CN104658187A - Operational risk management and control reminding method and device for power transmission line of power grid - Google Patents
Operational risk management and control reminding method and device for power transmission line of power grid Download PDFInfo
- Publication number
- CN104658187A CN104658187A CN201510065794.4A CN201510065794A CN104658187A CN 104658187 A CN104658187 A CN 104658187A CN 201510065794 A CN201510065794 A CN 201510065794A CN 104658187 A CN104658187 A CN 104658187A
- Authority
- CN
- China
- Prior art keywords
- risk
- point
- management
- transmission line
- personnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 60
- 238000000034 method Methods 0.000 title claims abstract description 43
- 238000012423 maintenance Methods 0.000 claims abstract description 15
- 238000012217 deletion Methods 0.000 claims abstract description 4
- 230000037430 deletion Effects 0.000 claims abstract description 4
- 230000005611 electricity Effects 0.000 claims description 36
- 231100001261 hazardous Toxicity 0.000 claims description 14
- 230000008676 import Effects 0.000 claims description 6
- 238000009795 derivation Methods 0.000 claims description 3
- 230000002093 peripheral effect Effects 0.000 claims description 3
- 230000002265 prevention Effects 0.000 claims description 3
- 230000003449 preventive effect Effects 0.000 claims description 3
- 230000000007 visual effect Effects 0.000 claims description 3
- 238000012986 modification Methods 0.000 abstract 1
- 230000004048 modification Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- 241000270295 Serpentes Species 0.000 description 1
- 241000256856 Vespidae Species 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 231100000614 poison Toxicity 0.000 description 1
- 230000007096 poisonous effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B21/00—Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
- G08B21/02—Alarms for ensuring the safety of persons
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Public Health (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Health & Medical Sciences (AREA)
- General Business, Economics & Management (AREA)
- Water Supply & Treatment (AREA)
- Theoretical Computer Science (AREA)
- Emergency Management (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention relates to an operational risk management and control reminding method and device for a power transmission line of a power grid. The method comprises two parts, namely management and configuration of risk points and field operational risk management and control, wherein the configuration and management of the risk points can add information of the risk points through the ways of excel introduction and manual maintenance, support the manual maintenance way to realize modification and deletion of the risk points and support checking of the risk points based on a GIS (geographic information system) after maintenance; in an operation process of the power transmission line, when operation staff enter the information of the risk points which are pre-maintained, geolocation information of the current operation staff is obtained, the actual distance between the operation staff and the position of the center of the risk points is calculated by using a two-point coordinate distance algorithm, and if the actual distance is within 50 m, the operation staff is reminded of risk which may exist by voice, thereby helping management staff complete field operation safely. By adopting the method provided by the invention, the operation staff of the power transmission line can be assisted in taking measures in advance to respond to the risk after continuous perfection, and the incidence of unsafe accidents is reduced.
Description
Technical field
The invention belongs to a kind of grid power transmission circuit operating risk management and control based reminding method and device technique field thereof.
Background technology
Grid power transmission circuit carries the important task of region transmission of electricity, and the fault of transmission line of electricity can cause large-area power failure, and the safe and stable operation of transmission line of electricity is huge on daily productive life impact.For ensureing that the health of transmission line of electricity is run, electric power enterprise drops into a large amount of human and material resources resources, and management and control transmission of electricity site work quality, ensures that transmission line of electricity is healthy.
Because transmission line of electricity distributed areas are wide, region span is large, has the regions such as forest, high mountain, perilous peak, outside environmental elements complexity is various, have the danger such as poisonous snake, falling rocks, steep cliff, hornet, dog, the personal safety accident of site work personnel is subject to great threat, often has the generation of dangerous accident.
Summary of the invention
Object of the present invention provides a kind of grid power transmission circuit operating risk management and control based reminding method to overcome the defect of above-mentioned prior art existence just, ensure that site work personnel personal safety is starting point from the analysis of management and control site work, by the actual practice experience of site work personnel for many years, in conjunction with power grid enterprises' risk management and control requirement, a kind of method that transmission line operation risk management and control is reminded is proposed, and practical application has been carried out in reality transmission of electricity site work, through constantly perfect, transmission line operation personnel can be helped to carry out risk handling measurement in advance, reduce dangerous accident to occur.
The object of the invention is to realize by following technical solution.
Grid power transmission circuit operating risk management and control based reminding method, the present invention includes risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely.
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
Site work risk management and control reminded contents is the information by site work personnel coordinate information and risk point, utilize GIS layer engineer's scale and coordinate combination, the actual range of computational tasks personnel and dangerous point, 50 meters of voice reminders in advance, after entering hazardous location, voice reminder notes the precautionary measures of risk again.
A kind of device of grid power transmission circuit operating risk management and control based reminding method, the present invention includes gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.
Advantage of the present invention: the invention provides a kind of method that truly feasible transmission line operation risk management and control is reminded, power transmission work personnel effective management and control risk in operation process can be helped, reduce the generation of dangerous accident.The effective management and control of operating risk, in conjunction with the risk point in risk system, effective management early warning of risk point is realized by device, intelligent computation operating personnel in operation process and the positional distance of dangerous point, and carry out voice reminder, inform operating personnel's dangerous information, carry out the precautionary measures in advance, reduce the generation of dangerous accident.Device is simple and easy to using, and operating personnel only need simple knowledge can learn to use, and through having gone practice in actual transmission line of electricity site work, tackling risk have very great help to transmission line of electricity site work personnel.
Accompanying drawing explanation
Fig. 1 is transmission line of electricity site work risk pipe schematic diagram of the present invention;
Fig. 2 is transmission line of electricity site work risk management and control schematic diagram of the present invention;
Fig. 3 is apparatus of the present invention structural representation.
Embodiment
Grid power transmission circuit operating risk management and control based reminding method, the present invention includes risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely.
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
Site work risk management and control reminded contents is the information by site work personnel coordinate information and risk point, utilize GIS layer engineer's scale and coordinate combination, the actual range of computational tasks personnel and dangerous point, 50 meters of voice reminders in advance, after entering hazardous location, voice reminder notes the precautionary measures of risk again.
See Fig. 3, a kind of device of grid power transmission circuit operating risk management and control based reminding method, the present invention includes gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.
Claims (2)
1. a grid power transmission circuit operating risk management and control based reminding method, is characterized in that, comprises risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely;
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
2. adopt a kind of device of grid power transmission circuit operating risk management and control based reminding method, it is characterized in that, comprise gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510065794.4A CN104658187B (en) | 2015-02-09 | 2015-02-09 | Operational risk management and control reminding method and device for power transmission line of power grid |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510065794.4A CN104658187B (en) | 2015-02-09 | 2015-02-09 | Operational risk management and control reminding method and device for power transmission line of power grid |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104658187A true CN104658187A (en) | 2015-05-27 |
CN104658187B CN104658187B (en) | 2017-02-22 |
Family
ID=53249253
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510065794.4A Active CN104658187B (en) | 2015-02-09 | 2015-02-09 | Operational risk management and control reminding method and device for power transmission line of power grid |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104658187B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105225410A (en) * | 2015-08-31 | 2016-01-06 | 国网山东省电力公司淄博供电公司 | Distribution line is close to method for early warning and equipment |
CN106123947A (en) * | 2016-06-12 | 2016-11-16 | 南宁思飞电子科技有限公司 | Intelligent power detection system |
CN108090701A (en) * | 2018-01-10 | 2018-05-29 | 广东电网有限责任公司珠海供电局 | A kind of field work safe risk management and control method based on geography information polymerization |
CN109272203A (en) * | 2018-08-24 | 2019-01-25 | 国网天津市电力公司电力科学研究院 | A kind of transmission line parameter test auxiliary system |
CN109508844A (en) * | 2017-09-15 | 2019-03-22 | 全球能源互联网研究院 | A kind of security risk analysis method and system for work compound |
CN112435424A (en) * | 2020-12-01 | 2021-03-02 | 国网辽宁省电力有限公司朝阳供电公司 | Dangerous point warning device and warning method for power line operation site |
CN112927412A (en) * | 2021-01-30 | 2021-06-08 | 上海电机学院 | Access control system for wind driven generator |
CN113792658A (en) * | 2021-09-15 | 2021-12-14 | 江苏迪赛司自动化工程有限公司 | Fire operation closed-loop automatic control method and system based on intelligent overall process monitoring |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101901430A (en) * | 2010-07-19 | 2010-12-01 | 北京恒泰实达科技发展有限公司 | Power grid risk management and control method and device |
CN103177396A (en) * | 2012-12-31 | 2013-06-26 | 浙江省电力公司 | Intelligentized whole-employee overall-process full-profession multidimensional risk management and control platform for site operations of power supply enterprises |
CN103295164A (en) * | 2013-05-31 | 2013-09-11 | 云南电网公司 | Power grid safety monitoring management information system and management method |
WO2014122930A1 (en) * | 2013-02-07 | 2014-08-14 | 日本電気株式会社 | Power control system |
US20140344124A1 (en) * | 2012-10-24 | 2014-11-20 | Causam Energy, Inc. | System, method, and apparatus for settlement for participation in an electric power grid |
US20150025696A1 (en) * | 2013-07-17 | 2015-01-22 | Carnegie Mellon University | Distributed Methods and Software For Balancing Supply and Demand In An Electric Power Network |
-
2015
- 2015-02-09 CN CN201510065794.4A patent/CN104658187B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101901430A (en) * | 2010-07-19 | 2010-12-01 | 北京恒泰实达科技发展有限公司 | Power grid risk management and control method and device |
US20140344124A1 (en) * | 2012-10-24 | 2014-11-20 | Causam Energy, Inc. | System, method, and apparatus for settlement for participation in an electric power grid |
CN103177396A (en) * | 2012-12-31 | 2013-06-26 | 浙江省电力公司 | Intelligentized whole-employee overall-process full-profession multidimensional risk management and control platform for site operations of power supply enterprises |
WO2014122930A1 (en) * | 2013-02-07 | 2014-08-14 | 日本電気株式会社 | Power control system |
CN103295164A (en) * | 2013-05-31 | 2013-09-11 | 云南电网公司 | Power grid safety monitoring management information system and management method |
US20150025696A1 (en) * | 2013-07-17 | 2015-01-22 | Carnegie Mellon University | Distributed Methods and Software For Balancing Supply and Demand In An Electric Power Network |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105225410A (en) * | 2015-08-31 | 2016-01-06 | 国网山东省电力公司淄博供电公司 | Distribution line is close to method for early warning and equipment |
CN106123947A (en) * | 2016-06-12 | 2016-11-16 | 南宁思飞电子科技有限公司 | Intelligent power detection system |
CN109508844A (en) * | 2017-09-15 | 2019-03-22 | 全球能源互联网研究院 | A kind of security risk analysis method and system for work compound |
CN108090701A (en) * | 2018-01-10 | 2018-05-29 | 广东电网有限责任公司珠海供电局 | A kind of field work safe risk management and control method based on geography information polymerization |
CN109272203A (en) * | 2018-08-24 | 2019-01-25 | 国网天津市电力公司电力科学研究院 | A kind of transmission line parameter test auxiliary system |
CN112435424A (en) * | 2020-12-01 | 2021-03-02 | 国网辽宁省电力有限公司朝阳供电公司 | Dangerous point warning device and warning method for power line operation site |
CN112927412A (en) * | 2021-01-30 | 2021-06-08 | 上海电机学院 | Access control system for wind driven generator |
CN113792658A (en) * | 2021-09-15 | 2021-12-14 | 江苏迪赛司自动化工程有限公司 | Fire operation closed-loop automatic control method and system based on intelligent overall process monitoring |
CN113792658B (en) * | 2021-09-15 | 2023-09-01 | 江苏迪赛司自动化工程有限公司 | Automatic control method and system for closed loop of fire operation in whole process intelligent monitoring |
Also Published As
Publication number | Publication date |
---|---|
CN104658187B (en) | 2017-02-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104658187A (en) | Operational risk management and control reminding method and device for power transmission line of power grid | |
Yoo et al. | Emergency evacuation plan for hazardous chemicals leakage accidents using GIS-based risk analysis techniques in South Korea | |
CN103558827B (en) | Mine emergency command communication and management information system | |
CN104951585A (en) | Grid equipment based typhoon warning method and device | |
CN104952212A (en) | Power-grid-GIS-based early warning method of geological disaster and apparatus thereof | |
CN101763605A (en) | Three-dimensional digital urban fire protection pre-control and management system | |
CN103676857A (en) | Solar ecological environment monitoring distributed-type system | |
CN205537756U (en) | Monitoring system based on big dipper | |
CN105184522A (en) | Substation polling offside warning system and warning method | |
CN104951998A (en) | Strong wind early warning modeling method and strong wind early warning modeling system based on power grid GIS (geographic information system) | |
CN107958343B (en) | Hazardous chemical substance disaster situation material scheduling method and system | |
CN112541684A (en) | BIM-based emergency dispatching command method, system, computer equipment and readable medium | |
CN104794657A (en) | Garden digital emergency command and dispatch system | |
CN103440347B (en) | A kind of heterogeneous Disaster Event universal modeling method and system | |
Buribayeva et al. | An autonomous emergency warning system based on cloud servers and SNS | |
CN103454648A (en) | Alarming rescuing system based on Beidou system and Android cell phone platform | |
CN116862710A (en) | Wisdom gas management platform | |
CN102488996A (en) | Fire hazard on-site positioning transmission system and method thereof | |
CN204178393U (en) | A kind of urban pipe network production and operation total management system | |
CN105512952A (en) | Safety prewarning information system for key dangerous sites | |
JP2014232435A (en) | Response system | |
RU147524U1 (en) | AUTOMATED INFORMATION SYSTEM TO SUPPORT MANAGEMENT DECISIONS IN THE CONDITIONS OF EMERGENCY SITUATION IN RAILWAY TRANSPORT | |
CN102013052A (en) | Diffusion simulation analysis system using three-dimensional GIS (geographic information system) in environmental emergency | |
CN205596351U (en) | Underground works safe risk real -time prewarning device of being under construction based on thing networking | |
CN103065194A (en) | Method of hazardous waste emergency early warning and response through 3S technologies and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |