CN103422407A - Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road - Google Patents

Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road Download PDF

Info

Publication number
CN103422407A
CN103422407A CN2012101514060A CN201210151406A CN103422407A CN 103422407 A CN103422407 A CN 103422407A CN 2012101514060 A CN2012101514060 A CN 2012101514060A CN 201210151406 A CN201210151406 A CN 201210151406A CN 103422407 A CN103422407 A CN 103422407A
Authority
CN
China
Prior art keywords
compound
desert
cement
kieselguhr
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101514060A
Other languages
Chinese (zh)
Inventor
支学军
苏泉
隋玉良
杨登峰
徐伟良
沈建忠
刘林林
朱燚
杜国松
苏伟征
张家勇
赵雄伟
余远平
陈远忠
梁斌
薛延丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION Co Ltd
Original Assignee
TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION Co Ltd filed Critical TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION Co Ltd
Priority to CN2012101514060A priority Critical patent/CN103422407A/en
Publication of CN103422407A publication Critical patent/CN103422407A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a construction process using cement diatomite to stabilize a desert sand mixture to build a Niger desert road, and aims to overcome the defects that in Niger desert materials for road construction are deficient, and road construction investment is high. The construction process using the cement diatomite to stabilize the desert sand mixture to build the Niger desert road comprises the following steps: A. line layout for construction, B. roadbed primary flatting, C. first water spraying, with sand immersed by water deeper than 20 cm, D. roadbed sand fine flatting, E. sand ridging of road shoulders, with the sand in both sides being wider than 50 cm, F. secondary water spraying, with an average water immersion depth being ensured, G. mixing and stirring of a mixture, H. loading and spreading of the mixture, I. mixture compaction and J. maintenance. In the step G, a mixing method by heaping or a mixing method on a road or a mixing method in a concentration plant is used for mixing and stirring of the mixture. The beneficial effects of the construction process are that: the construction process is simple, can better control the construction quality, and can reduce the construction cost.

