporation engineering, carries out proportion expression and refers and synthesizes, finally be modulated into high strength material and can combine together, realize integrated road in truck transport process and bear huger upper pressure, improve traffic condition, with low cost, structure is simple, mine hoisting remarkable benefit.
The constructing road method of this opencut comprises the following steps:
First, the soil property material in road pressure-bearing surface two meters of thickness is cleared out;
In road longitudinal section as shown in Figure 1, the thickness that road bears equipment pressure is generally 1.5-2 meters, therefore soil property material 1 in truck contact surface two meters of thickness is needed all to release, to change the single soil property material structure of road, carry out improving material hardness, realize integrated road in truck transport process and bear huger upper pressure, improve traffic condition.
Then, the soil property material cleared out and sandstone are undertaken mixing, stirring by the volume ratio of 2:1;
Note, in soil property material and sandstone whipping process, can not moisture be mixed, make material become drying by constantly stirring, condensation is block.
As shown in Figure 2, finally, the mixed material 2 after mix and blend is filled out back in road again, and at its top spreading wearing layer 3, then carry out health work.
The time of health work remains on more than two days, realizes material in two days and continues inner fusion, solidifies, and final height of formation solidification, bears high stress.
In addition, when road builds up, different gaps is there is between material, although can solidify in health process, condense, but after the going and back running and roll of heavy load truck, the gap of storeroom can become less, can obviously diminish before the volume of material compares and rolls, road surface inherently there is much low-lying, scarce material sections, in order to save constructing road cost, " playing drum " type road surface that this opencut road takes middle high both sides low, can avoid producing situation low-lying, in short supply because truck rolls in the use procedure in the early stage of newly-built road like this.
As shown in Figure 3, in newly-built road occupation process, because of repeatedly rolling of heavy load truck, often can there is uneven section in road surface, this section not only can affect driver driving truck, but also can accelerate the parts consumption of truck, work more economically, efficiently to make truck, blade machine 4 must carry out smooth to out-of-flatness section often, and the moment keeps road surface to be in flat condition, is convenient to travelling truck.
To sum up, the constructing road method of this opencut changes road materials structure by being mixed into sandstone in single soil property material, and improving material hardness, improves road transport quality, makes integrated road in truck transport process bear huger upper pressure.Overcome the difficulty that the existing method of repairing the roads is difficult to meet the operation of opencut heavy mechanical equipment normal transport.
The aforementioned description to concrete exemplary of the present invention is to illustrate and the object of illustration.These descriptions not want the present invention to be defined as disclosed precise forms, and obviously, according to above-mentioned instruction, can much change and change.The object selected exemplary embodiment and describe is to explain certain principles of the present invention and practical application thereof, thus those skilled in the art can be realized and utilize various different exemplary of the present invention and various different selection and change.Scope of the present invention is intended to limited by claims and equivalents thereof.

Claims (4)

1. a constructing road method for opencut, is characterized in that, comprise the following steps:
First, the soil property material of below road pressure-bearing surface is cleared out;
Then, the soil property material cleared out and sandstone are carried out mixing, stirring;
Finally, the mixed material after mix and blend is filled out back in road again, and at its top spreading wearing layer, then carry out health work.
2. the constructing road method of opencut according to claim 1, is characterized in that, the soil property material thickness cleared out below road pressure-bearing surface is two meters.
3. the constructing road method of opencut according to claim 1, is characterized in that, the soil property material cleared out and sandstone are undertaken mixing, stirring by the volume ratio of 2:1.
4. the constructing road method of opencut according to claim 1, is characterized in that, in the middle of the road surface adopting this constructing road method to build, high both sides are low.
CN201510198559.4A 2015-04-24 2015-04-24 Road construction method for strip mine Pending CN104846726A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510198559.4A CN104846726A (en) 2015-04-24 2015-04-24 Road construction method for strip mine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510198559.4A CN104846726A (en) 2015-04-24 2015-04-24 Road construction method for strip mine

Publications (1)

Publication Number Publication Date
CN104846726A true CN104846726A (en) 2015-08-19

Family

ID=53846685

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510198559.4A Pending CN104846726A (en) 2015-04-24 2015-04-24 Road construction method for strip mine

