CN102493308A - Bio-enzyme modified roller compacted concrete road engineering construction technology - Google Patents

Bio-enzyme modified roller compacted concrete road engineering construction technology Download PDF

Info

Publication number
CN102493308A
CN102493308A CN2011104147887A CN201110414788A CN102493308A CN 102493308 A CN102493308 A CN 102493308A CN 2011104147887 A CN2011104147887 A CN 2011104147887A CN 201110414788 A CN201110414788 A CN 201110414788A CN 102493308 A CN102493308 A CN 102493308A
Authority
CN
China
Prior art keywords
biology enzyme
road
engineering construction
bio
construction technology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104147887A
Other languages
Chinese (zh)
Inventor
孙瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XIUSHAN BRANCH CHONGQING KANGLU TECHNOLOGY CO LTD
Original Assignee
XIUSHAN BRANCH CHONGQING KANGLU TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XIUSHAN BRANCH CHONGQING KANGLU TECHNOLOGY CO LTD filed Critical XIUSHAN BRANCH CHONGQING KANGLU TECHNOLOGY CO LTD
Priority to CN2011104147887A priority Critical patent/CN102493308A/en
Publication of CN102493308A publication Critical patent/CN102493308A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a bio-enzyme modified roller compacted concrete road engineering construction technology in which bio-enzyme is used as a curing agent and which is low in construction cost, and is easy to implement, pollution-free, low-carbon and environment-friendly. The technology has the advantages that a road base has high intensity and water stability and a good effect of stabilizing and curing soil. Compared with the conventional road building material, a bio-enzyme road is high in load carrying property, good in road performance, and high in construction speed, and low in cost, and easy to construct; and compared with the conventional road building technology, a bio-enzyme road engineering construction technology can save fund by 10 to 20 percent, and has obvious economic benefit and social benefit; the road is easy to cure, and the bio-enzyme road engineering construction technology greatly reduces the using amount of lime and cement, so the resources are saved; the used materials are mostly waste slag, spoil, hole slag, building slag and other waste materials, damage to an ecological environment is reduced, and the bio-enzyme modified roller compacted concrete road engineering construction technology has obvious economic benefit and social benefit.

