CN104708559B - 一种固定与安装锅炉锅筒的方法 - Google Patents

一种固定与安装锅炉锅筒的方法 Download PDF

Info

Publication number
CN104708559B
CN104708559B CN201510129870.3A CN201510129870A CN104708559B CN 104708559 B CN104708559 B CN 104708559B CN 201510129870 A CN201510129870 A CN 201510129870A CN 104708559 B CN104708559 B CN 104708559B
Authority
CN
China
Prior art keywords
boiler pot
fixing
pot cylinder
support
gantry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510129870.3A
Other languages
English (en)
Other versions
CN104708559A (zh
Inventor
陆海英
孙爱华
罗旭东
张锐鹏
张云富
李永红
王安鑫
张振禹
季忠原
隗合新
任桂红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co ltd Of China Construction Sixth Engineering Bureau
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Industry Equipment Installation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Industry Equipment Installation Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201510129870.3A priority Critical patent/CN104708559B/zh
Publication of CN104708559A publication Critical patent/CN104708559A/zh
Application granted granted Critical
Publication of CN104708559B publication Critical patent/CN104708559B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Ladders (AREA)

Abstract

本发明公开了一种固定与安装锅炉锅筒的方法,该方法包括制作设置有两个龙门固定支架的工装、将锅炉锅筒就位于所述工装的两个龙门固定支架以及夹紧固定等步骤。其优点是:占地面积小,且对运输地面和运输空间要求较低,故适用性强;可同时固定两个锅炉锅筒,且固定状态稳定;便于超大、超重散装锅炉锅筒的固定与安装施工,也适用于类似于锅炉锅筒的各种筒状物的固定及安装,具有很好的实用性。

Description

一种固定与安装锅炉锅筒的方法
技术领域
本发明涉及一种固定设备的方法,更具体的说,本发明涉及一种用于固定与安装锅炉锅筒的方法。
背景技术
目前,在大型散装锅炉设备的安装施工中,大都采用机械吊车和倒链进行锅炉锅筒位置的调整与固定,这种方法虽然一直延用,但却存在以下问题:
(1)施工中使用的设备成本高;
(2)吊装过程中对运输地面和运输空间的要求高;
(3)被固定的锅炉锅筒不稳定,容易晃动。
发明内容
本发明的目的就是解决上述公知技术中存在的问题,并为此提供一种用于固定与安装锅炉锅筒的方法。
本发明的技术方案是:
一种固定与安装锅炉锅筒的方法,包括以下步骤:
(1)制作工装:所述的工装包括对称设置的两个龙门固定支架,所述的龙门固定支架包括平行设置的两个立柱以及设置在两个所述立柱顶部的上部横梁支撑和设置在两个所述立柱下部的下部横梁支撑,所述的上部横梁支撑上对称设置两个上部限位装置,所述的下部横梁支撑上对称设置两个下部限位装置,每个所述立柱的两侧分别设置有其上端与所述的上部横梁支撑固定且其下端支撑于地面的斜向支撑。
(2)将两个锅炉锅筒分别就位于两个所述龙门固定支架的上部横梁支撑和下部横梁支撑上,并使两个所述的锅炉锅筒分别靠紧所述上部限位装置和下部限位装置的一侧;
(3)分别精调两个所述锅炉锅筒的位置,直至其上下平齐,然后分别调整所述上部限位装置和下部限位装置的另一侧夹紧固定。
所述工装的龙门固定支架的一侧设置有爬梯;所述爬梯的上端穿过所述的上部横梁支撑。
本发明方法可以同时固定两个锅炉锅筒,并克服了公知技术中所存在的诸多问题,其有益效果在于:
(1)由于本发明在龙门固定支架上设置了可调节的上部限位装置和下部限位装置,可使被固定的锅炉锅筒状态稳定,避免晃动,从而顺利完成超大、超重散装锅炉锅筒的固定与安装工作;
(2)由于本发明中的龙门固定支架占地面积小,且对运输地面和运输空间要求较低,故适用性强;
(3)由于本发明中的龙门固定支架结构简单,易于制作,故制作时的机械设备及人力投入均较少,且所用材料的二次回收率高,故成本很低。
(4)本发明的设置不仅适用于锅炉锅筒的固定及安装,也适用于类似于锅炉锅筒的各种筒状物的固定及安装,具有很好的实用性。
附图说明
图1为本发明的结构示意图;
图2为图1主视图;
图3为图2侧视图。
图中标记:
1、龙门固定支架;2、上部横梁支撑;3、下部横梁支撑;
4、上部限位装置;5、下部限位装置;6、立柱;
7、爬梯;8、斜向支撑;9、锅炉锅筒。
具体实施方式
为使本发明更容易被清楚理解,以下结合附图和实施例对其技术方案进行详细说明:
图1、图2、图3分别以结构图、主视图、侧视图的方式示出了本发明固定与安装锅炉锅筒的工装结构以及利用该工装固定与安装锅炉锅筒的情况。
参照图1、图2、图3,本发明中的工装,包括对称设置的两个龙门固定支架1;所述的龙门固定支架1包括平行设置的两个立柱6,两个所述立柱6的顶部焊接固定上部横梁支撑2,两个所述立柱6的下部焊接固定下部横梁支撑3,所述的上部横梁支撑2上对称设置两个上部限位装置4,所述的下部横梁支撑3上对称设置两个下部限位装置5,每个所述立柱6的两侧分别设置有斜向支撑8,所述斜向支撑8的上端与所述的上部横梁支撑2焊接固定,所述斜向支撑8的下端支撑于地面。
为便于施工,本发明在所述龙门固定支架1的一侧设置了爬梯7,同时为保证所述爬梯7在施工过程中的安全稳定,本发明设置所述爬梯7的上端穿过所述的上部横梁支撑2。
在安装锅炉锅筒9的施工中,两个所述的龙门固定支架1分别以对称方式分立两边,当同时固定两个所述的锅炉锅筒9时,可将一个所述的锅炉锅筒9安放在两个所述龙门固定支架1的上部横梁支撑2上,并使其两端分别被所述的上部限位装置4夹紧固定;再将另一个所述的锅炉锅筒9安放在两个所述龙门固定支架1的下部横梁支撑3上,并使其两端分别被所述的下部限位装置5夹紧固定。
本发明固定与安装锅炉锅筒的方法可以同时固定两个锅炉锅筒9,其使用方法包括以下步骤:
(1)制作前述的工装。
(2)将两个所述的锅炉锅筒9分别就位于两个所述龙门固定支架1的上部横梁支撑2和下部横梁支撑3上,并使两个所述的锅炉锅筒9分别靠紧所述上部限位装置4和下部限位装置5的一侧;
(3)对两个分别就位于所述上部横梁支撑2和下部横梁支撑3上的锅炉锅筒9进行位置精调,直至两个所述的锅炉锅筒9上下平齐,然后分别调整所述上部限位装置4和下部限位装置5的另一侧夹紧固定。
以上参照附图和实施例,对本发明的技术方案进行了示意性描述,该描述没有限制性。本领域的技术人员应能理解,在实际应用中,本发明中的各个技术特征均有可能发生细微变化,而其他人员在其启示下也可能做出相似设计。特别需要指出的是:只要不脱离本发明的设计宗旨,所有显而易见的变化或相似设计均包含在本发明的保护范围之内。

Claims (3)

1.一种固定与安装锅炉锅筒的方法,其特征在于:该方法包括以下步骤:
(1)制作工装:所述的工装包括对称设置的两个龙门固定支架,所述的龙门固定支架包括平行设置的两个立柱以及设置在两个所述立柱顶部的上部横梁支撑和设置在两个所述立柱下部的下部横梁支撑,所述的上部横梁支撑上对称设置两个上部限位装置,所述的下部横梁支撑上对称设置两个下部限位装置,每个所述立柱的两侧分别设置有其上端与所述的上部横梁支撑固定且其下端支撑于地面的斜向支撑;
(2)将两个锅炉锅筒分别就位于两个所述龙门固定支架的上部横梁支撑和下部横梁支撑上,并使两个所述的锅炉锅筒分别靠紧所述上部限位装置和下部限位装置的一侧;
(3)分别精调两个所述锅炉锅筒的位置,直至其上下平齐,然后分别调整所述上部限位装置和下部限位装置的另一侧夹紧固定。
2.根据权利要求1所述的固定与安装锅炉锅筒的方法,其特征在于:所述工装的龙门固定支架的一侧设置有爬梯。
3.根据权利要求2所述的固定与安装锅炉锅筒的方法,其特征在于:所述爬梯的上端穿过所述的上部横梁支撑。
CN201510129870.3A 2015-03-24 2015-03-24 一种固定与安装锅炉锅筒的方法 Active CN104708559B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510129870.3A CN104708559B (zh) 2015-03-24 2015-03-24 一种固定与安装锅炉锅筒的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510129870.3A CN104708559B (zh) 2015-03-24 2015-03-24 一种固定与安装锅炉锅筒的方法

Publications (2)

Publication Number Publication Date
CN104708559A CN104708559A (zh) 2015-06-17
CN104708559B true CN104708559B (zh) 2016-06-15

Family

ID=53408548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510129870.3A Active CN104708559B (zh) 2015-03-24 2015-03-24 一种固定与安装锅炉锅筒的方法

Country Status (1)

Country Link
CN (1) CN104708559B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105196265B (zh) * 2015-10-28 2017-05-03 衡阳市大成锅炉有限公司 一种双锅筒本体组装架

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9475155B2 (en) * 2010-02-02 2016-10-25 Technip Usa, Inc. Ring gear based welding system
CN103192335B (zh) * 2013-04-29 2015-06-17 中发输配电设备(平湖)有限公司 圆筒状工件固定座
CN103464956A (zh) * 2013-08-07 2013-12-25 无锡市恒通石油机械有限公司 一种焊接滚轮架
CN203875552U (zh) * 2014-04-08 2014-10-15 郑州中鼎锅炉股份有限公司 一种锅筒对装翻转台
CN104308767B (zh) * 2014-09-03 2016-01-13 上海交通大学 大型薄壁筒形构件自动对接装配的协同定位装置
CN204209354U (zh) * 2014-10-31 2015-03-18 天津市中重金属结构有限公司 一种筒体焊接工装

Also Published As

Publication number Publication date
CN104708559A (zh) 2015-06-17

Similar Documents

Publication Publication Date Title
CN104675179B (zh) 自升式钢塔安装用吊架装置及钢塔施工方法
CN204112715U (zh) 一种u型可调托撑及模板支撑架体
CN203965037U (zh) 用于整车声学测试的多传声器固定装置
CN110424724A (zh) 一种工具式梁板模支架及其支模方法
CN205806689U (zh) 一种便于安装的管道吊架
CN205955239U (zh) 格构柱施工用校正架
CN104708559B (zh) 一种固定与安装锅炉锅筒的方法
CN205576749U (zh) 桥体梁架提升及调位装置
CN204554274U (zh) 一种支撑架装置
CN104563525B (zh) 一种箱式钢拱梁整体卧式组对方法
CN204702442U (zh) 一种塔吊基座的调平装置
CN207469096U (zh) 一种提篮拱拱脚钢管定位装置
CN103774694B (zh) 一种可调式钢筋笼定位胎架
CN104019285A (zh) 一种可调节管道支撑架
CN210820171U (zh) 预制t梁钢筋绑扎胎膜架
CN205421366U (zh) 一种用于逆作法立柱垂直度调整的叠拼式加强型调垂机构
CN204532376U (zh) 分体式升降施工台车
CN103418956A (zh) 伸缩式h型钢构加工专用支架
CN106555401B (zh) 用于导向管上部定位的台架
CN204310244U (zh) 螺杆钻具摆放架
CN105484661A (zh) 一种移动式斜梯
CN206455633U (zh) 一种支撑工装
CN203881530U (zh) 货叉疲劳实验装置
CN204624886U (zh) 斜撑杆式施工升降机的附着装置
CN203684709U (zh) 钢结构桁架组装倾角的调整装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 300450 No. 72, Hangzhou Road, Tanggu Binhai New Area, Tianjin

Co-patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Address before: 300451 Tanggu Binhai New Area, Hangzhou Road, No. 72, No.

Co-patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee before: CHINA CONSTRUCTION 6TH ENGINEERING BUREAU INDUSTRIAL EQUIPMENT INSTALLATION Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee after: China Construction Sixth Engineering Bureau Co., Ltd.

Address before: No. 72, Hangzhou Road, Tanggu, Binhai New Area, Tianjin 300450

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Patentee before: China Construction Sixth Engineering Bureau Co., Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.