Description

Adopt cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique
Technical field
The present invention relates to a kind of road in desert area field construction technology, especially relate to a kind of employing cement kieselguhr and stablize Desert Sand compound build Niger Highway Construction in Desert technique.
Background technology
At present, the build technology of the road in desert area treatment of the earth layer of domestic and international maturation mainly contains following several form:
1, bed course
Three grades of domestic standards and following low-grade highway, adopt clay punishment sand, natural gravel, geotextiles and geotechnical grid to add and fix the sand; Secondary and above standard highway, the most often adopt the natural gravel of natural gravel or geotextiles upper berth, and geotechnical grid adds and fixes the sand etc.
2, subbase and basic unit
Three grades of domestic standards and following low-grade highway, adopt the means of particulate material such as natural gravel, graded broken stone; And the husky semi-rigid material of the stabilized with inorganic binder such as cement, lime, flyash, cement adds the chemical addition agent stabilized sand, curing compound stabilized sand etc.Secondary and above standard highway, adopt the means of particulate material such as natural gravel, graded gravel, graded broken stone; The stabilized with inorganic binder such as cement, lime fly ash sand, the semi-rigid materials such as Aggregate Stabilized with Cement or rubble.
3, surface layer
Three grades of domestic standards and following low-grade highway, adopt pitch table place, bituminous concrete, mud knot rubble, mud knot gravel, brick or the concrete precast block road surface of mating formation usually; And the husky surface of the cement stabilizing of not yet applying pours into the water glass solution pavement technique.Secondary and above standard highway, adopt bituminous concrete, SBS and SBR modified asphalt concrete and new technology silicon-modified asphalt concrete, cement concrete pavement etc.
Because the material that can be used for building the road in Niger desert is very deficient, except abundant Desert Sand with local low-lying place is scattered is distributed with low-grade kieselguhr, do not have the outsourcing materials such as the required pitch of roadbed, ground surface material that sand, clay, gravel, rock, lime, flyash etc. are commonly used, cement, steel, rubble much all to need import, and must rely on the transport vehicle transportation of extraordinary desert, buying and freight are extremely high.Therefore build Road Site in Niger's desert area oil field, invest very high, unreasonable economically.
Summary of the invention
In order to overcome the material scarcity that can be used for building the road in Niger desert, build road and invest high deficiency, the invention provides a kind of employing cement kieselguhr and stablize Desert Sand compound build Niger Highway Construction in Desert technique.The cement kieselguhr that the applicant just the present invention relates to is stablized the Desert Sand compound and has been applied for separately patent.
The technical solution adopted for the present invention to solve the technical problems is: adopt cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, the steps include:
A. the construction line-putting,
B. roadbed is just flat,
C. once watering, immerse sand >=20cm,
D. the husky essence of roadbed is flat,
E. train husky curb, both sides >=50cm,
F. secondary waters, and guarantees that immersed depth is average,
G. compound mixes and stirs,
H. the compound material loading, pave,
I. compound compacting,
J. health.
Step G compound mixes and stirs and adopts heap companion's method or road-mix method or concentrated plant mixing method.
The invention has the beneficial effects as follows, according to Niger's desert area road materials scarcity, the characteristics that abundant Desert Sand and the fragmentary low-grade diatomite resource distributed are only arranged, by adding a small amount of Portland cement, Admixture mixing water mix forms, adopt the conventional road building machinery decking and rolling moulding such as land leveller, loader, bulldozer or paver, can be used as the decks such as Road Site bed course, subbase, basic unit, surface layer after health.Construction technology is simple, and the Control Engineering quality, reduce engineering cost preferably.
The accompanying drawing explanation
Fig. 1 is process chart of the present invention.
The specific embodiment
Below in conjunction with drawings and Examples, the invention will be further described.But those skilled in the art should know, the invention is not restricted to the listed specific embodiment, as long as spirit according to the invention all should be included in protection scope of the present invention.
Construction technology material therefor of the present invention is Niger's desert Desert Sand kieselguhr and cement admixture, and its component and content are:
Figure BDA00001640467400031
All percentage is percetage by weight.
Build secondary or secondary to get down the highway, the maximum particle diameter≤37mm of the stabilized sand compound individual particle that bed course is used; Maximum particle diameter≤the 26.5mm of the stabilized sand compound individual particle that subbase is used; Maximum particle diameter≤the 16mm of the stabilized sand compound individual particle that basic unit is used; Maximum particle diameter≤the 4.75mm of the stabilized sand compound individual particle that surface layer is used.
Building highway or Class I highway, the maximum particle diameter≤31.5mm of the stabilized sand compound individual particle that bed course is used; Maximum particle diameter≤the 19mm of the stabilized sand compound individual particle that subbase is used; Maximum particle diameter≤the 9.5mm of the stabilized sand compound individual particle that basic unit is used; Maximum particle diameter≤the 4.75mm of the stabilized sand compound individual particle that surface layer is used.