Description

Biology enzyme modification roller compacted concrete highway engineering construction technology
Technical field
The present invention relates to road construction technology, particularly a kind of biology enzyme modification roller compacted concrete highway engineering construction technology.
Background technology
At present, the highway in China construction is advanced by leaps and bounds, and invests huge.It is the semi-rigid type base of main material that sub-surface adopts with lime, flyash, cement and rubble more; Development along with highway construction; Consumption to constructional materialss such as sand, stones is also increasing, makes these natural resources day by day poor, and its exploitation is also more and more serious to the destruction of natural environment.Therefore, continually develop and utilize some new constructional materialss, the friendly type of built environment, resource-conserving highway are of great practical significance.
Dry discharge fly ash and desulfurated plaster that the patent No. 200410008727.0 has been produced when disclosing " a kind of soil-solidified-agent that is used for road construction " promptly with inferior coal of power plant burning or brown coal are main component; Participating in quicklime and/or cement, the plaster of paris, aluminum sulfate or alunite forces to mix to form; This method construction is complicated, and structure is unstable, damages easily; Life-span is not long, haves much room for improvement.
Summary of the invention
Technical problem to be solved by this invention provides a kind of biology enzyme modification roller compacted concrete highway engineering construction technology, and promptly providing a kind of is curing compound with the biology enzyme, builds cheap, easy, the pollution-free and low-carbon environment-friendly highway engineering construction technology of construction.
For solving the problems of the technologies described above, the technical scheme that the present invention adopted is that the construction technology step is following.
1. material is prepared.
A, raw material are prepared: prepare following mix: bio-modification agent, flexible fiber, coarse aggregate, sand, cement and biology enzyme, wherein mix material proportioning is: bio-modification agent: flexible fiber: coarse aggregate: sand: cement=2:1:1650:495:250.
B, mixed material mix and stir: at first with bio-modification agent, flexible fiber, coarse aggregate, sand, cement according to the proportioning of 2:1:1650:495:250 force dry mixing and; Then dry mixing with after material on evenly spray biology enzyme solution, the proportioning of biology enzyme and mixed material is 1L biology enzyme curing compound: 10m 3Mixed material then fully carries out wet-mixing and subsequent use.
2. former roadbed arrangement: at first carry out former roadbed roadbed arrangement, remove surperficial weeds, foreign material, soft base is handled, suitably changed and fill out, fully roll, recover center line, check and accept absolute altitude, planeness, carry out the flexure detection.
3. biology enzyme solidified earth base layer construction: spray 0.5 ‰ biology enzyme solution, static pressure is 2 times simultaneously.
4. descend the seal construction: spray a certain amount of water in biology enzyme solidified earth substrate surface; Artificial spreading 10-20mm rubble was to substrate surface after the surface reached certain degree of wetting; Reach 98% above coverage scale, then it is carried out vibroroller cmpacting, reach rubble and be embedded in substrate surface with the above pressure road of 16T; Cement paste spreading to the macadam that is in harmonious proportion again is surperficial, and cement paste is prepared according to 50kg/10m 2Prepare and spreading, require the compound concentration consistent and uniform, surperficial application rate reaches 100%.
5. modification grinding coagulation soil layer construction.
A, material pave: carry out paving operation immediately after the construction of following seal finishes, with after mixing and stirring qualified material and being transported to the scope of operation, adopt manual work to pave, flatten; Should confirm vertical and horizontal gradient and thickness before paving, even, the linear smoothness of accomplishing to pave does not have obviously low-lying and protuberance; Check the situation of gathering materials constantly; Should in time reject if any leaf, adhesive tape, over dimensioning stone, bulk foreign matter such as gather materials, check elevation, width, horizontal wall inscription, longitudinal gradient at last, accurately put the road type in order.
B, roll: pave length for rolling length with 20-30m,, can suitably shorten it and roll length if dry; It rolls length otherwise also answer proper extension, when the moisture content of material during near best saturation state, with 20T vibratory roller static pressure 2 times; Bulge, depression, material segregation are dealt with; Low frequency vibration rolls twice then, and dither rolls twice again, twice of last static pressure; The overlapping width of wheelmark should be greater than 10cm during the road roller operation, and rolling speed should be controlled at 0.5-1.0km/h, and nature, smoothness, attractive in appearance should be accomplished in the joint between per two sections of rolling, and do not have tangible seam phenomenon.
6. go up seal construction: after rolling end, with cement paste, biology enzyme modifier and fine sand according to the ratio of 1:1:1 be in harmonious proportion the back evenly spreading fill the road surface hole to road surface, eliminate the group of spending, the cloth trace is swept in manual work.
7. health is checked and accepted: after full-scale construction finishes; The watering health got final product in good time open to traffic in 5 days; The open initial stage of traffic should be established the special messenger and carried out the traffic clearance; Progressively let pass according to dilly → light type agricultural vehicle → load-carrying agri-vehicle → light truck → truck order in principle, between blanking time be 3 days, and then inspect for acceptance.
The invention has the beneficial effects as follows that the roadbase that biology enzyme is reinforced has higher intensity and water stability, has good stable curing effect to soil.Compare with method with traditional road materials such as cement stabilizing sand, biology enzyme road load-carrying properties are high, and pavement performance is good, sensation steadily, do not have jolt, tire makes an uproar little; Construction technology is simple, does not need special construction machinery, and quality requirement is all satisfied in plantmix and road-mix method construction, and speed of application is fast; Cost is low, compares with traditional road building technology, and the biology enzyme highway engineering construction technology 10-20% that can economize on the use of funds has remarkable economic efficiency and social benefit; Maintenance is simple, stability is high, pollution-free, the not blowdown of biology enzyme highway engineering construction technology, nontoxic, nothing corrosion; Really accomplished the strong basis sake; The biology enzyme road building technology has reduced lime, cement consumption significantly, thereby economizes on resources, and mostly the material that adopts is waste, spoir, hole slag, builds obsolete materials such as slag; Reduced destruction, had remarkable economic efficiency and social benefit ecological environment.
Description of drawings
Accompanying drawing is biological enzyme modification roller compacted concrete road structure sketch map.
Among the figure: 1. go up seal, 2. modification grinding coagulation soil layer 3. descends seal, 4. biology enzyme solidified earth basic unit, 5. former roadbed.
The specific embodiment
Be described further below in conjunction with the accompanying drawing specific embodiments of the invention.
In July, 2010, the inventor has done the engineering construction of biology enzyme modification roller compacted concrete actual road test property on the kiwi fruit garden road in village oneself, two river mouth, township, Cenxi, county, the Xiushan Mountain, Chongqing City, the construction long 2100m in road surface.Construction sequence is following:
At first prepare material, the good biological modifier of preparation, flexible fiber, coarse aggregate, sand, cement and biology enzyme, wherein mix material proportioning is: bio-modification agent: flexible fiber: coarse aggregate: sand: cement=2:1:1650:495:250.Carry out earlier dry mixing with, be about to the said ratio material and force to mix and stir, spray biology enzyme then, promptly dry mixing with after material on evenly spray biology enzyme solution, the proportioning of biology enzyme and mixed material is 1L biology enzyme curing compound: 10m 3Mixed material, spray fully carry out behind the biology enzyme wet-mixing with.
Carry out former roadbed 5 roadbeds arrangement simultaneously, remove surperficial weeds, foreign material, soft base is handled, suitably changed and fill out, fully roll, recover center line, check and accept absolute altitude, planeness, carry out the flexure detection; Spray 0.5 ‰ biology enzyme solution then, static pressure is 2 times simultaneously, carries out biology enzyme solidified earth base layer construction 4; Then descend seal 3 constructions, spray a certain amount of water in substrate surface before the construction, make former roadbed 5 surfaces reach certain degree of wetting; Artificial again spreading 10-20mm rubble is to substrate surface; Reach 98% above coverage scale, carry out vibroroller cmpacting, reach rubble and be embedded in substrate surface with the 20T road roller; Cement paste spreading to the macadam that then is in harmonious proportion is surperficial, and cement paste is prepared according to 50kg/10m 2Prepare and spreading, the compound concentration consistent and uniform, surperficial application rate reaches 100%.
Carry out 2 constructions of modification grinding coagulation soil layer after 3 constructions of following seal finish immediately, at first carry out paving operation,, can only carry out that manual work paves and levelling because the mountain construction operating condition is limited.Confirm good vertical and horizontal gradient and thickness before paving, even, the linear smoothness of accomplishing to pave does not have obviously low-lying and protuberance.The inspection situation of gathering materials is constantly in time rejected impurity such as leaf, adhesive tape, over dimensioning stone, bulk foreign matter such as gather materials, and checks elevation, width, horizontal wall inscription, longitudinal gradient then, accurately puts the road type in order; When the moisture content of material during near best saturation state, roll, roll length 30m; At first use 20T vibratory roller static pressure 2 times, bulge, depression, material segregation are dealt with, low frequency vibration rolls twice then; Then dither rolls twice, last static pressure 2 times, and the overlapping width of wheelmark is greater than 10cm during operation; Rolling speed is 1.0km/h, checks that at any time whether two joints between the section of rolling are natural, smooth, attractive in appearance, have or not tangible seam phenomenon.
After rolling end; And then go up seal construction, with cement paste, biology enzyme modifier and a small amount of fine sand be in harmonious proportion to the even spreading of certain proportion to road surface, filling road surface hole; Accomplish not have flower group, the cloth trace is swept in no obvious manual work, cement paste is according to 50kg/10m 2, biology enzyme modifier is according to 2kg/m 3Prepare, carry out an acceptance inspection at last.
After full-scale construction finishes, watering health 5 days, open to traffic then; Initial stage establishes the special messenger and carries out the traffic clearance; Progressively let pass according to dilly → light type agricultural vehicle → load-carrying agri-vehicle → light truck → truck order, between blanking time be 3 days, inspect for acceptance at last.
Use through the inside in 1 year, nowadays, this road surface is stable, groove, no surface porosity, dustless, no rut phenomenon are not cheated in fracture, and behavior in service is good.

