CN104766185A CN201510225174.2A CN201510225174A CN104766185A CN 104766185 A CN104766185 A CN 104766185A CN 201510225174 A CN201510225174 A CN 201510225174A CN 104766185 A CN104766185 A CN 104766185A
Authority
CN
China
Prior art keywords
information
module
outage
line
outage information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510225174.2A
Other languages
Chinese (zh)
Other versions
CN104766185B (en
Inventor
范荣奇
王晓鹏
马强
王进
刘传良
张辉
孙其振
慈文斌
雷鸣
廖大鹏
刘军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shandong Electric Power Co Ltd filed Critical State Grid Shandong Electric Power Co Ltd
Priority to CN201510225174.2A priority Critical patent/CN104766185B/en
Publication of CN104766185A publication Critical patent/CN104766185A/en
Application granted granted Critical
Publication of CN104766185B publication Critical patent/CN104766185B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a regional power grid power outage information studying and judging system and method based on power grid power outage characteristics. The system comprises an information collecting module, a line power outage judging module, a date platform file receiving and storing module, a power outage information optimizing module and a client side inquiring module. According to the regional power grid power outage information studying and judging system and method, fault tripping and operation power outage are accurately recognized by combining overhaul application ticket information declared by countries, through the logic relation of switch deflection time and according to the characteristics of fault tripping and operation power outage, invalid power outage information generated by remote signaling jitter is filtered out, the recognition rate of fault tripping and operation power outage is effectively increased, the false alarm rate caused by false sending of signals is decreased, and the accurate rate of the regional power grid power outage information is greatly increased. The regional power grid power outage information studying and judging system and method has important significance on improving the power supply reliability of regional power grids, supervising and executing orderly power consumption measures and starting emergent responses in time, and meanwhile a promoting role is played in improving the normalization level of counties calling EMS data and models.

Description

Area power grid outage information based on grid power blackout characteristic studies and judges system and method
Technical field
The present invention relates to power system automation technology field, specifically a kind of area power grid outage information based on grid power blackout characteristic studies and judges system and method.
Background technology
Power supply reliability refers to the ability of electric power system continued power, is the important indicator of the examination electric power system quality of power supply, reflects the satisfaction degree of power industry to national economy electrical energy demands, become one of standard of a measurement national economy development degree; Power supply reliability can be weighed by following a series of index: the equivalence hour of the average power off time of user, the average frequency of power cut of user, system blackout.The accuracy of power-off event directly determines the accuracy of fail-safe analysis, and the relevant information of therefore correctly measuring power-off event is the key of assessment power supply reliability.
In order to improve power supply reliability, provincial electric power company is necessary to grasp in real time line tripping under 10 ~ 110kV line outage information, particularly inclement weather conditions across the entire province and load loss situation.
At present, the means that provincial electric power company obtains the information of 10 ~ 110kV line outage across the entire province mainly contain three kinds: (1) dispatching system statistical report step by step, the shortcoming of this mode needs province ground county three Levels Scheduling person to notify step by step, add up, gather, real-time is poor, and has disperseed the energy of yardman's accident settlement; (2) sales department 95598 phone call for appeal telephone traffic, the shortcoming of this mode needs to accumulate the circuit that certain telephone traffic could find power failure indirectly, obtaining information not comprehensively, not directly, rapid, be only suitable for the supplementary means as monitoring outage information; (3) run mechanism for monitoring monitoring system, the shortcoming of this mode is that the information of system access and model are complete, can not meet actual needs.
Summary of the invention
For overcoming the deficiency that above-mentioned prior art exists, the invention provides a kind of area power grid outage information based on grid power blackout characteristic and study and judge system and method, it effectively can improve the discrimination had a power failure to fault trip and operation, improves the reliability that area power grid is powered.
The present invention solves the technical scheme that its technical matters takes: a kind of area power grid outage information based on grid power blackout characteristic studies and judges system, it is characterized in that, comprise information acquisition module, line outage judge module, data platform file reception and memory module, outage information optimizes module and client query module;
Described information acquisition module is the information such as the remote signalling of each area power grid, remote measurement, accident are total, interval summation protection act in order to gather, and the relevant information of collection is sent to line outage judge module;
Described line outage judge module carries out seizure and the classification process of outage information according to the criterion that line fault tripping operation and operation have a power failure in order to information such as, interval summation protection act total to the remote signalling received, remote measurement, accident, result is sent in the form of a file data platform file reception and memory module;
Query Result, in order to gather and to store the outage information of each area power grid, sends to outage information to optimize module according to querying condition by described data platform file reception and memory module;
Described outage information is optimized module and is optimized Query Result in order to adopt telesignalling dithering filtration and the measure of repair ticket coupling, and the outage information after optimizing is sent to client query module;
Described client query module, in order on the one hand querying condition information is sent to data platform file reception and memory module, receives on the other hand and optimizes the outage information after module optimization through outage information.
Preferably, described information acquisition module and line outage judge module are configured in the tune side, ground in each area, described data platform file reception and memory module are configured in province's ground two-level scheduler integrated data platform, and described outage information optimizes module and client query module is configured in province's tune side, adjust the information acquisition module of side gather the basic data of each area power grid and send to line outage judge module with being configured in, line outage judge module carries out discriminatory analysis to the basic data gathered, and result is sent to data platform file reception and memory module with document form, carry out gathering and storing after data platform file reception and memory module receive file, economize and adjust by client query module input inquiry condition, Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module, outage information is optimized module and is optimized Query Result and the outage information after optimizing is pushed to client query module.
Preferably, described information acquisition module adjusts the Back ground Information of all 35kV and 110kV transformer stations of EMS system acquisition this area by ground, comprise the information such as remote signalling, remote measurement, accident are total, interval summation protection act, wherein the relevant information of transformer station belonging to company of county adjusts integral system directly to gather by ground county or county turns the mode sent out and gathers; Described line outage judge module is adjust on ground the independent judgment service that the basis of EMS system is developed, the criterion that this judgement service adopts remote signalling displacement, remote measurement sudden change and accident resultant signal to combine, carry out 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and statistics that have a power failure, and differentiation and statistics were sent to data platform file reception and memory module once at interval of five minutes in the form of a file; The file at every turn received carries out gathering and storing by described data platform file reception and memory module; Described outage information optimizes the feature that module has a power failure according to fault trip and operation, adjust the dispatching maintenance ticket situation submitted to formulate to optimize filtering rule by the logical relation of switch changed position time and in conjunction with various places county and Query Result is optimized, a large amount of invalid signals is filtered, effectively improves rate of accurateness; Described client query module can region-by-region, inquire about the whole province 10kV main line at times, the tripping operation of 35kV and 110kV line fault, operation have a power failure and the information such as load loss, provides real-time monitoring to regional grid power blackout information and historical query with visual means.
Present invention also offers a kind of area power grid outage information analysis method based on grid power blackout characteristic, be applied to the area power grid outage information based on grid power blackout characteristic described above and study and judge system, for adding up each regional 10kV main line, the tripping operation of 35kV and 110kV line fault and operation power failure bar, improve each area power grid line outage discrimination and accuracy, it is characterized in that, comprise the following steps:
1) side deployment information acquisition module and line outage judge module is respectively adjusted on each ground, in province, ground two-level scheduler integrated data platform disposes data platform file reception and memory module, adjusts sidepiece administration outage information to optimize module and client query module in province;
2) information acquisition module is adjusted the basic service data of EMS each area power grid of system acquisition all 35kV and 110kV transformer station by ground and is sent to line outage judge module;
3) the comprehensive remote signalling displacement of line outage judge module, remote measurement sudden change and accident resultant signal carry out line outage and study and judge, and send to data platform file reception and memory module by studying and judging result with the form of E formatted file;
4) result of studying and judging received carries out gathering and storing by data platform file reception and memory module;
5) client query module sends querying condition to data platform file reception and memory module;
6) Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module;
7) outage information optimizes module according to fault trip, the operation characteristic operating power failure and telecontrol equipment, adjust the dispatching maintenance ticket situation submitted to filter line outage information by the logical relation of switch changed position time and in conjunction with various places county, and be pushed to client query module by the outage information after enquiring result optimizing.