SiO in Desert Sand 2Content is 93%~99%; Diatom shell content 20%~35% before Purification of Diatomite, Desert Sand content 63.5%~74%, clay≤1%, and lyotropic salt composition and the Fe of minute quantity 2O 3Etc. mineralogical composition, diatom shell content 80%~95% after purifying.
Admixture is efficient retardation water reducing agent or retarding agent.
The construction technology that adopts above-mentioned material to build Niger's desert highway, the steps include:
A. the construction line-putting,
B. roadbed is just flat,
C. once watering, immerse sand >=20cm,
D. the husky essence of roadbed is flat,
E. train husky curb, both sides >=50cm,
F. secondary waters, and guarantees that immersed depth is average,
G. compound mixes and stirs,
H. the compound material loading, pave
I. compound compacting
J. health.
Step G compound mixes and stirs and adopts heap companion's method or road-mix method or concentrated plant mixing method.
Niger's road in desert area, the construction of place cement kieselguhr stabilized sand mixture structure layer mainly comprise Niger's ore separation of diatomite, kieselguhr full water soaking, sub-layer preparation, compound mix, mixture laying and roll.
According to the quality specifications grade difference of engineering quantity size, place and road, the construction technology of taking and matching equipment are also different.Specific construction technique is as follows:
1, the back court compound takes heap to mix method (also claim collect together the method for mixing), and front court takes loader, bulldozer smooth, and road roller rolls.Concrete operation is as follows:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, the general time is for soaking about 48 hours.
(2) kieselguhr after immersion is other gets Desert Sand with excavator or loader on the spot, the match ratio definite according to sampling test is converted to volume ratio, scene is mixed and is joined compound (as kieselguhr: Desert Sand=1: 3 fills 1 bucket kieselguhr with excavator and mixes to refilling 3 bucket Desert Sand to stockpiles after the compound stockpile).
(3) the mixing stockpile that will mix after joining is raised and is mixed 1~2 time with loader or excavator again, until evenly.
(4) after loader or excavator will mix the stockpile shaping roughly, measure its pine heap volume with steel ruler, be converted to volume ratio according to the definite match ratio of test, sacked cement (preferably retarded cement), water and the artificial cooperating equipment of Admixture are spread in uniform in and mix the stockpile surface, again mix and stir 2~3 times, until evenly.Initial water content is controlled and should be exceeded 2%~4% of optimum moisture content, and to offset the moisture evaporation in the construction at high temperature process of desert, concrete initial water content is adjusted through measuring temperature at that time of construction and wind speed.
(5) prepare husky base sub-layer.At first base course (sub-layer) is carried out setting-out, leveling, sprinkles water, rolls.To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.After rolling, use with the distinguishing material marking per car of husky base color compound unload truck position (calculating in advance the area that paves of per car compound).
(6) compound mixed and stirred is transported to job site.With smooth equipment (as loader, bulldozer or land leveller), compound is carried out to leveling work, this process and follow-up rolling should be no more than 3 hours.
(7) with compacting equipment, to flattening complete compound, rolled.The face that rolls should be closely knit and bright and clean, avoids passing, stops up bag and rub with the hands and split phenomenon.
2, the back court compound takes heap to mix method (also claiming to collect together the method for mixing), and front court takes paver to pave, and road roller rolls.Concrete operation is as follows:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, generally soak about 48 hours.
(2) kieselguhr after immersion is other gets Desert Sand with excavator or loader on the spot, the match ratio definite according to sampling test is converted to volume ratio, scene is mixed and is joined compound (as: kieselguhr: Desert Sand=1: 3 fills 1 bucket kieselguhr with excavator and mixes to refilling 3 bucket Desert Sand to stockpiles after the compound stockpile).
(3) the mixing stockpile that will mix after joining is raised and is mixed 1~2 time with loader or excavator again, until evenly basic.
(4) after loader or excavator will mix the stockpile shaping roughly, measure its pine heap volume with steel ruler, be converted to volume ratio according to the definite match ratio of test, sacked cement (preferably retarded cement), water and the artificial cooperating equipment of Admixture are spread in uniform in and mix the stockpile surface, again mix and stir 2~3 times, until evenly.Initial water content is controlled and should be exceeded 2%~4% of optimum moisture content, and to offset the moisture evaporation in the construction at high temperature process of desert, concrete initial water content is adjusted through measuring temperature at that time of construction and wind speed.
(5) prepare husky base sub-layer.At first base course (sub-layer) is carried out setting-out, leveling, sprinkles water, rolls.To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.After rolling, use with the distinguishing material marking per car of husky base color compound unload truck position (calculating in advance the area that paves of per car compound).
(6) compound mixed and stirred is transported to job site.Use the paver compound that paves, because the evaporation of desert area moisture is very fast, road roller should roll immediately following paver, and (each rolls paragraph and is no more than 30 meters), pave and the work of rolling must complete before the cement initial set.
3, the back court compound is taked road-mix method, and loader, bulldozer or land leveller leveling are taked in front court, and road roller rolls.Concrete operation is as follows:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time is about 48 hours usually.
(2) prepare husky base sub-layer.At first base course (sub-layer) is carried out setting-out, leveling, sprinkles water, rolls.To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.