Claims (7)

1. biology enzyme modification roller compacted concrete highway engineering construction technology; Its operation is checked and accepted and is formed by material preparation, the arrangement of former roadbed, biology enzyme solidified earth base layer construction, seal construction down, the construction of modification grinding coagulation soil layer, upward seal construction, health; It is characterized in that the described material material in preparing is made up of bio-modification agent, flexible fiber, coarse aggregate, sand, cement and biology enzyme, and its component ratio is biological modifier: flexible fiber: coarse aggregate: sand: cement=2:1:1650:495:250; And with its by proportioning force dry mixing with, then dry mixing with after material on evenly spray biology enzyme solution, the proportioning of biology enzyme and mixed material is 1L biology enzyme curing compound: 10m 3Mixed material.
2. biology enzyme modification roller compacted concrete highway engineering construction technology according to claim 1; It is characterized in that described former roadbed arrangement is at first with former roadbed roadbed arrangement; Remove surperficial weeds, foreign material, soft base is handled, suitably changed and fill out, fully roll; Recover center line, check and accept absolute altitude, planeness, carry out the flexure detection.
3. according to the described biology enzyme modification of claim 1-2 roller compacted concrete highway engineering construction technology, it is characterized in that described biology enzyme solidified earth base layer construction is the surface sprinkling 0.5 ‰ biology enzyme solution after former roadbed arrangement, static pressure is 2 times simultaneously.
4. according to the described biology enzyme modification of claim 1-3 roller compacted concrete highway engineering construction technology; It is characterized in that the construction of described seal down is to spray a certain amount of water in biology enzyme solidified earth substrate surface; Artificial spreading 10-20mm rubble was to substrate surface after the surface reached certain degree of wetting; Reach 98% above coverage scale, then it is carried out vibroroller cmpacting, reach rubble and be embedded in substrate surface with the above pressure road of 16T; Cement paste spreading to the macadam that is in harmonious proportion again is surperficial, and cement paste is prepared according to 50kg/10m 2Prepare and spreading, require the compound concentration consistent and uniform, surperficial application rate reaches 100%.
5. according to the described biology enzyme modification of claim 1-4 roller compacted concrete highway engineering construction technology, it is characterized in that described modification grinding coagulation soil layer construction is to carry out material earlier to pave, carry out paving operation immediately after seal construction instantly finishes; With after mixing and stirring qualified material and being transported to the scope of operation, adopt manual work to pave, flatten, should confirm vertical and horizontal gradient and thickness before paving; Even, the linear smoothness of accomplishing to pave; Do not have obviously low-lying and protuberance, the situation of gathering materials of inspection is constantly in time rejected leaf, adhesive tape, over dimensioning stone, bulk foreign matter such as gather materials; Check elevation, width, horizontal wall inscription, longitudinal gradient at last, accurately put the road type in order; Then roll, pave length for rolling length, when the moisture content of material during near best saturation state with 20-30m; With 20T vibratory roller static pressure 2 times, bulge, depression, material segregation are dealt with, low frequency vibration rolls twice then; Dither rolls twice again, twice of last static pressure; The overlapping width of wheelmark should be greater than 10cm during the road roller operation, and rolling speed should be controlled at 0.5-1.0km/h, and nature, smoothness, attractive in appearance should be accomplished in the joint between per two sections of rolling, and do not have tangible seam phenomenon.
6. according to the described biology enzyme modification of claim 1-5 roller compacted concrete highway engineering construction technology; It is characterized in that the construction of described upward seal is after rolling end; With cement paste, biology enzyme modifier and fine sand according to the ratio of 1:1:1 be in harmonious proportion the back evenly spreading fill the road surface hole to road surface.
7. biology enzyme modification roller compacted concrete highway engineering construction technology according to claim 1; It is characterized in that it is after full-scale construction finishes that described health is checked and accepted, watering health 5 days, open to traffic again; The open initial stage establishes the special messenger and carries out the traffic clearance; Progressively let pass according to dilly → light type agricultural vehicle → load-carrying agri-vehicle → light truck → truck order, whenever increased by one type of vehicle, and then inspect for acceptance at a distance from 3 days.
CN2011104147887A 2011-12-13 2011-12-13 Bio-enzyme modified roller compacted concrete road engineering construction technology Pending CN102493308A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104147887A CN102493308A (en) 2011-12-13 2011-12-13 Bio-enzyme modified roller compacted concrete road engineering construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104147887A CN102493308A (en) 2011-12-13 2011-12-13 Bio-enzyme modified roller compacted concrete road engineering construction technology

