CN109272203A - A kind of transmission line parameter test auxiliary system - Google Patents
A kind of transmission line parameter test auxiliary system Download PDFInfo
- Publication number
- CN109272203A CN109272203A CN201810971467.9A CN201810971467A CN109272203A CN 109272203 A CN109272203 A CN 109272203A CN 201810971467 A CN201810971467 A CN 201810971467A CN 109272203 A CN109272203 A CN 109272203A
- Authority
- CN
- China
- Prior art keywords
- module
- test
- transmission line
- line parameter
- task
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063118—Staff planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
The present invention relates to a kind of transmission line parameters to test auxiliary system, including task release module, process control module, safety prompt function module, interpretation of result module and the report generation module integrated;The task release module issues the transmission line parameter test assignment information received to work group member;The process control module carries out process control to entire transmission line parameter test assignment;The full reminding module reminds the security risk in transmission line parameter test assignment implementation procedure;The interpretation of result module carries out Macro or mass analysis to the test data in transmission line parameter test process;The report generation module generates corresponding working report and test archive after test assignment completion.The present invention has rational design, carries out soup-to-nuts service to transmission line parameter test assignment, effectively promotes the efficiency of test and reduces the security risk during task execution, can provide reference for related specific purpose tool software development.
Description
Technical field
The invention belongs to transmission line of electricity technical field, especially a kind of transmission line parameter tests auxiliary system.
Background technique
After transmission line of electricity is newly-built or rebuilding construction is completed, before power transmission puts into operation, need to carry out commissioning test to its work
Frequency parameter measures, and provides data for work such as system load flow, transient stability and relay protection setting calculations and supports.In recent years
Come, transmission line of electricity is newly-built or " three across " transformation frequently, project amount is big, and corresponding parameter testing task is heavier.Meanwhile in order to abundant
Using transmission of electricity corridor land resource, channel transmission capacity, the more common-tower double-returns of transmission line of electricity or more times erections are improved.Work as parallel arrangement
Or when scissors crossing alive circuit, higher voltage can be induced under test line, seriously threaten testing crew and instrument
Safety.Thus, the efficiency of transmission line parameter test job and safety seem particularly significant.
There are more device manufacturers to develop dedicated test equipment now to test transmission line parameter, with more
Mend the deficiency in conventional test methodologies.In the detailed process that test is implemented, testing crew is needed to reach route both ends to be measured existing
, by communicating with each other and cooperation is tested.Made by the objective factors such as weather, traffic, field condition and instrumentation, tool
With etc. human factors influence, testing crew is difficult to ensure the accuracy of the execution efficiency and test result of test process, and
The security incident of induced electricity injury and instrument is easy to happen during test.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of transmission line parameters to test auxiliary system,
The efficiency of test can effectively be promoted and reduce the security risk during task execution.
The present invention solves its technical problem and adopts the following technical solutions to achieve:
A kind of transmission line parameter tests auxiliary system, including integrate task release module, Row control mould
Block, safety prompt function module, interpretation of result module and report generation module;The task release module joins the transmission line of electricity received
Number test assignment information issues work group member;The process control module is to entire transmission line parameter test assignment
Carry out process control;The full reminding module proposes the security risk in transmission line parameter test assignment implementation procedure
It wakes up;The interpretation of result module carries out Macro or mass analysis to the test data in transmission line parameter test process;The report is raw
Corresponding working report and test archive are generated after test assignment completion at module.
The task release module includes authority distribution module and mission bit stream module, and the authority distribution module is to working group
The permission of member is configured;The mission bit stream module provides editor and the look facility of mission bit stream.
The process control module includes that communication module, task verification module, Advance data quality module and task carry out module;
The communication module provides communication function for work group member, the task verify module before test assignment starts to set out and
Test terminates to verify task before leaving, the Advance data quality module provided for work group member the weather of needs, traffic,
Instrument and historic task information, the task carry out module and provide control, exchange and guidance to the implementation that transmission line parameter is tested
Information.
The safety prompt function module includes test safety prompt function module and other safety prompt function modules, the test safety prompt function
Module carries out safety prompt function to the process tested in test site, other safety prompt function modules to remove on-the-spot test its
He carries out safety prompt function at process.