(3) Desert Sand is transported to roadbed thick flat by smaller vehicle, thickness 22cm, the mode that complete kieselguhr, cement and the Admixture of immersion taked to beat grid, manually evenly pave on the Desert Sand surface.Initial water content according to calculated in advance is sprinkled water on surface, and initial water content is controlled and should be exceeded 2%~4% of optimum moisture content, and to offset the moisture evaporation in the construction at high temperature process of desert, concrete initial water content is adjusted through measuring temperature at that time of construction and wind speed.
(4) with mixing apparatus (as tractor, turnplow, disc harrow or soil stabilizer), mix and stir 2~4 times, until evenly.
(5) with smooth equipment (as loader, bulldozer or land leveller), compound is carried out to leveling work, this process and follow-up rolling should complete before the cement initial set.
(6) with compacting equipment, to flattening complete compound, rolled.The face that rolls is more closely knit and bright and clean, avoids passing, stops up bag and rub with the hands and split phenomenon.
4, the back court compound takes to concentrate plant mixing method, and loader, bulldozer or land leveller leveling are taked in front court, and road roller rolls.Concrete operation is as follows:
(1) set up stabilized soil mixing plant, debug qualified standby.
(2) kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time is about 48 hours.
(3) prepare husky base sub-layer.At first base course (sub-layer) is carried out setting-out, leveling, sprinkles water, rolls.To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.After rolling, use with the distinguishing material marking per car of husky base color compound unload truck position (calculating in advance the area that paves of per car compound).
(4) according to the definite match ratio of the prior sampling test in laboratory, loader material loading (kieselguhr, Desert Sand) is to the blending station feed bin, and Electronic Control cement, Admixture material loading speed and kieselguhr, Desert Sand belt speed mate simultaneously.Initial water content is controlled and should be exceeded 2%~3% of optimum moisture content, and to offset the moisture evaporation in the construction at high temperature process of desert, concrete initial water content is adjusted through measuring temperature at that time of construction and wind speed.
(5) with haulage vehicle, compound is transported to roadbed, with smooth equipment (as loader, bulldozer or land leveller), compound is carried out to leveling work, this process and follow-up rolling should be tried one's best fast, and all work must complete before the cement initial set.
(6) with compacting equipment, to flattening complete compound, rolled.Evidence, pneumatic-tired rollers have rolling effect preferably than single-drum road roller etc., and the face that rolls is more closely knit and bright and clean, can effectively avoid passing, stop up bag and rub with the hands and split phenomenon.
5, the back court compound is taked to concentrate plant mixing method, and the front court paver paves, and road roller rolls.Concrete operation is as follows:
(1) set up stabilized soil mixing plant, debug qualified standby.
(2) kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time is 48 hours usually.
(3) prepare husky base sub-layer.At first base course (sub-layer) is carried out setting-out, leveling, sprinkles water, rolls.To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.After rolling, use with the distinguishing material marking per car of husky base color compound unload truck position (calculating in advance the area that paves of per car compound).
(4) the definite match ratio according to sampling test, loader material loading (kieselguhr, Desert Sand) is to the blending station feed bin, simultaneously Electronic Control cement, Admixture material loading speed and kieselguhr, Desert Sand belt speed coupling.Initial water content is controlled and should be exceeded 2%~3% of optimum moisture content, and to offset the moisture evaporation in the construction at high temperature process of desert, concrete initial water content is adjusted through measuring temperature at that time of construction and wind speed.
(5) with tipping lorry, the compound mixed and stirred is transported to job site.Use the paver compound that paves, because the evaporation of desert area moisture is very fast, road roller should be closelyed follow paver and be rolled (each rolls paragraph and is no more than 30 meters), paves and roll before being operated in the cement initial set to complete.
Construction technology main points of the present invention:
(1) select higher natural diatomaceous earth and the Desert Sand of purity to mix and stir, mixing and stirring must be even, and below maximum particle diameter 3cm;
(2) definite external adding water ratio such as the temperature when mixing and stirring, wind speed;
(3) pave and mix speed should finish within 4 hours, should adopt retarded cement, initial setting time to be not less than 4 hours as far as possible;
(4) can suitably sprinkle water on surface after the construction, and cover health 7 days with Polypropylence Sheet in time.
The major function of Admixture is for increasing the time of setting of cement, but improve mobility and the application property of cement kieselguhr stabilized sand, slow down moisture evaporation rate under the high temperature hot environment, during delaying from mix to the decking and rolling molding construction simultaneously, hydrated reaction of cement speed, reduce and postpone loss of strength.
Where necessary, can also lay the single or multiple lift geosynthetics at husky base end face and play as separation layer is double the effect that Sha Ji is stable, as high-strength polyethylene establishment cloth etc.
It should be noted that above-described embodiment is example and unrestricted the present invention, those skilled in the art can design a lot of alternate embodiments and not break away from the claim scope of this patent.