Preferably, it is according to actual motion characteristic during line outage that described line outage judge module carries out the process that line outage studies and judges, the information such as comprehensive analysis remote signalling displacement, remote measurement sudden change and accident resultant signal, realize 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and collection that have a power failure, it has a power failure and studies and judges according to as follows:
1) when monitoring line switching sub-gate signal, whether have before and after checking that corresponding accident is total, interval total or protection act signal in 60 seconds, before checking this switch changed position, whether 1 second flow is greater than 5 amperes through the electric current of switch simultaneously, if meet above-mentioned condition simultaneously, is then judged to primary fault tripping operation; Introduce remote measurement amount as trip criteria, can be that operation has a power failure or the circuit carrying out signal debugging that had a power failure is rejected from tripping operation information by part reality on the one hand, the tripping operation on the other hand for the extension wire that charges will not include scope of statistics in;
2) if only monitor line switching sub-gate signal, front and back find no in 60 seconds that corresponding accident is total, interval total or protection act signal, be then judged to single job and have a power failure.
Preferably, described outage information optimization module by the logical relation of switch changed position time to the process that line outage information is filtered is:
1) if tripping operation information is more than or equal to 3 in same circuit one day, be then judged to be mistaking signal, filter the tripping operation information of this circuit;
2) if being more than or equal to appears in same transformer station synchronization, 3 line switchings divide, switching signal, are judged to be that RTU is restarted and cause signal to reset the wrong report caused, filter the outage information of this type of circuits all;
3) if same circuit occurs in one day being more than or equal to 2 operation power cut records, then merged into a record, the opening time after merging uses the opening time of Article 1 record, and the closing time after merging uses the closing time of the last item record;
4) if an operation power cut record, its switch separating brake and closing time interval are less than or equal to 30 minutes, be then judged to be invalid operation power cut record, filtered.
Preferably, described outage information optimizes module by conjunction with the dispatching maintenance ticket situation of various places county tune submission to the process that line outage information is filtered being:
1) mate in the dispatching maintenance ticket of various places county tune submission according to the title of dead line, if find the maintenance application of this circuit, and line switching opening time is later than dispatching maintenance ticket submission time, 1 hour is no more than on-stream time early than applying for, then judge with maintenance, this outage information applies for that the match is successful, the type according to maintenance application is that outage information stamps " meter stops " or " non-meter stops " label;
2) the fault trip information with " meter stops " or " non-meter stops " label is moved in operation outage information;
3) if dead line detects corresponding dispatching maintenance ticket, and switch opening time is later than dispatching maintenance ticket on-stream time, early than dispatching maintenance ticket time of completion, then judge that this outage information, is filtered caused by signal debugging for carrying out during line maintenance.
Beneficial effect of the present invention is as follows:
The present invention constructs a kind of area power grid outage information and studies and judges system, passage adjusts the information acquisition module of side with being deployed in, line outage judge module gathers the basic data of each department electrical networks and in addition discriminatory analysis, and judged result is supplied to the data platform file reception and memory module that are deployed in province's ground two-level scheduler integrated data platform with document form, carry out gathering and storing after data platform file reception and memory module receive file, economize when real-time information and the historical data of each area power grid power failure is ask in investigation and pass through client query module input inquiry condition, preliminary judged result sends to outage information to optimize module according to querying condition by data platform file reception and memory module, outage information is optimized the preliminary judged result of module to line outage judge module and is optimized, a large amount of invalid signals is filtered, effectively improve rate of accurateness, outage information result after optimization is pushed to client query module by the module of outage information optimization simultaneously, client query module can region-by-region, inquire about the whole province each department 10kV main line at times, the tripping operation of 35kV and 110kV line fault, operation have a power failure and the information such as load loss, provides real-time monitoring to regional grid power blackout information and historical query with visual means.
Area power grid outage information analysis method of the present invention studies and judges system for carrier with area power grid outage information, according to the feature that fault trip has a power failure with operation, by the logical relation of switch changed position time, and the dispatching maintenance ticket information of declaring is adjusted in conjunction with various places county, accurate identification fault trip and operation have a power failure, the invalid outage information that telesignalling dithering produces is filtered, effectively improve the discrimination that fault trip and operation are had a power failure, reduce the rate of false alarm because mistaking signal causes, drastically increase the accuracy rate of area power grid outage information.
The present invention enables provincial electric power company grasp the outage information of the whole province's each department 10kV main line, 35kV and 110kV circuit real-time and accurately, line tripping particularly under inclement weather conditions and load loss situation, eliminate provincial electric power company to the supervision blind area of 10 ~ 110kV line outage situation, for raising area power grid power supply reliability, the measure of implementation and supervision ordered electric, timely startup emergency response is significant, and to improving, ground county adjusts EMS data, the standardized level of model plays facilitation simultaneously.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is further described:
Fig. 1 is system construction drawing of the present invention;
Fig. 2 is method flow diagram of the present invention;
Fig. 3 is the process flow diagram that line outage of the present invention is studied and judged;
Fig. 4 is the process flow diagram that the measure of employing repair ticket of the present invention coupling is filtered line outage information.
Embodiment
For clearly demonstrating the technical characterstic of this programme, below by embodiment, and in conjunction with its accompanying drawing, the present invention will be described in detail.Disclosing hereafter provides many different embodiments or example is used for realizing different structure of the present invention.Of the present invention open in order to simplify, hereinafter the parts of specific examples and setting are described.In addition, the present invention can in different example repeat reference numerals and/or letter.This repetition is to simplify and clearly object, itself does not indicate the relation between discussed various embodiment and/or setting.It should be noted that parts illustrated in the accompanying drawings are not necessarily drawn in proportion.Present invention omits the description of known assemblies and treatment technology and process to avoid unnecessarily limiting the present invention.
Scheduling EMS system has been a set of very ripe system, particularly with the county's My Perspective On The Co-building project implementation that lands, the Back ground Information of the overwhelming majority 35kV and 110kV transformer station of the whole province can realize directly adopting, and the transformer station temporarily cannot directly adopted individually can adopt county to turn the mode sent out.Compared with the three kinds of means obtaining the information of 10 ~ 110kV line outage across the entire province in current each provincial electric power company, the present invention has that access information is comprehensive, electric network model accurately, real-time and the high advantage of accuracy.