The interpretation of result module includes being successfully tested analysis module and test crash analysis module;This is successfully tested analysis
Module analyzes the data for completing test, which analyzes the case where unfinished test.
The report generation module includes working report generation module and test archive generation module;The working report is raw
Work executive condition report is generated for reporting at module, which generates test process and result report is used
In archive.
The advantages and positive effects of the present invention are:
The present invention has rational design, passes through task publication, Row control, safety prompt function, interpretation of result and report generation function
Can, soup-to-nuts service is carried out to transmission line parameter test assignment, the efficiency of test is effectively promoted and reduces task execution process
In security risk, reference can be provided for related specific purpose tool software development.
Detailed description of the invention
Fig. 1 is that system of the invention constitutes schematic diagram;
Fig. 2 is the composition and functional schematic of task release module of the invention;
Fig. 3 is the composition and functional schematic of process control module of the invention;
Fig. 4 is the composition and functional schematic of safety prompt function module of the invention;
Fig. 5 is the composition and functional schematic of interpretation of result module of the invention;
Fig. 6 is the composition and functional schematic of report generation module of the invention;
Fig. 7 is the aid illustration flow chart that the present invention is used for transmission line parameter test assignment.
Specific embodiment
The present invention is further described below in conjunction with attached drawing.
A kind of transmission line parameter test auxiliary system, as shown in Figure 1, including task release module 1, process control module
2, safety prompt function module 3, interpretation of result module 4 and report generation module 5.The task release module includes authority distribution mould
Block 6 and mission bit stream module 7, as shown in Figure 2.The process control module includes communication module 8, task verification module 9, letter
It ceases optimization module 10 and task carries out module 11, as shown in Figure 3.The safety prompt function module includes test safety prompt function module
12 and other safety prompt function modules 13, as shown in Figure 4.The interpretation of result module includes being successfully tested analysis module 14 and surveying
Failure analysis module 15 is tried, as shown in Figure 5.The report generation module includes working report generation module 16 and test archive
Generation module 17, as shown in Figure 6.
The task release module mainly to the transmission line parameter test assignment information received to work group member into
Row publication.Wherein, the authority distribution module is configured the permission of work group member, and priority assignation includes administrator's power
Limit, task editing authority and task check permission;The mission bit stream module mainly provides the editor of mission bit stream and checks
Function, mission bit stream include: line name, voltage class, total track length, erection mode, segmentation situation, wire type;Test
Time, test site, testing crew, test apparatus, managing security tools and instruments, vehicle drivers;Personnel's division of labor, pilot project, test step
Suddenly, safety measure, Analysis about Dangerous Point and work ticket.
The process control module carries out process control to entire transmission line parameter test assignment.Wherein, described
Communication module be mainly work group member provide communication function, information include text information, pictorial information, voice messaging and
Location information.The task is verified before module is mainly left before test assignment starts to set out with test end to task
It is verified, it includes: that personnel verify, vehicle is verified, instrument is verified, managing security tools and instruments is verified and work ticket core that task, which verifies content,
It looks into.The Advance data quality module is mainly that work group member provides the letter such as weather, traffic, instrument and historic task needed
Breath, specifically includes weather forecast, path optimization, automobile navigation, instrument tool specification and historic task remarks.The task
It carries out module and mainly provides control, exchange and tutorial message to the implementation of transmission line parameter test, it is real-time to specifically include road
Positioning, process intelligent reminding, both-end automated communications and test operation guidance.
The safety prompt function module mainly carries out the security risk in transmission line parameter test assignment implementation procedure
It reminds.Wherein, the test safety prompt function module mainly carries out safety prompt function, tool to the process tested in test site
Body uses safety prompt function and instrument including test environment safety prompt function, site safety measure prompting, testing procedure safety prompt function, tool
Device safe operation is reminded.Other described safety prompt function modules mainly carry out safety prompt function to other processes except on-the-spot test,
Specifically include: meteorology is reminded, traffic safety and emergency instruct.
The interpretation of result module mainly carries out Macro or mass analysis to the test data in transmission line parameter test process.