Claims (7)

1. one kind adopts cement kieselguhr to stablize Desert Sand compound build Niger Highway Construction in Desert technique, the steps include:
A. the construction line-putting,
B. roadbed is just flat,
C. once watering, immerse sand >=20cm,
D. the husky essence of roadbed is flat,
E. train husky curb, both sides >=50cm,
F. secondary waters, and guarantees that immersed depth is average,
G. compound mixes and stirs,
H. the compound material loading, pave,
I. compound compacting,
J. health.
2. adopt according to claim 1 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described step G compound mixes and stirs and adopts heap companion's method or road-mix method or concentrated plant mixing method.
3. adopt according to claim 2 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described compound mixes and stirs back court and adopts heap to mix method, front court takes loader, bulldozer smooth, and road roller rolls, process:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time 44~50 hours;
(2) kieselguhr after immersion is other gets Desert Sand with excavator or loader on the spot, and the match ratio definite according to sampling test is converted to volume ratio, and scene is mixed and joined compound;
(3) the mixing stockpile that will mix after joining is raised and is mixed 1~2 time with loader or excavator again, until evenly;
(4) after loader or excavator will mix the stockpile shaping roughly, with steel ruler, measure its pine heap volume, according to the definite match ratio of test, be converted to volume ratio, cement, water and Admixture are spread in uniform in and mix the stockpile surface, again mix and stir 2~3 times;
(5) prepare husky base sub-layer, at first base course is carried out setting-out, leveling, sprinkles water, rolls; To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky; Use the truck position of unloading with the distinguishing material marking per car of husky base color compound after rolling;
(6) compound mixed and stirred is transported to job site, with smooth equipment, compound is carried out to leveling work, this process and follow-up rolling should be no more than 3 hours;
(7) with compacting equipment, to flattening complete compound, rolled, the face that rolls is closely knit, bright and clean, without passing, stop up bag and rubbing with the hands, splits phenomenon.
4. adopt according to claim 2 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described compound mixes and stirs back court and adopts heap to mix method, and front court takes paver to pave, and road roller rolls, and operation is as follows:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time 44~50 hours;
(2) kieselguhr after immersion is other gets Desert Sand with excavator or loader on the spot, and the match ratio definite according to sampling test is converted to volume ratio, and scene is mixed and joined compound;
(3) the mixing stockpile that will mix after joining is raised and is mixed 1~2 time with loader or excavator again, until evenly;
(4) after loader or excavator will mix the stockpile shaping roughly, with steel ruler, measure its pine heap volume, according to the definite match ratio of test, be converted to volume ratio, cement, water and Admixture are spread in uniform in and mix the stockpile surface, again mix and stir 2~3 times;
(5) prepare husky base sub-layer, at first base course is carried out setting-out, leveling, sprinkles water, rolls; To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky.Use the truck position of unloading with the distinguishing material marking per car of husky base color compound after rolling;
(6) compound mixed and stirred is transported to job site, uses the paver compound that paves, paving and rolling before being operated in the cement initial set completes.
5. adopt according to claim 2 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described compound mixes and stirs back court and adopts road-mix method, loader, bulldozer or land leveller leveling are taked in front court, and road roller rolls, and operation is as follows:
(1) at first kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time 44~50 hours;
(2) prepare husky base sub-layer, at first base course is carried out setting-out, leveling, sprinkles water, rolls; To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky;
(3) Desert Sand is transported to roadbed thick flat by smaller vehicle, thickness 22cm, the mode that complete kieselguhr, cement and the Admixture of immersion taked to beat grid, manually evenly pave on the Desert Sand surface; Initial water content according to calculated in advance is sprinkled water on surface;
(4) with mixing apparatus, mix and stir 2~4 times, until evenly;
(5) with smooth equipment, compound is carried out to leveling work, this process and follow-up rolling before the cement initial set complete;
(6) with compacting equipment, to flattening complete compound, rolled, the face that rolls is closely knit, bright and clean, without passing, stop up bag and rubbing with the hands, splits phenomenon.
6. adopt according to claim 1 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described compound mixes and stirs back court and takes to concentrate plant mixing method, loader, bulldozer or land leveller leveling are taked in front court, and road roller rolls, and operation is as follows:
(1) set up stabilized soil mixing plant, debug qualified standby;
(2) kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time 44~50 hours;
(3) prepare husky base sub-layer, at first base course is carried out setting-out, leveling, sprinkles water, rolls; To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky; Use the truck position of unloading with the distinguishing material marking per car of husky base color compound after rolling;
(4) the definite match ratio according to sampling test, the loader material loading is to the blending station feed bin, simultaneously Electronic Control cement, Admixture material loading speed and kieselguhr, Desert Sand belt speed coupling;
(5) with haulage vehicle, compound is transported to roadbed, with smooth equipment, compound is carried out to leveling work, this process and follow-up rolling should be tried one's best fast, and all work must complete before the cement initial set;
(6) with compacting equipment, to flattening complete compound, rolled, the face that rolls is closely knit, bright and clean, without passing, stop up bag and rubbing with the hands, splits phenomenon.
7. adopt according to claim 2 cement kieselguhr to stablize the Desert Sand compound and build Niger's Highway Construction in Desert technique, it is characterized in that: described compound mixes and stirs back court and takes to concentrate plant mixing method, and the front court paver paves, and road roller rolls, and operation is as follows:
(1) set up stabilized soil mixing plant, debug qualified standby;
(2) kieselguhr is transported to ward or the cofferdam of digging pit on the spot, uses water saturates fully, soak time 44~50 hours;
(3) prepare husky base sub-layer, at first base course is carried out setting-out, leveling, sprinkles water, rolls; To remain and water in the material loading paving process, guarantee that at least the thick sand bed of 20cm is not dry husky; Use the truck position of unloading with the distinguishing material marking per car of husky base color compound after rolling;
(4) the definite match ratio according to sampling test, the loader material loading is to the blending station feed bin, simultaneously Electronic Control cement, Admixture material loading speed and kieselguhr, Desert Sand belt speed coupling;
(5) with tipping lorry, the compound mixed and stirred is transported to job site, paving and rolling before being operated in the cement initial set completes.
CN2012101514060A 2012-05-15 2012-05-15 Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road Pending CN103422407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101514060A CN103422407A (en) 2012-05-15 2012-05-15 Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101514060A CN103422407A (en) 2012-05-15 2012-05-15 Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road