Publications (1)

Publication Number Publication Date
CN102493308A true CN102493308A (en) 2012-06-13

Family

ID=46185164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104147887A Pending CN102493308A (en) 2011-12-13 2011-12-13 Bio-enzyme modified roller compacted concrete road engineering construction technology

Country Status (1)

Country Link
CN (1) CN102493308A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912804A (en) * 2012-11-20 2013-02-06 长沙理工大学 Biological enzyme soil solidification-based side slope ecological protection method
CN103882788A (en) * 2014-03-12 2014-06-25 湖南瑞霦科技有限公司 Road building method based on modified roller compacted concrete pavement on enzyme soil solidified base layer
CN103882787A (en) * 2014-03-12 2014-06-25 湖南瑞霦科技有限公司 Pavement structure based on modified roller compacted concrete pavement on enzyme soil solidified base layer
CN104152148A (en) * 2014-07-16 2014-11-19 中南大学 Method for preparing pavement base material by stabilizing iron tailings by novel soil stabilizer
CN108677667A (en) * 2018-03-26 2018-10-19 美尚生态景观股份有限公司 A kind of method of constructing roadway based on biological enzyme soil-solidified-agent
CN109914178A (en) * 2019-03-06 2019-06-21 浙江工业大学 A kind of biological enzyme curing materials integration paved roads construction method
CN110725175A (en) * 2019-09-30 2020-01-24 杭州园林设计院股份有限公司 Novel sandy soil pavement
CN111501455A (en) * 2020-04-23 2020-08-07 山东交通学院 Construction process for reinforcing roadbed by combining biological enzyme curing material with cured powder soil roadbed and compacted sand piles
CN111877072A (en) * 2020-08-05 2020-11-03 山东鲁桥建设有限公司 Method for solidifying new and old roadbed joint by using biological enzyme material
CN112555503A (en) * 2020-12-01 2021-03-26 上海宝冶集团有限公司 Biological enzyme curing method for backfilling pipeline groove

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04237702A (en) * 1991-01-21 1992-08-26 Tsutomu Honma Paving method
CN1156775A (en) * 1996-10-07 1997-08-13 北京大康技术发展公司 Solidifying enzyme building material and use thereof
CN101250018A (en) * 2007-08-17 2008-08-27 顾鹤雷 Method for treating silt, sludge and/or nocuous hurtful solid waste by employing biological cured protease and use of product thereof
CN201109894Y (en) * 2007-08-06 2008-09-03 杨毅男 Road structure made using soil solidifying agent
CN102092916A (en) * 2010-12-16 2011-06-15 无锡利得生态环境科技有限公司 Biological solidification and stabilization method of bottom mud in riverways and lakes

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04237702A (en) * 1991-01-21 1992-08-26 Tsutomu Honma Paving method
CN1156775A (en) * 1996-10-07 1997-08-13 北京大康技术发展公司 Solidifying enzyme building material and use thereof
CN201109894Y (en) * 2007-08-06 2008-09-03 杨毅男 Road structure made using soil solidifying agent
CN101250018A (en) * 2007-08-17 2008-08-27 顾鹤雷 Method for treating silt, sludge and/or nocuous hurtful solid waste by employing biological cured protease and use of product thereof
CN102092916A (en) * 2010-12-16 2011-06-15 无锡利得生态环境科技有限公司 Biological solidification and stabilization method of bottom mud in riverways and lakes