As shown in Figure 1, a kind of area power grid outage information based on grid power blackout characteristic of the present invention studies and judges system, and it comprises information acquisition module, line outage judge module, data platform file reception and memory module, outage information optimizes module and client query module; Described information acquisition module and line outage judge module are configured in the tune side, ground in each area, described data platform file reception and memory module are configured in province's ground two-level scheduler integrated data platform, and described outage information optimizes module and client query module is configured in province's tune side.Adjust the information acquisition module of side gather the basic data of each area power grid and send to line outage judge module with being configured in, line outage judge module carries out discriminatory analysis to the basic data gathered, and result is sent to data platform file reception and memory module with document form, carry out gathering and storing after data platform file reception and memory module receive file, economize when real-time information and the historical data of each area power grid power failure is ask in investigation and pass through client query module input inquiry condition, Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module, outage information is optimized module and is optimized Query Result and the outage information after optimizing is pushed to client query module.
The function that area power grid outage information based on grid power blackout characteristic of the present invention studies and judges each ingredient of system is as follows:
Described information acquisition module is the information such as the remote signalling of each area power grid, remote measurement, accident are total, interval summation protection act in order to gather, and the relevant information of collection is sent to line outage judge module; Information acquisition module adjusts the general procedure of EMS system as ground, and the stability of EMS system and reliability can not be adjusted over the ground to have an impact;
Described line outage judge module carries out seizure and the classification process of outage information according to the criterion that line fault tripping operation and operation have a power failure in order to information such as, interval summation protection act total to the remote signalling received, remote measurement, accident, result is sent in the form of a file data platform file reception and memory module; Adjust the Stability and dependability requirement of EMS system with considering, independently line outage judge module need be increased in tune side, ground judgement process is carried out to Information Monitoring, and judged result is supplied to data platform file reception and memory module;
Query Result, in order to gather and to store the outage information of each area power grid, sends to outage information to optimize module according to querying condition by described data platform file reception and memory module;
Described outage information is optimized module and is optimized Query Result in order to adopt telesignalling dithering filtration and the measure of repair ticket coupling, and the outage information after optimizing is sent to client query module;
Described client query module, in order on the one hand querying condition information is sent to data platform file reception and memory module, receives on the other hand and optimizes the outage information after module optimization through outage information.
Preferably, in system of the present invention, described information acquisition module adjusts the Back ground Information of all 35kV and 110kV transformer stations of EMS system acquisition this area by ground, comprise remote signalling, remote measurement, accident be total, interval is total, the information such as protection act, wherein the relevant information of transformer station belonging to company of county adjusts integral system directly to gather by ground county or county turns the mode sent out and gathers; Described line outage judge module is adjust on ground the independent judgment service that the basis of EMS system is developed, the criterion that this judgement service adopts remote signalling displacement, remote measurement sudden change and accident resultant signal to combine, carry out 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and statistics that have a power failure, and differentiation and statistics were sent to data platform file reception and memory module once at interval of five minutes in the form of a file; The file at every turn received carries out gathering and storing by described data platform file reception and memory module; Described outage information optimizes the feature that module has a power failure according to fault trip and operation, adjust the dispatching maintenance ticket situation submitted to formulate to optimize filtering rule by the logical relation of switch changed position time and in conjunction with various places county and Query Result is optimized, a large amount of invalid signals is filtered, effectively improves rate of accurateness; Described client query module can region-by-region, inquire about the whole province 10kV main line at times, the tripping operation of 35kV and 110kV line fault, operation have a power failure and the information such as load loss, provides real-time monitoring to regional grid power blackout information and historical query with visual means.
As shown in Figure 2, a kind of area power grid outage information analysis method based on grid power blackout characteristic of the present invention, be applied to the area power grid outage information based on grid power blackout characteristic described above and study and judge system, for adding up each regional 10kV main line, the tripping operation of 35kV and 110kV line fault and operation power failure bar, improve each area power grid line outage discrimination and accuracy, analysis method comprises the following steps:
1) side deployment information acquisition module and line outage judge module is respectively adjusted on each ground, in province, ground two-level scheduler integrated data platform disposes data platform file reception and memory module, adjusts sidepiece administration outage information to optimize module and client query module in province;
2) information acquisition module is adjusted the basic service data of EMS each area power grid of system acquisition all 35kV and 110kV transformer station by ground and is sent to line outage judge module;
3) the comprehensive remote signalling displacement of line outage judge module, remote measurement sudden change and accident resultant signal carry out line outage and study and judge, and send to data platform file reception and memory module by studying and judging result with the form of E formatted file;
4) result of studying and judging received carries out gathering and storing by data platform file reception and memory module;
5) client query module sends querying condition to data platform file reception and memory module;
6) Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module;
7) outage information optimizes module according to fault trip, the operation characteristic operating power failure and telecontrol equipment, adjust the dispatching maintenance ticket situation submitted to filter line outage information by the logical relation of switch changed position time and in conjunction with various places county, and be pushed to client query module by the outage information after enquiring result optimizing.
Preferably, in the method for the invention, it is according to actual motion characteristic during line outage that described line outage judge module carries out the process that line outage studies and judges, the information such as comprehensive analysis remote signalling displacement, remote measurement sudden change and accident resultant signal, realize 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and collection that have a power failure, it has a power failure and studies and judges according to as follows:
1) when monitoring line switching sub-gate signal, whether have before and after checking that corresponding accident is total, interval total or protection act signal in 60 seconds, before checking this switch changed position, whether 1 second flow is greater than 5 amperes through the electric current of switch simultaneously, if meet above-mentioned condition simultaneously, is then judged to primary fault tripping operation; Introduce remote measurement amount as trip criteria, can be that operation has a power failure or the circuit carrying out signal debugging that had a power failure is rejected from tripping operation information by part reality on the one hand, the tripping operation on the other hand for the extension wire that charges will not include scope of statistics in;
2) if only monitor line switching sub-gate signal, front and back find no in 60 seconds that corresponding accident is total, interval total or protection act signal, be then judged to single job and have a power failure.
Preferably, in the method for the invention, described outage information is optimized module and by the logical relation of switch changed position time to the process that line outage information is filtered is:
1) if tripping operation information is more than or equal to 3 in same circuit one day, be then judged to be mistaking signal, filter the tripping operation information of this circuit;
2) if being more than or equal to appears in same transformer station synchronization, 3 line switchings divide, switching signal, are judged to be that RTU is restarted and cause signal to reset the wrong report caused, filter the outage information of this type of circuits all;