Wherein, analysis module is successfully tested mainly to analyze the data for completing test, specifically include test result summarize, theoretical meter
Count value, expert analyzing system.Test crash analysis module mainly analyzes the case where unfinished test, specifically includes line
Road construction, test connection, instrumentation and test environment.
The report generation module mainly generates corresponding working report and test archive after test assignment completion.
Wherein, the working report generation module mainly generates work executive condition report for reporting, specifically include task,
Personnel equipment, performance, other illustrate.The test archive generation module mainly generates test process and result report
For achieving, task list, testing program, process record and test report are specifically included.
The present invention executes the whole work process of task, as shown in fig. 7, comprises:
(1) it receives an assignment.Transmission line parameter test assignment distributes people by task and is issued to work responsible person.
(2) previous work.Work responsible person determines work group member according to mission bit stream, formulates work plan, writes examination
Proved recipe case and preparation ticket, and reported to Work distributing people.
(3) authority distribution.Work distributing people adds work using the authority distribution module 6 in task release module 1 and forms
Member is simultaneously allocated its permission, and Work distributing people has administrator right, and work responsible person has task editing authority, remaining
There is work group member task to check permission.
(4) mission bit stream is edited.The responsible person that works believes task using the mission bit stream module 7 in task release module 1
Breath is edited, including when line name, voltage class, total track length, erection mode, segmentation situation, wire type, test
Between, test site, testing crew, test apparatus, managing security tools and instruments, vehicle drivers, personnel's division of labor, pilot project, test procedure,
Safety measure, Analysis about Dangerous Point and work ticket etc..
(5) release task message.The responsible person that works uses 7 release tasks of mission bit stream module in task release module 1
Information.
(6) mission bit stream is checked.Work group member with permission uses the mission bit stream module in task release module 1
7 check mission bit stream.
(7) task is verified.Task core of the work group member before task starts to set out, in process for using control module 2
It looks into personnel, vehicle, instrument, managing security tools and instruments and work ticket that 9 pairs of this subtasks of module are related to verify, it is ensured that intact complete
After set out.
(8) testing location is reached.Work group member is divided into two teams and goes to route both ends scene to be measured.When driving,
Advance data quality module 10 in process control module 2 can enable weather forecast, path optimization and automobile navigation service, improve traveling
Efficiency, while task progress module 11 can enable road real-time navigation capability, and two teams personnel is facilitated to understand respective position in real time.Two
Team personnel can be used the communication module 8 in process control module 2 and communicate, and send the letter such as text, picture, voice, position
Breath, it is possible to use Advance data quality module 10 inquires the history remark information of test site, understands this test assignment in advance.Driving
In the process, other safety prompt function modules 13 in safety prompt function module 3 can issue automatically meteorological and traffic safety and remind.
(9) on-the-spot test.After two teams work group member reaches respective test site, the task in process control module 2
Process intelligent reminding can be issued by carrying out module 11, instruct work group member carry out corresponding live preparation, test connection and
Communication module 8 can be used during the test and carry out communicational aspects by test operation, work group member.In safety prompt function module 3
Test safety prompt function module 12 can issue safety prompt function during work group member's on-the-spot test, including test environment,
Site safety measure, testing procedure, tool use and instrumentation etc..Work group member can be used mission bit stream module 7 into
Row job enquiry and use information optimization module 10 carry out instrument tool and illustrate inquiry etc..During the test in case of safety
Event, other safety prompt function modules 13 in safety prompt function module 3 can provide emergency guidance.
(10) interpretation of result.Work group member is tested by step, if be successfully tested, result is entered by work responsible person
In interpretation of result module 4, the analysis module 14 therein that is successfully tested can automatically summarize test result, and provide corresponding line
The theoretical calculation numerical value of road parameter, while test value and theoretical value are compared and analyzed using expert analyzing system.If surveyed
Examination goes wrong, and the test crash analysis module 15 in interpretation of result module 4 can be to possible reason, such as line construction, test
The information such as wiring, instrumentation, test environment influence.
(11) report is generated.After being successfully tested, the meeting automatic work of report generation module 5, working report therein generates mould
Block 16 generates the working report comprising task, personnel equipment, performance, other explanations and is used to report, and test archive is raw
The test archive comprising task list, testing program, process record and test report is generated for achieving at module 17.
(12) task is verified.Work group member verifies module 9 before test terminates, leaves test site, using task
The people, object and the formality that are related to are verified.
(13) it returns.All working group membership returns, and returns to Advance data quality module 10, communication module 8, other safety on the way
The work such as reminding module 10, provide and go to identical service in road.
(14) task is completed.Work responsible person is reported accordingly and filing-up work.
It is emphasized that embodiment of the present invention be it is illustrative, without being restrictive, therefore packet of the present invention
Include and be not limited to embodiment described in specific embodiment, it is all by those skilled in the art according to the technique and scheme of the present invention
The other embodiments obtained, also belong to the scope of protection of the invention.
Claims (6)
1. a kind of transmission line parameter tests auxiliary system, it is characterised in that: including integrate task release module, stream
Process control module, safety prompt function module, interpretation of result module and report generation module;The task release module is defeated to what is received
Electric line parameter testing mission bit stream issues work group member;The process control module is to entire transmission line parameter
Test assignment carries out process control;The full reminding module is to the security risk in transmission line parameter test assignment implementation procedure
It is reminded;The interpretation of result module carries out Macro or mass analysis to the test data in transmission line parameter test process;It is described
Report generation module generates corresponding working report and test archive after test assignment completion.
2. a kind of transmission line parameter tests auxiliary system according to claim 1, it is characterised in that: the task issues mould
Block includes authority distribution module and mission bit stream module, which is configured the permission of work group member;It should
Mission bit stream module provides editor and the look facility of mission bit stream.
3. a kind of transmission line parameter tests auxiliary system according to claim 1, it is characterised in that: the Row control mould
Block includes that communication module, task verification module, Advance data quality module and task carry out module;The communication module is work group member
Communication function is provided, which verifies module before test assignment starts to set out and test before end is left to task
It is verified, which provides weather, traffic, instrument and the historic task information of needs for work group member, should
Task carries out module and provides control, exchange and tutorial message to the implementation that transmission line parameter is tested.
4. a kind of transmission line parameter tests auxiliary system according to claim 1, it is characterised in that: the safety prompt function mould
Block includes test safety prompt function module and other safety prompt function modules, which surveys in test site
The process of examination carries out safety prompt function, which carries out safety prompt function to other processes except on-the-spot test.
5. a kind of transmission line parameter tests auxiliary system according to claim 1, it is characterised in that: the interpretation of result mould
Block includes being successfully tested analysis module and test crash analysis module;This be successfully tested analysis module to complete test data into
Row analysis, the test crash analysis module analyze the case where unfinished test.
6. a kind of transmission line parameter tests auxiliary system according to claim 1, it is characterised in that: the report generation
Module includes working report generation module and test archive generation module;The working report generation module generates work executive condition
For report for reporting, which generates test process and result report for achieving.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810971467.9A CN109272203A (en) | 2018-08-24 | 2018-08-24 | A kind of transmission line parameter test auxiliary system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810971467.9A CN109272203A (en) | 2018-08-24 | 2018-08-24 | A kind of transmission line parameter test auxiliary system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109272203A true CN109272203A (en) | 2019-01-25 |
Family
ID=65154495
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810971467.9A Pending CN109272203A (en) | 2018-08-24 | 2018-08-24 | A kind of transmission line parameter test auxiliary system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109272203A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2722259Y (en) * | 2004-08-25 | 2005-08-31 | 江苏省电力公司南京供电公司 | Power frequency parameter measuring device of high-voltage transmission circuit |
CN101403779A (en) * | 2008-11-12 | 2009-04-08 | 河南电力试验研究院 | Parameter measuring apparatus and system for high tension power line |
CN103308796A (en) * | 2013-05-23 | 2013-09-18 | 中国南方电网有限责任公司超高压输电公司检修试验中心 | System capable of guaranteeing parameter test work safety of ac/dc (alternating current/direct current) transmission line |
CN104658187A (en) * | 2015-02-09 | 2015-05-27 | 云南电网有限责任公司西双版纳供电局 | Operational risk management and control reminding method and device for power transmission line of power grid |
CN106355665A (en) * | 2016-08-24 | 2017-01-25 | 山东鲁昂电气有限公司 | Transmission line inspecting comprehensive management system |
CN106408453A (en) * | 2016-09-23 | 2017-02-15 | 国家电网公司 | GIS-based power transmission line intelligent inspection system |
CN108288128A (en) * | 2018-02-28 | 2018-07-17 | 中国电力科学研究院有限公司 | A kind of transmission line of electricity methods of risk assessment and system |
-
2018
- 2018-08-24 CN CN201810971467.9A patent/CN109272203A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2722259Y (en) * | 2004-08-25 | 2005-08-31 | 江苏省电力公司南京供电公司 | Power frequency parameter measuring device of high-voltage transmission circuit |
CN101403779A (en) * | 2008-11-12 | 2009-04-08 | 河南电力试验研究院 | Parameter measuring apparatus and system for high tension power line |
CN103308796A (en) * | 2013-05-23 | 2013-09-18 | 中国南方电网有限责任公司超高压输电公司检修试验中心 | System capable of guaranteeing parameter test work safety of ac/dc (alternating current/direct current) transmission line |
CN104658187A (en) * | 2015-02-09 | 2015-05-27 | 云南电网有限责任公司西双版纳供电局 | Operational risk management and control reminding method and device for power transmission line of power grid |
CN106355665A (en) * | 2016-08-24 | 2017-01-25 | 山东鲁昂电气有限公司 | Transmission line inspecting comprehensive management system |
CN106408453A (en) * | 2016-09-23 | 2017-02-15 | 国家电网公司 | GIS-based power transmission line intelligent inspection system |
CN108288128A (en) * | 2018-02-28 | 2018-07-17 | 中国电力科学研究院有限公司 | A kind of transmission line of electricity methods of risk assessment and system |
Non-Patent Citations (1)
Title |
---|
徐文燕: "《西安交通大学出版社》", 28 February 2018 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109634187A (en) | A kind of AGV remote monitoring system | |
WO2016034140A1 (en) | Gis map-based dynamic status plotting system and method | |
CN108335377B (en) | GIS technology-based automatic check method for road inspection vehicle service | |
CN203840375U (en) | System for analyzing inspection quality of railway inspector | |
DE212016000186U1 (en) | simulation system | |
CN107705042A (en) | The method for inspecting and device of power equipment | |
CN110113397B (en) | Airport guarantee vehicle automatic in-place reporting system based on GIS | |
CN103500377A (en) | Integrated maintenance-operation management method and system for electric service ATP (Automatic Train Protection) vehicle-mounted equipment in railway | |
CN106314486B (en) | The fusion method of Locomotive Turnround practical figure and planning chart | |
CN104202086A (en) | Optical cable fault location method | |
CN113077168B (en) | Machine patrol operation risk management and control system and method | |
CN105857349A (en) | Precise train positioning system based on comprehensive positioning | |
CN111332341A (en) | Implementation method for entering route handling of centralized control station based on CTC3.0 | |
CN104732608A (en) | Real-time quality testing method and device and inspection system | |
CN205862379U (en) | Electric power equipment inspection system | |
CN108010282A (en) | The method for drafting of figure and the rescue skills in toxic gas place when toxic gas is distributed | |
CN115982954A (en) | Power transmission line three-dimensional simulation model construction system and model construction method | |
CN205724644U (en) | Transmission line of electricity emergency first-aid repair dispatching patcher | |
CN111260256A (en) | Visual flight guarantee management method | |
CN109272203A (en) | A kind of transmission line parameter test auxiliary system | |
Huang et al. | Preliminary analysis and simulation of railroad dispatcher workload | |
CN104301388A (en) | Large running system monitoring and analyzing management system | |
EP3629312A1 (en) | Vehicle guidance device position determining system | |
CN110579144A (en) | Surface mine blasting integration service management system | |
CN110490321A (en) | Railway traffic engineering Safety Supervision method for early warning and monitoring system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190125 |