CN104790989A - Device and method for releasing anchoring of mining chemical anchor rope - Google Patents

Device and method for releasing anchoring of mining chemical anchor rope Download PDF

Info

Publication number
CN104790989A
CN104790989A CN201510134723.5A CN201510134723A CN104790989A CN 104790989 A CN104790989 A CN 104790989A CN 201510134723 A CN201510134723 A CN 201510134723A CN 104790989 A CN104790989 A CN 104790989A
Authority
CN
China
Prior art keywords
anchor
anchor cable
cartridge bag
special
mozzle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510134723.5A
Other languages
Chinese (zh)
Other versions
CN104790989B (en
Inventor
张农
张天池
徐骁勇
潘东江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201510134723.5A priority Critical patent/CN104790989B/en
Publication of CN104790989A publication Critical patent/CN104790989A/en
Priority to AU2015387576A priority patent/AU2015387576B2/en
Priority to PCT/CN2015/098032 priority patent/WO2016150211A1/en
Application granted granted Critical
Publication of CN104790989B publication Critical patent/CN104790989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Piles And Underground Anchors (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses a device and method for releasing anchoring of a mining chemical anchor rope. The device and method are suitable for roadway anchoring releasing operation. The device mainly comprises four parts including a chemical bag, a flow guide pipe, a specially-made anchor ring and a throttle valve. Acid liquor in the chemical bag is led into a gap between the specially-made anchor ring and the anchor rope through the flow guide pipe, the anchor rope is corroded and weakened through the acid liquor, and waste liquor generated after a reaction flows out through a flow guide hole in the lower side of the specially-made anchor ring. Then, the anchoring releasing effect is achieved through the hysteresis mining pressure. The corrosion speed can be set by controlling the flowing speed of the throttle valve or adjusting the concentration of the acid liquor of the chemical bag to adjust the anchor rope failure time. By means of the device, the anchoring releasing construction technology is simplified, and the labor intensity of workers is reduced; in addition, the anchoring failure time can be artificially controlled, the safety of the anchoring releasing procedure is improved, and the device is simple in structure and easy to popularize.