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
付崇仁等: "新材料在铁路货场地面硬化中的应用", 《铁道货运》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912804A (en) * 2012-11-20 2013-02-06 长沙理工大学 Biological enzyme soil solidification-based side slope ecological protection method
CN103882788B (en) * 2014-03-12 2015-10-28 湖南瑞霦科技有限公司 Based on the method for constructing roadway of the modification roller compacted concrete surface layer of enzyme soil cured substrate layer
CN103882788A (en) * 2014-03-12 2014-06-25 湖南瑞霦科技有限公司 Road building method based on modified roller compacted concrete pavement on enzyme soil solidified base layer
CN103882787A (en) * 2014-03-12 2014-06-25 湖南瑞霦科技有限公司 Pavement structure based on modified roller compacted concrete pavement on enzyme soil solidified base layer
CN103882787B (en) * 2014-03-12 2015-10-28 湖南瑞霦科技有限公司 Based on the road structure of the modification roller compacted concrete surface layer of enzyme soil cured substrate layer
CN104152148B (en) * 2014-07-16 2018-05-01 中南大学 Soil curing agent stablizes the method that iron tailings prepares road surface base layer material
CN104152148A (en) * 2014-07-16 2014-11-19 中南大学 Method for preparing pavement base material by stabilizing iron tailings by novel soil stabilizer
CN108677667A (en) * 2018-03-26 2018-10-19 美尚生态景观股份有限公司 A kind of method of constructing roadway based on biological enzyme soil-solidified-agent
CN109914178A (en) * 2019-03-06 2019-06-21 浙江工业大学 A kind of biological enzyme curing materials integration paved roads construction method
CN110725175A (en) * 2019-09-30 2020-01-24 杭州园林设计院股份有限公司 Novel sandy soil pavement
CN111501455A (en) * 2020-04-23 2020-08-07 山东交通学院 Construction process for reinforcing roadbed by combining biological enzyme curing material with cured powder soil roadbed and compacted sand piles
CN111877072A (en) * 2020-08-05 2020-11-03 山东鲁桥建设有限公司 Method for solidifying new and old roadbed joint by using biological enzyme material
CN112555503A (en) * 2020-12-01 2021-03-26 上海宝冶集团有限公司 Biological enzyme curing method for backfilling pipeline groove

Similar Documents

Publication Publication Date Title
CN102493308A (en) Bio-enzyme modified roller compacted concrete road engineering construction technology
CN107059573B (en) Construction method for solidifying soil body as road water stabilization layer
CN104402339B (en) The constructional method of pervious concrete
CN104891888B (en) A kind of imitative stone material environment-friendly concrete pavior brick and its manufacture method
CN109914178B (en) Construction method for integrally paving road by using bio-enzyme curing material
CN103882788B (en) Based on the method for constructing roadway of the modification roller compacted concrete surface layer of enzyme soil cured substrate layer
CN107419644A (en) It is a kind of to be used as Tourism Ecological road, the construction technology of rural highway by the use of soil body solidification
CN107827409B (en) Permeable road and construction method thereof
CN105924124A (en) Soil stabilizer for reinforcing roadbed base
CN105386381A (en) Pickaxe crushing and grouting recycling method for old cement concrete pavement
CN105133452A (en) Road three-slag base in-situ cold regeneration construction method
CN101250044A (en) Road subbase course material and method for preparing same
CN101624275A (en) Pavement material adopting regenerative raw materials including construction wastes and discarded glass to replace sand and stone
CN100570059C (en) The job practices of compound consolidated soil sub-surface
CN112830737A (en) Multi-admixture steel slag lean concrete base layer material and application thereof
CN106517944A (en) Solidified granular soil produced by utilizing waste and old materials from building project
CN204940039U (en) Plant stone Bridge Surface Paving by Cement structure for one kind
CN104529322A (en) Iron tailings roller compacted concrete for pavement
CN204589746U (en) A kind of composite road surface structure being applicable to saturated dredger soft soil area Heavy Traffic condition
CN103242013A (en) Low-quality-flyash concrete pavement material and construction method thereof
CN111041929A (en) Light-emitting pervious concrete road based on recycled aggregate and construction method thereof
CN202492776U (en) Compound ion soil curing agent and road structure paved by acetylene sludge
CN104878672A (en) Stone-planted cement concrete bridge deck paving structure and method
CN204185743U (en) A kind of Desulphurization roadbed cement pavement structure
CN205134120U (en) Super thick cement stabilized macadam base

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120613