Country Status (1)

Country Link
CN (1) CN104846726A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625131A (en) * 2015-12-29 2016-06-01 内蒙古包钢钢联股份有限公司 Road quick repairing method
CN105971609A (en) * 2016-06-03 2016-09-28 华能伊敏煤电有限责任公司 Ramp replacement mode for electric shovel excavation
CN111155403A (en) * 2020-01-20 2020-05-15 芜湖海螺水泥有限公司 Method for constructing surface mine road

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1401853A (en) * 2002-08-06 2003-03-12 张炳宏 Road building method, solid and liquid solidifying agents thereby and method for producing them
CN101319483A (en) * 2008-07-22 2008-12-10 安蓉建设总公司 Roadbed filling construction method with physically improved fine sand
CN102900001A (en) * 2012-10-22 2013-01-30 中国水电建设集团路桥工程有限公司 Construction method for road foundation
JP2013100638A (en) * 2011-11-07 2013-05-23 Shiima Consultant:Kk Soil improvement method
CN103174073A (en) * 2013-03-22 2013-06-26 中国十九冶集团有限公司 Desert silt soil backfill compaction construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1401853A (en) * 2002-08-06 2003-03-12 张炳宏 Road building method, solid and liquid solidifying agents thereby and method for producing them
CN101319483A (en) * 2008-07-22 2008-12-10 安蓉建设总公司 Roadbed filling construction method with physically improved fine sand
JP2013100638A (en) * 2011-11-07 2013-05-23 Shiima Consultant:Kk Soil improvement method
CN102900001A (en) * 2012-10-22 2013-01-30 中国水电建设集团路桥工程有限公司 Construction method for road foundation
CN103174073A (en) * 2013-03-22 2013-06-26 中国十九冶集团有限公司 Desert silt soil backfill compaction construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625131A (en) * 2015-12-29 2016-06-01 内蒙古包钢钢联股份有限公司 Road quick repairing method
CN105971609A (en) * 2016-06-03 2016-09-28 华能伊敏煤电有限责任公司 Ramp replacement mode for electric shovel excavation
CN111155403A (en) * 2020-01-20 2020-05-15 芜湖海螺水泥有限公司 Method for constructing surface mine road

Similar Documents

Publication Publication Date Title
CN107059573B (en) Construction method for solidifying soil body as road water stabilization layer
CN109914178B (en) Construction method for integrally paving road by using bio-enzyme curing material
CN104846726A (en) Road construction method for strip mine
CN103194947B (en) A kind of temporary road ballast lump having enough to meet the need use
CN102493308A (en) Bio-enzyme modified roller compacted concrete road engineering construction technology
CN108660890A (en) Native construction method is stablized in a kind of road cement stabilization soil and environment-friendly water-based solidification
CN104631274A (en) Temporary road pavement technology
CN109537385A (en) The filling roadbed construction technology of silt
CN109537655A (en) A kind of scoop loader and its application suitable for complex working condition
CN103422407A (en) Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road
CN102535290A (en) Method for curing red mud roadbed by using liquid red mud curing agent
DE102006000920B4 (en) Method for environmentally friendly production of underground stations of suburban trains and the like
CN102261028B (en) Application method of cemented backfilling material on strip mine dustproof road surface for automobile transportation
CN107447617A (en) A kind of dust-proof curing process of temporary construction road
CN104831605B (en) Subgrade and pavement is compacted edge and helps mechanical equipment without formwork erection construction paving
CN203064982U (en) Transporting device for mountain high slope construction materials
Rodovalho et al. Sequential glory hole approach as a new mining method for sustainable operations
CN205420936U (en) Highway road bed of filling
CN203902543U (en) Ground-mountain cable crane system for transportation of heavy goods in isolated high and steep mountain slope
RU2365698C1 (en) Strengthening method of road pavement
Anagnostou et al. Tunnelling Switzerland
Avalle Reducing haul road maintenance costs and improving tyre wear through the use of impact rollers
RU2593399C1 (en) Method for recovery of layers of road pavement
CN112900409B (en) Dust suppression method for soil road for transportation
CN108755362A (en) Base cures cold regeneration construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819