CN104790569A - 一种免模剪力墙及其施工方法 - Google Patents
一种免模剪力墙及其施工方法 Download PDFInfo
- Publication number
- CN104790569A CN104790569A CN201510202754.XA CN201510202754A CN104790569A CN 104790569 A CN104790569 A CN 104790569A CN 201510202754 A CN201510202754 A CN 201510202754A CN 104790569 A CN104790569 A CN 104790569A
- Authority
- CN
- China
- Prior art keywords
- concrete
- block
- shear
- concrete prefabricated
- formwork
- Prior art date
Links
- 238000010276 construction Methods 0.000 title abstract description 20
- 238000010792 warming Methods 0.000 claims description 13
- 230000003014 reinforcing Effects 0.000 claims description 8
- 239000000463 materials Substances 0.000 claims description 5
- 238000009415 formwork Methods 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 230000002787 reinforcement Effects 0.000 abstract 2
- 238000010586 diagrams Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 239000010410 layers Substances 0.000 description 3
- 238000000034 methods Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 280000603137 Block as companies 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 230000002708 enhancing Effects 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 239000000203 mixtures Substances 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
Abstract
Description
技术领域
:
[0001] 本发明涉及建筑施工领域,具体指一种免模剪力墙及其施工方法。
背景技术
:
[0002]目前,高层建筑中大多采用现浇混凝土剪力墙作为承重结构,但现浇混凝土剪力墙施工过程中需采用大量模板,耗费大量的人力、物力,施工成本高,施工速度慢,效益低。一般多采用木模板,在生产使用过程中耗费大量的森林资源,回收利用率低,给我国环境带来严重危害。
发明内容
:
[0003] 有鉴于此,本发明提供了一种免模剪力墙。该剪力墙施工工序简单,无需支模、拆模,或者拼装模板,大量节省了人力、物力,减少了施工成本,提高了施工速度,且不对环境造成破坏。
[0004] 为了实现上述目的,本发明采用如下技术方案:一种免模剪力墙,包括混凝土预制侧模块、钢筋笼、现浇混凝土,其特征在于:所述混凝土预制模块上安装了吊装桁架,吊装桁架通过螺帽与混凝土预制模块连接,吊装桁架可拆卸,混凝土预制模块上设置有孔洞,孔洞中插有套管,在所述套管中插入对拉螺栓;其特征还在于:混凝土预制模块上设置至少一个定位件。制作上述免模剪力墙的施工步骤包括:(I)绑扎好钢筋笼后,吊装混凝土预制侧模块至指定位置;(2)拆除桁架,插入套管,安装对拉螺栓并拧紧后浇筑混凝土,待混凝土达到一定强度后,拆除对拉螺栓,最终形成剪力墙。混凝土预制侧模块的大小可根据实际工程所需在工厂进行预制,运输至施工现场再进行吊装和拼接。吊装桁架包括螺帽、吊装桁架支撑钢管、吊装桁架腹杆、桁架紧固螺帽组成,吊装桁架的设置目的在于方便混凝土预制侧模块的吊装,且吊装桁架可以拆卸,拆卸掉吊装桁架后可以进行回收利用,节省资源和施工成本。