Publications (1)

Publication Number Publication Date
CN103422407A true CN103422407A (en) 2013-12-04

Family

ID=49647760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101514060A Pending CN103422407A (en) 2012-05-15 2012-05-15 Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road

Country Status (1)

Country Link
CN (1) CN103422407A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638339A (en) * 2017-01-18 2017-05-10 甘肃省治沙研究所 Algae blanket and preparing method thereof
CN108708244A (en) * 2018-06-22 2018-10-26 杜宇 A kind of highway road surface and preparation method thereof not cracked
CN112064438A (en) * 2020-08-12 2020-12-11 包头钢铁(集团)有限责任公司 Method for paving ore transportation highway
CN112746540A (en) * 2020-12-24 2021-05-04 龙建路桥股份有限公司 Construction method for reinforcing aeolian sand to pass through roadbed in geocell
CN114059563A (en) * 2021-11-09 2022-02-18 中铁八局集团第七工程有限公司 Multi-material layered filling method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07158047A (en) * 1993-10-13 1995-06-20 Maeda Corp High moisture content soil improving material and construction method for road bed and banking
CN1294228A (en) * 1999-10-27 2001-05-09 北京大学 Method for building highway on desert
CN101503871A (en) * 2009-03-19 2009-08-12 中铁十一局集团有限公司 Dry-method construction method for drift-sand roadbed
CN101608419A (en) * 2009-07-21 2009-12-23 中铁二十一局集团有限公司 Desert area migratory dune land railway bed construction method
CN101962928A (en) * 2010-08-12 2011-02-02 中铁二十二局集团第一工程有限公司 Construction method for processing aeolian sand roadbed base through impacting and grinding

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07158047A (en) * 1993-10-13 1995-06-20 Maeda Corp High moisture content soil improving material and construction method for road bed and banking
CN1294228A (en) * 1999-10-27 2001-05-09 北京大学 Method for building highway on desert
CN101503871A (en) * 2009-03-19 2009-08-12 中铁十一局集团有限公司 Dry-method construction method for drift-sand roadbed
CN101608419A (en) * 2009-07-21 2009-12-23 中铁二十一局集团有限公司 Desert area migratory dune land railway bed construction method
CN101962928A (en) * 2010-08-12 2011-02-02 中铁二十二局集团第一工程有限公司 Construction method for processing aeolian sand roadbed base through impacting and grinding

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
隋玉良: "尼日尔某沙漠公路路基设计与施工", 《施工技术》, vol. 40, no. 339, 25 April 2011 (2011-04-25), pages 3 - 4 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638339A (en) * 2017-01-18 2017-05-10 甘肃省治沙研究所 Algae blanket and preparing method thereof
CN106638339B (en) * 2017-01-18 2022-04-08 甘肃省治沙研究所 Algae blanket and preparation method thereof
CN108708244A (en) * 2018-06-22 2018-10-26 杜宇 A kind of highway road surface and preparation method thereof not cracked
CN108708244B (en) * 2018-06-22 2023-03-17 杜宇 Highway pavement base without cracks and preparation method thereof
CN112064438A (en) * 2020-08-12 2020-12-11 包头钢铁(集团)有限责任公司 Method for paving ore transportation highway
CN112746540A (en) * 2020-12-24 2021-05-04 龙建路桥股份有限公司 Construction method for reinforcing aeolian sand to pass through roadbed in geocell
CN114059563A (en) * 2021-11-09 2022-02-18 中铁八局集团第七工程有限公司 Multi-material layered filling method

Similar Documents

Publication Publication Date Title
WO2022028038A1 (en) Novel embankment construction method using calcareous sand concrete
CN109914178B (en) Construction method for integrally paving road by using bio-enzyme curing material
CN106587835B (en) A kind of cold mixing formula Cement emulsified asphalt concrete and its method for paving
CN101602946B (en) Overmoisture soil stabilizer and method for solidifying soil
CN101691736A (en) Construction method for reconstructing old concrete pavement by paving asphalt-concrete surface layer
CN109853310A (en) A kind of dredging silt industrial residue composite curing light soil and roadbed placement in layers construction method
CN101255040A (en) Preparation of recycled road construction material from construction waste and its preparation method and construction method
CN111485468B (en) Premixed foam asphalt base layer and subbase layer in-situ cold regeneration construction method
CN103422407A (en) Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road
CN101532273B (en) Anti-rutting road surface RS2000 modified asphalt mixture proportion and construction technology
CN108570897A (en) A kind of paving method of pavement of road base
CN101255044A (en) Preparation of recycled road construction material from waste concrete and its preparation method and construction method
WO2025140510A1 (en) Soil solidifying agent, layered pavement structure and construction method therefor
CN113699852A (en) Environment-friendly high-strength solidified soil construction process
CN103011729A (en) Method for controlling pavement dust pollution of transportation road in mining area
CN101429746A (en) Road paving method and stirring machine used in the same
CN211472012U (en) Signal lamp crossing filling type composite pavement
CN112523021A (en) Cement soil roadbed cushion for highway engineering and construction process and detection method thereof
CN105064163A (en) Cement stabilization macadam base layer ultrahigh reverse slope section one-time molding construction method
CN114808586B (en) Construction method for asphalt pavement anti-cracking in severe cold region
CN103420645A (en) Cement and diatomite stabilized desert sand mixture for constructing Niger desert highway
CN115745482A (en) Preparation method and application of soil-concreted rock composite material for roadbed base layer
Congress Guidelines for soil and granular material stabilization using cement, lime & fly ash
CN110904757A (en) Construction method of lime soil roadbed
CN109796173A (en) A kind of cement stabilized macadam alloy slag aggregate and its application

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131204