Description

A kind of mining chemical anchor cable moves back anchor device and method
Technical field
The present invention relates to a kind of mining chemical anchor cable and move back anchor device and method, what be particularly useful for tunnel moves back anchor operation.
Background technology
The supporting of coal road bolting rope is the support pattern that China generally adopts, and it has the advantages such as easy and simple to handle, supporting effect is good, but also can cause the outstanding top of face end larger area, and cause termination methane accumulation, this brings great hidden danger to top board and gas administration.Thus how to ensure that top board is not caving before work plane pushes through, being caving in time after work plane pushes through is the problem that coal roadway support needs solution badly.For this reason, often carry out in coal mining activity process moving back anchor operation.
Generally adopt mechanical type to move back anchor at present, mainly there is following problem: after moving back anchor, top board loses anchored force immediately, easily roof fall occurs; Move back anchor process to stretch the meaning, add bulk caving risk; Move back anchor weak effect, efficiency is low, and anchor cable decortication takes place frequently; Move back anchor arrangement heavier, not easy to operate, cost is higher, uses limited.Therefore need badly and propose a kind of Novel disk withdrawal anchor device and method, solve an above-mentioned difficult problem.
Summary of the invention
Technical problem: the object of the invention is the defect of moving back anchor method for existing machinery formula, proposes a kind of mining chemical anchor cable and moves back anchor device and method, utilize the chemical anchor cable manual control anchoring body out-of-service time, thus reach the effect that safety moves back anchor.
Technical scheme: mining chemical anchor cable of the present invention moves back anchor device, comprise and be set on lockset on anchor cable revealed section and pallet, special anchor ring is provided with between described lockset and pallet, the radial direction of described special anchor ring has asymmetric two pod apertures up and down, mozzle is provided with in a pod apertures on top, mozzle is connected with the cartridge bag be located on top board, and cartridge bag is the mix acid liquor of 5 ~ 12mol/L built with concentration; Described mozzle is provided with choke valve.
Use the mining chemical anchor cable of said apparatus to move back anchor method, comprise the steps:
A. the cartridge bag be connected with mozzle and special anchor ring is prepared on ground;
When b. installing anchor cable, be arranged between lockset and pallet by special anchor ring, other operation is identical with anchor cable installation procedure;
C., during working face extraction, delayed hydraulic support column one cuts dark, is fixed on by cartridge bag on the top board of anchor cable pallet outside;
D. the pod apertures of one end of mozzle with special anchor ring top is connected; Acid solution in cartridge bag is flow automatically under gravity, and the pod apertures through mozzle, special anchor ring top enters in the space of anchor cable and special anchor ring, corrodes anchor cable; Reacted waste liquid is flowed out by the pod apertures on the downside of special anchor ring;
E. install warning line at delayed hydraulic support column 0.5m place, forbid that personnel cross, prevent the mix acid liquor drippage harm workers ' health in cartridge bag;
F. anchor cable is by after acid liquid corrosion, and tensile strength reduces greatly, utilizes delayed mining pressure afterwards, realizes moving back anchor;
G. treat that hydraulic support is pushed ahead one and cut dark, repeat c, d, e, until complete the back production of whole work plane.
The volume of described cartridge bag is 100 ~ 500mL, and the height of cartridge bag is identical with anchor cable pallet height.
Acid solution hydrochloric acid, nitric acid or sulfuric acid solution in described cartridge bag.
Described special anchor ring external diameter 5 ~ 30mm larger than anchor cable lock external diameter, internal diameter 5 ~ 10mm larger than anchor cable diameter.
By regulating choke valve setting acid solution flow velocity, the out-of-service time controlling rope erosion is between 1 ~ 12 hour.
Beneficial effect: owing to have employed technique scheme, the present invention compared with prior art tool has the following advantages:
1. utilize strong acid fast erosion anchor cable, weaken the tensile strength of anchor cable.Utilize delayed mining pressure afterwards, reach and destroy the effect of anchor cable, save strong acid consumption, and workman to move back anchor operating environment safer;
2. by controlling acid strength or flow velocity, the controlled of failure of cable time can be realized;
3. move back anchor ring large compared with lockset diameter, reduce the stress of lockset to pallet and concentrate, improve the force environment of pallet;
4. structure of the present invention is simple, is easy to operation, reduces labour intensity, simplify and move back anchor construction technology, is easy to promote.
Accompanying drawing explanation
Fig. 1 is anchor cable sectional structure schematic diagram of the present invention;
Fig. 2 (a) is the top view of the special anchor ring of the present invention;
Fig. 2 (b) is the sectional drawing of the special anchor ring of the present invention.
In figure: 1-anchor cable; 2-cartridge bag; 3-mozzle; 4-choke valve; 5-pod apertures; 6-lockset; The special anchor ring of 7-; 8-pallet; 9-top board.
Detailed description of the invention
Below in conjunction with accompanying drawing, one embodiment of the present of invention are further described:
Mining chemical anchor cable of the present invention moves back anchor device, forms primarily of cartridge bag 2, mozzle 3, stream valve 4, lockset 6, special anchor ring 7 and joint pallet 8.Lockset 6 and pallet 8 are set on anchor cable 1 revealed section, described special anchor ring 7 is located between lockset 6 and pallet 8, the radial direction of described special anchor ring 7 has asymmetric two pod apertures 5 up and down, mozzle 3 is provided with in a pod apertures 5 on top, mozzle 3 is connected with the cartridge bag 2 be located on top board 9, and cartridge bag 2 is the mix acid liquor of 5 ~ 12mol/L built with concentration; Described mozzle 3 is provided with choke valve 4.
Mining chemical anchor cable of the present invention moves back anchor method, and step is as follows:
A. the cartridge bag 2 be connected with mozzle 3 and special anchor ring 7 is prepared on ground; The volume of described cartridge bag 2 is 100 ~ 500mL, and the height of cartridge bag 2 is highly identical with anchor cable pallet 8.Cartridge bag 2 is the hydrochloric acid of 5 ~ 12mol/L, nitric acid or sulfuric acid solution built with concentration, mozzle 3 is equipped with choke valve 4, prepares special anchor ring 7 simultaneously, described special anchor ring 7 external diameter 5 ~ 30mm larger than anchor cable lock external diameter, internal diameter 5 ~ 10mm larger than anchor cable diameter.Have two pod apertures 5 on the top of side of special anchor ring 7 and the bottom of offside, special anchor ring 7, through anti-corrosion treatment, does not react with mixed acid.
When b. installing anchor cable 1 during crossheading driving, be arranged between lockset 6 and pallet 8 by special anchor ring 7, other operation is identical with anchor cable 1 installation procedure;
C., during working face extraction, delayed hydraulic support column one cuts dark 1m, and the cartridge bag 2 that will be connected to mozzle 3 is fixed on the top board 9 of anchor cable pallet 8 outside;
D. the pod apertures 5 of one end of mozzle 3 with special anchor ring 7 top is connected; Acid solution in cartridge bag 2 is flow automatically under gravity, and the pod apertures 5 through mozzle 3, special anchor ring 7 top enters in the space of anchor cable 1 and special anchor ring 7, corrodes anchor cable 1; Reacted waste liquid is flowed out by the pod apertures 5 on the downside of special anchor ring 7; Acid solution flow velocity is set, to control the rope erosion out-of-service time by regulating choke valve 4; By regulating choke valve 4 to set acid solution flow velocity, the out-of-service time controlling anchor cable 1 corrosion is between 1 ~ 12 hour.
E. install warning line at delayed hydraulic support column 0.5m place, forbid that personnel cross, prevent the mix acid liquor drippage harm workers ' health in cartridge bag 2;
F. anchor cable 1 is by after acid liquid corrosion, and tensile strength reduces greatly, utilizes delayed mining pressure afterwards, realizes moving back anchor effect;
G. treat that hydraulic support is pushed ahead one and cut dark, repeat c, d, e, until complete the back production of whole work plane.