带吊装桁架的混凝土预制侧模块的制作过程如下:浇筑混凝土预制侧模块混凝土,待混凝土还未完全硬化时,将吊装桁架安装在混凝土预制侧模块表面,使其一端螺帽没入混凝土内,螺帽上还可焊接锚固钢筋,增强吊装桁架与混凝土预制侧模块间的粘结力,待混凝土完全硬化达到强度后,吊装桁架与混凝土预制侧模块形成整体。混凝土预制模块上设置有孔洞,在剪力墙两侧混凝土预制模块吊装完毕后,将套管插入两侧混凝土预制模块上的孔洞,再将对拉螺栓杆插入套管内,在端部放置垫板,拧上螺帽,其中垫板紧靠着混凝土预制侧模块外侧,套管长度为两块垫板之间的净间距。采用上述技术方案的目的在于,拉结剪力墙两侧混凝土预制模块,浇筑混凝土时,抵抗混凝土对剪力墙两侧混凝土预制模块产生的侧压力,保证剪力墙墙体的浇筑质量。为方便混凝土预制侧模块间吊装时安装搭接,在混凝土预制侧模块边缘位置设置至少一个定位件。吊过程中,上下混凝土预制侧模块或左右混凝土预制侧模块靠自身的定位件进行定位安装搭接,使得它们能安装位置精准,搭接连续,不会出现错台现象,保证了剪力墙的整体性能和施工质量,同时也确保整个墙面平整美观。
[0005] 进一步的在本发明技术方案中,混凝土预制侧模块内侧设置保温板。设置保温板的目的在于提高剪力墙的保温隔热性能。
[0006] 进一步的在本发明技术方案中,所述靠近保温板的混凝土预制侧模块上预埋有抗剪连接件,抗剪连接件由高强度、导热系数小的硬质材料制成。抗剪连接件穿过保温板,连接保温板两侧的混凝土预制侧模块和现浇混凝土层,从而对保温板两侧的混凝土预制侧模块和现浇混凝土层产生较好的拉结作用,使得保温板两侧的混凝土预制侧模块和现浇混凝土层能够协同作用,共同受力,提高剪力墙的整体性和受力性能。
[0007] 本发明提供的免模剪力墙,由于采用混凝土预制侧模块作为剪力墙两侧外模板,无需再进行另外的支模、拆模作业,混凝土预制模块可以实现工厂化生产、标准化作业,有效提高了施工效率,有效缩短了构件的施工周期,降低了操作者的劳动强度,节省了施工的成本。另外,混凝土预制侧模块安装有吊装桁架,运输至施工现场即可进行吊装,十分简单方便,吊装桁架可拆卸,拆卸后的吊装桁架可以回收利用,节省施工成本和资源。
[0008] 以下结合附图和具体实施例对本发明进行详细描述,但不作为对本发明的限制。
附图说明
:
[0009] 以下附图中,I为混凝土预制侧模块,2为钢筋笼,3为现浇混凝土,4为螺帽,5为吊装桁架,6为定位件,7为套管,8为对拉螺栓,9为混凝土预制侧模块上孔洞,10为吊装桁架支撑钢管,11为吊装桁架紧固螺帽,12为吊装桁架腹杆,13为保温板,14为抗剪连接件,15为垫块。
[0010] 图1为混凝土预制侧模块整体示意图;
[0011]图2为带吊装桁架的混凝土预制侧模块结构图;
[0012] 图3为吊装桁架结构示意图;
[0013] 图4为吊装后混凝土预制侧模块拼装结构图;
[0014] 图5为对拉螺栓安装示意图;
[0015]图6为免模剪力墙内部结构示意图;
[0016]图7为免模剪力墙整体结构示意图;
[0017]图8为免模剪力墙另一实施例;
[0018] 图9为抗剪连接件示意图;
[0019] 图10为混凝土预制侧模块另一实施例。
具体实施方式
:
[0020] 下面结合本发明实施例中的附图,对本发明实施例中的技术方案作进一步说明。
[0021] 本发明如图1-10所示。
[0022] 参考图1-7所示,一种免模剪力墙,包括混凝土预制侧模块1,钢筋笼2,现浇混凝土 3。混凝土预制侧模块I在工厂制作,其上带有可拆卸吊装桁架5,吊装桁架5与混凝土预制侧模块I间由螺帽连接,吊装桁架5由螺帽4、吊装桁架支撑钢管10,吊装桁架紧固螺帽11,吊装桁架腹杆12组成。混凝土预制侧模块I四周均设置有定位件6,施工吊装混凝土预制侧模块I至指定位置时,上下或左右混凝土预制侧模块I之间靠定位件6精准定位,确保混凝土预制侧模块间拼接连续,表面平整,不会出现错台现象。混凝土预制侧模块I上还设置有孔洞9,呈梅花状布置。孔洞9的作用在于便于安装对拉螺栓8。剪力墙两侧混凝土预制侧模块I均吊装到位后,拆除吊装桁架5,在孔洞9中插入套管7,在套管7中插入对拉螺栓8并拧紧螺帽,可以在浇筑混凝土时,将两侧混凝土预制侧模块I相互拉结抵抗混凝土对其作用的侧压力,保证墙体的浇筑质量。为防止混凝土预制侧模块制作时的误差或施工时的误差,孔洞9直径略大于套管7外径。对拉螺栓8上设置了垫块15,垫块15紧贴混凝土预制侧模块外侧,套管7的长度为两垫块15之间的净间距,确保浇筑过程中混凝土不会从孔洞9溢出,同时流入孔洞9内的混凝土增加了现浇混凝土 3与混凝土预制侧模块间粘结力。其施工方法为:(I)绑扎好钢筋笼2后,吊装混凝土预制侧模块I至指定位置;(2)拆除吊装桁架5,插入套管7,安装对拉螺栓8并拧紧后浇筑混凝土,待混凝土达到一定强度后,拆除对拉螺栓8,最终形成剪力墙。
[0023] 参考图8-10,一种免模剪力墙,包括混凝土预制侧模块1,钢筋笼2,现浇混凝土 3,保温板13。该免模剪力墙内设置有保温板13,增强了墙体的保温节能效果。保温板13设置在其中一混凝土预制侧模块内侧,如图8所示。为解决保温板13两侧混凝土预制侧模块I和现浇混凝土 3的协同工作问题,在混凝土预制侧模块I上设置抗剪连接件14,。抗剪连接件14预埋在混凝土预制侧模块I上,如图10所示。抗剪连接件14由高强度、导热系数小的硬质材料制成。多个抗剪连接件14将混凝土预制侧模块I和现饶混凝土 3连接,使其共同受力,共同变形,提高了墙体的整体性能。
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510202754.XA CN104790569A (zh) | 2015-04-26 | 2015-04-26 | 一种免模剪力墙及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510202754.XA CN104790569A (zh) | 2015-04-26 | 2015-04-26 | 一种免模剪力墙及其施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104790569A true CN104790569A (zh) | 2015-07-22 |
Family
ID=53555716
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510202754.XA CN104790569A (zh) | 2015-04-26 | 2015-04-26 | 一种免模剪力墙及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104790569A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105317137A (zh) * | 2015-10-14 | 2016-02-10 | 史世英 | 预制墙体、墙板及其施工方法以及预制墙板生产方法 |
CN105544815A (zh) * | 2016-02-07 | 2016-05-04 | 天津鑫德源特能源科技发展有限公司 | 一种现浇筑预制免拆卸整体装配保温外模板装配结构 |
CN106869365A (zh) * | 2017-01-19 | 2017-06-20 | 中国核工业华兴建设有限公司 | 一种带有不规则密集孔洞剪力墙的施工方法 |
WO2018161732A1 (zh) * | 2017-03-07 | 2018-09-13 | 刁宏伟 | 一种带有对拉螺栓的叠合板式夹心保温剪力墙及安装方法 |
CN109184023A (zh) * | 2018-09-13 | 2019-01-11 | 山东斯普瑞节能科技有限公司 | 建筑用墙体保温装饰防火模块复合体系 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05141025A (ja) * | 1991-11-22 | 1993-06-08 | Ohbayashi Corp | 鉄筋コンクリート壁の構築方法 |
CN203795663U (zh) * | 2014-03-07 | 2014-08-27 | 北方工业大学 | 一种具有自保温功能的复合剪力墙 |
-
2015
- 2015-04-26 CN CN201510202754.XA patent/CN104790569A/zh not_active Application Discontinuation
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05141025A (ja) * | 1991-11-22 | 1993-06-08 | Ohbayashi Corp | 鉄筋コンクリート壁の構築方法 |
CN203795663U (zh) * | 2014-03-07 | 2014-08-27 | 北方工业大学 | 一种具有自保温功能的复合剪力墙 |
Non-Patent Citations (1)
Title |
---|
刘金洪 等: "《我是木工能手》", 31 May 2006 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105317137A (zh) * | 2015-10-14 | 2016-02-10 | 史世英 | 预制墙体、墙板及其施工方法以及预制墙板生产方法 |
CN105544815A (zh) * | 2016-02-07 | 2016-05-04 | 天津鑫德源特能源科技发展有限公司 | 一种现浇筑预制免拆卸整体装配保温外模板装配结构 |
CN105544815B (zh) * | 2016-02-07 | 2019-09-03 | 天津鑫德源特能源科技发展有限公司 | 一种现浇筑预制免拆卸整体装配保温外模板装配结构 |
CN106869365A (zh) * | 2017-01-19 | 2017-06-20 | 中国核工业华兴建设有限公司 | 一种带有不规则密集孔洞剪力墙的施工方法 |
CN106869365B (zh) * | 2017-01-19 | 2019-05-10 | 中国核工业华兴建设有限公司 | 一种带有不规则密集孔洞剪力墙的施工方法 |
WO2018161732A1 (zh) * | 2017-03-07 | 2018-09-13 | 刁宏伟 | 一种带有对拉螺栓的叠合板式夹心保温剪力墙及安装方法 |
CN109184023A (zh) * | 2018-09-13 | 2019-01-11 | 山东斯普瑞节能科技有限公司 | 建筑用墙体保温装饰防火模块复合体系 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203546589U (zh) | 钢梁-整体式挑臂预制混凝土桥面板组合梁桥 | |
CN202441391U (zh) | 隧道二次衬砌混凝土安装止水带的端头模板装置 | |
CN103397705A (zh) | 建筑物叠合楼板与钢筋桁架剪力墙的连接结构 | |
CN102071797A (zh) | 纤维增强免抹灰免拆一体化保温模板和外墙保温施工工艺 | |
CN103397696B (zh) | 耐震、预制的钢筋桁架剪力墙混合结构建筑物 | |
CN202380609U (zh) | 一种可进行工业化生产的预拼装轻质墙板 | |
CN203475598U (zh) | 耐震、预制的钢筋桁架剪力墙混合结构建筑物 | |
CN204098253U (zh) | 一种改进型加气混凝土砌块外墙保温结构 | |
CN106703269A (zh) | 一种带钢桁架的预应力混凝土叠合板及制作方法 | |
CN102400506A (zh) | 一种无模板耗能钢板剪力墙及其施工方法 | |
CN104989102A (zh) | 一种改进的混凝土墙、柱施工方法 | |
CN107143034A (zh) | 一种装配式混凝土框架结构梁柱刚性连接节点 | |
CN105019573A (zh) | 一种具有保温功能的预制外墙模板结构体系及其施工方法 | |
CN108360723B (zh) | 一种带立体桁架临时支撑的装配式大模块半焊接叠合梁板结构 | |
CN105064555A (zh) | 叠合装饰层和保温层的结构墙板及施工方法 | |
CN106284655A (zh) | 预制混凝土梁柱栓接连接节点及连接方法 | |
CN105484391A (zh) | 轻质保温grc免拆模板制作保温防水墙体的施工方法 | |
CN103388357B (zh) | 耐震、预制的钢管剪力墙混合结构建筑物 | |
CN105421188A (zh) | 装配式临时道路的施工方法 | |
CN103422620B (zh) | 一种预制中空型钢混凝土柱及其拼接结构和拼接方法 | |
CN204826423U (zh) | 一种预制装配式混凝土构件用钢筋套筒灌浆连接件 | |
CN107542196A (zh) | 预应力混凝土双向叠合板及制作方法 | |
CN104790522B (zh) | 预制装配式型钢混凝土柱—钢梁框架结构体系及施工方法 | |
CN204326337U (zh) | 一种预应力混凝土带肋薄板双向叠合板楼盖 | |
CN105756202A (zh) | 结合叠合楼板的装配式剪力墙齿槽式连接结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
C06 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150722 |
|
RJ01 | Rejection of invention patent application after publication |