3) if same circuit occurs in one day being more than or equal to 2 operation power cut records, then merged into a record, the opening time after merging uses the opening time of Article 1 record, and the closing time after merging uses the closing time of the last item record;
4) if an operation power cut record, its switch separating brake and closing time interval are less than or equal to 30 minutes, be then judged to be invalid operation power cut record, filtered.
Preferably, in the method for the invention, described outage information is optimized module and by adjusting the dispatching maintenance ticket situation submitted in conjunction with various places county to the process that line outage information is filtered is:
1) mate in the dispatching maintenance ticket of various places county tune submission according to the title of dead line, if find the maintenance application of this circuit, and line switching opening time is later than dispatching maintenance ticket submission time, 1 hour is no more than on-stream time early than applying for, then judge with maintenance, this outage information applies for that the match is successful, the type according to maintenance application is that outage information stamps " meter stops " or " non-meter stops " label;
2) the fault trip information with " meter stops " or " non-meter stops " label is moved in operation outage information;
3) if dead line detects corresponding dispatching maintenance ticket, and switch opening time is later than dispatching maintenance ticket on-stream time, early than dispatching maintenance ticket time of completion, then judge that this outage information, is filtered caused by signal debugging for carrying out during line maintenance.
The present invention carry out based on the area power grid outage information of grid power blackout characteristic study and judge process mainly comprise fault trip with operation have a power failure differentiate, telesignalling dithering filters, dispatching maintenance ticket mates three links.
As shown in Figure 3, the present invention's criterion of carrying out line fault tripping operation is for having switch changed position (by be incorporated into point) signal, total (or interval the is total or protection act) signal of accident and electric current before switch changed position is greater than 5 amperes.Introduce remote measurement amount as trip criteria, on the one hand can by actual for a part to have a power failure for operation or had a power failure to reject from tripping operation information at the circuit carrying out signal debugging, mean that the tripping operation of charging extension wire will not include system statistics on the other hand.In actual applications; when monitoring a certain switch changed position (by be incorporated into point) signal; namely the accident whether having respective switch before and after switch changed position in 60 seconds total (or interval is total or protection act) signal is checked; if have, check whether the switch changed position electric current of first 1 second is greater than 5 amperes further; if three conditions are all satisfied, be then judged to primary fault tripping operation.
The criterion that line loop operation has a power failure, for only there being switch changed position (by be incorporated into point) signal, does not have accident total (or interval always or protection act) signal.In actual applications; when monitoring a certain switch changed position (by be incorporated into point) signal; namely check the accident whether having respective switch before and after switch changed position in 60 seconds total (or interval is total or protection act) signal, if not, be judged to operation and have a power failure.
There is work value according to switch changed position (by be incorporated into point) front 1 second flow through switch, add up the load loss that this line outage causes, put aside the situation of load prepared auto restart.
For 10kV circuit, system only pays close attention to the relevant information of transformer station's outlet switch (main line switch), and main line switch has a power failure and namely thinks line outage; For 35kV and 110kV circuit, system only pays close attention to the relevant information of source-side switches, and power supply slowdown monitoring switch has a power failure and namely thinks line outage.
Every 5 minutes of line outage judge module generates a file, and this file was named according to the generation moment, content be generate 10kV main line that in first 5 minutes of moment, this area occurs, the tripping operation of 35kV and 110kV line fault, operation have a power failure and the information such as load loss.Data platform file reception and memory module calling in every 5 minutes once comprise the file of outage information, in order to prevent loss of data, data platform file reception and memory module call 6 files in first 30 minutes at every turn, if call successfully, then by file warehousing, for successful file of putting in storage, do not cover in calling below, for the file of unsuccessful warehouse-in, in time calling of 5 below, still likely successfully put in storage.
There is the problem that remote signals is frequently shaken in some transformer station, the RTU of some transformer station is not bery stable, occurs the situation that batch remote signalling conjugates simultaneously, and also carry out signal debugging during some line outage and upload a large amount of signal, these situations all can cause misreport of system.It is after analysing in depth various wrong report information that outage information optimizes module, according to the feature that fault trip and operation have a power failure, by the logical relation of switch changed position time, the situation of dispatching maintenance ticket is submitted in conjunction with relevant unit, formulate series of optimum filtering rule, the judged result of line outage judge module is optimized, a large amount of invalid signals is filtered, effectively improves rate of accurateness.
If one the circuit information number that tripped in a day is more than or equal to 3, then think caused by signal jitter, system will filter out all tripping operation information of this circuit; If at synchronization, certain transformer station occurs that many line switchings close displacement (being more than or equal to 3) by assigning to, then think that this station RTU is restarted the signal caused and resetted, system will filter out corresponding outage information; If one operate power cut record, its switch separating brake and closing time interval are less than or equal to 30 minutes, and system will filter out this outage information; If one circuit had many to operate the record had a power failure in one day, then system is merged into a new record, and the opening time of new record is the opening time of Article 1 record, and the closing time of new record is the closing time of the last item record.
As shown in Figure 4; accuracy rate is studied and judged in order to improve further; identify and be mistaken for fault trip because sending out the total or protection act signal of accident by mistake and be actually the information that operation has a power failure; reject the false outage information that interruption maintenance circuit carries out signal debugging generation, outage information is mated with dispatching maintenance ticket by outage information optimization module.For an outage information, system is mated in the dispatching maintenance ticket submitted in relevant unit according to the title of power failure equipments, if the match is successful, then the type according to dispatching maintenance ticket after corresponding outage information stamps " meter stops " or " non-meter stops " label.Mend for relevant unit after preventing line tripping and propose maintenance application, require that switch opening time is later than application submission time, and be no more than 1 hour on-stream time early than application.Tripping operation information with " meter stops " or " non-meter stops " label belongs to the operation by mistake sending out accident total (interval total, protection act) signal more and has a power failure, and system will move on to operation power failure list from tripping operation list this type of information; The how true genus operation of operation outage information with " meter stops " or " non-meter stops " label has a power failure.
For an outage information, system is mated in the dispatching maintenance ticket submitted in relevant unit according to the title of power failure equipments, if the match is successful and switch opening time is later than dispatching maintenance ticket on-stream time, and early than dispatching maintenance ticket time of completion, then think that this outage information is carried out signal debugging and caused between circuit turn(a)round, filtered.
By the area power grid outage information analysis method based on grid power blackout characteristic provided by the invention, economize and adjust side can grasp the whole province's each department electric network fault tripping operation and operation outage information comprehensively, significantly improve the accuracy of fault trip and operation outage information.
The above is the preferred embodiment of the present invention, and for those skilled in the art, under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications are also regarded as protection scope of the present invention.

Claims (7)

1. the area power grid outage information based on grid power blackout characteristic studies and judges system, it is characterized in that, comprises information acquisition module, line outage judge module, data platform file reception and memory module, outage information optimizes module and client query module;
The remote signalling of each area power grid, remote measurement, accident are total, interval summation protection act information in order to gather for described information acquisition module, and total to the remote signalling of collection, remote measurement, accident, interval summation protection act information are sent to line outage judge module;
Described line outage judge module carries out seizure and the classification process of outage information according to the criterion that line fault tripping operation and operation have a power failure in order to, interval summation protection act information total to the remote signalling received, remote measurement, accident, result is sent to data platform file reception and memory module in the form of a file;
Query Result, in order to gather and to store the outage information of each area power grid, sends to outage information to optimize module according to querying condition by described data platform file reception and memory module;
Described outage information is optimized module and is optimized Query Result in order to adopt telesignalling dithering filtration and the measure of repair ticket coupling, and the outage information after optimizing is sent to client query module;
Described client query module, in order on the one hand querying condition information is sent to data platform file reception and memory module, receives on the other hand and optimizes the outage information after module optimization through outage information.
2. the area power grid outage information based on grid power blackout characteristic according to claim 1 studies and judges system, it is characterized in that, described information acquisition module and line outage judge module are configured in each ground and adjust side, described data platform file reception and memory module are configured in province's ground two-level scheduler integrated data platform, and described outage information optimizes module and client query module is configured in province's tune side, adjust the information acquisition module of side gather the basic data of each area power grid and send to line outage judge module with being configured in, line outage judge module carries out discriminatory analysis to the basic data gathered, and result is sent to data platform file reception and memory module with document form, carry out gathering and storing after data platform file reception and memory module receive file, economize and adjust by client query module input inquiry condition, Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module, outage information is optimized module and is optimized Query Result and the outage information after optimizing is pushed to client query module.
3. the area power grid outage information based on grid power blackout characteristic according to claim 1 and 2 studies and judges system, it is characterized in that, described information acquisition module adjusts the Back ground Information of all 35kV and 110kV transformer stations of EMS system acquisition this area by ground, comprise that remote signalling, remote measurement, accident are total, interval summation protection act information, wherein the relevant information of transformer station belonging to company of county adjusts integral system directly to gather by ground county or county turns the mode sent out and gathers; Described line outage judge module is adjust on ground the independent judgment service that the basis of EMS system is developed, the criterion that this judgement service adopts remote signalling displacement, remote measurement sudden change and accident resultant signal to combine, carry out 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and statistics that have a power failure, and differentiation and statistics were sent to data platform file reception and memory module once at interval of five minutes in the form of a file; The file at every turn received carries out gathering and storing by described data platform file reception and memory module; Described outage information optimizes the feature that module has a power failure according to fault trip and operation, adjust the dispatching maintenance ticket situation submitted to formulate to optimize filtering rule by the logical relation of switch changed position time and in conjunction with various places county and Query Result is optimized, a large amount of invalid signals is filtered, effectively improves rate of accurateness; Described client query module can region-by-region, inquire about the whole province 10kV main line at times, the tripping operation of 35kV and 110kV line fault, operation have a power failure and load loss information, provides real-time monitoring to regional grid power blackout information and historical query with visual means.
4. based on the area power grid outage information analysis method of grid power blackout characteristic, be applied to the area power grid outage information based on grid power blackout characteristic according to claim 1 and study and judge system, for adding up each regional 10kV main line, the tripping operation of 35kV and 110kV line fault and operation power failure bar, improve each area power grid line outage discrimination and accuracy, it is characterized in that, comprise the following steps:
1) side deployment information acquisition module and line outage judge module is respectively adjusted on each ground, in province, ground two-level scheduler integrated data platform disposes data platform file reception and memory module, adjusts sidepiece administration outage information to optimize module and client query module in province;
2) information acquisition module is adjusted the basic service data of EMS each area power grid of system acquisition all 35kV and 110kV transformer station by ground and is sent to line outage judge module;
3) the comprehensive remote signalling displacement of line outage judge module, remote measurement sudden change and accident resultant signal carry out line outage and study and judge, and send to data platform file reception and memory module by studying and judging result with the form of E formatted file;
4) result of studying and judging received carries out gathering and storing by data platform file reception and memory module;
5) client query module sends querying condition to data platform file reception and memory module;
6) Query Result sends to outage information to optimize module according to querying condition by data platform file reception and memory module;
7) outage information optimizes module according to fault trip, the operation characteristic operating power failure and telecontrol equipment, adjust the dispatching maintenance ticket situation submitted to filter line outage information by the logical relation of switch changed position time and in conjunction with various places county, and be pushed to client query module by the outage information after enquiring result optimizing.
5. the area power grid outage information analysis method based on grid power blackout characteristic according to claim 4, it is characterized in that, it is according to actual motion characteristic during line outage that described line outage judge module carries out the process that line outage studies and judges, comprehensive analysis remote signalling displacement, remote measurement sudden change and accident resultant signal information, realize 10kV main line, the tripping operation of 35kV and 110kV line fault and operate the automatic discrimination and collection that have a power failure, it has a power failure and studies and judges according to as follows:
1) when monitoring line switching sub-gate signal, whether have before and after checking that corresponding accident is total, interval total or protection act signal in 60 seconds, before checking this switch changed position, whether 1 second flow is greater than 5 amperes through the electric current of switch simultaneously, if meet above-mentioned condition simultaneously, is then judged to primary fault tripping operation; Introduce remote measurement amount as trip criteria, can be that operation has a power failure or the circuit carrying out signal debugging that had a power failure is rejected from tripping operation information by part reality on the one hand, the tripping operation on the other hand for the extension wire that charges will not include scope of statistics in;
2) if only monitor line switching sub-gate signal, front and back find no in 60 seconds that corresponding accident is total, interval total or protection act signal, be then judged to single job and have a power failure.
6. the area power grid outage information analysis method based on grid power blackout characteristic according to claim 4, is characterized in that, described outage information is optimized module and by the logical relation of switch changed position time to the process that line outage information is filtered is:
1) if tripping operation information is more than or equal to 3 in same circuit one day, be then judged to be mistaking signal, filter the tripping operation information of this circuit;
2) if being more than or equal to appears in same transformer station synchronization, 3 line switchings divide, switching signal, are judged to be that RTU is restarted and cause signal to reset the wrong report caused, filter the outage information of this type of circuits all;
3) if same circuit occurs in one day being more than or equal to 2 operation power cut records, then merged into a record, the opening time after merging uses the opening time of Article 1 record, and the closing time after merging uses the closing time of the last item record;
4) if an operation power cut record, its switch separating brake and closing time interval are less than or equal to 30 minutes, be then judged to be invalid operation power cut record, filtered.
7. the area power grid outage information analysis method based on grid power blackout characteristic according to claim 4, it is characterized in that, described outage information is optimized module and by adjusting the dispatching maintenance ticket situation submitted in conjunction with various places county to the process that line outage information is filtered is:
1) mate in the dispatching maintenance ticket of various places county tune submission according to the title of dead line, if find the maintenance application of this circuit, and line switching opening time is later than dispatching maintenance ticket submission time, 1 hour is no more than on-stream time early than applying for, then judge with maintenance, this outage information applies for that the match is successful, the type according to maintenance application is that outage information stamps " meter stops " or " non-meter stops " label;
2) the fault trip information with " meter stops " or " non-meter stops " label is moved in operation outage information;
3) if dead line detects corresponding dispatching maintenance ticket, and switch opening time is later than dispatching maintenance ticket on-stream time, early than dispatching maintenance ticket time of completion, then judge that this outage information, is filtered caused by signal debugging for carrying out during line maintenance.
CN201510225174.2A 2015-05-06 2015-05-06 Area power grid outage information based on grid power blackout characteristic studies and judges system and method Expired - Fee Related CN104766185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510225174.2A CN104766185B (en) 2015-05-06 2015-05-06 Area power grid outage information based on grid power blackout characteristic studies and judges system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510225174.2A CN104766185B (en) 2015-05-06 2015-05-06 Area power grid outage information based on grid power blackout characteristic studies and judges system and method

Publications (2)

Publication Number Publication Date
CN104766185A true CN104766185A (en) 2015-07-08
CN104766185B CN104766185B (en) 2018-03-02

Family

ID=53647999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510225174.2A Expired - Fee Related CN104766185B (en) 2015-05-06 2015-05-06 Area power grid outage information based on grid power blackout characteristic studies and judges system and method

Country Status (1)

Country Link
CN (1) CN104766185B (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105226813A (en) * 2015-09-11 2016-01-06 国家电网公司 A kind of method based on electrical power distribution automatization system statistics customer interrupted number
CN105334839A (en) * 2015-12-16 2016-02-17 国家电网公司 10kV distribution network equipment management system
CN108764596A (en) * 2018-03-28 2018-11-06 广州供电局有限公司 The monitoring method and monitoring system of the power failure of metering automation system
CN108988487A (en) * 2018-06-19 2018-12-11 国电南瑞科技股份有限公司 A kind of grid power blackout event recognition method based on multidimensional data
CN109742854A (en) * 2018-12-27 2019-05-10 国网吉林省电力有限公司电力科学研究院 It is a kind of that method is actively reported for repairment based on intelligent electric meter data processing
CN110083644A (en) * 2019-03-04 2019-08-02 广东电网有限责任公司 A kind of distribution line significant blackouts event method for early warning and system
CN110244163A (en) * 2019-06-20 2019-09-17 国网湖南省电力有限公司 Stop send a telegram in reply event hierarchy intelligence analysis method and device in a kind of area
CN110970995A (en) * 2019-03-26 2020-04-07 重庆甘润科技有限公司 Transmission type management and control system for key indexes of safe operation of power grid
CN111060816A (en) * 2019-12-20 2020-04-24 南京亚派科技股份有限公司 Information management system based on intelligent switch and management method thereof
CN111107146A (en) * 2019-12-17 2020-05-05 国网湖南省电力有限公司 Real-time distribution method of power grid accident information
CN111257686A (en) * 2020-01-15 2020-06-09 国家电网有限公司 Intelligent tripping analysis system based on data sharing analysis
CN112288403A (en) * 2020-10-30 2021-01-29 国网安徽省电力有限公司怀远县供电公司 Method and system for accurately pushing power failure information to user, electronic equipment and storage medium
CN112347149A (en) * 2020-11-05 2021-02-09 国网山东省电力公司泰安供电公司 Signal summary display system, method and equipment based on EMS
CN112736898A (en) * 2020-12-15 2021-04-30 国网河北省电力有限公司石家庄市栾城区供电分公司 Intelligent tripping analysis system based on data sharing analysis
CN113570345A (en) * 2021-08-13 2021-10-29 国网江苏省电力有限公司南通供电分公司 Power failure range automatic identification system based on construction project circuit diagram
CN113960411A (en) * 2021-10-18 2022-01-21 国网安徽省电力有限公司电力科学研究院 Multi-source data fusion-based comprehensive study and judgment method for fault tripping of power transmission line

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565572A (en) * 2011-12-04 2012-07-11 江苏省电力公司南京供电公司 Platform and method for judging fault of match power grid
CN103278736A (en) * 2013-04-12 2013-09-04 南方电网科学研究院有限责任公司 Method for automatically inquiring and diagnosing and publishing diagnosis result of thunder and lightning of breaker coil
CN103490520A (en) * 2011-12-04 2014-01-01 江苏省电力公司南京供电公司 Power distribution network fault treatment method
CN103514516A (en) * 2013-09-27 2014-01-15 国家电网公司 Method for obtaining power grid device failure information based on calculation of multi-source redundant information
WO2014122929A1 (en) * 2013-02-07 2014-08-14 日本電気株式会社 Power control system
CN104459474A (en) * 2014-12-22 2015-03-25 国网上海市电力公司 Intelligent distribution network fault recognition method
CN104463712A (en) * 2014-12-22 2015-03-25 国网上海市电力公司 Intelligent distribution network fault information statistical analysis system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565572A (en) * 2011-12-04 2012-07-11 江苏省电力公司南京供电公司 Platform and method for judging fault of match power grid
CN103490520A (en) * 2011-12-04 2014-01-01 江苏省电力公司南京供电公司 Power distribution network fault treatment method
WO2014122929A1 (en) * 2013-02-07 2014-08-14 日本電気株式会社 Power control system
CN103278736A (en) * 2013-04-12 2013-09-04 南方电网科学研究院有限责任公司 Method for automatically inquiring and diagnosing and publishing diagnosis result of thunder and lightning of breaker coil
CN103514516A (en) * 2013-09-27 2014-01-15 国家电网公司 Method for obtaining power grid device failure information based on calculation of multi-source redundant information
CN104459474A (en) * 2014-12-22 2015-03-25 国网上海市电力公司 Intelligent distribution network fault recognition method
CN104463712A (en) * 2014-12-22 2015-03-25 国网上海市电力公司 Intelligent distribution network fault information statistical analysis system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张远来 等: ""基于调度运行管理系统的配电网故障研判方案"", 《电力系统自动化》 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105226813A (en) * 2015-09-11 2016-01-06 国家电网公司 A kind of method based on electrical power distribution automatization system statistics customer interrupted number
CN105334839A (en) * 2015-12-16 2016-02-17 国家电网公司 10kV distribution network equipment management system
CN105334839B (en) * 2015-12-16 2018-01-09 国家电网公司 10kV distribution net equipment management systems
CN108764596A (en) * 2018-03-28 2018-11-06 广州供电局有限公司 The monitoring method and monitoring system of the power failure of metering automation system
CN108988487A (en) * 2018-06-19 2018-12-11 国电南瑞科技股份有限公司 A kind of grid power blackout event recognition method based on multidimensional data
CN108988487B (en) * 2018-06-19 2022-06-21 国电南瑞科技股份有限公司 Power grid power failure event identification method based on multidimensional data
CN109742854A (en) * 2018-12-27 2019-05-10 国网吉林省电力有限公司电力科学研究院 It is a kind of that method is actively reported for repairment based on intelligent electric meter data processing
CN110083644A (en) * 2019-03-04 2019-08-02 广东电网有限责任公司 A kind of distribution line significant blackouts event method for early warning and system
CN110970995B (en) * 2019-03-26 2021-09-07 国网重庆市电力公司 Transmission type management and control system for key indexes of safe operation of power grid
CN110970995A (en) * 2019-03-26 2020-04-07 重庆甘润科技有限公司 Transmission type management and control system for key indexes of safe operation of power grid
CN110244163B (en) * 2019-06-20 2022-03-11 国网湖南省电力有限公司 Intelligent stage-level studying and judging method and device for power failure and recovery events of transformer area
CN110244163A (en) * 2019-06-20 2019-09-17 国网湖南省电力有限公司 Stop send a telegram in reply event hierarchy intelligence analysis method and device in a kind of area
CN111107146A (en) * 2019-12-17 2020-05-05 国网湖南省电力有限公司 Real-time distribution method of power grid accident information
CN111060816A (en) * 2019-12-20 2020-04-24 南京亚派科技股份有限公司 Information management system based on intelligent switch and management method thereof
CN111257686A (en) * 2020-01-15 2020-06-09 国家电网有限公司 Intelligent tripping analysis system based on data sharing analysis
CN112288403A (en) * 2020-10-30 2021-01-29 国网安徽省电力有限公司怀远县供电公司 Method and system for accurately pushing power failure information to user, electronic equipment and storage medium
CN112347149A (en) * 2020-11-05 2021-02-09 国网山东省电力公司泰安供电公司 Signal summary display system, method and equipment based on EMS
CN112736898A (en) * 2020-12-15 2021-04-30 国网河北省电力有限公司石家庄市栾城区供电分公司 Intelligent tripping analysis system based on data sharing analysis
CN113570345A (en) * 2021-08-13 2021-10-29 国网江苏省电力有限公司南通供电分公司 Power failure range automatic identification system based on construction project circuit diagram
CN113570345B (en) * 2021-08-13 2024-01-19 国网江苏省电力有限公司南通供电分公司 Automatic power failure range identification system based on construction project circuit diagram
CN113960411A (en) * 2021-10-18 2022-01-21 国网安徽省电力有限公司电力科学研究院 Multi-source data fusion-based comprehensive study and judgment method for fault tripping of power transmission line
CN113960411B (en) * 2021-10-18 2023-10-20 国网安徽省电力有限公司电力科学研究院 Power transmission line fault tripping comprehensive research and judgment method based on multi-source data fusion

Also Published As

Publication number Publication date
CN104766185B (en) 2018-03-02

Similar Documents

Publication Publication Date Title
CN104766185A (en) Regional power grid power outage information studying and judging system and method based on power grid power outage characteristics
CN104182815B (en) A kind of power supply reliability acquisition methods and system
CN104578426B (en) Detection method for information comprehensive analysis and intelligent alarming application
CN104410067A (en) Zone area power failure analyzing method based on common transformer and analysis of big data acquired by users
CN109066988B (en) System and method for preferentially identifying and reporting power failure events of topology level of tail-end power grid
CN102928809A (en) Electric energy metering device remote monitoring diagnostic system and working method thereof
CN103607042B (en) The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town
CN105978148B (en) The domestic intelligent safe distribution of electric power system and its long-distance monitoring method that can remotely monitor
CN104635198B (en) Remote monitoring and diagnosing method for electric energy metering device with timely fault finding function
CN104133986A (en) Multi-business-object-oriented distribution network warning information integrated rational analysis method
CN101741137B (en) Network centralized emergency power supply automatic switching method
CN108665186A (en) Distribution transforming heavy-overload blackouts monitoring method and device based on metering automation system
CN104678348B (en) Remote monitoring and diagnosing method for electric energy metering device with high efficiency
CN107769197B (en) A kind of voltage sag source positioning system based on grid equipment topology
CN103956831B (en) The intelligent diagnosing method of a kind of transmission line distribution transforming phase shortage alarm
CN109687590A (en) A kind of be classified stops send a telegram in reply report method, system
CN108988487A (en) A kind of grid power blackout event recognition method based on multidimensional data
CN202939301U (en) Remote monitoring diagnosis system of electric energy metering device
CN106340951A (en) Hierarchical distributed intelligent regional bus-bar automatic transfer switch system
CN108919044A (en) A kind of unit style distribution network failure active identification method based on mutual verification scheme
CN104714206B (en) Remote monitoring and diagnosing method for electric energy metering device capable of finding faults timely
CN105871645A (en) Automatic collecting and publishing device for grid fault information
CN205882851U (en) That takes trouble record ripples joins in marriage power system fault indicator
CN108388653B (en) Method for identifying opening type of 10kV outgoing line switch of transformer substation
CN109599946A (en) A kind of Efficient fault diagnostic method of power distribution automation switch

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180302

Termination date: 20190506

CF01 Termination of patent right due to non-payment of annual fee