Claims (5)

1. a mining chemical anchor cable moves back anchor device, comprise and be set on lockset (6) on anchor cable (1) revealed section and pallet (8), it is characterized in that: between described lockset (6) and pallet (8), be provided with special anchor ring (7), the radial direction of described special anchor ring (7) has asymmetric two pod apertures (5) up and down, mozzle (3) is provided with in a pod apertures (5) on top, mozzle (3) is connected with the cartridge bag (2) be located on top board (9), and cartridge bag (2) is the mix acid liquor of 5 ~ 12mol/L built with concentration; Described mozzle (3) is provided with choke valve (4).
2. use the mining chemical anchor cable of device described in claim 1 to move back an anchor method, it is characterized in that comprising the steps:
A. the cartridge bag (2) be connected with mozzle (3) and special anchor ring (7) is prepared on ground;
When b. installing anchor cable (1), be arranged on by special anchor ring (7) between lockset (6) and pallet (8), other operation is identical with anchor cable (1) installation procedure;
C. during working face extraction, delayed hydraulic support column one cuts dark, is fixed on by cartridge bag (2) on the outside top board (9) of anchor cable pallet (8);
D. one end of mozzle (3) is connected with the pod apertures (5) on special anchor ring (7) top; Acid solution in cartridge bag (2) is flow automatically under gravity, and the pod apertures (5) through mozzle (3), special anchor ring (7) top enters in the space of anchor cable (1) and special anchor ring (7), corrodes anchor cable (1); Reacted waste liquid is flowed out by the pod apertures (5) of special anchor ring (7) downside;
E. install warning line at delayed hydraulic support column 0.5 m place, forbid that personnel cross, prevent the mix acid liquor drippage harm workers ' health in cartridge bag (2);
F. anchor cable (1) is by after acid liquid corrosion, and tensile strength reduces greatly, utilizes delayed mining pressure afterwards, realizes moving back anchor;
G. treat that hydraulic support is pushed ahead one and cut dark, repeat c, d, e, until complete the back production of whole work plane.
3. the mining chemical anchor cable of one according to claim 2 moves back anchor method, it is characterized in that: the volume of described cartridge bag (2) is 100 ~ 500mL, and the height of cartridge bag (2) is highly identical with anchor cable pallet (8).
4. the one according to Claims 2 or 3 is mining, and chemical anchor cable moves back anchor method, it is characterized in that: acid solution hydrochloric acid, nitric acid or sulfuric acid solution in described cartridge bag (2).
5. the mining chemical anchor cable of one according to claim 2 moves back anchor device and method, it is characterized in that: by regulating choke valve (4) setting acid solution flow velocity, the out-of-service time that control anchor cable (1) is corroded is between 1 ~ 12 hour.
CN201510134723.5A 2015-03-25 2015-03-25 Device and method for releasing anchoring of mining chemical anchor rope Active CN104790989B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201510134723.5A CN104790989B (en) 2015-03-25 2015-03-25 Device and method for releasing anchoring of mining chemical anchor rope
AU2015387576A AU2015387576B2 (en) 2015-03-25 2015-12-21 Mining chemical anchor cable anchor-unhooking apparatus and method
PCT/CN2015/098032 WO2016150211A1 (en) 2015-03-25 2015-12-21 Mining chemical anchor cable anchor-unhooking apparatus and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510134723.5A CN104790989B (en) 2015-03-25 2015-03-25 Device and method for releasing anchoring of mining chemical anchor rope

Publications (2)

Publication Number Publication Date
CN104790989A true CN104790989A (en) 2015-07-22
CN104790989B CN104790989B (en) 2017-04-12

Family

ID=53556123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510134723.5A Active CN104790989B (en) 2015-03-25 2015-03-25 Device and method for releasing anchoring of mining chemical anchor rope

Country Status (3)

Country Link
CN (1) CN104790989B (en)
AU (1) AU2015387576B2 (en)
WO (1) WO2016150211A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016150211A1 (en) * 2015-03-25 2016-09-29 中国矿业大学 Mining chemical anchor cable anchor-unhooking apparatus and method
CN114673538A (en) * 2022-04-21 2022-06-28 天地科技股份有限公司 Anchor cable withdrawal device and anchor cable withdrawal method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111272553B (en) * 2020-03-16 2023-06-02 天地科技股份有限公司 Anchor rod stress corrosion test device, in-situ mechanical test system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4732059A (en) * 1986-12-30 1988-03-22 A.T. & G. Company Driver for reinforcement bar chemical anchor
JP2009256881A (en) * 2008-04-11 2009-11-05 E Planner Kk Construction method of net for preventing fall of exfoliation concrete
CN102644470A (en) * 2012-04-18 2012-08-22 李治中 General energy-saving quick anchoring method and general energy-saving quick anchor rod
CN202544884U (en) * 2012-04-18 2012-11-21 李治中 Simple, quick and reliable anchor rod
CN203655322U (en) * 2014-01-21 2014-06-18 中国矿业大学 Anchor removing device for anchor rope

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4162133A (en) * 1977-09-21 1979-07-24 The Eastern Company Resin reinforced expansion anchor and method of installation
WO2008051728A2 (en) * 2006-10-19 2008-05-02 Jennmar Corporation A breakable rock bolt
CN201650323U (en) * 2010-03-27 2010-11-24 中国矿业大学 Grouting anchor rope
CN103590843B (en) * 2013-11-21 2015-10-21 山东大学 A kind of full-thread bolt pretightning force bringing device and method of operating can moving back anchor fast
CN203559915U (en) * 2013-11-21 2014-04-23 山东大学 Full-thread anchor bolt pre-tightening force applying device capable of automatically returning anchor
CN104790989B (en) * 2015-03-25 2017-04-12 中国矿业大学 Device and method for releasing anchoring of mining chemical anchor rope

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4732059A (en) * 1986-12-30 1988-03-22 A.T. & G. Company Driver for reinforcement bar chemical anchor
JP2009256881A (en) * 2008-04-11 2009-11-05 E Planner Kk Construction method of net for preventing fall of exfoliation concrete
CN102644470A (en) * 2012-04-18 2012-08-22 李治中 General energy-saving quick anchoring method and general energy-saving quick anchor rod
CN202544884U (en) * 2012-04-18 2012-11-21 李治中 Simple, quick and reliable anchor rod
CN203655322U (en) * 2014-01-21 2014-06-18 中国矿业大学 Anchor removing device for anchor rope

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016150211A1 (en) * 2015-03-25 2016-09-29 中国矿业大学 Mining chemical anchor cable anchor-unhooking apparatus and method
CN114673538A (en) * 2022-04-21 2022-06-28 天地科技股份有限公司 Anchor cable withdrawal device and anchor cable withdrawal method

Also Published As

Publication number Publication date
CN104790989B (en) 2017-04-12
AU2015387576B2 (en) 2017-12-07
AU2015387576A1 (en) 2017-03-16
WO2016150211A1 (en) 2016-09-29

Similar Documents

Publication Publication Date Title
CN103321654B (en) The method of flexible air-bag process coal mine roadway roof collapse
CN201232558Y (en) Fully-mechanized mining cutting hole full-section anchored net support
CN104533452B (en) A kind of underground coal mine crushes coal body stagewise grouting strengthening method
CN205189893U (en) Be used for a lane coal column to wearing reinforced (rfd) supporting construction
CN103306714B (en) Gas control method for drilling hole and hole three-purpose in close-range coal seam group bottom drainage roadway
CN103485717A (en) Fully-hydraulic four-arm anchor rod/anchor cable drill carriage
CN115749713B (en) Rock stratum variable frequency pulse seam net fracturing method and equipment
CN102518436A (en) Method for controlling tectonic rock burst in coal mine tunneling
CN107304676A (en) A kind of prevention and controls for leaving bump under coal column
CN104790989A (en) Device and method for releasing anchoring of mining chemical anchor rope
CN105909284B (en) A kind of high working face coal wall caving prevents control method
CN105781590A (en) Technology for disassembling negative rings of TBM (tunnel boring machine) arrival hole
CN105697018A (en) Shaft excavation construction technology
CN110656936A (en) Mine roof directional roof cutting pressure relief method based on static expanding agent
CN203270578U (en) Underground pile foundation pulling device with steel wire rope sleeve clamp
CN202073568U (en) Vertical shaft pipeline fixing device
CN102296974B (en) Rapid maintaining method for broken roof in stope
CN201560775U (en) Temporary support device for coal mine tunneling
CN205778950U (en) A kind of band self-drilling type can recognize that the Bolt System of loosening country rock drill bit
CN115075794A (en) Segmented fracturing coal body pressure relief system and application method
CN103742177B (en) Design method for strong mine pressure roadway support
CN202017505U (en) Pipe roof supporting device
CN206830214U (en) A kind of device for preventing that anchor cable is truncated
CN205733660U (en) A kind of transport erecting device of drilling platforms preventer
CN209925020U (en) Mine dust intelligence control system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 221116 Research Institute of China University of Mining and Technology,, Jiangsu

Applicant after: China University of Mining & Technology

Address before: 221116 Research Institute, China University of Mining and Technology, Xuzhou University, Jiangsu, China,

Applicant before: China University of Mining & Technology

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant